MONTHYEARIR 05000237/20230052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2023005; 05000249/2024005) ML24061A1702024-03-0101 March 2024 Request for Information for the NRC Age-Related Degradation Inspection: Inspection Report 05000237/2024010 and 05000249/2024010 IR 05000237/20230062024-02-28028 February 2024 Annual Assessment Letter for Dresden Nuclear Station, Units 2 and 3 (Report 05000237/2023006; 05000249/2023006) ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23087A0852023-03-28028 March 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000237/20220062023-03-0101 March 2023 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2022006 and 05000249/2022006) ML23037A9192023-02-0707 February 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000237/2023011 and 05000249/2023011 ML22318A1842022-11-15015 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000237/2023401; 05000249/2023401 ML22306A2172022-11-0202 November 2022 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20220052022-08-22022 August 2022 Updated Inspection Plan for Dresden Nuclear Power Station (Report 05000237/2022005; 05000249/2022005) ML22068A0862022-03-0909 March 2022 Reissue Dresden Nuclear Power Station, Units 2 and 3 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML22062B0522022-03-0404 March 2022 Information Request for an Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection IR 05000237/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000237/2021006 and 05000249/2021006) ML22027A3592022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000010, License No. DPR-2 IR 05000237/20220102021-12-21021 December 2021 Notification of NRC DBAI (Programs) and Initial RFI Inspection Report 05000237/2022010 05000249/2022010 ML21265A2262021-09-22022 September 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000237/2021004 05000249/2021004 IR 05000237/20210052021-09-0101 September 2021 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3, Report 05000237/2021005 and 05000249/2021005 ML21096A1752021-04-0606 April 2021 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000237/2021011; 05000249/2021011 IR 05000237/20200062021-03-0404 March 2021 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020006 and 05000249/2020006) ML20337A4242020-12-0202 December 2020 Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection 05000237/2021401 and 05000249/2021401 ML20302A4602020-10-28028 October 2020 Request for Information for an NRC Triennial Baseline Deisgn Bases Assurance Inspection (Team): Inspection Report 05000237/2021010; 05000249/202101 IR 05000237/20200052020-09-0101 September 2020 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020005 and 05000249/2020005) IR 05000237/20190062020-03-0303 March 2020 Annual Assessment Letter for Dresden, Units 2 and 3 (Report 05000237/2019006 and 05000249/2019006, 05000237/2019006 and 05000249/2019006) ML19290G5152019-10-15015 October 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20190052019-08-28028 August 2019 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2019005 and 05000249/2019005) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000237/20180062019-03-0404 March 2019 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018006 and 05000249/2018006) ML19008A3912019-01-0707 January 2019 Initial Information Request (Part 2) for the Upcoming Phase IV License Renewal Inspection, Dated 01/07/19 (DRS-J. Corujo-Sandin) IR 05000237/20180052018-08-28028 August 2018 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018005 and 05000249/2018005) IR 05000237/20170062018-03-0202 March 2018 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017006 and 05000249/2017006) IR 05000237/20170112018-01-0202 January 2018 NRC Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness Inspection Report 05000237/2017011 and 05000249/2017011 ML17354B0352017-12-20020 December 2017 U1: CY2018 Master Inspection Plan IR 05000237/20170052017-08-28028 August 2017 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017005 and 05000249/2017005) ML17240A2672017-08-25025 August 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Dresden, Units 2 and 3 ML17236A0742017-08-23023 August 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2017004; 05000249/2017004 IR 05000237/20160062017-03-0101 March 2017 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2016006 and 05000249/2016006) ML16351A1072016-12-15015 December 2016 Master Inspection Plan - Calendar Year 2017 IR 05000237/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3,(Report 05000237/2016005; 05000249/2016005) ML16242A0712016-08-26026 August 2016 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000237/2017007; 05000249/2017007 ML16070A1102016-03-0909 March 2016 Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000237/2016009; 05000249/2016009 IR 05000237/20150062016-03-0202 