ML18054B572: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 14: Line 14:
| page count = 5
| page count = 5
}}
}}
See also: [[see also::IR 05000255/1990005]]


=Text=
=Text=
{{#Wiki_filter:* consumers  
{{#Wiki_filter:* consumers Power PDWERINli NtlCHlliAN'S PROGRESS General Offices: 1945 West Parnall Road, Jackson, Ml 49201 o (517) 788-1636 April 23, 1990 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 DOCKET 50-255 -LICENSE DPR-20 -PALISADES PLANT -RESPONSE TO INSPECTION REPORT 90005; NOTICE OF VIOLATION Kenneth W Berry Director Nuclear licensing Nuclear Regulatory Commission (NRC) Inspection Report 255/90005, dated March 22, 1990 documented the results of an_examination of previously iden-* tified environmental qualification (EQ) inspection findings and resulted in the issuance of two violations.
Power PDWERINli  
As was noted in the Inspection Report, we had implemented corrective actions to resolve all findings and concerns with one exception, the electrical penetration connector.
NtlCHlliAN'S  
In accordance with 10CFR2.201, our response to each of the identified examples of noncompliance follows: Violation 50-255/90005-03 (DRS): 10CFR50, Appendix B, Criterion XVI, "Corrective Action" requires that measures be established to assure that conditions-adverse to quality, including formances, are promptly identified and corrected.
PROGRESS General Offices: 1945 West Parnall Road, Jackson, Ml 49201 o (517) 788-1636 April 23, 1990 Nuclear Regulatory  
In the case of significant conditions adverse to quality, the measures shall assure that the cause of the condition is determined and corrective action is taken to preclude repetition.
Commission  
The corrective action taken shall be documented and reported to levels of management.
Document Control Desk Washington, DC 20555 DOCKET 50-255 -LICENSE DPR-20 -PALISADES  
Contrary to the above, Consumers Power Company failed to assure that the corrective action taken in response to a previously identified EQ Severity Level IV violation was adequate in that the licensee failed to demons*trate the qualification of potted connectors used on Viking electrical penetrations.
PLANT -RESPONSE TO INSPECTION  
Insulation resistance (IR) measurements were not taken during the accident portion of the EQ test. These measurements are necessary to ensure that instrument accuracy requirements are met and that low voltage control circuits will perform their safety function during accident conditions.
REPORT 90005; NOTICE OF VIOLATION  
Reason For Violation It was previously identified in NRC Report 255/86032 that the EQ file for potted connectors used on containment electrica]
Kenneth W Berry Director Nuclear licensing  
penetrations did not OC0490-0330-NL04 i::i
Nuclear Regulatory  
* Nuclear Regulatory Commission
Commission (NRC) Inspection  
:Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 2 adequately address the effects of IR breakdown on the accuracy of associated instruments under the environmental conditions that could be expected during a loss of coolant accident (LOCA). The basis for this conclusion was that neither insulation resistance nor leakage current test data had been collected during simulated LOCA conditions.
Report 255/90005, dated March 22, 1990 documented  
Although test data was not available to demonstrate the adequacy of potted _connectors during a LOCA transient, test data was available to demonstrate that connector IR values are acceptable both before and after a LOCA, and that the potted connectors which serve EQ cuits will not fail catastrophically during an accident.
the results of an_examination  
In response to this observation, Consumers Power Company elected to qualify the potted connectors to the "Guidelines for Evaluating Environmental cation of Class lE Electrical Equipment in Operating Reactors", November 1979 (DOR Guidelines) by demonstrating that the connectors were manufactured and tested to Military Specification (MIL SPEC) C-5015G, "General Specification for Electrical Connectors, Circular Threaded, AN Type". The intended purpose of demonstrating that the connectors were manufactured and tested to the MIL SPEC was to allow the use of MIL SPEC C-5015G IR breakdown data as a cation basis. At the time that this qualification method was chosen, we believed that it satisfied DOR guidelines.
of previously  
Although the information contained in our EQ files provides reasonable ance that our potted connectors meet MIL SPEC requirements, we are unable to provide documentation that conclusively proves they were manufactured and tested to MIL SPEC C-5015G. As a result, it was concluded by the NRC tors that our use of MIL SPEC IR Breakdown data did not satisfy DOR lines, and that the qualification of our potted connectors remained undemonstrated.
iden-* tified environmental  
This lack of conclusive proof has resulted in a decision to replace the potted connectors.
qualification (EQ) inspection  
Corrective Action Taken And Results Achieved We have performed an operability determination for the EQ instrument circuits and control circuits associated with the potted connectors.
findings and resulted in the issuance of two violations.  
The results of this operability determination indicate that these connectors are acceptable for use until they can be replaced.
As was noted in the Inspection  
This operability determination was transmitted in our letters dated February 6, 1990 and February 7, 1990 and considered the impact of IR breakdown on circuit operation during a LOCA transient.
Report, we had implemented  
