| title = Mid-Cycle Performance Review and Inspection Plan - LaSalle County Station, Units 1 and 2
| title = Mid-Cycle Performance Review and Inspection Plan - LaSalle County Station, Units 1 and 2
| author name = Riemer K R
| author name = Riemer K
| author affiliation = NRC/RGN-III/DRP/RPB2
| author affiliation = NRC/RGN-III/DRP/RPB2
| addressee name = Crane C M
| addressee name = Crane C
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| docket = 05000373, 05000374
| docket = 05000373, 05000374

Revision as of 21:13, 12 July 2019

Mid-Cycle Performance Review and Inspection Plan - LaSalle County Station, Units 1 and 2
ML072430200
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 08/31/2007
From: Kenneth Riemer
NRC/RGN-III/DRP/RPB2
To: Crane C
Exelon Generation Co, Exelon Nuclear
References
Download: ML072430200 (7)


Text

August 31, 2007 Mr. Christopher M. Crane President and Chief Nuclear Officer

Exelon Nuclear

Exelon Generation Company, LLC

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

LASALLE COUNTY STATION UNITS 1 AND 2

Dear Mr. Crane:

On August 14, 2007, the NRC staff completed its performance review of the LaSalle County Station Units 1 and 2 for the first half of the calendar year 2007 assessment cycle.

Our technical staff reviewed performance indicators (PIs) for the most recent quarter and

inspection results over the previous 12 months.

The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at

your facility.

This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Information" will include

the security cornerstone review and resultant inspection plan.

Plant performance for the most recent quarter at LaSalle County Station Units 1 and 2 was within the Licensee Response column of the NRC's Action Matrix, based on all inspection

findings being classified as having very low safety significance (Green) and all PIs indicating

performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to

conduct reactor oversight process (ROP) baseline inspections at your facility.

The enclosed inspection plan details the inspections, less those related to security, scheduled through December 31, 2008. The inspection plan is provided to allow for the resolution of any

scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.

Routine resident inspections are not listed due to their ongoing and continuous nature. Of note, the plan includes a component design bases inspection, a biennial PI&R inspection, and a

triennial fire protection inspection. The inspections in the last nine months of the inspection plan

are tentative and may be revised at the end-of-cycle review.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC

Public Document Room or from the Pub licly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

C. Crane The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the

inspection plan, we will contact you to discuss the change as soon as possible. Please contact

me at (630) 829-9628 with any questions you may have regarding this letter or the inspection

plan.Sincerely, /RA/Kenneth Riemer, Chief, Reactor Projects Branch 2

Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18

Enclosure:

LaSalle County Station Units 1 and 2 Inspection/Activity Plan DISTRIBUTION:

See next page C. Crane The NRC is currently evaluating the scope and frequency of all the baseline inspection procedures. If the results of the evaluation, or any other circumstances, cause us to change the

inspection plan, we will contact you to discuss the change as soon as possible. Please contact

me at (630) 829-9628 with any questions you may have regarding this letter or the inspection

plan.Sincerely, /RA/Kenneth Riemer, Chief Reactor Projects Branch 2

Division of Reactor Projects Docket Nos. 50-373; 50-374 License Nos. NPF-11; NPF-18

Enclosure:

LaSalle County Station Units 1 and 2 Inspection/Activity Plan DISTRIBUTION:

See next page DOCUMENT NAME: G:\Branch TSS\ALL MOC\midcycle 2006 to 2007\LaSalle\LASA 2007 MOC letter.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIINAMEKRiemer:dtpDATE08/31/07 OFFICIAL RECORD COPY Letter to C. Crane from K. Riemer dated August 31, 2007

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

LASALLE COUNTY STATION UNITS 1 AND 2cc w/encl:Site Vice President - LaSalle County Station LaSalle County Station Plant Manager

