ML13179A093: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 54: Line 54:
OEDO Region I AJohnson.
OEDO Region I AJohnson.
NRR RidsNrrDeEsgb Resource ADAMS Accession Nos.: Package ML 13178A358; Meeting Notice ML 13136A203; Meeting Handouts ML 13178A360 and M L13179A086:
NRR RidsNrrDeEsgb Resource ADAMS Accession Nos.: Package ML 13178A358; Meeting Notice ML 13136A203; Meeting Handouts ML 13178A360 and M L13179A086:
Meeting S ummary ML 1 31 7 9A093 \ *Via email OFFICE DORULPLI-21PM DE/SLS DORULPLI-21LA DORULPLI-2/BC 1 DORULPLI-21PM NAME PBamford KKarwoski ABaxter* VRodriguez  
Meeting S ummary ML 1 31 7 9A093 \ *Via email OFFICE DORULPLI-21PM DE/SLS DORULPLI-21LA DORULPLI-2/BC 1 DORULPLI-21PM NAME PBamford KKarwoski ABaxter* VRodriguez
:PBamford DATE 6/28/13 7/8113 07116/13 7117/13 17/17/13 i OFFICIAL RECORD COpy}}
:PBamford DATE 6/28/13 7/8113 07116/13 7117/13 17/17/13 i OFFICIAL RECORD COpy}}

Revision as of 18:58, 28 April 2019

6/17/2013 - Summary of Meeting with Exelon to Discuss Recent Once-Through Steam Generator Tube-to-Tube Wear at Three Mile Island, Unit 1
ML13179A093
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 07/17/2013
From: Bamford P J
Plant Licensing Branch 1
To:
Bamford P J
Shared Package
ML13178A358 List:
References
TAC MF1787
Download: ML13179A093 (4)


Text

UNITED STATES ",v'v "'1' ","!' ,",,,,,°11NUCLEAR REGULATORY COMMISSION t:: WASHINGTON, D.C. 20555*0001

<< 0 :;; 3: f fJ"J July17,2013

        • .jI(

Exelon Generation Company, LLC (Exelon)

Three Mile Island, Unit 1

SUMMARY

OF JUNE 17, 2013, MEETING WITH EXELON TO DISCUSS RECENT ONCE-THROUGH STEAM GENERATOR TUBE-TO-TUBE WEAR AT THREE MILE ISLAND, UNIT 1 (TAC NO. MF1787) On June 17, 2013, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives from Exelon Generation Company, LLC (Exelon, the licensee).

Representatives from AREVA (the vendor) also participated in the meeting. The purpose of the meeting was to discuss recent steam generator inservice inspection results at Three Mile Island, Unit 1 (TMI-1). Specifically, the meeting was held to discuss the results of the root cause investigation regarding tube-to-tube wear indications in the replacement once-through steam generators at TMI-1. This meeting was a follow-up to a meeting held on January 26,2012 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML 120270416), which discussed inspection results both at TMI-1 and Arkansas Nuclear One (ANO), Unit 1. The licensee presented background information regarding the inspection results from the fall of 2011, which was when the issue was discovered at TMI-1. The NRC staff asked if there were three wear indications at any elevation on any of the tubes. After the meeting, the licensee confirmed that there are two tubes in the 'A' steam generator that have three wear indications at one elevation.

There are none in 'B' steam generator.

The licensee provided trend data, updated since the previous meeting held on January 26, 2012, with data from the most recent refueling outage at ANO, Unit 1. The data generally shows that the growth rate tends to decrease as operating time accrues. The NRC staff questioned two instances where that did not seem to be the case. The licensee indicated that some differences would be expected in the observed data. The NRC staff also noted that it is apparent that the wear can initiate in cycles beyond the first operating cycle. The licensee and vendor postulated that this could happen due to variances in local conditions, including the actual heatup and cooldown process, at those specific tube locations, and/or inspection variability.

The licensee explained that when hot, the steam generator tubes are in compreSSion and when cold, the tubes are in tension. The licensee stated that the root cause of the tube-to-tube wear was a combination of four contributing causes: 1. Margin to buckling was non-conservative in the design, 2. The outside shell of the steam generator is cooler than the design value, 3. The tube preload is less tensile than the value used in the design analysis, and 4. Lateral loads/accelerations are sufficient to cause the observed wear.

