ML20149F548

From kanterella
Jump to navigation Jump to search
Insp Rept 50-160/87-08 on 871216,880104-05 & 14-22. Violations Noted.Major Areas Inspected:Operations & Health Physics Activities Re Contamination Event During Wk of 870817 & Followup of Previous Enforcement Issues
ML20149F548
Person / Time
Site: Neely Research Reactor
Issue date: 02/10/1988
From: Burnett P, Dan Collins, Fredrickson P, Herdt A, Kuzo G, Verrelli D
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20149F517 List:
References
50-160-87-08, 50-160-87-8, NUDOCS 8802170242
Download: ML20149F548 (20)


See also: IR 05000160/1987008

Text

  • i'

-;

amiev . UNITE 3 STATES

[m 'o

NUCLEAR Cf GULATORY COMMISSION.

4 REclON 11

. /' . ' n

y j 101 V ARIETTA STREET,N.W.

W t ATLANTA,oEORot A 3o323

\, * * * * * */ '

~

'

p n i O 1Q98

Report No.: 50 160/87-08

Licensee: Gecrgia Institute of Technology

225 North Avenue

Atlanta, GA 30332

Docket No.: 50-160 License No.: R-97

Facility Name: Georgia Institute of Technology Research Reactor (GTRR)

Inspection Co uc d: December 16, 1987, anuary 4-5 and 14-22, 1988

'

Inspectors:

.

. > t<41

. Fredrickson, Team Leader

^ 7- _Efate

'

2 S'igned

//0!k

m.

{A t 8 k

G. B.'Kuzys

pFd.rIW.

Date{igned ,

'

P M . BuYRWTE ~ '

mad . ,_ _ __sf -/# - 8 8

Date Signed

Accompanying Person  : A. am . P ef:t Ma 4.r

'

Approved by: / ,

s / 'l '*2 J - M ' 96*

/"D M. Verrelli, Branch 'ief '

Date Signed  ?

% ivision of Reactor Pr ects 3

h./. $M N 2 - 10 ~ Lj ,

                              D. H. Collins, Branch Chief                                          Date Signed
                                                                                                                  '
                              Di s n f Radiation Safety and Safeguards
                                       e
                                              0[t                                               ~ 0llOf86
                              A.     . Herdt, Branch Chief                                         Dat6 Signed
                              Division of Reactor Safety                                                           '

s

                                                                 SUMMARY
                                                                                                                  .
             Scope: This special team inspection involved onsite review of GTRR operations
             and health physics activities regarding a contamination event which occurred                         ,
             during the week of August 17, 1987, and followup of allegations, Technical                            i
             Specification changes, and licensee actions regarding previous enforcement
             issues.                                                                                              ,
                                                                                                                  I
         8802170242 880210                                                                                        -
          PDR     ADOCK 05000160                                                                                  i
         G                       PDR                                                                              h
                                                                                                                  i

E

    >>.
               .
        ..
                     ,j .

Ia

                                                                                                   '
  u
                                                    2

c r .