A follow-up response to NRC questions regarding the operability determinations was transmitted in our letter dated February 16, Corrective Actions Taken To Avoid Further Non-Compliance We are currently in the process of replacing the potted connectors that serve EQ circuits with qualified connectors and will update our EQ files to reflect the proper qualification requirements for these connectors.
corrective  
Date When Full Compliance Will Be Achieved_
actions to resolve all findings and concerns with one exception, the electrical  
Replacement of potted connectors and update of the EQ file for these tors is scheduled to be complete by the end of the 1990 Fall Refueling Outage. OC0490-0330-NL04   
penetration  
connector.  
In accordance  
with 10CFR2.201, our response to each of the identified  
examples of noncompliance  
follows: Violation  
50-255/90005-03 (DRS): 10CFR50, Appendix B, Criterion  
XVI, "Corrective  
Action" requires that measures be established  
to assure that conditions-adverse  
to quality, including formances, are promptly identified  
and corrected.  
In the case of significant  
conditions  
adverse to quality, the measures shall assure that the cause of the condition  
is determined  
and corrective  
action is taken to preclude repetition.  
The corrective  
action taken shall be documented  
and reported to  
levels of management.  
Contrary to the above, Consumers  
Power Company failed to assure that the corrective  
action taken in response to a previously  
identified  
EQ Severity Level IV violation  
was adequate in that the licensee failed to demons*trate  
the qualification  
of potted connectors  
used on Viking electrical  
penetrations.  
Insulation  
resistance (IR) measurements  
were not taken during the accident portion of the EQ test. These measurements  
are necessary  
to ensure that instrument  
accuracy requirements  
are met and that low voltage control circuits will perform their safety function during accident conditions.  
Reason For Violation  
It was previously  
identified  
in NRC  
Report 255/86032  
that the EQ file for potted connectors  
used on containment  
electrica]  
penetrations  
did not OC0490-0330-NL04  
i::i
* Nuclear Regulatory  
Commission  
:Palisades  
Plant Response to Inspection  
Report 9005; Notice of Violation  
April 23, 1990 2 adequately  
address the effects of IR breakdown  
on the accuracy of associated  
instruments  
under the environmental  
conditions  
that could be expected during a loss of coolant accident (LOCA). The basis for this conclusion  
was that neither insulation  
resistance  
nor leakage current test data had been collected  
during simulated  
LOCA conditions.  
Although test data was not available  
to demonstrate  
the adequacy of potted _connectors  
during a LOCA transient, test data was available  
to demonstrate  
that connector  
IR values are acceptable  
both before and after a LOCA, and that the potted connectors  
which serve EQ cuits will not fail catastrophically  
during an accident.  
In response to this observation, Consumers  
Power Company elected to qualify the potted connectors  
to the "Guidelines  
for Evaluating  
Environmental cation of Class lE Electrical  
Equipment  
in Operating  
Reactors", November 1979 (DOR Guidelines)  
by demonstrating  
that the connectors  
were manufactured  
and tested to Military Specification (MIL SPEC) C-5015G, "General Specification  
for Electrical  
Connectors, Circular Threaded, AN Type". The intended purpose of demonstrating  
that the connectors  
were manufactured  
and tested to the MIL SPEC was to allow the use of MIL SPEC C-5015G IR breakdown  
data as a cation basis. At the time that this qualification  
method was chosen, we believed that it satisfied  
DOR guidelines.  
Although the information  
contained  
in our EQ files provides reasonable ance that our potted connectors  
meet MIL SPEC requirements, we are unable to provide documentation  
that conclusively  
proves they were manufactured  
and tested to MIL SPEC C-5015G. As a result, it was concluded  
by the NRC tors that our use of MIL SPEC IR Breakdown  
data did not satisfy DOR lines, and that the qualification  
of our potted connectors  
remained undemonstrated.  
This lack of conclusive  
proof has resulted in a decision to replace the potted connectors.  
Corrective  
Action Taken And Results Achieved We have performed  
an operability  
determination  
for the EQ instrument  
circuits and control circuits associated  
with the potted connectors.  
The results of this operability  
determination  
indicate that these connectors  
are acceptable  
for use until they can be replaced.  
This operability  
determination  
was transmitted  
in our letters dated February 6, 1990 and February 7, 1990 and considered  
the impact of IR breakdown  
on circuit operation  
during a LOCA transient.  
A follow-up  
response to NRC questions  
regarding  
the operability  
determinations  
was transmitted  
in our letter dated February 16,  
Corrective  
Actions Taken To Avoid Further Non-Compliance  
We are currently  
in the process of replacing  
the potted connectors  
that serve EQ circuits with qualified  
connectors  
and will update our EQ files to reflect the proper qualification  
requirements  
for these connectors.  
Date When Full Compliance  
Will Be Achieved_  
Replacement  
of potted connectors  
and update of the EQ file for these tors is scheduled  
to be complete by the end of the 1990 Fall Refueling  
Outage. OC0490-0330-NL04   