March 2016 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Inspection Report 05000237/2015006 and 05000249/2015006) ML16011A4852016-01-11011 January 2016 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 ML15357A1282015-12-21021 December 2015 Master Inspection Plan - Calendar Year 2016 ML15322A3722015-11-18018 November 2015 IR 05000237/2016008; 05000249/2016008 February 8 - 12, 2016; and February 22 - 26, 2016, Dresden Nuclear Power Station, Units 2 and 3; Request for Information for an NRC Pilot Component Design Bases Inspection IR 05000237/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2015005; 05000249/2015005) IR 05000237/20140012015-03-0404 March 2015 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3, (Report 05000237/2014001; 05000249/2014001) IR 05000237/20130012014-03-0404 March 2014 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2013001; 05000249/2013001) ML14003A2832014-01-0303 January 2014 Fire Protection Request for Information ML13308B2322013-11-0404 November 2013 Ltr 11/4/13 Dresden, Unit 2 and 3, Notification to Perform an Inspection of Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestone 1-7 and Request for Information IR 05000237-14-405; 05000249-144-40 ML13301A7352013-10-28028 October 2013 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Dresden Nuclear Power Station, Units 2 and 3 2024-08-28
[Table view] Category:Letter
MONTHYEARML24291A0272024-10-31031 October 2024 NRC Letter to C. Mayer Illinois SHPO Request to Initiate Section 106 Consultation for Subsequent License Renewal of Units 2 and 3 RS-24-103, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-10-21021 October 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors RS-24-102, Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-5912024-10-21021 October 2024 Supplement to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-591 RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24225A2132024-09-26026 September 2024 Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval ML24253A0942024-09-23023 September 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID L-2024-Sle-0002) (Docket Numbers: 50-237 and 50-249) ML24270A0332024-09-20020 September 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVPLTR 24-0030, ISFSI Annual Effluent Release Report2024-09-20020 September 2024 ISFSI Annual Effluent Release Report IR 05000237/20244022024-09-19019 September 2024 – Security Baseline Inspection Report 05000237/2024402 and 05000249/2024402 - (Public) ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24255A8642024-09-0606 September 2024 Rscc Wire & Cable LLC Dba Marmon Industrial Energy & Infrastructure - Part 21 Retraction of Final Notification ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000237/20230052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2023005; 05000249/2024005) ML24239A3972024-08-23023 August 2024 Rssc Wire & Cable LLC Dba Marmon - Part 21 Final Notification - 57243-EN 57243 IR 05000237/20240022024-08-14014 August 2024 Integrated Inspection Report 05000237/2024002 and 05000249/2024002 ML24215A2912024-08-14014 August 2024 Request for Withholding Information from Public Disclosure Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations IR 05000237/20240102024-08-0909 August 2024 NRC Age-Related Degradation Inspection Report 05000237/2024010 and 05000249/2024010 ML24157A0792024-08-0808 August 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID L-2024-Sle-0002) (Docket Numbers: 50-237, and 50-249) IR 05000237/20230112024-08-0707 August 2024 Reissue - Dresden Nuclear Power Station, Units 2 and 3 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 IR 05000237/20200012024-08-0606 August 2024 Reissue - Dresden Nuclear Power Station, Units 2 and 3 - Integrated Inspection Report 05000237/2020001 and 05000249/2020001 ML24184A1712024-08-0202 August 2024 SLRA Schedule Letter RS-24-073, Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information2024-07-31031 July 2024 Alternative Schedule to Complete Decommissioning Beyond 60 Years of Permanent Cessation of Operations – Additional Information Supporting Request to Withhold Security-Related Information ML24136A1322024-07-30030 July 2024 Transmittal Letter for Renewed License ML24208A0962024-07-25025 July 2024 57243-EN 57243 - Rssc Wire & Cable LLC, Dba Marmon - Part 21 Notification ML24193A0882024-07-24024 July 2024 Request for Withholding Information from Public Disclosure for Dresden Nuclear Power Station, Unit 1 Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations (Docket 50-10) ML24204A1862024-07-24024 July 2024 – Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2; TSTF-591, Revision 0; and 10 CFR 50.69 IR 05000237/20243012024-06-27027 June 2024 NRC Initial License Examination Report 05000237/2024301; 05000249/2024301 ML24138A0572024-06-26026 June 2024 – Issuance