Issue date | Title | Topic | |
---|---|---|---|
ML20217H871 | 15 October 1997 | Part 21 Rept Re Potential Safety Hazard for Some 3/4 Sch 40 Pipe Shipped to CP&L & VA Power Corp.Matl Has Been Found to Have Areas Where Wall Thickness Falls Below Minimum Allowed by SA 312 Specification.Customers Have Been Notified | |
ML20211M649 | 8 October 1997 | Addenda 1 to Part 21 Rept Re Weldments on Opposed Piston & Coltec-Pielstick Emergency stand-by Diesel gen-set lube-oil & Jacket Water Piping Sys.Revised List of Potentially Affected Utils to Include Asterisked Utils,Submitted | |
ML20211H791 | 30 September 1997 | Part 21 Rept Re Failure of Weldment Associated w/lube-oil Piping Sys on 970804 at Millstone,Unit 2.Root Cause Is Not Yet Known.Quality of Weldment Is Being Considered.Listed Util Sites Affected | |
ML18153A143 | 10 June 1997 | Part 21 Rept Re Possible Machining Defect in Certain Stainless Steel Swagelok Tube Fitting Bodies.Facilities Have Been Notified About Possible Problem | |
ML18153B084 | 26 September 1994 | Suppl to 940902 Initial Part 21 Rept Re Defect W/Governor Valves Used in turbine-driven Pumps Mfg by Dresser-Rand to Formally Addresss Written 30 Day Rept Requirement of 10CFR21(c)(3)(ii) | |
ML18153B060 | 2 September 1994 | Initial Part 21 Rept Re Steam Drive AFW Pump Governor Valve Mfg by Dresser-Rand.Maint Procedure to Stroke Governor Valve Stem Performed Weekly & Monitoring of Corrosion Build Up in Gland Seal Leakoff Area Performed Weekly | |
ML20059H772 | 17 January 1994 | Part 21 Rept Re Virginia Power Notifying Fairbands Morse Via Failure Analysis Rept NESML-Q-058 of Defective Air Start Distributor cam,16104412 | |
ML20059F263 | 7 January 1994 | Part 21 Rept Re Air Start Distributor Cam Mfg by Fairbanks Morse.Mfg Suggests That Site Referenced in Encl App I Inspect Air Start Distributor Cam as Soon as Practical | |
ML20044G543 | 26 May 1993 | Part 21 Rept Re Rosemount Model 1154 Series H Pressure Transmitters W/Temp Performance Characteristics Not in Compliance W/Specs.Vendor in Process of Notifying Customers.Sample Notification Ltr to Util Encl | |
ML20126F808 | 22 December 1992 | Part 21 Rept Re Possible Condition of Gag Plug in Cap of Valves That Cause Valves Not to Lift to Requirement for Providing Full Capacity.Affected Customers Notified.Removal of Caps &/Or Gag Plugs Recommended | |
ML18153D081 | 3 August 1992 | Interim Part 21 Rept Re Analysis of Klockner-Moeller Model NZM6-63,480 Volt Circuit Breakers.Initially Reported on 920701.Lever Fracture Should Be Examined to Determine If Any Cleaning Sprays or Purifying Agents Have Been Used | |
ML20101L966 | 1 July 1992 | Part 21 Rept Re Discovery of Klockner-Moeller 480-volt Breaker in Tripped Condition Due to Fracture of Plastic Arm within Breaker.Two of Three Failed Breakers Sent to Mfg for Analysis.Results Expected by End of Jul 1992 | |
ML20059M175 | 24 September 1990 | Supplemental Part 21 Rept 1 Re Defect in Coltec Industries, Inc Connecting Rod Assemblies Nuts/Bolts on Model 38TD8-1/8 Emergency Generators.Initially Reported on 851120.Nuts/bolts for Assemblies at Stated Plants Inspected & Replaced | |
ML20012C105 | 7 March 1990 | Part 21 Rept Re Several Failures of Fairbanks Morse Engine Div Piston Pins/Bushings on Upper Pistons.Caused by Incorrect Surface Pattern on Piston Pins.Piston Pins Under Listed Purchase Orders to Be Removed & Replaced | |
ML18153C101 | 2 February 1990 | Part 21 Rept Re Two of Three Pc Cards in GE Type SLV11A1 Over/Undervoltage Relays Failing to Produce Output.Short Between Leads Would Result in Damage to Component 1C5. Sketch of Threshold Detection Board Encl | |
ML20247D301 | 12 July 1989 | Part 21 Rept 10CFR21-0047 Re Control Wiring Insulation of Inner Jacket Used on General Motors Diesel Generator Sets Identified as 999 or MP Series.Encl List of Owners of Units Notified | |
ML20246K740 | 26 April 1989 | Part 21 Rept Re Incorrectly Stamped Name Plates on Certain Asco Nuclear Qualified Valves.Vendor Will Contact Each Affected Facility & Furnish Correctly Stamped Plates & in Near Future Discontinue Sale of Rebuild Kits for Valves | |
ML20205F321 | 10 October 1988 | Part 21 Rept Re Potential Deviation from Tech Spec Concerning Ry Indicators Due to Operating Temp Effect on Analog Meter Movement.Initially Reported on 881006.Customers Verbally Notified on 881006-07 | |
