ML071970172: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 15: | Line 15: | ||
=Text= | =Text= | ||
{{#Wiki_filter:}} | {{#Wiki_filter:July 19, 2007LICENSEE:PPL Susquehanna, LLC (PPL)FACILITY:Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2) | ||
==SUBJECT:== | |||
==SUMMARY== | |||
OF JUNE 29, 2007, CATEGORY 1 WORKING-LEVELMEETING WITH PPL TO DISCUSS STEAM DRYER ANALYSIS, LICENSING, DESIGN APPROACH, AND POWER ASCENSION TEST | |||
PLANSOn June 29, 2007, a public meeting was held between the U.S. Nuclear RegulatoryCommission (NRC), and representatives of PPL and its vendor, General Electric-Hitachi, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss PPL's steam dryer finite element analysis, licensing, design approach, and power ascension test plans. Certain portions of the meeting were closed to the public as some of the presentation material and discussion were determined to be proprietary in nature.PPL provided an overview of the SSES 1 and 2 replacement steam dryer licensing, design,instrumentation, and test plans for the proposed constant pressure power uprate (CPPU). | |||
PPL's conclusion is summarized as follows:(1) the steam dryer licensing basis is conservative and meets the American Society of Mechanical Engineers (ASME) fatigue limit of 13,600 pounds per square inch; (2) the fabricated replacement steam dryer will have reduced stress intensities and increased margins to the ASME fatigue limit;(3) the revised finite element model provides results less than the ASME limit; (4) the replacement steam dryer is designed and fabricated in accordance with Title 10 of the Code of Federal Regulations, Part 50, Appendix B using improved design and fabrication techniques;(5) the Unit 1 steam dryer will be instrumented for 107% current licensed thermal power (CLTP), will demonstrate structural adequacy of the new steam dryer design, and will validate dryer analysis tools;(6) the power ascension test program will be slow and deliberate, consists of an acceptancecriteria based on the 13,600 fatigue limit, will confirm no acoustic resonances at 114% | |||
CLTP, will allow validation of analysis and dryer design prior to full CPPU operation, and will confirm acceptability of the dryer up to full CPPU conditions. | |||
PPL Susquehanna, LLC- 2 -PPL also discussed its corrective actions related to a modeling input error in the finite elementanalysis, as well as its approach in responding to NRC staff's request for supplemental information (Agency Documents Access and Management System (ADAMS) Accession No. | |||
ML071920490). | |||
There were no members of the public in attendance, and no public meeting feedback forms were received. Enclosure 1 is a list of meeting attendees and Enclosure 2 is a non-proprietary copy of the licensee's slides presented at the meeting. A proprietary copy of the licensee's presentation slides can be found in ADAMS (Accession No. ML071980285). Please direct any inquiries to me at 301-415-1030, or rvg@nrc.gov./RA/Richard V. Guzman, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388 | |||
==Enclosures:== | |||
: 1. List of Attendees | |||
: 2. Licensee's Handouts/Slides (Non-Proprietary)cc w/encls: See next page | |||
ML071970172OFFICELPLI-1/PMLPLI-1/LALPLI-1/BCNAMERGuzmanSLittleMKowalDATE7/18/077/18/077/19/07 LIST OF ATTENDEESNUCLEAR REGULATORY COMMISSION (NRC)NUCLEAR REACTOR REGULATION (NRR) CATEGORY 1 MEETINGWITH PPL SUSQUEHANNA, LLC (PPL)REPLACEMENT STEAM DRYER ANALYSIS, DESIGN, AND TESTING PLANSFOR THE PROPOSED EXTENDED POWER UPRATE APPLICATIONSUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2JUNE 27, 2007NAME ORGANIZATION1. Richard GuzmanNRC/NRR/Plant Licensing Branch I-12. Kamal ManolyNRC/NRR/Mechanical and Civil Engineering Branch | |||
: 3. John WuNRC/NRR/Mechanical and Civil Engineering Branch | |||
: 4. Chakrapani BasavarajuNRC/NRR/Mechanical and Civil Engineering Branch | |||
: 5. William JessupNRC/NRR/Mechanical and Civil Engineering Branch | |||
: 6. Tom ScarbroughNRC/NRR/Component Performance and Testing Branch | |||