           Results:. . Four violations with multiple examples for each were identified -
           failure to' have adequate procedures and failure to follow precedures for
           handling and manipulating experiment material and for surveying and evaluating          ;
           potential radiological hazards; failure to conduct adequate radiation surveys           ,
           of the reactor. building and GTRR personnel and their personal property for
           evaluation of exposure to radioactive material; failure to conduct adequate air
           sampling and bioassay analyses for evaluation of personnel exposure to airborne
           radioactive material during experiment and decontamination actlyities; and
           failure to document and maintain records of radioactive material contamination
           surveys conducted.                                                                    .;
                                       .
                                                                                                   !
                                                                                                   P
                                                                                                   L
                                 e
                                                                                                   u
                                                                                                   ;
                                                                                                   ,
                                                                                                   .
                                                                                                   l
                                                                                                   l
                                                                                                   l
                                                                                                   r
                                                                                                   P
                                                                                                   !
                                                                                                   .
                                                                                                   ,
                                                                                                   ;
                                                                                      _ _ _ . ._
                                             ..- -             -            .__
   +,    '                                         -
                                                                             ,
                                                                                                                               h
                                                                         '
                          s
                                                                                                                         ,                        ,a
                 , c, .
 +                                                                                                                            y
 ,
                                                               -                   ,
             .
                 *
                                                                                       ,
                                                                                      '~
                                                                                                                             x        ;
                                                                                .,"-        s
                                                                                                                                               . )5 . <f
                                                                                                                                                    ,
                                                                                                                                           ,
                 a
                                                             (                             REPORT DETAILS                                      D       ,
                                                           ..
                                                                                                                                                                 ,
                                                                                                                                                                   <
                                   .,                N                 . s'                                                    7
                   1.       .' Persons Contacted                              's              s
                                                         /
                              License'e 'fmployee s s                                                                                             ,
                                                        ,             W '            
                           *R. Boyd, Manager,:0f fic'e of Radiation Safety
                           *W.        Downs', Senior Reactor Operator
                                                                 '
                              B. Kahn, Radiation Safety Officer                                                                    ' .'
                                                                                                                                         '
                       #*R5'Karam, Director, Nuclear Research Center                                                                     r."
                        #*R. ?iacDonald, Associate Director, Nuclear Research Center
                           *L. McDovcil,' Manager of Reactor Operations                                                                    .
                                                                                                                                                                       ,.
                           *S. Millspaugh, Health Physicist
                              A. Moore, Director, Research Communications Office
                           *P. Sharpe~, Heal.th Physicist
                           #T. Stolson, Vici President for Research                                                              ,
                                                                                                                               ,           x
                                                                                                                                                                 ~
                              Other licensee employees contacted included technicians auds offico
                              personnel.                                                                                                        A
                                                                s
                                                 _
                                                                                                                                             ,                 .
                                                                                                                                      ,
                              Nuclear Regulatory Commission attending the second exit intervien                                                                      
                                                                                                                                                                        ^
                           #A. Adams, Project Manager, Nuclear Reactor Regulation, Washington,'C.                                      O                   "c
                           #M. Ernst, Deputy Regional Administrator, Region II
                            * Attended exit interview on January 5, 1988
                           # Attended exit interview on January 22, 1988                                           -                                   "
                                                                                                                 s  /
                   2.          Exit Interview (30703)
               -
                              The inspec' tion scope and findings were summarized on January 5.1988, and
                              January 22, 1988, with those persons indicated in Paragraph 1 abov6; The
                               inspector 4iescribed the areas inspected and discussed in detail the
                               inspection findings.                                    On Jinuary 5,1988, the inspector discussed four
                               apparent violations with multiple examples for each in regard to a topaz
                             - i rradiatio(' experiment which resulted in the subsequent release of
                               contaminated material within the reactor containment building during the
                              week of August 17, 1987. The violations involved the failure to have                                                            ,,
                               adequate procedures and the failure to follow procedures for handling and
                              manipulating experiment mater W and for surveying and evaluating
                               potential radiological hazafds (Paragraphs 3.b, 3.c, and 3.d); failure to
                            . conduct adequate radiation surveys' of the reactor building and GTRR
                            # personnel and their personal property potentially exposed to radioactive
                               contamination (Paragraphs ,3.c and 3.d); , failure to conduct adequate air
                               sampling and bioassay analyses to evaluate personnel exposure to airborne r '
                               radioactive contamination durino. the experiment and decontamination
                               activities in the recctor containment building (Paragraph 3.d); and
         .                     failure to document and maintain records of radiological contamination and                                      ~~
      *      '
                               personnel surveys conducted (Paragraphs 3.c and 3.d). At'this meeting the
                               inspector also reviewed an appbrent violation concerning ariministrative
           s,-                                                               .
                                  ,
        ,, ,                     j/'                               s       A                                               '%
                                                             '                                                                 ~
                                                                     u
                                           '                                                                   '
                         ,
                                   $    .,
                                                     ..

-

                             ,
                               .
                                      u      *
                                               .
                                                   .-                         .
                                                                                                          '                            E
                                                                                                                                                           ,
                *
           .
                                                        2

.