ML20153F415 | 12 August 1988 | Part 21 Rept Re Procurement of Heat Tracing Matls from Nelson Electric Corp Not Meeting 10CFR21 Requirements. Initially Reported on 880810.Nelson Electric Corp Removed from Approved safety-related Vendor List | |
ML20235U027 | 7 October 1987 | Part 21 Rept Re Westinghouse Plant Steam Generator Tubes Susceptible to High Cycle Fatigue Failure Similar to 870715 Event at North Anna Unit 1.Caused by Mean Stress in Tube & Superimposed Alternating Stress | Flow Induced Vibration |
ML20207T806 | 20 February 1987 | Part 21 & Deficiency Rept Re Defect in Recirculation Spray Hxs.Initially Reported on 870218.Original HX Design Did Not Consider External Pressurization of Diaphragm Seal Plate W/O Presence of Internal Pressure as Balance.Mods Scheduled | |
ML20211E166 | 28 January 1987 | Part 21 & Deficiency Rept Re Rockwell Engineering Co Steel Columns W/Laminations in Web.Initially Reported on 861112. Ultrasonic Testing of Suspect Matls Completed.Action Plan to Replace 13 Defective Columns Summarized | |
ML20214H752 | 12 November 1986 | Part 21 Rept Re Potential Defect in New Svc Water Spray Array Support Sys Mfg by Inland Steel Co.Initially Reported on 861107.Positive Identification & Ultrasonic Testing of Suspect Matls Will Be Completed by 861201 | |
ML20214F977 | 7 November 1986 | Part 21 Rept Re New Svc Water Spray Array Sys Supports Supplied by Inland Steel Co.Util Will Provide Positive Identification & Ultrasonic Testing Results of Suspect Matl. Identification Process Will Be Complete by 861201 | |
ML20206S084 | 30 June 1986 | Part 21 Rept Re Possible Cut Wires in Wire Harness of Bbc Brown Boveri K600/K800 Circuit Breakers.Initially Reported on 860509.Safety Implications Listed.Gear Guard Designed to Prevent Cut Wires | |
ML20197J637 | 12 May 1986 | Part 21 Rept Re Possibility of Power Supply hang-up When Energizing Slv Relays.Changes Made in Power Supply Circuitry.Slv Relays,W/Mods Incorporated in Latest Designs, Extensively Tested W/O Power Supply Failures | |
ML20137X389 | 27 February 1986 | Part 21 Rept Re Possible Defect in Model KMG-HRH Noble Gas Radiation Monitor W/Enhanced Detector Model KDGM-HR. Initially Reported on 860222.Vendor Will Request Utils for Listed Plants to Determine If Monitors Defective | |
ML20137S444 | 26 November 1985 | Part 21 Rept Re Unparallel Fitup of Nut to Mating Surface of Connecting Rod Cap & Nonperpendicular Faces of Nuts to Thread Pitch Line.Nuts & Bolts in Assembled Calvert Cliffs Onsite Spare Engine Will Be Replaced | |
ML20133B251 | 16 September 1985 | Part 21 Rept Re Defective Electronically Coded Vinyl Key Cards,Pyrotronics Model 1310,used for Security Electronic Access Control Sys.Initially Reported on 850913.Five Defective Cards Destroyed.New Cards Will Be Tested | |
ML20126C690 | 5 June 1985 | Part 21 Rept Re Generator Failure.Concurs W/Encl Louis Allis That Interpolar Connectors Be Removed | |
ML20127N062 | 13 May 1985 | Part 21 Rept Re Incorrect Short Time Delay Band Lever Inadequately Installed in Low Voltage K-line Circuit Breaker Electromechanical Overcurrent Trip Device.Visual Insp to Determine If Correct Lever Installed Recommended | |
RBG-18701, Attachment of Final Deficiency Rept DR-138 Re ITE-Gould Type 2150 Overload Relays Out of Calibr.Relays Sent Back & Replaced w/L10 Overload Relays.Response to Request for Addl Info Re Surry & North Anna SPDS Encl | 20 August 1984 | Attachment of Final Deficiency Rept DR-138 Re ITE-Gould Type 2150 Overload Relays Out of Calibr.Relays Sent Back & Replaced w/L10 Overload Relays.Response to Request for Addl Info Re Surry & North Anna SPDS Encl | Safe Shutdown |
ML20094D906 | 19 July 1984 | Interim Deficiency Rept,Item 176 Re Kerite Co Single Conductor Power Cables Damaged,But Undetected by Insp & Testing.Initially Reported on 840619.Final Rept by 841215 | |
ML20092D971 | 15 June 1984 | Part 21 Rept Re Thermal Nonrepeatability & Other Calibr Errors in Barton Lot 1 Transmitters.Initially Reported on 840615.Transmitter Defects Identified & Expected Error Deviations Calculated.Utils Notified | |