Regulatory Assurance Manager - LaSalle County Station

Chief Operating Officer

Senior Vice President - Nuclear Services

Senior Vice President - Mid-West Regional

Operating Group

Vice President - Mid-West Operations Support

Vice President - Licensing and Regulatory Affairs

Director Licensing - Mid-West Regional

Operating Group

Manager Licensing - Clinton and LaSalle

Senior Counsel, Nuclear, Mid-West Regional

Operating Group

Document Control Desk - Licensing

Assistant Attorney General

Illinois Emergency Management Agency

State Liaison Officer

Chairman, Illinois Commerce Commission

Grundy County Board Chairman

Mayor of Ottawa

Mayor of Streator

City Manager of Streator

Director, Grundy County Emergency Management

Agency Mayor of Seneca

Mayor of Grand Ridge

Mayor of Ransom

Sheriff, LaSalle County

LaSalle County Board Chairman

Director, LaSalle County Emergency Management

Agency Mayor of Marseilles

Mayor of Verona

Mayor of Kinsman

INPO Letter to C. Crane from K. Riemer dated August 31, 2007

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -

LASALLE COUNTY STATION UNITS 1 AND 2 DISTRIBUTION

RAG1 DMS6 TEB SPS1 RidsNrrDirslpab

JLC1 MAS KGO JKH3 RML2 SAM9 DEK DRPIII DRSIII PLB1 TXN LaSalle Inspection / Activity Plan 09/01/2007

-12/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/28/2007 Report 22 6 BI ENG-COMPONENT DESIGN BASES INSPECTION Baseline Inspections 08/27/2007 09/28/2007 1 7111121 IP Component Design Bases Inspection 2 BI OL-BIENNIAL REQUAL. PROGRAM INSPECTION Baseline Inspections 11/26/2007 11/30/2007 1 7111111B IP Licensed Operator Requalification Program 3 BI PI&R-BIENNIAL PI&R INSPECTION Baseline Inspections 11/26/2007 12/14/2007 1 71152B IP Identification and Resolution of Problems 1 BI ENG-ENGINEERING INSERVICE INSPECTION Baseline Inspections 02/11/2008 03/07/2008 1 7111108G IP Inservice Inspection Activities - BWR 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 02/18/2008 02/22/2008 1 7112101 IP A ccess Control to Radiologically Significant Areas Baseline Inspections 02/18/2008 02/22/2008 1 7112102 IP A LARA Planning and Controls 1 BI ENG-BIENNIAL MAINTENANCE EFFECTIVENESS INSP.

Baseline Inspections 03/24/2008 03/28/2008 1 7111112B IP Maintenance Effectiveness 3 BI EP-EP EXERCISE INSPECTION / PI VERIFICATION Baseline Inspections 04/28/2008 05/02/2008 1 7111401 IP Exercise Evaluation Baseline Inspections 04/28/2008 05/02/2008 1 71151-EP01 IP Drill/Exercise Performance Baseline Inspections 04/28/2008 05/02/2008 1 71151-EP02 IP ERO Drill Participation Baseline Inspections 04/28/2008 05/02/2008 1 71151-EP03 IP A lert & Notification System 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 05/19/2008 05/23/2008 1 7112103 IP Radiation Monitoring Instrumentation and Protective Equipment Baseline Inspections 05/19/2008 05/23/2008 1 71151-BI01 IP Reactor Coolant System Activity Baseline Inspections 05/19/2008 05/23/2008 1 71151-OR01 IP Occupational Exposure Control Effectiveness Baseline Inspections 05/19/2008 05/23/2008 1 71151-PR01 IP RETS/ODCM Radiological Effluent 1 BI ENG-BIENNIAL HEAT SINK INSPECTION Baseline Inspections 05/26/2008 05/30/2008 1 7111107B IP Heat Sink Performance 3 OL EXAM-LASALLE INITIAL LICENSE EXAM VALIDATION Not Applicable 07/28/2008 08/01/2008 1 W90184 LASALLE - INITIAL EXAM - JULY/AUG 2008 1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 08/25/2008 08/29/2008 1 7112101 IP A ccess Control to Radiologically Significant Areas Baseline Inspections 08/25/2008 08/29/2008 1 7112102 IP A LARA Planning and Controls 3 OL EXAM-LASALLE INITIAL LICENSE EXAMINATION Not Applicable 08/18/2008 08/29/2008 1 W90184 LASALLE - INITIAL EXAM - JULY/AUG 2008 2 BI OL-BIENNIAL REQUAL. PROGRAM INSPECTION Baseline Inspections 10/20/2008 10/24/2008 1 7111111B IP Licensed Operator Requalification Program This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

LaSalle Inspection / Activity Plan 09/01/2007

-12/31/2008 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/28/2007 Report 22 3 BI ENG-TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 12/01/2008 12/19/2008 1 7111105T IP Fire Protection [Triennial]

1 BI RP-RADIATION PROTECTION BASELINE INSPECTION Baseline Inspections 12/08/2008 12/12/2008 1 7112202 IP Radioactive Material Processing and Transportation This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.