MONTHYEARML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23087A0852023-03-28028 March 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000237/20220062023-03-0101 March 2023 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2022006 and 05000249/2022006) ML23037A9192023-02-0707 February 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000237/2023011 and 05000249/2023011 ML22318A1842022-11-15015 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000237/2023401; 05000249/2023401 ML22306A2172022-11-0202 November 2022 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20220052022-08-22022 August 2022 Updated Inspection Plan for Dresden Nuclear Power Station (Report 05000237/2022005; 05000249/2022005) ML22068A0862022-03-0909 March 2022 Reissue Dresden Nuclear Power Station, Units 2 and 3 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection ML22062B0522022-03-0404 March 2022 Information Request for an Triennial 10 CFR 50.59 (Evaluation of Changes, Tests, and Experiments) Baseline Inspection IR 05000237/20210062022-03-0202 March 2022 Annual Assessment Letter (Report 05000237/2021006 and 05000249/2021006) ML22027A3592022-01-26026 January 2022 U1: CY2022 Inspection Plan, Docket No. 05000010, License No. DPR-2 IR 05000237/20220102021-12-21021 December 2021 Notification of NRC DBAI (Programs) and Initial RFI Inspection Report 05000237/2022010 05000249/2022010 ML21265A2262021-09-22022 September 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000237/2021004 05000249/2021004 IR 05000237/20210052021-09-0101 September 2021 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3, Report 05000237/2021005 and 05000249/2021005 ML21096A1752021-04-0606 April 2021 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000237/2021011; 05000249/2021011 IR 05000237/20200062021-03-0404 March 2021 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020006 and 05000249/2020006) ML20337A4242020-12-0202 December 2020 Information Request for the Cyber-Security Full Implementation Inspection, Notification to Perform Inspection 05000237/2021401 and 05000249/2021401 ML20302A4602020-10-28028 October 2020 Request for Information for an NRC Triennial Baseline Deisgn Bases Assurance Inspection (Team): Inspection Report 05000237/2021010; 05000249/202101 IR 05000237/20200052020-09-0101 September 2020 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2020005 and 05000249/2020005) IR 05000237/20190062020-03-0303 March 2020 Annual Assessment Letter for Dresden, Units 2 and 3 (Report 05000237/2019006 and 05000249/2019006, 05000237/2019006 and 05000249/2019006) ML19290G5152019-10-15015 October 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 IR 05000237/20190052019-08-28028 August 2019 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2019005 and 05000249/2019005) ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000237/20180062019-03-0404 March 2019 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018006 and 05000249/2018006) ML19008A3912019-01-0707 January 2019 Initial Information Request (Part 2) for the Upcoming Phase IV License Renewal Inspection, Dated 01/07/19 (DRS-J. Corujo-Sandin) IR 05000237/20180052018-08-28028 August 2018 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2018005 and 05000249/2018005) IR 05000237/20170062018-03-0202 March 2018 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017006 and 05000249/2017006) IR 05000237/20170112018-01-0202 January 2018 NRC Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness Inspection Report 05000237/2017011 and 05000249/2017011 ML17354B0352017-12-20020 December 2017 U1: CY2018 Master Inspection Plan IR 05000237/20170052017-08-28028 August 2017 Updated Inspection Plan for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2017005 and 05000249/2017005) ML17240A2672017-08-25025 August 2017 Information Request to Support Upcoming Temporary Instruction 2515/191 Inspection at Dresden, Units 2 and 3 ML17236A0742017-08-23023 August 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2017004; 05000249/2017004 IR 05000237/20160062017-03-0101 March 2017 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2016006 and 05000249/2016006) ML16351A1072016-12-15015 December 2016 Master Inspection Plan - Calendar Year 2017 IR 05000237/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3,(Report 05000237/2016005; 05000249/2016005) ML16242A0712016-08-26026 August 2016 Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000237/2017007; 05000249/2017007 ML16070A1102016-03-0909 March 2016 Request for Information for an NRC Pilot Design Bases