Regulatory  
Regulatory Commission Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 This outage is currently scheduled to begin in September 1990. A detailed sunnnary of our current replacement schedule for the potted connectors was provided in our letter dated March 1, 1990. Violation 50-255/90005-04 (DRS): 10CFR50.49, Paragraph f, requires each item of electrical equipment important to safety be qualified by testing, or testing and analysis.
Commission  
3 Contrary to the above, the licensee identified auxiliary feedwater (AFW) control circuit relays R/0727 and R/07.49, located in a harsh environment, that were omitted from the EQ Master Equipment List and consequently not qualified by testing or testing and analysis.
Palisades  
Reason For Violation We identified that relays R/0727 and R/0749 were installed in junction boxes JL-263 and JL-264 during a walkdown of junction boxes located outside of containment that was being performed in order to identify junction boxes that were susceptible to flooding.
Plant Response to Inspection  
The affected relays are installed in related flow indication and flow control circuits for one train of the AFW system. Junction boxes JL-263 and JL-264 are both located in the component cooling water (CCW) pump room, which is classified as a harsh environment, and each contained one relay. Relays R/0727 and R/0749 were installed in 1982 as an Appendix R modification under Facility Change FC-407-14A.
Report 9005; Notice of Violation  
The purpose of this modification was to allow transfer of one train of AFW flow indication and flow control to the auxiliary hot shutdown control panel (C-150) following a fire in the Control Room. Although these relays are located in a harsh environment, they were not added to the EQ list during modification package preparation.
April 23, 1990 This outage is currently  
Exclusion of these relays from the EQ list resulted from inadequate rative control of the modification process, and inadequate communications between the personnel responsible for defining the EQ list and the personnel who prepared the AFW relay modification package. At the time when engineering and field implementation of the Facility Change were being performed, the EQ list for Palisades was in the process of being finalized.
scheduled  
Also, Plant cation procedures did not require evaluation of new equipment for potential addition to the EQ list. We concur with the NRC evaluation of this deficiency as an example of noncompliance.
to begin in September  
Corrective Action Taken And Results Achieved An engineering analysis (EA-PAL-90-014-1) has been performed for relays R/0727 and R/0749 in order to determine the potential effects of a harsh operating environment.
1990. A detailed sunnnary of our current replacement  
This analysis reached the following conclusions:
schedule for the potted connectors  
: 1. Relays R/0727 and R/0749 are normally de-energized and are only energized when AFW flow control and indication are transferred to the auxiliary hot shutdown panel following a fire in the Control Room. A OC0490-0330-NL04   
was provided in our letter dated March 1, 1990. Violation  
" Nuclear Regulatory Commission Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 harsh environment is not postulated in the CCW pump room during this event. 4 2. A credible failure mechanism could not be identified which would cause relays R/0727 and R/0749 to energize as a result of an adverse ing environmental, and thereby affect Control Room indication and control of AFW flow. 3. The redundant AFW train is fully qualified and does not contain a similar transfer relay installation in its control circuitry.
50-255/90005-04 (DRS): 10CFR50.49, Paragraph  
: 4. The contacts on relays R/0727 and R/0749 are only used for AFW flow indication and control circuits and could only affect operation of these circuits if the post-to-post or post-to-ground resistance decreased significantly.
f, requires each item of electrical  
A comparison of the electrical resistance for these relays and a States terminal block has been performed.
equipment  
The results of this comparative evaluation indicate that the expected decrease in electrical resistance for relays R/0727 and R/0749 under harsh environmental conditions would not result in a significant flow indication or flow control error. The States terminal block was chosen for this comparison because it has been tested and it has a similar base material composition and terminal post configuration as the affected relays. Based on the results of this engineering analysis, it can be determined that although relays R/0727 and R/0749 are not qualified, their ability to transfer AFW flow indication and flow control to the auxiliary hot shutdown panel following a fire in the Control Room is not adversely affected.
important  