                   changes.made to the licensee organization without an approved amendment to
                   the Technical Specifications (TS).           A violation regarding the
                   reorganization will not be issued at this . time since the licensee had
                   informed the NRC during a May 4,1987, Enforcement Conference, of the
                  . reorganization and since the licensee had taken the position during the
                   Conference that this change was necessary to enhance safety. Further, NRC
                   representatives stated in the January 22, 1988 exit-interview, that the
                   present organizational structure was being reviewed by NRC, Office of
                   Nuclear Reactor Regulation (NRR) for its adequacy. NRC management stated
                   that the inspection findings indicate that there had been no improvement
                   in the licensee's performance 'since .the May 4, 1987 enforcement
                   conference, and may indicate problems in management control. Licensee
                   representatives stated that they believed management control had been
                   strengthened since July 1,1987, when the GTRR management reorganization
                   occurred. Tne licensee agreed to review the violations and respond
                   appropriately. The licensee did not identify as proprietary any of the
                   material provided to or reviewed by the inspector during this inspection.
             3.    Followup of the August 17-21, 1987, Contamiration Event (93700)
                   a.    Event Identification
                         On December 16, 1987, while reviewing management reorganization
                         concerns for the GTRR program,         the  inspector identified a
                         contamination event which occurred at the reactor facility during the
                         week of August 17, 1987.       The event involved the handling and
                         manipulation of topaz irradiation experiment material which resulted
                         in the release of radioactive contamination, initially identified as
                         Cadmium-115 (Cd-115), within the reactor containment building.
                         Licensee staff stated that subsequent decontamination efforts were
                         required to reduce contamination to normal levels in specific areas
                         of the reactor building. At the time of the December 1987 NRC
                         insp ction, a detailed description and evaluation of the event had
                         not been prepared by licensee staff or management. This inspection
                         was continued on January 4-5,      1988, and continued with a team
                         inspection conducted from January 14-22, 1988. The purpose of the
     <                   inspection was to assess the adequacy of the licensee's operations
                         and health physics programs, and to evaluate licensee management's
                         ability to address and evaluate any potential health and safety
                         issues associated with the design, completion and evaluation of
   e                     irradiation experiments.
 '
         ~
                   b.    Topaz Irradiation Experiments
   J
                         The inspector reviewed selected procedures, records, and memoranda,
                         and interviewed GTRR operations and health physics staff and
                         management concerning topaz irradiation experiments and the
                         subsequent August 1987 radioactive contamination event.
       .
                         TS 6.4.b(2) and 6.4.b(6) require written procedures to be provided
                         and utilized for installation and removal of experiments and
               _ _ _ _ _ _ _ _ - _
   *
 ,
                                                  3
       experimental facilities; and radiation and radioactive contamination
       control.
       Topaz gemstones had been irradiated using the GTRR facilities since -
     ' April.1987. Topaz gemstones to be irradiated ~were placed within an
       aluminum (A1) canister which was lined with a layer of cadmium (Cd).
       The topaz experiment criteria were specified in licensee procedure,

<

       Request for Minor Experiment Approval, GTRR Reference No. R7420,
       dated April 4,                 1987, which detailed experiment conditions and
       expected radiation levels.                  Experiment criteria included limiting
       irradiation times to 30 megawatt hours (MW-hrs.) and listed the .
       expected radiation levels from the cadmium and aluminum material used
       in the experiment to be "nil."                  After an initial topaz irradiation
       conducted during April 1987, surveys showed that a maximum measured
       radiation dose of 3 rads per hour (R/hr) at 1 inch from the
       experiment material (outside of the Al canister) was recorded
       following various irradiation times.                    Licensee procedure 3102,
       Quality Assurance for Experiments, dated October 28, 1982, specified
       that the primary Quality Assurance (QA) document was                        the
       Experimenters Checklist and Schedule Form.                  This procedure required
       that for Ca*.egory 4 Experiments - Internal, for example, the topaz
       irradiation experiment, the approval form to address quantitative
       controls of the experiment (e.g. irradiation time, flux levels,
       reactivity effects, etc.). From discussion with cognizant licensee
       personnel and review of topaz irradiation experiment data, the
       inspector determined that calculations for the activation of the
       cadmium and aluminum were not included in the evaluation of the
       expected radiation levels from the experiment.                    Furthermore, the
       unexpected high dose rates recorded for the 'nitial April 1987
       experiment were ignored by the operators during the QA review of the
       experiment results. The failure to follow procedures to properly
       evaluate the expected activation of irradiated material' and
       subsequent dose rates for the topaz irradiation experiment was
       identified                  as an   example of a violation       of Technical
       Specification 6.4.b(6)                 (50-160/87-08-01a).    In addition,    the

'

        inspector noted that the procedure did not specify a time frame for
       such reviews to be conducted or a method of review of findings by
       management.                  Based on the lack of these essential elements in the
       procedure, the procedure was inadequate and was identified as another .
       example of a violation of Technical Specification 6.4.b(6)
       (50-160/87-08-01a).