ML20088A623 | 28 March 1984 | Part 21 Rept Re Abnormal Wear on Linear Converter Units Mfg & Furnished to Power Generating Facilities.Caused by Actuator Hunting.All Customers Provided Field Lubrication Procedure | |
ML20081C511 | 9 March 1984 | Part 21 Rept Re Status Update Concerning Abnormal Wear on Linear Converters.Test Program Underway.Results of Investigation Indicate Excessive Wear Caused by Hunting of Control Circuitry | |
ML20086N042 | 2 January 1984 | Final Part 21 Rept Re Potential Problem Concerning Radiography of Branch Connection Welds Covered by Reinforcing Pads.Welds at Byron,Braidwood & North Anna Acceptable.Weld 7 at Clinton Reradiographed | |
PLA-1902, Interim Deficiency Rept Re Isolation of Nitrogen Makeup Sys. Also Reportable Per Part 21.Initially Reported on 830912. Permanent Design Mod Will Be Implemented.Final Rept Will Be Submitted in Dec 1983 | 10 October 1983 | Interim Deficiency Rept Re Isolation of Nitrogen Makeup Sys. Also Reportable Per Part 21.Initially Reported on 830912. Permanent Design Mod Will Be Implemented.Final Rept Will Be Submitted in Dec 1983 | |
ML20086N238 | 4 October 1983 | Supplemental Part 21 Rept Re Radiographic Record Evaluation, Supplying Addl Data to 830624 Submittal.Records Show That 90 Degree Branch Connections Furnished to North Anna 1 & 2 Jobsites.No Nozzles Supplied to Zimmer.Related Info Encl | |
PLA-1872, Second Interim Deficiency Rept Re GE Reactor Mode Switch. Initially Reported on 830407.Mode Switch Redesigned.Sample Will Be Independently Tested.Also Reported Per Part 21.Final Rept Will Be Submitted by Dec 1983 | 30 September 1983 | Second Interim Deficiency Rept Re GE Reactor Mode Switch. Initially Reported on 830407.Mode Switch Redesigned.Sample Will Be Independently Tested.Also Reported Per Part 21.Final Rept Will Be Submitted by Dec 1983 | |
ML20023E054 | 27 May 1983 | Deficiency Rept Re Narrow Range Resistance Temp Detectors Installed to Meet License Condition Failing to Operate.Cause Under Investigation.Detectors Replaced.Testing Modified Until Design Revised.Also Reportable Per Part 21 | |
ML20023C510 | 6 May 1983 | Final Deficiency Rept Re Nonconforming Class IE Radiation Monitoring Sys Electronic Modules Mfg by Victoreen,Inc Due to Breakdown of QA Program.Initially Reported on 820917. Vendor Revised QA Program Reviewed & Approved | |
ML20050A892 | 12 March 1982 | Interim Part 21 Rept Re 1/2-inch & 3/8-inch Plates Used in Category 1 Seismic Supports,Initially Reported 820310. Supports Containing 3/8-inch Plates Examined & hands-on Search of 1/2-inch Matl Conducted.Reportable Per Part 21 | |
ML20039C144 | 18 December 1981 | Final Deficiency Rept Re Failure of RHR Sys LPCI Injection Valve 1F017-B,initially Reported 811120.Locking Mechanism Devised to Attach anti-rotation Pin to Stem Collar.Also Reported Per Part 21 | Anchor Darling |
ML20011A713 | 19 October 1981 | Final Deficiency Rept Re Inlet Piping Configurations for Pressurizer Safety Relief Valves W/Large Pressure Drops Possibly Leading to Valve Chatter,Initially Reported 810916. Inlet Piping Design Will Be Revised to Limit Pressure Loss | |
ML20010G676 | 9 September 1981 | Final Deficiency Rept Re Available NPSH for Recirculation Spray Pumps,Originally Reported on 770812.Recirculation Spray Pump Arrangement Has Been Modified to Set Pumps Lower in Elevation.Assumptions Used Are Conservative | |
ML20010C611 | 14 August 1981 | Part 21 Rept Re Potential for Stress Corrosion Cracking of Anchor Bolts,Originally Reported on 810813.Utils That Have Plants for Which Vendor Has Supports & Restraints Design Responsibility Will Be Notified of Problem | |
ML20010J180 | 13 August 1981 | Supplemental Deficiency Rept Re Max Dose Rates on Containment Floor Exceeding Values Presented in FSAR, Initially Reported 780428.Addl Schielding Adequate to Reduce Max Containment Dose Rates.Supporting Documentation Encl | |
ML20009F957 | 20 July 1981 | Interim Deficiency Rept Re Structural Integrity of Certain RCS Attached Pipe Not Verified for Postulated Breaks in RCS Piping,Originally Reported on 810129.Actions Will Be Taken to Ensure Adequacy of Design.Also Reported Per Part 21 | |
ML20003E419 | 30 March 1981 | Interim Deficiency Rept Re Spurious Opening of Turbine Bypass Valves,Initially Reported 810309.Opening of Valves Could Result in DNBR Limits Being Exceeded.Also Reported Per Part 21 |