This clusion is primarily based on the fact that harsh environmental conditions would not be expected in the CCW pump room during this event. Additionally, since the relays are de-energized except when AFW flow indication and flow control have been transferred to the auxiliary hot shutdown panel, it is not considered likely that subjecting the relays to a harsh environment would result in any abnormal operability affects during operations when AFW flow control and indication have not been transferred.
to safety be qualified  
We have also performed an evaluation of other circuits that are required to transfer indication and control from the Control Room to the auxiliary hot shutdown panel. The purpose of this evaluation was to determine if there were any other transfer circuitry components that should have been designated as EQ equipment and that were not included on the EQ list. No other transfer circuitry components were identified during the evaluation that should have been designated as EQ equipment.
by testing, or testing and analysis.  
Corrective Actions To Avoid Further Non-Compliance We are reviewing our current modification process to determine if it has adequate controls to ensure that new EQ equipment is added to the EQ list. Procedural controls added since the 1982 AFW relay modification require that an EQ evaluation is performed for each modification.
3 Contrary to the above, the licensee identified  
This EQ evaluation is reviewed by an individual who is familiar with EQ requirements and provides OC0490-0330-NL04 I I ' I *Nuclear Regulatory Commission Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 assurance that new EQ equipment is added to the EQ list. Additionally, a review is being performed to identify whether other equipment nee.ds to be added to the EQ list as a result of modifications that were performed by outside organizations and installed during the approximate 1981 to 1986 time frame. 5 We will also perform testing in order to qualify the relay contacts for R/0727 and R/0749 to the requirements of 10CFR50.49(k).
auxiliary  
This testing will include an evaluation of relay insulation resistance under harsh environmental conditions.
feedwater (AFW) control circuit relays R/0727 and R/07.49, located in a harsh environment, that were omitted from the EQ Master Equipment  
Date When Full Compliance Will Be Achieved During discussions with NRC Inspectors, we had previously stated that we would complete qualification of relays R/0727 and R/0749 by June 1, 1990. This schedule was predicated on our ability to obtain test data for these relays from other sources. We have been unable to obtain this data and must fore perform testing in order to obtain the necessary qualification data. As a result, final environmental testing and qualification of AFW relays R/0727 and R/0749 and incorporation of the EQ data into EQ files is now expected to be complete by September 1, 1990. Review of the adequacy of our current modification program EQ controls and of modifications prepared by outside organizations are expected .to be complete by June .1, 1990. Kenneth W Berry Director, Nuclear Licensing CC Administrator, Region III, USNRC NRC Resident Inspector  
List and consequently  
-Palisades OC0490-0330-NL04}}
not qualified  
by testing or testing and analysis.  
Reason For Violation  
We identified  
that relays R/0727 and R/0749 were installed  
in junction boxes JL-263 and JL-264 during a walkdown of junction boxes located outside of containment  
that was being performed  
in order to identify junction boxes that were susceptible  
to flooding.  
The affected relays are installed  
in related flow indication  
and flow control circuits for one train of the AFW system. Junction boxes JL-263 and JL-264 are both located in the component  
cooling water (CCW) pump room, which is classified  
as a harsh environment, and each contained  
one relay. Relays R/0727 and R/0749 were installed  
in 1982 as an Appendix R modification  
under Facility Change FC-407-14A.  
The purpose of this modification  
was to allow transfer of one train of AFW flow indication  
and flow control to the auxiliary  
hot shutdown control panel (C-150) following  
a fire in the Control Room. Although these relays are located in a harsh environment, they were not added to the EQ list during modification  
package preparation.  
Exclusion  
of these relays from the EQ list resulted from inadequate rative control of the modification  
process, and inadequate  
communications  
between the personnel  
responsible  
for defining the EQ list and the personnel  
who prepared the AFW relay modification  
package. At the time when engineering  
and field implementation  
of the Facility Change were being performed, the EQ list for Palisades  
was in the process of being finalized.  
Also, Plant cation procedures  
did not require evaluation  
of new equipment  
for potential  
addition to the EQ list. We concur with the NRC evaluation  
of this deficiency  
as an example of noncompliance.  
Corrective  
Action Taken And Results Achieved An engineering  
analysis (EA-PAL-90-014-1)  
has been performed  
for relays R/0727 and R/0749 in order to determine  
the potential  
effects of a harsh operating  
environment.  
This analysis reached the following  
conclusions:  