l For the August 1987 event, the topaz experiment was irradiated ! intermittently from July 17, 1987, to August 14, 1987. The inspector

       noted that the actual irradiati3n conditions, that is, dates,
        ir.adiation duration and power, and reactivity effects were not
       provided on the Experimenter's Checklist and Schedule form as required.
        Review of the control room operations log indicated that the
       August 1987 topaz experiment was irradiated for 41.8 MW-hrs. compared
        to the 30 MW-hrs. allowed by the Experiment Approval Form. The failure
        to follow procedural time limitation for irradiation of the topaz
                                         -
 -
     '
   .
                                        4
       experiment was identified as an additional example of a violation of
       TS 6.4.b(2) requirements (50-160/87-08-01b).
       For ' irradiation, the Al canister had been .placed in the reactor
       through vertical ports accessed by removal of-shielded plugs located
       on the top of the reactor shield. _ Subsequent to irradiation, the
       topaz experiment materials were maintained in the shut-down reactor
       to allow short-live activation products to decay. For the August
       1987 topaz experiment, irradiation was terminated on August 14, 1987,
       and the experiment material was maintained in the reactor .until
       August 17, 1987. On August 17, 1987, the material was removed from
       the reactor vertical port using licensee procedure, Extended
       Radiation Work Permit, Insertion and Removal of Routine Samples from
       Vertical Irradiation Facilities by Licensed Reactor Operators,_ dated
       July 23, 1981. Upon removal of the material from the reactor, the
       total beta gamma dose rate at orie foot from the experiment material
       (aluminum canister) measured approximately 3 R/hr. From discussions
       with licensee personnel and review of training and experiment
       records, the removal of material from the reactor was conducted as
       authorized by the licensee RWP procedure.      The experiment material   -
       was transferred for storage to a shielded lead cask (pig) located
       nearby on the southeast edge of the top of the reactor shield.
       On August 18, 1987, the operator removed the experiment material
       from, and placed the material on top of, the storage pig. In an
       attempt to determine the source of the unexpected high dose rates      .;
       recorded for the experiment material, the operator opened the
       aluminum canister and transferred the topaz into a glass beaker. The     '
       dose rates measured for the topaz and the aluminum canister which        .
                                                                                 '
       still contained the cadmium layer were not recorded. However, the
       operator stated that both the cenister tnd topaz material showed high
       radiation levels.      The operator replaced the aluminum canister
       containing the cadmium material into the storage pig and the topaz
       behind a shielded area and exited from the area on. top of the reactor
       shield. The operator stated that no procedures, other than the RWP
       utilized for removal of the experiment from the reactor, were used to
       detail the handling and manipulation of the experiment material. The
       inspector noted that external dose rates were expected to be
       significant, approximately 3 R/hr at 1 foot from the material on

.

       August 16, 1987, and questioned what criteria were followed to limit

'

       personnel whole body and extremity exposures during handling of the
       material. The operator stated that health physics training and good
       practices were followed.        The inspector discussed training with
       licensee staff and management and noted that the operator had
       received self-monitoring approval which allowed his handling of the
       material. The operator stated that tongs (12-18" in length) were
       utilized for handling the canisters to decrease extremity exposure,
       and that the manipulation and transfer of the topaz from the canister
       was conducted in less than 30 minutes. Monitoring of extremity
       exposures was not conducted and whole body exposures were monitored
       using film badges (see Paragraph 3.d).
                                                                             .
 *

.

