Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML20153E233 | 26 August 1988 | Forwards Status of Site Stabilization Activities,Per R Auluck Request.Tva Has Completed All Major Site Stabilization Activities at Plant W/Only Minor Maint Activities Remaining | |
ML20133N732 | 24 October 1985 | Forwards Proposed Cancellation Plans for Plants Officially Canceled on 840829.Requests Withdrawal of CPPR-150,CPPR-152, CPPR-172 & CPPR-173.W/two Oversize Drawings | |
ML20134E321 | 14 August 1985 | Advises of Corporate Approval of Change in Planned Dates for Commercial Operation for coal-fired Inola Station,To Be Built on Site of Canceled Black Fox Station.Units 1 & 2 Scheduled for Completion in Dec 1996 & 1998,respectively | |
ML20132B415 | 12 June 1985 | Forwards Application for Waiver of Withdrawal Fees Under 10CFR170.12(b).NRC Delays in Issuance of CPs Deprived Util of Opportunity to Effect Withdrawal Before 1981 Operative Date of Regulation Charging Withdrawal Fees | |
ML18029A398 | 27 February 1985 | Responds to RM Diggs 850117 & 0211 Ltrs Re Determination of Fees for Const Extension Requests.Util Supports NRC Determination & Will Submit Fees | |
ML20096F873 | 5 September 1984 | Forwards Motion to Terminate Appellate Jurisdiction.W/O Encl.Related Correspondence | |
ML20091R572 | 8 June 1984 | Requests Precise Delineation of Applicable Regulations & Accounting of Prof Staff Hours Expended Re Review Costs Charged for Withdrawal of CP Application.Waiver of Any Interest Penalty Requested | |
ML20080F801 | 3 February 1984 | Requests Deletion of Gw Muench & Rl Range from Address Label | |
ML20023C336 | 12 May 1983 | Forwards Details of Deferral Plans for Yellow Creek Nuclear Plant. | |
ML20071B974 | 24 February 1983 | Reiterates 830121 Request for CP Extension Until 870901 to Permit Final Decision Re Future of Nuclear Units Based on Load Growth/Demand.Deferral Plan Details to Be Submitted by 830506 | |
ML20069D869 | 20 September 1982 | Forwards Black Fox Station Soil Stabilization & Erosion Control Program, Per ASLB 820618 Memorandum & Order.Plan Addresses Concerns Raised in NRC 820602 Submittal | |
ML20055C061 | 6 August 1982 | Forwards Info Re QA for Deferred Plants,In Response to NRC .Possible Cancellation of Some Units Will Be Discussed at Future Meeting of TVA Board of Directors | |
ML20054K888 | 29 June 1982 | Forwards Yellow Creek Nuclear Plant Socioeconomic Monitoring & Mitigation Rept YCNP-SMR-7, Jan-June 1981 | |
ML20054K153 | 23 June 1982 | Informs That Final Deficiency Repts for Listed Nonconformances Will Not Be Submitted Until Final Decision Is Made Re Const of Projects | |
ML20069B961 | 2 March 1982 | Informs of Changes Re Slowdown in Const Activities.Busing of Employees No Longer Justifiable Due to Lower Employment Levels & Const Schedule Changes.Waterfowl Wetlands Wildlife Monitoring Results Show Const Has Not Affected Wildlife | |
ML20041A561 | 16 February 1982 | Announces Cancellation of Black Fox Station,Confirming 820216 Verbal Notification.Site Will Be Preserved for Const of Future Power Generation Projects | |
ML20039B558 | 17 December 1981 | Forwards Yellow Creek Nuclear Plant Socioeconomic Monitoring & Mitigation Rept, Per Fes Section 4.5.2.5 | |
ML20039B705 | 11 December 1981 | Forwards Response to NRC 811203 Ltr Requesting Updated Info on Generic Issues A-10,A-31,A-36,A-42,A-43,A-44,A-45,A-46, A-47 & A-48 for SER Suppl.Svc List Encl | |
ML20039A281 | 4 December 1981 | Notifies That Environ Const Noise Monitoring Procedures Will Be Revised at Hartsville & Yellow Creek & Terminated at Phipps Bend.Changes Caused by Slowdown & Cessation of Const. Summary of Const Noise Monitoring Program History Encl | Siren |
ML20140B277 | 9 September 1981 | Forwards Amend 16 to Psar.Review Copies Forwarded w/810901 Ltr | |
ML20140B285 | 1 September 1981 | Forwards Amend 16 to Psar.Remaining Copies Forthcoming.Amend Begins New Vol of Psar,Designated as Addendum I | |
ML20009D931 | 8 July 1981 | Forwards Response to IE Bulletin 81-03, Flow Blockage of Cooling Water to Safety Sys Components by Corbicula Sp (Asiatic Clam) & Mytilus Sp (Mussel). | Biofouling |
ML20004B402 | 21 May 1981 | Responds to Violations Noted in IE Insp Repts 50-566/81-02 & 50-567/81-02 Re Failure to Establish Adequate Measures to Control Welding & Nondestructive Exam.Rept Revises 810330 Rept to Reflect Bend Sample Fissure Evaluation Results | |
ML19350D912 | 20 May 1981 | Forwards Yellow Creek Nuclear Plant Socioeconomic Monitoring & Mitigation Rept, Jan-June 1981 | |