1. Relays R/0727 and R/0749 are normally de-energized  
and are only energized  
when AFW flow control and indication  
are transferred  
to the auxiliary  
hot shutdown panel following  
a fire in the Control Room. A OC0490-0330-NL04   
" Nuclear Regulatory  
Commission  
Palisades  
Plant Response to Inspection  
Report 9005; Notice of Violation  
April 23, 1990 harsh environment  
is not postulated  
in the CCW pump room during this event. 4 2. A credible failure mechanism  
could not be identified  
which would cause relays R/0727 and R/0749 to energize as a result of an adverse ing environmental, and thereby affect Control Room indication  
and control of AFW flow. 3. The redundant  
AFW train is fully qualified  
and does not contain a similar transfer relay installation  
in its control circuitry.  
4. The contacts on relays R/0727 and R/0749 are only used for AFW flow indication  
and control circuits and could only affect operation  
of these circuits if the post-to-post  
or post-to-ground  
resistance  
decreased  
significantly.  
A comparison  
of the electrical  
resistance  
for these relays and a States terminal block has been performed.  
The results of this comparative  
evaluation  
indicate that the expected decrease in electrical  
resistance  
for relays R/0727 and R/0749 under harsh environmental  
conditions  
would not result in a significant  
flow indication  
or flow control error. The States terminal block was chosen for this comparison  
because it has been tested and it has a similar base material composition  
and terminal post configuration  
as the affected relays. Based on the results of this engineering  
analysis, it can be determined  
that although relays R/0727 and R/0749 are not qualified, their ability to transfer AFW flow indication  
and flow control to the auxiliary  
hot shutdown panel following  
a fire in the Control Room is not adversely  
affected.  
This clusion is primarily  
based on the fact that harsh environmental  
conditions  
would not be expected in the CCW pump room during this event. Additionally, since the relays are de-energized  
except when AFW flow indication  
and flow control have been transferred  
to the auxiliary  
hot shutdown panel, it is not considered  
likely that subjecting  
the relays to a harsh environment  
would result in any abnormal operability  
affects during operations  
when AFW flow control and indication  
have not been transferred.  
We have also performed  
an evaluation  
of other circuits that are required to transfer indication  
and control from the Control Room to the auxiliary  
hot shutdown panel. The purpose of this evaluation  
was to determine  
if there were any other transfer circuitry  
components  
that should have been designated  
as EQ equipment  
and that were not included on the EQ list. No other transfer circuitry  
components  
were identified  
during the evaluation  
that should have been designated  
as EQ equipment.  
Corrective  
Actions To Avoid Further Non-Compliance  
We are reviewing  
our current modification  
process to determine  
if it has adequate controls to ensure that new EQ equipment  
is added to the EQ list. Procedural  
controls added since the 1982 AFW relay modification  
require that an EQ evaluation  
is performed  
for each modification.  
This EQ evaluation  
is reviewed by an individual  
who is familiar with EQ requirements  
and provides OC0490-0330-NL04
I I ' I *Nuclear Regulatory  
Commission  
Palisades  
Plant Response to Inspection  
Report 9005; Notice of Violation  
April 23, 1990 assurance  
that new EQ equipment  
is added to the EQ list. Additionally, a review is being performed  
to identify whether other equipment  
nee.ds to be added to the EQ list as a result of modifications  
that were performed  
by outside organizations  
and installed  
during the approximate  
1981 to 1986 time frame. 5 We will also perform testing in order to qualify the relay contacts for R/0727 and R/0749 to the requirements  
of 10CFR50.49(k).  
This testing will include an evaluation  
of relay insulation  
resistance  
under harsh environmental  
conditions.  
Date When Full Compliance  
Will Be Achieved During discussions  
with NRC Inspectors, we had previously  
stated that we would complete qualification  
of relays R/0727 and R/0749 by June 1, 1990. This schedule was predicated  
on our ability to obtain test data for these relays from other sources. We have been unable to obtain this data and must fore perform testing in order to obtain the necessary  
qualification  
data. As a result, final environmental  
testing and qualification  
of AFW relays R/0727 and R/0749 and incorporation  
of the EQ data into EQ files is now expected to be complete by September  
1, 1990. Review of the adequacy of our current modification  
program EQ controls and of modifications  
prepared by outside organizations  
are expected .to be complete by June .1, 1990. Kenneth W Berry Director, Nuclear Licensing  
CC Administrator, Region III, USNRC NRC Resident Inspector  
-Palisades  
OC0490-0330-NL04
}}

