PLA-5574, November 2002 Monthly Operating Report for Susquehanna Steam Electric Station

From kanterella
(Redirected from PLA-5574)
Jump to navigation Jump to search
November 2002 Monthly Operating Report for Susquehanna Steam Electric Station
ML023610188
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 12/13/2002
From: Richard Anderson
Susquehanna
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PLA-5574, R41-2A
Download: ML023610188 (7)


Text

't I i Richard L. Anderson PPL Susquehanna, LLC Vice President - Nuclear Operations 769 Salem /Boulevard Berwick, PA 18603 Tel. 570.542.3883 Fax 570.542.1504 RLAnderson @pplweb corn

  • TM December 13, 2002 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Mail Station OPI-17 Washington, D.C. 20555 SUSQUEHANNA STEAM ELECTRIC STATION MONTHLY OPERATING REPORTS Docket Nos. 50-387/NPF-14 and 50-3881NPF-22 PLA-5574 R41-2A The November 2002 Monthly Operating Reports for Susquehanna SES Units I and 2 are attached.

Very truly yours, JJHI/cmm cc: NRC Region 1 NRC Sr. Resident Inspector, Mr. S. Hansell NRC Sr. Project Manager, Mr. T. G. Colburn NRC Project Manager, Mr. E. M. Thomas

OPERATING DATA REPORT DOCKET NO. 50-387 UNIT One DATE 12/13/02 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 OPERATING STATUS

1. Unit Name: Susquehanna Steam Electric Station (U 1)
2. Reporting Period: November 2002
3. Design Electrical Rating (Net MWe): 1115
4. Maximum Dependable Capacity (Net MWe): 1105 This Month Yr.-to-Date Cumulative
5. Hours in Reporting Period 720 8,016 170,785
6. Number of Hours Reactor Was Critical 720 6,818.3 141,120.5
7. Hours Generator On-Line 720 6,749.8 138,909.8
8. Unit Reserve Shutdown Hours 0 0 0
9. Net Electrical Energy Generated (MWH) 801,384 7,194,733 142,421,642 NOTES:

Page 1 of 1

UNIT SHUTDOWNS DOCKET NO. 50-387 UNIT One DATE 12/13/02 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 REPORT MONTH November 2002 No. Date Type Duration Reason Method of Cause & Corrective Action I (Hours) 2 Shutting To Prevent Recurrence Down Reactor 3 No Shutdowns this month.

Summary: The only significant power change during November was a reduction to 82% for a control rod sequence exchange on 11/23102.

I1. 2. 3.

F. Forced Reason: Method:

S. Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continuation from previous month E - Operator Training & Licensee Exam 5 - Other F - Administrative G - Operational Error (Explain)

Page 1 of I

SUSQUEHANNA STEAM ELECTRIC STATION Docket Number: 50-387 Dale: 12/13/02 Completed by: J. J. Hennings Telephone: (570) 542-3747 Challenjes to Main Steam Safety Relief Valves None.

OPERATING DATA REPORT DOCKET NO. 50-388 UNIT Two DATE 12/13/02 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 OPERATING STATUS

1. Unit Name: Susquehanna Steam Electric Station (U2)
2. Reporting Period: November 2002
3. Design Electrical Rating (Net MWe): 1117
4. Maximum Dependable Capacity (Net MWe): 1111 This Month Yr.-to-Date Cumulative
5. Hours in Reporting Period 720 8016 ,156,025
6. Number of Hours Reactor Was Critical 720 7,748.4 135,405.4
7. Hours Generator On-Line 720 7,696 0 ,133,462.7
8. Unit Reserve Shutdown Hours 0 0 0
9. Net Electrical Energy Generated (MWH) 802,039 8,479,103 139,283,933 NOTES:

Page 1 of 1

UNIT SHUTDOWNS DOCKET NO. 50-388 UNIT Two DATE 12/13/02 COMPLETED BY J. J. Hennings TELEPHONE (570) 542-3747 REPORT MONTH November 2002 No. Date Type Duration Reason Method of Cause & Corrective Action 1 (Hours) 2 Shutting to Prevent Recurrence Down Reactor 3

No shutdowns in November.

Summary: A control rod sequence exchange was performed on 11/02/02, at 83% power. Power reductions of approximately 10% were conducted for control rod adjustments on 11/9, 11/16 and 11/30.

1. 2. 3.

F. Forced Reason: Method:

S. Scheduled A - Equipment Failure (Explain) 1 - Manual B - Maintenance or Test 2 - Manual Scram C - Refueling 3 - Automatic Scram D - Regulatory Restriction 4 - Continuation from previous month E - Operator Training & Licensee Exam 5 - Other F - Administrative G - Operational Error (Explain)

Page 1 of 1

SUSQUEHANNA STEAM ELECTRIC STATION Docket Number: , 50-388 Datei 12/13/02 Completed by: J. J. Hennings Telephone: (570) 542-3747 Challenges to Main Steam Safety Relief Valves None.