: 7. Tom AlexionNRC/NRR/Generic Communication and Power Uprate | |||
: 8. Rick PagodinPPL | |||
: 9. Micheal CrowthersPPL | |||
: 10. Michael GorskiPPL | |||
: 11. John BartosPPL | |||
: 12. John KraisPPL | |||
: 13. Kevin BrowningPPL | |||
: 14. Craig NicholsGeneral Electric - Hitachi | |||
: 15. Mike BridgesGeneral Electric - Hitachi | |||
: 16. Jim KlapprothGeneral Electric - Hitachi | |||
: 17. Larry KingGeneral Electric - Hitachi | |||
: 18. Rico BettiGeneral Electric - Hitachi | |||
: 19. Dan PapponeGeneral Electric - Hitachi | |||
: 20. Joseph FerranteNuclear Management Company - Monticello | |||
: 21. Shelly KuglerPublic Service Enterprise Group Nuclear - Hope Creek | |||
: 22. Jamie Mallon Public Service Enterprise Group Nuclear - Hope Creek | |||
: 23. Gary PavisConstellation Energy Group - Nine Mile Point | |||
: 24. Steve Hambric NRC Contractor | |||
: 25. Vic ShahNRC Contractor | |||
: 26. Samir ZiadaNRC ContractorEnclosure 1 MEETING SLIDES (Non-proprietary version)Enclosure 2 Susquehanna Steam Electric Station, Units 1 and 2 cc: | |||
Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Cornelius J. GannonVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Robert M. PaleyGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Supervisor -Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Ronald E. SmithGeneral Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Manager - Quality AssurancePPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc. | |||
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission | |||
475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township P.O. Box 405 Berwick, PA 18603-0035Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803}} |
Revision as of 21:37, 10 November 2018
ML071970172 | |
Person / Time | |
---|---|
Site: | Susquehanna |
Issue date: | 07/19/2007 |
From: | Guzman R V NRC/NRR/ADRO/DORL/LPLI-1 |
To: | |
Guzman R V, NRR/DORL, 415-1030 | |
References | |
Download: ML071970172 (7) | |
Text
July 19, 2007LICENSEE:PPL Susquehanna, LLC (PPL)FACILITY:Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2)
SUBJECT:
SUMMARY
OF JUNE 29, 2007, CATEGORY 1 WORKING-LEVELMEETING WITH PPL TO DISCUSS STEAM DRYER ANALYSIS, LICENSING, DESIGN APPROACH, AND POWER ASCENSION TEST
PLANSOn June 29, 2007, a public meeting was held between the U.S. Nuclear RegulatoryCommission (NRC), and representatives of PPL and its vendor, General Electric-Hitachi, at NRC Headquarters, One White Flint North, 11555 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss PPL's steam dryer finite element analysis, licensing, design approach, and power ascension test plans. Certain portions of the meeting were closed to the public as some of the presentation material and discussion were determined to be proprietary in nature.PPL provided an overview of the SSES 1 and 2 replacement steam dryer licensing, design,instrumentation, and test plans for the proposed constant pressure power uprate (CPPU).
PPL's conclusion is summarized as follows:(1) the steam dryer licensing basis is conservative and meets the American Society of Mechanical Engineers (ASME) fatigue limit of 13,600 pounds per square inch; (2) the fabricated replacement steam dryer will have reduced stress intensities and increased margins to the ASME fatigue limit;(3) the revised finite element model provides results less than the ASME limit; (4) the replacement steam dryer is designed and fabricated in accordance with Title 10 of the Code of Federal Regulations, Part 50, Appendix B using improved design and fabrication techniques;(5) the Unit 1 steam dryer will be instrumented for 107% current licensed thermal power (CLTP), will demonstrate structural adequacy of the new steam dryer design, and will validate dryer analysis tools;(6) the power ascension test program will be slow and deliberate, consists of an acceptancecriteria based on the 13,600 fatigue limit, will confirm no acoustic resonances at 114%
CLTP, will allow validation of analysis and dryer design prior to full CPPU operation, and will confirm acceptability of the dryer up to full CPPU conditions.