Revision as of 00:55, 17 August 2019

Responds to NRC 900322 Ltr Re Violations Noted in Insp Rept 50-255/90-05.Corrective Actions:Operability Determination for Environ Qualification Instrument Circuits & Control Circuits Associated W/Potted Connectors Performed
ML18054B572
Person / Time
Site: Palisades Entergy icon.png
Issue date: 04/23/1990
From: Berry K
CONSUMERS ENERGY CO. (FORMERLY CONSUMERS POWER CO.)
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9004270001
Download: ML18054B572 (5)


Text

  • consumers Power PDWERINli NtlCHlliAN'S PROGRESS General Offices: 1945 West Parnall Road, Jackson, Ml 49201 o (517) 788-1636 April 23, 1990 Nuclear Regulatory Commission Document Control Desk Washington, DC 20555 DOCKET 50-255 -LICENSE DPR-20 -PALISADES PLANT -RESPONSE TO INSPECTION REPORT 90005; NOTICE OF VIOLATION Kenneth W Berry Director Nuclear licensing Nuclear Regulatory Commission (NRC) Inspection Report 255/90005, dated March 22, 1990 documented the results of an_examination of previously iden-* tified environmental qualification (EQ) inspection findings and resulted in the issuance of two violations.

As was noted in the Inspection Report, we had implemented corrective actions to resolve all findings and concerns with one exception, the electrical penetration connector.

In accordance with 10CFR2.201, our response to each of the identified examples of noncompliance follows: Violation 50-255/90005-03 (DRS): 10CFR50, Appendix B, Criterion XVI, "Corrective Action" requires that measures be established to assure that conditions-adverse to quality, including formances, are promptly identified and corrected.

In the case of significant conditions adverse to quality, the measures shall assure that the cause of the condition is determined and corrective action is taken to preclude repetition.

The corrective action taken shall be documented and reported to levels of management.

Contrary to the above, Consumers Power Company failed to assure that the corrective action taken in response to a previously identified EQ Severity Level IV violation was adequate in that the licensee failed to demons*trate the qualification of potted connectors used on Viking electrical penetrations.

Insulation resistance (IR) measurements were not taken during the accident portion of the EQ test. These measurements are necessary to ensure that instrument accuracy requirements are met and that low voltage control circuits will perform their safety function during accident conditions.