Inspection on the Implementation of the Environmental Qualification Program Inspection Report 05000237/2016009; 05000249/2016009 IR 05000237/20150062016-03-0202 March 2016 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Inspection Report 05000237/2015006 and 05000249/2015006) ML16011A4852016-01-11011 January 2016 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Dresden Nuclear Power Station, Units 2 and 3 ML15357A1282015-12-21021 December 2015 Master Inspection Plan - Calendar Year 2016 ML15322A3722015-11-18018 November 2015 IR 05000237/2016008; 05000249/2016008 February 8 - 12, 2016; and February 22 - 26, 2016, Dresden Nuclear Power Station, Units 2 and 3; Request for Information for an NRC Pilot Component Design Bases Inspection IR 05000237/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2015005; 05000249/2015005) IR 05000237/20140012015-03-0404 March 2015 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3, (Report 05000237/2014001; 05000249/2014001) IR 05000237/20130012014-03-0404 March 2014 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2013001; 05000249/2013001) ML14003A2832014-01-0303 January 2014 Fire Protection Request for Information ML13308B2322013-11-0404 November 2013 Ltr 11/4/13 Dresden, Unit 2 and 3, Notification to Perform an Inspection of Temporary Instruction 2201/004, Inspection of Implementation of Interim Cyber Security Milestone 1-7 and Request for Information IR 05000237-14-405; 05000249-144-40 ML13301A7352013-10-28028 October 2013 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Dresden Nuclear Power Station, Units 2 and 3 ML13246A2172013-09-0303 September 2013 2013 Dresden MOC Letter Combined IR 05000237/20120012013-03-0404 March 2013 Annual Assessment Letter for Dresden Nuclear Power Station, Units 2 and 3 (Report 05000237/2012001 and 05000249/2012001) ML12277A1872012-10-0303 October 2012 ISI Request for Information 2023-07-06
[Table view] Category:Letter
MONTHYEARIR 05000237/20230042024-02-0202 February 2024 Integrated Inspection Report 05000237/2023004 and 05000249/2023004 IR 05000010/20230012024-01-17017 January 2024 NRC Inspection Report 05000010/2023001 (Drss) ML23354A2812024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0031 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-121, Sixth Ten-Year Interval Inservice Testing Program2023-11-30030 November 2023 Sixth Ten-Year Interval Inservice Testing Program SVPLTR 23-0037, Core Operating Limits Report for Cycle 292023-11-29029 November 2023 Core Operating Limits Report for Cycle 29 RS-23-119, Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information2023-11-10010 November 2023 Supplemental Information Letter for Part 73 Exemption Request - Responses to Request for Confirmatory Information ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums RS-23-107, Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-11-0808 November 2023 Relief Request I5R-22, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-102, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-10-16016 October 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23279A0712023-10-0606 October 2023 Response to NRC Dresden Nuclear Power Station, Units 2 and 3 - Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 ML23269A0662023-09-28028 September 2023 Proposed Alternative Request RV-23H Associated with the Sixth 10-Year Inservice Testing Interval ML23265A1322023-09-27027 September 2023 Proposed Alternative Request RV-03 Associated with the Sixth 10-Year Inservice Testing Interval ML23205A1362023-09-20020 September 2023 Proposed Alternative Request RV-02D Associated with the Sixth IST Interval IR 05000237/20230112023-09-0606 September 2023 Comprehensive Engineering Team Inspection Report 05000237/2023011 and 05000249/2023011 RS-23-071, Application to Adopt TSTF-564, Safety Limit MCPR2023-08-30030 August 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs IR 05000237/20234022023-08-29029 August 2023 Security Baseline Inspection Report 05000237/2023402 and 05000249/2023402 IR 05000237/20230022023-08-0808 August 2023 Integrated Inspection Report 05000237/2023002 and 05000249/2023002 ML23212A9892023-08-0303 August 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23174A1502023-08-0303 August 2023 Issuance of Amendment Nos. 282 and 275 Control Rod Scram Times ML23193A0052023-07-28028 July 2023 Subsequent License Renewal Application Public Meeting Summary of Pre-Submittal Meeting ML23192A6292023-07-11011 July 2023 Correction Letter - Issuance of Amendment Nos. 281 and 274 Regarding Transition to GNF3 Fuel (EPID L-2022-LLA-0121) (Non-Proprietary) ML23144A3142023-07-0606 July 2023 Issuance of Amendment Nos. 281 and 274 Transition to GNF3 Fuel (EPID L-2022-LLA-0121) - Nonproprietary ML23187A0462023-07-0606 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000237/2023004 ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III SVPLTR 23-0021, Registration of Use of Casks to Store Spent Fuel2023-06-20020 June 2023 Registration of Use of Casks to Store Spent Fuel RS-23-078, Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times2023-06-16016 June 2023 Supplement to License Amendment Request to Revise Technical Specification 3.1.4, Control Rod Scram Times RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20233012023-05-30030 May 2023 NRC Initial License Examination Report 05000237/2023301; 05000249/2023301 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23132A0932023-05-17017 May 2023 Information Meeting (Public Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Dresden Power Station, Units 2 and 3 RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0018, Submittal of 2022 Annual Radiological Environmental Operating Report2023-05-15015 May 2023 Submittal of 2022 Annual Radiological Environmental Operating Report IR 05000237/20230012023-05-0404 May 2023 Integrated Inspection Report 05000237/2023001 and 05000249/2023001 SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI IR 05000237/20234012023-04-26026 April 2023 Cyber Security Inspection Report 05000237/2023401 and 05000249/2023401 ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration IR 05000237/20235012023-04-21021 April 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000237/2023501 and 05000249/2023501 ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel SVPLTR 23-0014, Annual Dose Report for 20222023-04-15015 April 2023 Annual Dose Report for 2022 ML23088A2242023-04-0505 April 2023 Regulatory Audit Report Regarding License Amendment Request to Transition to GNF3 Fuel ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 2024-02-02
[Table view] |
Text
August 31, 2006 Mr. Christopher M. Crane President and Chief Nuclear Officer Exelon Nuclear Exelon Generation Company, LLC 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
DRESDEN NUCLEAR POWER STATION
Dear Mr. Crane:
On August 7, 2006, the NRC staff completed its performance review of the Dresden Nuclear Power Station for the first half of the calendar year 2006 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous 12 months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in Accordance with 10 CFR 2.390 will include the physical protection review and a resultant inspection plan.
Plant performance for the most recent quarter at Dresden Units 2 and 3 was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility. We also plan on performing inspection procedure 71004, Power Uprate, to inspect activities related to the steam dryer replacement on Unit 3 during the fall 2006 refueling outage and plan to perform the same inspection procedure during the proposed Unit 2 refueling outage in the fall 2007.
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2008. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
In addition, the resident inspectors plan to perform Temporary Instruction 2515/169, Mitigating Systems Performance Index Verification, prior to the end of calendar year 2006. The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan DISTRIBUTION:
See next page
C. Crane In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS),is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 630-829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Reactor Projects Branch 1 Division of Reactor Projects Docket Nos. 50-237; 50-249;72-037 License Nos. DPR-19; DPR-25
Enclosure:
Dresden Inspection/Activity Plan DISTRIBUTION:
See next page DOCUMENT NAME:G:\Branch TSS\ALL MOC\midcycle 2005 to 2006\dresden\Dresden MOC Letter 2006.wpd X Publicly Available G Non-Publicly Available G Sensitive X Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E RIII RIII RIII NAME MRing:sls DATE 08/16/2006 OFFICIAL RECORD COPY