of Amendment Nos. 285 and 278 Application to Adopt TSTF-564, Safety Limit MCPR ML24138A1812024-06-18018 June 2024 Aging Management Audit Plan Regarding the Subsequent License Renewal Application Review ML24128A2742024-06-14014 June 2024 Notice of Acceptance and Opportunity for Hearing - Letter RS-24-063, Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-222024-06-14014 June 2024 Response to Request for Additional Information for 10 CFR 50.55a Request No. I5R-22 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24156A2332024-06-11011 June 2024 Letter Supplemental Information for Alternative Schedule to Complete Decommissioning Beyond 60-Years of Permanent Cessation of Operations ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24183A2752024-05-30030 May 2024 Registration of Use of Casks to Store Spent Fuel SVPLTR 24-0020, Registration of Use of Casks to Store Spent Fuel2024-05-30030 May 2024 Registration of Use of Casks to Store Spent Fuel RS-24-056, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2024-05-28028 May 2024 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24145A0432024-05-23023 May 2024 Registration of Use of Casks to Store Spent Fuel 10 CFR 72.212 SVPLTR 24-0019, Registration of Use of Casks to Store Spent Fuel2024-05-23023 May 2024 Registration of Use of Casks to Store Spent Fuel ML24158A0012024-05-22022 May 2024 License Amendment Request to Adopt TSTF-564 (EPID L-2023-LLA-0120) Illinois State Concurrence ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24135A0722024-05-10010 May 2024 Submittal of 2023 Annual Radiological Environmental Operating Report ML24129A1352024-05-0808 May 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, and TSTF-59 ML24134A1132024-05-0808 May 2024 Retraction: LER 2303-001-00 for Dresden Nuclear Power Station, Unit 2, HPCI Inoperable Due to Air Void Accumulation ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) 2024-09-06
[Table view] |
Text
August 31, 2006 Mr. Christopher M. Crane President and Chief Nuclear Officer
Exelon Nuclear
Exelon Generation Company, LLC
4300 Winfield Road
Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DRESDEN NUCLEAR POWER STATION
Dear Mr. Crane:
On August 7, 2006, the NRC staff completed its performance review of the Dresden Nuclear Power Station for the first half of the calendar year 2006 assessment cycle. Our technical staff
reviewed performance indicators (PIs) for the most recent quarter and inspection results over
the previous 12 months. The purpose of this lette r is to inform you of our assessment of yoursafety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as "Exempt from Public Disclosure in
Accordance with 10 CFR 2.390" will include the physical protection review and a resultant
inspection plan.
Plant performance for the most recent quarter at Dresden Units 2 and 3 was within the Licensee Response Column of the NRC's Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on performing inspection
procedure 71004, "Power Uprate," to inspect activities related to the steam dryer replacement
on Unit 3 during the fall 2006 refueling outage and plan to perform the same inspection
procedure during the proposed Unit 2 refueling outage in the fall 2007.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2008. The inspection plan is provided to allow for the resolution
of any scheduling conflicts and personnel availabilit y issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
In addition, the resident inspectors plan to perform Temporary Instruction 2515/169, "Mitigating
Systems Performance Index Verification," pr ior to the end of calendar year 2006. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).If circumstances arise which cause us to c hange the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any
questions you may have regarding this letter or the inspection plan.
Sincerely,/RA/Mark A. Ring, Chief Reactor Projects Branch 1
Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan DISTRIBUTION:
See next page C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public
Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),is accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).If circumstances arise which cause us to c hange the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any
questions you may have regarding this letter or the inspection plan.
Sincerely,/RA/Mark A. Ring, Chief Reactor Projects Branch 1
Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan DISTRIBUTION:
See next pageDOCUMENT NAME:G:\Branch TSS\ALL MOC\midcycle 2005 to 2006\dresden\Dresden MOC Letter 2006.wpdX Publicly Available G Non-Publicly Available G SensitiveX Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIERIIIRIIIRIIINAMEMRing:slsDATE08/16/2006 OFFICIAL RECORD COPY C. Crane-3-cc w/encl:Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager
Regulatory Assurance Manager - Dresden
Chief Operating Officer
Senior Vice President - Nuclear Services
Senior Vice President - Mid-West Regional
Operating Group
Vice President - Mid-West Operations Support
Vice President - Licensing and Regulatory Affairs
Director Licensing - Mid-West Regional
Operating Group
Manager Licensing - Dresden and Quad Cities
Senior Counsel, Nuclear, Mid-West Regional
Operating Group
Document Control Desk - Licensing
Assistant Attorney General
Illinois Emergency Management Agency
State Liaison Officer
Chairman, Illinois Commerce Commission
Will County Executive
Will County Sheriff Director, Will County Emergency
Management Agency Mayor of Joliet
City Manager of Joliet
Kendall County Board Chairman
Kendall County Sheriff
Grundy County Board Chairman
Grundy County Sheriff
Grundy County Emergency Management Agency
Mayor of Morris Minooka Village President
Mayor of Coal City
Mayor of Carbon Hill
Mayor of Diamond
Mayor of Braidwood
Mayor of Wilmington
Channahon Village President Channahon Village Administrator
Mayor of Shorewood Shorewood Village Administrator
Mayor of Elwood
INPO C. Crane ADAMS Distribution:
DXC1 TEB MXB RidsNrrDirslpab
JLC1 GEG KGO RML2 SRI Dresden
DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)
Dresden Inspection / Activity Plan 09/01/2006
-03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2006 12:57:48 Report 22 2 71004-POWER UPRATE Other Routine 04/01/2006 12/31/2006 2, 3 71004 IP Power Uprate 2 MOD5059-MODIFICATION/50.59 INSPECTION Baseline Inspections 09/18/2006 10/06/2006 2, 3 7111102 IP Evaluation of Changes, Tests, or Experiments Baseline Inspections 09/18/2006 10/06/2006 2, 3 7111117B IP Permanent Plant Modifications 2 TI-2515/169 MSPI VERIFICATION Safety Issues 10/01/2006 12/31/2006 2, 3 2515/169 IP Mitigating Systems Performance Index Verification 1 ISI-ISI BASELINE INSPECTION Baseline Inspections 11/13/2006 11/17/2006 2, 3 7111108G IP Inservice Inspection Activities - BWR 1 7112102-ALARA OUTAGE INSP Baseline Inspections 11/13/2006 11/17/2006 2, 3 7112101 IP A ccess Control to Radiologically Significant Areas Baseline Inspections 11/13/2006 11/17/2006 2, 3 7112102 IP A LARA Planning and Controls 1 ISFSI-ISFSI INSPECTION Other Routine 11/15/2006 12/15/2006 2, 3 60854 IP Preoperational Testing Of An ISFSI Other Routine 11/15/2006 12/15/2006 2, 3 60854.1 IP Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating P 4 ISFSI-ISFSI INSPECTION Other Routine 01/01/2007 03/31/2007 2 60855.1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 1 71122.02-TRANSPORTATION AND RADWASTE Baseline Inspections 01/08/2007 01/12/2007 2, 3 7112202 IP Radioactive Material Processing and Transportation 1 MAINT EF-MAINTENANCE EFFECTIVENESS Baseline Inspections 02/26/2007 03/02/2007 2, 3 7111112B IP Maintenance Effectiveness 1 71122.01-RADIOLOGICAL EFFLUENTS Baseline Inspections 03/05/2007 03/09/2007 2, 3 7112201 IP Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems Baseline Inspections 03/05/2007 03/09/2007 2, 3 71151 IP Performance Indicator Verification 1 7111401-EP EXERCISE & PI INSP Baseline Inspections 03/19/2007 03/23/2007 2, 3 7111401 IP Exercise Evaluation Baseline Inspections 03/19/2007 03/23/2007 2, 3 71151 IP Performance Indicator Verification 3 FY 2007-DRESDEN INIT PREP 04/2007 Not Applicable 04/02/2007 04/06/2007 2 W90160 OL - INITIAL EXAM - DRESDEN - APR/MAY 2007 5 CDBI-COMPONENT DESIGN BASES INSPECTION Baseline Inspections 04/16/2007 05/25/2007 2, 3 7111121 IP Component Design Bases Inspection 3 FY 2007-DRESDEN INIT EXAM 04&05/2007 Not Applicable 04/23/2007 05/04/2007 2 W90160 OL - INITIAL EXAM - DRESDEN - APR/MAY 2007 1 71121.01-RADIOLOGICAL ACCESS CONTROL Baseline Inspections 06/25/2007 06/29/2007 2, 3 7112101 IP A ccess Control to Radiologically Significant Areas This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Dresden Inspection / Activity Plan 09/01/2006
-03/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2006 12:57:48 Report 22 1 71121.01-RADIOLOGICAL ACCESS CONTROL Baseline Inspections 06/25/2007 06/29/2007 2, 3 71151 IP Performance Indicator Verification 1 71121.02-ALARA PROGRAM Baseline Inspections 10/29/2007 11/02/2007 2, 3 7112102 IP A LARA Planning and Controls Baseline Inspections 10/29/2007 11/02/2007 2, 3 71151 IP Performance Indicator Verification 1 ISI-ISI BASELINE INSPECTION Baseline Inspections 11/05/2007 11/09/2007 2 7111108G IP Inservice Inspection Activities - BWR 1 71121.03-INSTRUMENTATION & SCBA Baseline Inspections 02/11/2008 02/15/2008 2, 3 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment 3 FPI-TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 03/03/2008 03/21/2008 2, 3 7111105T IP Fire Protection [Triennial]
1 HEATSINK-HEAT SINK INSPECTION Baseline Inspections 03/24/2008 03/28/2008 2, 3 7111107B IP Heat Sink Performance This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.