Reason For Violation It was previously identified in NRC Report 255/86032 that the EQ file for potted connectors used on containment electrica]

penetrations did not OC0490-0330-NL04 i::i

  • Nuclear Regulatory Commission
Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 2 adequately address the effects of IR breakdown on the accuracy of associated instruments under the environmental conditions that could be expected during a loss of coolant accident (LOCA). The basis for this conclusion was that neither insulation resistance nor leakage current test data had been collected during simulated LOCA conditions.

Although test data was not available to demonstrate the adequacy of potted _connectors during a LOCA transient, test data was available to demonstrate that connector IR values are acceptable both before and after a LOCA, and that the potted connectors which serve EQ cuits will not fail catastrophically during an accident.

In response to this observation, Consumers Power Company elected to qualify the potted connectors to the "Guidelines for Evaluating Environmental cation of Class lE Electrical Equipment in Operating Reactors", November 1979 (DOR Guidelines) by demonstrating that the connectors were manufactured and tested to Military Specification (MIL SPEC) C-5015G, "General Specification for Electrical Connectors, Circular Threaded, AN Type". The intended purpose of demonstrating that the connectors were manufactured and tested to the MIL SPEC was to allow the use of MIL SPEC C-5015G IR breakdown data as a cation basis. At the time that this qualification method was chosen, we believed that it satisfied DOR guidelines.

Although the information contained in our EQ files provides reasonable ance that our potted connectors meet MIL SPEC requirements, we are unable to provide documentation that conclusively proves they were manufactured and tested to MIL SPEC C-5015G. As a result, it was concluded by the NRC tors that our use of MIL SPEC IR Breakdown data did not satisfy DOR lines, and that the qualification of our potted connectors remained undemonstrated.

This lack of conclusive proof has resulted in a decision to replace the potted connectors.

Corrective Action Taken And Results Achieved We have performed an operability determination for the EQ instrument circuits and control circuits associated with the potted connectors.

The results of this operability determination indicate that these connectors are acceptable for use until they can be replaced.

This operability determination was transmitted in our letters dated February 6, 1990 and February 7, 1990 and considered the impact of IR breakdown on circuit operation during a LOCA transient.

A follow-up response to NRC questions regarding the operability determinations was transmitted in our letter dated February 16, Corrective Actions Taken To Avoid Further Non-Compliance We are currently in the process of replacing the potted connectors that serve EQ circuits with qualified connectors and will update our EQ files to reflect the proper qualification requirements for these connectors.

Date When Full Compliance Will Be Achieved_

Replacement of potted connectors and update of the EQ file for these tors is scheduled to be complete by the end of the 1990 Fall Refueling Outage. OC0490-0330-NL04

Regulatory Commission Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 This outage is currently scheduled to begin in September 1990. A detailed sunnnary of our current replacement schedule for the potted connectors was provided in our letter dated March 1, 1990. Violation 50-255/90005-04 (DRS): 10CFR50.49, Paragraph f, requires each item of electrical equipment important to safety be qualified by testing, or testing and analysis.

3 Contrary to the above, the licensee identified auxiliary feedwater (AFW) control circuit relays R/0727 and R/07.49, located in a harsh environment, that were omitted from the EQ Master Equipment List and consequently not qualified by testing or testing and analysis.

Reason For Violation We identified that relays R/0727 and R/0749 were installed in junction boxes JL-263 and JL-264 during a walkdown of junction boxes located outside of containment that was being performed in order to identify junction boxes that were susceptible to flooding.

The affected relays are installed in related flow indication and flow control circuits for one train of the AFW system. Junction boxes JL-263 and JL-264 are both located in the component cooling water (CCW) pump room, which is classified as a harsh environment, and each contained one relay. Relays R/0727 and R/0749 were installed in 1982 as an Appendix R modification under Facility Change FC-407-14A.

The purpose of this modification was to allow transfer of one train of AFW flow indication and flow control to the auxiliary hot shutdown control panel (C-150) following a fire in the Control Room. Although these relays are located in a harsh environment, they were not added to the EQ list during modification package preparation.

Exclusion of these relays from the EQ list resulted from inadequate rative control of the modification process, and inadequate communications between the personnel responsible for defining the EQ list and the personnel who prepared the AFW relay modification package. At the time when engineering and field implementation of the Facility Change were being performed, the EQ list for Palisades was in the process of being finalized.