C. Crane cc w/encl: Site Vice President - Dresden Nuclear Power Station Dresden Nuclear Power Station Plant Manager Regulatory Assurance Manager - Dresden Chief Operating Officer Senior Vice President - Nuclear Services Senior Vice President - Mid-West Regional Operating Group Vice President - Mid-West Operations Support Vice President - Licensing and Regulatory Affairs Director Licensing - Mid-West Regional Operating Group Manager Licensing - Dresden and Quad Cities Senior Counsel, Nuclear, Mid-West Regional Operating Group Document Control Desk - Licensing Assistant Attorney General Illinois Emergency Management Agency State Liaison Officer Chairman, Illinois Commerce Commission Will County Executive Will County Sheriff Director, Will County Emergency Management Agency Mayor of Joliet City Manager of Joliet Kendall County Board Chairman Kendall County Sheriff Grundy County Board Chairman Grundy County Sheriff Grundy County Emergency Management Agency Mayor of Morris Minooka Village President Mayor of Coal City Mayor of Carbon Hill Mayor of Diamond Mayor of Braidwood Mayor of Wilmington Channahon Village President Channahon Village Administrator Mayor of Shorewood Shorewood Village Administrator Mayor of Elwood INPO
C. Crane ADAMS Distribution:
DXC1 TEB MXB RidsNrrDirslpab JLC1 GEG KGO RML2 SRI Dresden DRPIII DRSIII PLB1 TXN ROPreports@nrc.gov (inspection reports, final SDP letters, any letter with an IR number)
Page 1 of 2 Dresden 08/30/2006 12:57:48 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71004 - POWER UPRATE 2 2, 3 IP 71004 Power Uprate 04/01/2006 12/31/2006 Other Routine MOD5059 - MODIFICATION/50.59 INSPECTION 2 2, 3 IP 7111102 Evaluation of Changes, Tests, or Experiments 09/18/2006 10/06/2006 Baseline Inspections 2, 3 IP 7111117B Permanent Plant Modifications 09/18/2006 10/06/2006 Baseline Inspections TI - 2515/169 MSPI VERIFICATION 2 2, 3 IP 2515/169 Mitigating Systems Performance Index Verification 10/01/2006 12/31/2006 Safety Issues ISI - ISI BASELINE INSPECTION 1 2, 3 IP 7111108G Inservice Inspection Activities - BWR 11/13/2006 11/17/2006 Baseline Inspections 7112102 - ALARA OUTAGE INSP 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 11/13/2006 11/17/2006 Baseline Inspections 2, 3 IP 7112102 ALARA Planning and Controls 11/13/2006 11/17/2006 Baseline Inspections ISFSI - ISFSI INSPECTION 1 2, 3 IP 60854 Preoperational Testing Of An ISFSI 11/15/2006 12/15/2006 Other Routine 2, 3 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating P 11/15/2006 12/15/2006 Other Routine ISFSI - ISFSI INSPECTION 4 2 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 01/01/2007 03/31/2007 Other Routine 71122.02 - TRANSPORTATION AND RADWASTE 1 2, 3 IP 7112202 Radioactive Material Processing and Transportation 01/08/2007 01/12/2007 Baseline Inspections MAINT EF - MAINTENANCE EFFECTIVENESS 1 2, 3 IP 7111112B Maintenance Effectiveness 02/26/2007 03/02/2007 Baseline Inspections 71122.01 - RADIOLOGICAL EFFLUENTS 1 2, 3 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems 03/05/2007 03/09/2007 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 03/05/2007 03/09/2007 Baseline Inspections 7111401 - EP EXERCISE & PI INSP 1 2, 3 IP 7111401 Exercise Evaluation 03/19/2007 03/23/2007 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 03/19/2007 03/23/2007 Baseline Inspections FY 2007 - DRESDEN INIT PREP 04/2007 3 2 W90160 OL - INITIAL EXAM - DRESDEN - APR/MAY 2007 04/02/2007 04/06/2007 Not Applicable CDBI - COMPONENT DESIGN BASES INSPECTION 5 2, 3 IP 7111121 Component Design Bases Inspection 04/16/2007 05/25/2007 Baseline Inspections FY 2007 - DRESDEN INIT EXAM 04&05/2007 3 2 W90160 OL - INITIAL EXAM - DRESDEN - APR/MAY 2007 04/23/2007 05/04/2007 Not Applicable 71121.01 - RADIOLOGICAL ACCESS CONTROL 1 2, 3 IP 7112101 Access Control to Radiologically Significant Areas 06/25/2007 06/29/2007 Baseline Inspections This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 2 Dresden 08/30/2006 12:57:48 Inspection / Activity Plan Report 22 09/01/2006 - 03/31/2008 Unit No. of Staff Planned Dates Inspection Number Inspection Activity Title on Site Start End Type 71121.01 - RADIOLOGICAL ACCESS CONTROL 1 2, 3 IP 71151 Performance Indicator Verification 06/25/2007 06/29/2007 Baseline Inspections 71121.02 - ALARA PROGRAM 1 2, 3 IP 7112102 ALARA Planning and Controls 10/29/2007 11/02/2007 Baseline Inspections 2, 3 IP 71151 Performance Indicator Verification 10/29/2007 11/02/2007 Baseline Inspections ISI - ISI BASELINE INSPECTION 1 2 IP 7111108G Inservice Inspection Activities - BWR 11/05/2007 11/09/2007 Baseline Inspections 71121.03 - INSTRUMENTATION & SCBA 1 2, 3 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 02/11/2008 02/15/2008 Baseline Inspections FPI - TRIENNIAL FIRE PROTECTION INSPECTION 3 2, 3 IP 7111105T Fire Protection [Triennial] 03/03/2008 03/21/2008 Baseline Inspections HEATSINK - HEAT SINK INSPECTION 1 2, 3 IP 7111107B Heat Sink Performance 03/24/2008 03/28/2008 Baseline Inspections This report does not include INPO and OUTAGE activities.