-The first three contributing causes all tend to result in tube bowing, sufficient to cause tube-to-tube contact. Excitation forces created by either random turbulence or "flutter" (contributing cause number 4) are then sufficient to result in wear. The licensee does not plan to implement any operational restrictions as a result of this root cause analysis, however, further evaluation is planned in the upcoming refueling outage, including a full tube inspection and possibly performing field testing to measure the in-generator tube axial pre-load.

The licensee provided handouts that guided the meeting discussion.

A non-proprietary version of the handouts can be found at ADAMS Accession No. ML 13178A360.

A list of attendees is provided in the Enclosure.

Members of the public that participated in the meeting provided questions and comments that were addressed during the meeting. Meeting feedback forms were made available to the attendees, however, none were filled out and submitted to the NRC meeting contact. Please direct any inquiries to me at 301-415-2833 or peter.bamford@nrc.gov.

Peter Bamford Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.

List of cc w/encl: Distribution via LIST OF JUNE 17,2013, MEETING WITH EXELON GENERATION COMPANY, ONCE-THROUGH STEAM GENERATOR TUBE-TO-TUBE ROOT CAUSE INVESTIGATION RESULTS AT THREE MILE ISLAND, UNIT Exelon Jay Smith Mark Torborg James Barstow Stephanie Hanson John Piazza Wendy Croft Michael Fitzwater Randy Stewart AREVA Jeff Fleck TimWiger Dan Bauer Hasan Charkas John Remark Michael Street Craig Kelley PUBLIC (via teleconference)

Dennis Dyckman, PA state Scott Portzline, TMI Alert Dan Meatheany, Entergy Bob Clark, Entergy Peter Bamford, Office of Nuclear Reactor Regulation (NRR) Kenneth Karwoski, NRR Gloria Kulesa, NRR Veronica Rodriguez, NRR Gregory Makar, Office of New Reactors David Werkheiser, Region I (RI) James Trapp, RI Timothy O'Hara, RI Aloysius Obodoako, NRR Neil Sheehan, Office of Public Affairs Enclosure

-The first three contributing causes all tend to result in tube bowing, sufficient to cause tube-to-tube contact. Excitation forces created by either random turbulence or "flutter" (contributing cause number 4) are then sufficient to result in wear. The licensee does not plan to implement any operational restrictions as a result of this root cause analysis, however further evaluation is planned in the upcoming refueling outage, including a full tube inspection and possibly performing field testing to measure the in-generator tube axial pre-load.

The licensee provided handouts that guided the meeting discussion.

A non-proprietary version of the handouts can be found at ADAMS Accession No. ML 13178A360.

A list of attendees is provided in the Enclosure.

Members of the public that participated in the meeting provided questions and comments that were addressed during the meeting. Meeting feedback forms were made available to the attendees, however, none were filled out and submitted to the NRC meeting contact. Please direct any inquiries to me at 301-415-2833 or peter.bamford@nrc.gov.

Ira! Peter Bamford Plant Licensing Branch 1-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-289

Enclosure:

List of Attendees cc w/encl: Distribution via ListServ DISTRIBUTION:

PUBLIC RidsNrrPMThreeMilelsland Resource TWertz. NRR Branch Reading RidsNrrLAABaxter Resource KKarwoski.

NRR RidsAcrsAcnw_MailCTR Resource RidsRgnlMailCenter Resource AObodoako.

NRR RidsNrrDorlLpll-2 Resource VCampbeli.

OEDO Region I AJohnson.

NRR RidsNrrDeEsgb Resource ADAMS Accession Nos.: Package ML 13178A358; Meeting Notice ML 13136A203; Meeting Handouts ML 13178A360 and M L13179A086:

Meeting S ummary ML 1 31 7 9A093 \ *Via email OFFICE DORULPLI-21PM DE/SLS DORULPLI-21LA DORULPLI-2/BC 1 DORULPLI-21PM NAME PBamford KKarwoski ABaxter* VRodriguez

PBamford DATE 6/28/13 7/8113 07116/13 7117/13 17/17/13 i OFFICIAL RECORD COpy