Also, Plant cation procedures did not require evaluation of new equipment for potential addition to the EQ list. We concur with the NRC evaluation of this deficiency as an example of noncompliance.

Corrective Action Taken And Results Achieved An engineering analysis (EA-PAL-90-014-1) has been performed for relays R/0727 and R/0749 in order to determine the potential effects of a harsh operating environment.

This analysis reached the following conclusions:

1. Relays R/0727 and R/0749 are normally de-energized and are only energized when AFW flow control and indication are transferred to the auxiliary hot shutdown panel following a fire in the Control Room. A OC0490-0330-NL04

" Nuclear Regulatory Commission Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 harsh environment is not postulated in the CCW pump room during this event. 4 2. A credible failure mechanism could not be identified which would cause relays R/0727 and R/0749 to energize as a result of an adverse ing environmental, and thereby affect Control Room indication and control of AFW flow. 3. The redundant AFW train is fully qualified and does not contain a similar transfer relay installation in its control circuitry.

4. The contacts on relays R/0727 and R/0749 are only used for AFW flow indication and control circuits and could only affect operation of these circuits if the post-to-post or post-to-ground resistance decreased significantly.

A comparison of the electrical resistance for these relays and a States terminal block has been performed.

The results of this comparative evaluation indicate that the expected decrease in electrical resistance for relays R/0727 and R/0749 under harsh environmental conditions would not result in a significant flow indication or flow control error. The States terminal block was chosen for this comparison because it has been tested and it has a similar base material composition and terminal post configuration as the affected relays. Based on the results of this engineering analysis, it can be determined that although relays R/0727 and R/0749 are not qualified, their ability to transfer AFW flow indication and flow control to the auxiliary hot shutdown panel following a fire in the Control Room is not adversely affected.

This clusion is primarily based on the fact that harsh environmental conditions would not be expected in the CCW pump room during this event. Additionally, since the relays are de-energized except when AFW flow indication and flow control have been transferred to the auxiliary hot shutdown panel, it is not considered likely that subjecting the relays to a harsh environment would result in any abnormal operability affects during operations when AFW flow control and indication have not been transferred.

We have also performed an evaluation of other circuits that are required to transfer indication and control from the Control Room to the auxiliary hot shutdown panel. The purpose of this evaluation was to determine if there were any other transfer circuitry components that should have been designated as EQ equipment and that were not included on the EQ list. No other transfer circuitry components were identified during the evaluation that should have been designated as EQ equipment.

Corrective Actions To Avoid Further Non-Compliance We are reviewing our current modification process to determine if it has adequate controls to ensure that new EQ equipment is added to the EQ list. Procedural controls added since the 1982 AFW relay modification require that an EQ evaluation is performed for each modification.

This EQ evaluation is reviewed by an individual who is familiar with EQ requirements and provides OC0490-0330-NL04 I I ' I *Nuclear Regulatory Commission Palisades Plant Response to Inspection Report 9005; Notice of Violation April 23, 1990 assurance that new EQ equipment is added to the EQ list. Additionally, a review is being performed to identify whether other equipment nee.ds to be added to the EQ list as a result of modifications that were performed by outside organizations and installed during the approximate 1981 to 1986 time frame. 5 We will also perform testing in order to qualify the relay contacts for R/0727 and R/0749 to the requirements of 10CFR50.49(k).

This testing will include an evaluation of relay insulation resistance under harsh environmental conditions.

Date When Full Compliance Will Be Achieved During discussions with NRC Inspectors, we had previously stated that we would complete qualification of relays R/0727 and R/0749 by June 1, 1990. This schedule was predicated on our ability to obtain test data for these relays from other sources. We have been unable to obtain this data and must fore perform testing in order to obtain the necessary qualification data. As a result, final environmental testing and qualification of AFW relays R/0727 and R/0749 and incorporation of the EQ data into EQ files is now expected to be complete by September 1, 1990. Review of the adequacy of our current modification program EQ controls and of modifications prepared by outside organizations are expected .to be complete by June .1, 1990. Kenneth W Berry Director, Nuclear Licensing CC Administrator, Region III, USNRC NRC Resident Inspector

-Palisades OC0490-0330-NL04