                                   5~
                                                                                 t-
   - During a tour of the area on top of the . reactor on January 4,1988,
    the inspector noted that tongs and other equipment were not available
    for use. Also, the inspector noted that the area on top of the
    reactor shield was maintained as a contaminated area and required
    shoe covers and gloves as minimum protective clothing- (PC). -The
    operator stated that on August 18, 1987, only the minimum PCs were -
    worn. The inspector discussed personnel surveys conducted by the-
    operator on August.18, 1987, subsequent to handling the experiment
    material. The operator could not remember if he had conducted a
   . personal radiation survey (frisk) prior to exiting the area on top of
    the reactor and indicated that survey meters often were not available
    at the access step-off pad area.     Furthermore, -review of procedures.
    indicated that frisks were not required to be performed. The absence
    of survey equipment in this area was confirmed during the tour of the
    reactor building conducted on January 4, 1988. Prior to exiting the
    reactor containment building, the operator surveyed (frisked) his
    hands and shoe bottoms as required at the reactor containment'
    building access area and stated that radioactive contamination was
    not detected ~ at that time. The operator then departed from the
    campus and returned to his residence via public transportation.
    According to the operator involved, other individuals were not in the
     immediate area on the top of the reactor shield or on the ground
     /loor area immediately beneath where the experiment material was
    handled.    In addition, the operator confirmed that he was the last
    individual to leave the reactor containment building on August 18,
     1987.
    The inspector reviewed selected Radiation Work Permits (RWPs), and
                                                                                 '
    health physics and operations procedures and discussed the handling
    and manipulation of experiment materials in open areas, such as on
    top of the reactor shield, subsequent to irradiation experiment:,.
    Licensee representatives stated that irradiated samples had been
    handled (opened) and manipulated in the area on top of the reactor
     shield. This area did not have fume hoods or containment structures
    available to minimize the spread of contamination while handling
    experiment material. The inspector noted that neither the health
    physics nor operations procedures addressed the proper methods for
    radiation contamination control and exposure control associated with
    these activities in this open area.           Furthermore, licensee
    Procedure 9280, Personnel Surveying, indicated that surveys "should"
    be conducted immediately af ter exiting any contaminated area or
                                          .
    working with any contaminated material but did not require such
     surveys.   The inspector noted that to control the spread of
    contamination, surveys must be conducted at exit points to all
    contaminated or contamination control areas. The failure to have
    adequate operation and health physics procedures to control or
    prevent the spread of radioactive contamination and to control
    personnel    exposure while handling and manipulating irradiated
    experiment material was identified as an additional example of a
    violation of TS 6.4.b(6) (50-160/87-08-01c).
        - _.                                -                          _       -
                   _-                         .
<-    f
        . .
                                            '
   ;.
            c. Identification of Contamination
               10.CFR 20.201(b) requires the licensee .to make or 'cause to be made
               such surveys as (1) may be necessary for the licensee to comply with
               regulations > in this .part, and (2) are reasonable under. the         ,
               circumstances to evaluate the extent of radiation hazards that may be
               present.
               10 CFR 20.401(b) requires each licensee to maintain records in the
               same units used in this part, showing the results of surveys required
               by 20.201(b). 10 CFR 20.401(c) requires that records of results of
               surveys and monitoring maintained pursuant to Paragraph 20.201(b) of
               this section shall be preserved for two years after completion of the
               survey.
               In the afternoon of August 19, 1987, radioactive contamination,
               approximately 100-200 counts per minute (cpm) ab)ve-background, was
               found'on the first (main) floor of the reactor c ntainment building
               during routine surveillance activities.      Discussion with cognizant
               licensee health physics staff indicated that followup surveys of the
               licensee facilities showed radioactive contamination in the south to
               southwest areas of the reactor containment building including the
               floor area on top of the reactor shield near the storage pigs; the
               main floor and on equipment located there; and on a- catwalk located
               approximately 30 feet across from, and at the same elevation as the
               top of the reactor shield.
               From discussion with cognizant licensee representatives the inspector
               determined that from approximately one-fourth to one-third of the.
               reactor containment building had measurable contamination above
               background levels. Licensee representatives stated that they
               believed the spread of contamination occurred on August 18, 1987,
               when the operator opened the Al canister and manipulated the topaz
               experiment material in the area on top of the reactor shield.
               Additional supp rt for this conclusion was based on review of
               activities conducted at the GTRR prior to discovery of the
               contamination, the location of the highest radiation levels, and the
               direction of the spread of contamination. That is, ventilation to
               the reactor building exhausted its flow in a southerly direction
               across the reactor top area where the experiment material was
               handled. This air flow was believed to have caused the distribution
               of contamination in the reactor containment building.
               The inspector reviewed licensee records of weekly gross radiological
                surveys conducted during August 1987. For a August 19, 1987 survey,
               only the south main floor area, directly beneath the top of the
                reactor shield area where the experiment material was handled,
                indicated radiation levels approximately 100-200 cpm above
               background. The inspector noted that these survey records did not
                show survey results for all areas in the reactor containment, for
                example, the area on top of the reactor. From discussion with

