U-600667, Informs of Rev to FSAR Section 13.2.2.1.5 Re Accelerated Requalification of Licensed Operators.Rev Adds Condition That Operator Be Removed from Licensed Duties Until Retrained & Reexamined

From kanterella
(Redirected from U-600667)
Jump to navigation Jump to search
Informs of Rev to FSAR Section 13.2.2.1.5 Re Accelerated Requalification of Licensed Operators.Rev Adds Condition That Operator Be Removed from Licensed Duties Until Retrained & Reexamined
ML20203L414
Person / Time
Site: Clinton Constellation icon.png
Issue date: 08/21/1986
From: Spangenberg F
ILLINOIS POWER CO.
To: Butler W
Office of Nuclear Reactor Regulation
References
U-600667, NUDOCS 8608260187
Download: ML20203L414 (1)


Text

U-600667 L30-86 (08- 2 D-L 1A.120

/LLINDIS POWER COMPANY CLINTON POWER STATION. P.o. BOX 678, CLINTON, ILLINOIS 61727 August 21, 1986 Docket No. 50-461 Director of Nuclear Reactor Regulation Attention: Dr. W. R. Butler, Director BWR Project Directorate No. 4 '

Division of BWR Licensing U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

Clinton Power Station Final Safety Analysis Report (FSAR) Section 13.2 Training

Dear Dr. Butler:

Illinois Power is revising its position on accelerated requalification for licensed operators. FSAR Section 13.2.2.1.5

" Accelerated Retraining" will be revised to include the following condition for placing a licensed operator in the accelerated retraining program:

"Not meeting the NRC passing criteria for an annual exam.

In addition, the licensee shall be removed from all licensed duties until successful completion of the accelerated retraining program. Successful completion shall require a reexa=ination in each unsatisfactory category or a retake of the entire examination as deter-mined by the Director - Nuclear Training."

This change is expected to resolve NRC Staff concerns on this issue. The FSAR will be revised in a future amendment to reflect this change.

Please contact me if you have any questions on this matter.

Sincerely yours, G' t wf F.A.Spahgenbhg Manager - Licensing and Safety PJT/cke cc: B. L. Siegel, NRC Clinton Licensing Project Manager NRC Resident Office Illinois Department of Nuclear Safety Regional Administrator, Region III, USNRC \