Transmittal Letter for Renewed License
ML24136A132
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 07/30/2024
From: Beverly Smith
NRC/NRR/DNRL
To: Peters K
Vistra Operations Company
Shared Package
ML24136A131 List:
References
Download: ML24136A132 (1)


Text

Mr. Ken J. Peters Senior Vice President and Chief Nuclear Officer Attention: Regulatory Affairs Vistra Operations Company LLC Comanche Peak Nuclear Power Plant 6322 N FM 56 P.O. Box 1002 Glen Rose, TX 76043

SUBJECT:

ISSUANCE OF RENEWED FACILITY OPERATING LICENSE NOS. NPF-87 AND NPF-89 FOR COMANCHE PEAK NUCLEAR POWER PLANT, UNITS 1 AND 2

Dear Ken J. Peters:

The U.S. Nuclear Regulatory Commission (NRC) has issued Renewed Facility Operating License Nos. NPF-87 and NPF-89 to Vistra Operations Company LLC for Comanche Peak Nuclear Power Plant (Comanche Peak), Units 1 and 2, respectively. The NRC issued the renewed facility operating licenses upon completion of its review of your application dated October 3, 2022 (Agencywide Documents Access and Management System Package Accession No. ML22297A247), as supplemented by letters dated April 6, 2023 (ML23096A302),

April 24, 2023 (ML23114A377), and January 31, 2024 (ML24031A608).

Renewed Facility Operating License Nos. NPF-87 and NPF-89 for Comanche Peak expire at midnight on February 8, 2050, for Unit 1, and February 2, 2053, for Unit 2.

The technical basis for issuing the renewed facility operating licenses for Comanche Peak is set forth in Safety Evaluation Report Related to the License Renewal of Comanche Peak Nuclear Power Plant, Units 1 and 2, issued March 2024 (ML24078A230). to this letter is Renewed Facility Operating License No. NPF-87 and Technical Specifications for Comanche Peak, Unit 1. to this letter is Renewed Facility Operating License No. NPF-89 and Technical Specifications for Comanche Peak, Unit 2.

No changes were made to the Technical Specifications as a result of this license renewal.

The results of the environmental review related to the issuance of the renewed licenses are given in the record of decision provided as Enclosure 3 to this letter and in NUREG-1437, Supplement 60, Generic Environmental Impact Statement for License Renewal of Nuclear July 30, 2024 Plants Regarding License Renewal of Comanche Peak Nuclear Power Plant, issued April 2024 (ML24078A261). is a draft copy of the related Federal Register notice of issuance of the renewed licenses as sent to the Office of the Federal Register for publication.

If you have any questions regarding this matter, please contact the license renewal project manager, Mr. Mark Yoo, by email at Mark.Yoo@nrc.gov.

Sincerely, Brian W. Smith, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-445 and 50-446

Enclosures:

1. Comanche Peak Nuclear Power Plant, Unit 1, Renewed Facility Operating License and Technical Specifications
2. Comanche Peak Nuclear Power Plant, Unit 2, Renewed Facility Operating License and Technical Specifications
3. Record of Decision
4. Copy of Draft Federal Register Notice cc: Listserv Signed by Smith, Brian on 07/30/24

Package: ML24136A131 Letter: ML24136A132 Renewed License, Unit 1: ML24136A133 Renewed License, Unit 2: ML24136A134 Record of Decision: ML24136A135 Federal Register Notice: ML24136A136

  • via eConcurrence NRR-106 OFFICE PM: DNRL: NLRP* BC: DNRL: NLRP* LA: DNRL: NRLB* Tech Editor*

NAME MYoo LGibson KBratcher QTE DATE 05/15/2024 05/XX/2024 05/15/2024 05/28/2024 OFFICE PM: DORL* BC: DORL* BC: NMSS: REFS* BC: DNRL: NLRP*

NAME SLee JRankin SKoenick LGibson DATE 07/11/2024 06/05/2024 06/14/2024 06/21/2024 OFFICE OGC (NLO)* D: DNRL* OD: NRR D: DNRL*

NAME MCarpentier BSmith AVeil BSmith DATE 07/05/2024 07/30/2024 07/17/2024

Enclosure 1

Comanche Peak Nuclear Power Plant, Unit 1

Renewed Facility Operating License:

ADAMS Accession No. ML24136A133

Technical Specifications:

ADAMS Accession No. ML053180521

The Technical Specifications did not change as a result of the renewal of the license for Comanche Peak Nuclear Power Plant, Unit 1.

Enclosure 1 Enclosure 2

Comanche Peak Nuclear Power Plant, Unit 2

Renewed Facility Operating License:

ADAMS Accession No. ML24136A134

Technical Specifications:

ADAMS Accession No. ML053180525

The Technical Specifications did not change as a result of the renewal of the license for Comanche Peak Nuclear Power Plant, Unit 2.

Enclosure 2 Enclosure 3

Comanche Peak Nuclear Power Plant, Units 1 and 2 License Renewal Record of Decision

ADAMS Accession No. ML24136A135

Enclosure 3 Enclosure 4

Copy of the Draft Federal Register Notice of Renewed Facility Operating Licenses Comanche Peak Nuclear Power Plant, Units 1 and 2

ADAMS Accession No. ML24136A136

Enclosure 4