ML19350C781 | 30 March 1981 | Responds to NRC 810304 Ltr Re Violations Noted in IE Insp Repts 50-566/81-02 & 50-567/81-02.Corrective Actions: Certification of Welders Previously Certified Were Revoked & Are Tracking Potentially Unacceptable Welds | |
ML19341D302 | 26 February 1981 | Forwards Revised Description of Onsite Meteorological Measurements Program.Revision Will Be Included in OL Application | |
ML19341A083 | 23 December 1980 | Responds to NRC 801125 Ltr Re Violations Noted in IE Insp Repts 50-566/80-17 & 50-567/80-17.Corrective Actions:Part Ii,Section 5.1 of Div of Nuclear Power Operational QA Manual Rewritten | |
ML19345D587 | 5 December 1980 | Forwards Socioeconomic Monitoring & Mitigation Rept, Semiannual Rept for Jul-Dec.Rept Prepared for Fes | |
ML19338G610 | 24 October 1980 | Requests Expedited Review of Newport News Industrial Corp Draft Topical Rept Re Vol Reduction Sys.Util Plans to Utilize Sys at Units 1 & 2 | |
ML19338G215 | 21 October 1980 | Forwards Response to NRC 800926 Lr Re Violation Noted in IE Insp Repts 50-566/80-14 & 50-567/80-14.Corrective Actions: Review of Concrete Test Dispositioned in Qcir 51057 Showed Design Strength Should Be Realized at Later than Design Age | |
ML19338G428 | 3 October 1980 | Submits Second Revised Response to Infraction Noted in IE Insp Repts 50-566/80-03 & 50-567/80-03.Corrective Actions: Radiographs Made Before 800207 re-examined for Deficiencies. Film Processing & Shim Placement Guidelines Established | |
ML19331D144 | 18 August 1980 | Forwards Revised Final Response to IE Insp Repts 50-566/ 80-03 & 50-567/80-03.Response Reflects Util Decision to Radiograph Addl Seven Welds.Rept Will Be Submitted by 801027 Re Film Darkening Problem,Per NRC Request | |
ML19338E124 | 18 August 1980 | Responds to NRC 800228 Ltr Re Violations Noted in IE Insp Repts 50-566/80-03 & 50-567/80-03.Corrective Actions: Radiographs Before 800207 re-examined & Radiographers Instructed in Requirements of Shim Placement | |
ML19320C024 | 11 July 1980 | Forwards Revised Final Deficiency Rept Re Placement of Earthfill in Essential Raw Cooling Water Spray Pond | |
ML19320C547 | 10 July 1980 | Forwards Final Deficiency Rept Re Const QA Audit | |
ML19320C537 | 10 July 1980 | Forwards Final Deficiency Rept Re Placement of Earthfill in ERCW Spray Pond | |
ML19320C225 | 9 July 1980 | Forwards Second Interim Deficiency Rept Re Const QA Audit. Next Rept Will Be Submitted by 800820.W/o Encl | |
ML19318B975 | 20 June 1980 | Advises That List of Matls to Be Used in Const of Fire Stops & Characteristics Re Flammability & Fire Retardancy Will Be Provided 1 Yr Subsequent to Receipt of CP | |
ML19318A375 | 13 June 1980 | Forwards Final Deficiency Rept Re Defective Concrete Pour in Auxiliary Bldg | |
ML19310A431 | 10 June 1980 | Responds to IE Insp Repts 50-566/80-03 & 50-567/80-03 Re Failure to Establish Adequate Measures to Control Radiography.Radiography of Welds Scheduled for Completion by 800701 | |
ML19312E485 | 27 May 1980 | Forwards First Interim Deficiency Rept Re Placement & Compaction of Concrete Pour A2-D1 | |
ML19316B071 | 27 May 1980 | Forwards First Interim Deficiency Rept Re Const QA Audit YC-C-80-05.Next Rept Will Be Submitted by 800710 | |
ML19323F136 | 21 May 1980 | Forwards First Interim Deficiency Rept Re Const QA Audit | |
ML19323J077 | 19 May 1980 | Responds to NRC 800424 Ltr Re Violations Noted in IE Insp Repts 50-566/80-07 & 50-567/80-07.Corrective Actions:Purge Air Blower Filters & Solenoid Valve Cleaned | |
ML19323G600 | 19 May 1980 | Advises That Ah Gutterman Will No Longer Appear in Proceedings on Behalf of Util | |
ML19309H495 | 5 May 1980 | Forwards Second Interim Deficiency Rept Re Incorrect Use of Inertia Resulting in shear-related,cross-sectional Property Calculations for Control Bldg | |
ML19309G416 | 28 April 1980 | Forwards Revised Response to Violation Noted in IE Insp Repts 50-566/80-03 & 50-567/80-03 Re Failure to Establish & Control Radiography.Film Interpreters & Radiographers Instructed in Shim Placement | |
ML19312E333 | 28 April 1980 | Responds to NRC 800228 Ltr Re Violations Noted in IE Insp Repts 50-566/80-03 & 50-567/80-03.Corrective actions:800324 & 0421 Submittals revised.Re-evaluation of Radiographs Showed Only Seven Welds Will Require Reradiographing | |
ML19312E342 | 21 April 1980 | Responds to NRC 800228 Ltr Re Violations Noted in IE Insp Repts 50-566/80-03 & 50-567/80-03.Advises That Revised Response to 800409 Ltr Will Be Submitted by 800428 | |
ML19344D669 | 21 April 1980 | Forwards First Interim Deficiency Rept Re Defective Concrete Pour in Auxiliary Bldg.Next Rept Will Be Submitted by 800613 |