PPL Susquehanna, LLC- 2 -PPL also discussed its corrective actions related to a modeling input error in the finite elementanalysis, as well as its approach in responding to NRC staff's request for supplemental information (Agency Documents Access and Management System (ADAMS) Accession No.
There were no members of the public in attendance, and no public meeting feedback forms were received. Enclosure 1 is a list of meeting attendees and Enclosure 2 is a non-proprietary copy of the licensee's slides presented at the meeting. A proprietary copy of the licensee's presentation slides can be found in ADAMS (Accession No. ML071980285). Please direct any inquiries to me at 301-415-1030, or rvg@nrc.gov./RA/Richard V. Guzman, Senior Project ManagerPlant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388
Enclosures:
- 1. List of Attendees
- 2. Licensee's Handouts/Slides (Non-Proprietary)cc w/encls: See next page
ML071970172OFFICELPLI-1/PMLPLI-1/LALPLI-1/BCNAMERGuzmanSLittleMKowalDATE7/18/077/18/077/19/07 LIST OF ATTENDEESNUCLEAR REGULATORY COMMISSION (NRC)NUCLEAR REACTOR REGULATION (NRR) CATEGORY 1 MEETINGWITH PPL SUSQUEHANNA, LLC (PPL)REPLACEMENT STEAM DRYER ANALYSIS, DESIGN, AND TESTING PLANSFOR THE PROPOSED EXTENDED POWER UPRATE APPLICATIONSUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2JUNE 27, 2007NAME ORGANIZATION1. Richard GuzmanNRC/NRR/Plant Licensing Branch I-12. Kamal ManolyNRC/NRR/Mechanical and Civil Engineering Branch
- 3. John WuNRC/NRR/Mechanical and Civil Engineering Branch
- 4. Chakrapani BasavarajuNRC/NRR/Mechanical and Civil Engineering Branch
- 5. William JessupNRC/NRR/Mechanical and Civil Engineering Branch
- 6. Tom ScarbroughNRC/NRR/Component Performance and Testing Branch
- 7. Tom AlexionNRC/NRR/Generic Communication and Power Uprate
- 8. Rick PagodinPPL
- 9. Micheal CrowthersPPL
- 10. Michael GorskiPPL
- 11. John BartosPPL
- 12. John KraisPPL
- 13. Kevin BrowningPPL
- 14. Craig NicholsGeneral Electric - Hitachi
- 15. Mike BridgesGeneral Electric - Hitachi
- 16. Jim KlapprothGeneral Electric - Hitachi
- 17. Larry KingGeneral Electric - Hitachi
- 18. Rico BettiGeneral Electric - Hitachi
- 19. Dan PapponeGeneral Electric - Hitachi
- 20. Joseph FerranteNuclear Management Company - Monticello
- 21. Shelly KuglerPublic Service Enterprise Group Nuclear - Hope Creek
- 22. Jamie Mallon Public Service Enterprise Group Nuclear - Hope Creek
- 23. Gary PavisConstellation Energy Group - Nine Mile Point
- 24. Steve Hambric NRC Contractor
- 25. Vic ShahNRC Contractor
- 26. Samir ZiadaNRC ContractorEnclosure 1 MEETING SLIDES (Non-proprietary version)Enclosure 2 Susquehanna Steam Electric Station, Units 1 and 2 cc:
Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Cornelius J. GannonVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Robert M. PaleyGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Supervisor -Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Ronald E. SmithGeneral Manager - Site Preparedness and Services PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Manager - Quality AssurancePPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, EsqAssoc. General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.
212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission
475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township P.O. Box 405 Berwick, PA 18603-0035Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803