m

     -       -  -
       -
.. .
                                        7
         cognizant licensee representatives, and review'of a memorandum from
         R. Boyd, Manager, Office of Radiation Safety to, R. Karam, Director,
         GTRR, dated August 20, 1987, the highest measurement of radioactive
         contamination was 20 mR/hr noted on.a maslin wipe'of a large area on
         top of the reactor shield where the irradiated topaz experiment was
         ~ handled on August 18, 1987     Initial licensee gamma spectroscopy
         analyses of some contaminated material indicated Cadmium-115 (Cd-115)
         as the main contaminant. Although surveys .of contamination were
         made, licensee representatives stated that detailed surveys defining
         the area and quantitative amounts'of radioactive contamination on all
          surfaces (for example walls and vertical surfaces potentially exposed
         to the airborne contamination in the reactor building) were not
         conducted. The failure to conduct adequate surveys of the reactor
         building following the discovery of contamination to evaluate the
         extent of radiation hazards that may be present was identified as a
         violation of 10 CFR 20.201(b) requirements (50-160/87-02a). In
         addition, the failure to maintain records of the limited surveys
         conducted on August 19-20 as a result of the contamination event was
          identified   as  a   Violation of 10 CFR 20.401 requirements
         (50-160/87-08-03a).
         On August 19-20, 1987, decontamination of the reactor containment
         bu!1 ding was conducted by the GTRR operators with assistance provided
         by the health physics staff.       On August 19, 1987, one of the
         operators, the individual involved in handling the topaz experiment
         material the previous day, detected contamination on.his pants cuff
         and shoe. The shoe was decontaminated but all contamination
         (approximately 500 cpm) on the pants could not be readily removed.
         The contaminated p?nt material was collected and discarded as
          radioactive waste.'    Licensee individuais concluded that the
          individual became contaminated during decontamination efforts.
         However, these pants had been worn by the operator on August 18,
          1987, and the inspector questioned if the contamination could-
         have occurred during handling of the experiment material.         The
          inspector noted that the operator Fad not worn a lab coat nor had he
         conducted a whole body frisk on August 18, 1987.        The inspector
         questioned if the licensee had surveyed the operator's residence and
         personal possessions to verify that radioactive material had not been
         transferred from the reactor buildirg on the operator's clothing.
          Licensee representatives stated that on August 19, 1987, the operator
         was instructed to conduct a survey of his residence and personal
         property using the appropriate instrumentation.       Results of this
          survey were not available to the inspector. During the pre-exit
         meeting conducted on January 5, 1988, with licensee staf f, the
         operator stated that the survey of his residence and personal
         property had not been conducted as licensee personnel were led to
         believe. The failure to conduct a survey to verify the absence of
          radioactive contamination at the operator's residence was identified
         as additional example of violation of 10 CFR 20.201(b) requirements
          (50-160/87-08-02b).

L

 *
   ,
     ~

.

                                         8
          The inspector reviewed the August 21, 1987, survey results for the
          reactor building following decontamination activities.      Surveys from
          the ' upper level clean area and first floor of the containment
          building showed levels of less than 200 disintegrations per minute
          per 100 square centimeters-(dpm/100 cm2 ). Surveys of the floor.on
          top of the reactor shield and the top of the storage pigs maintained
          there measured 300 dpm/100 cm2 and 400 dpm/100 cm2 respectively.
          During the inspection, licensee representatives . stated that an
          evaluation into the cause of the apparently loose radioactive
          particulates that were released from the Al canister would be
          conducted after radiation levels had subsided. On January 20, 1988,
          radiation levels at 6 inches from the canister were approximately
          600 mR/hr. The inspector noted that based on the initial August 17,
          1987,    radiation levels and the known half-life of Cd-115
          (approximately 54 hours), the radiation _ levels were not reduced - as
          expected for the January 20, 1988 measurement and were indicative of
          the presence of other radionuclides. Although the inspector was
          unable to sample the contaminants directly because of the high
          radiation levels and the possibility of spreading loose contamination
          by manipulation of the canister, a wipe sample was collected from the
          storage pig which was contaminated. An NRC laboratory qualitative
          gamma spectroscopy analysis showed the following: Zinc-65, 245 day
          half-life;    Cadmium-109,   453 day   half-life;   Tin-113, 115 day
          half-life;    and Antimony-124,    60.4 day   half-life.   Based on
          discussions with licensee representatives, another radionuclide
          identified,    i.e.,   Cobalt-60, was attributable to previous
          contamination of the storage pig. From the new radioactive materials
          identified, both licensee and NRC representatives concluded that the
          contaminants were activation products of the cadmium and soldering
          material used in fabricating the cadmium layer used in the
          experiment.    The inspector noted that Technical Specification 3.4
          required materials of construction, fabrication and assembly
          techniques be specified.       Licensee representatives stated that
          materials and assembly techniques were not specified for the topar
          irradiation experiment.     The failure to have procedures for the
          construction and fabrication of the experiment material was
          identified as another example of a violation of TS 6.4.b(6)
          (50-160/87-08-01d).
       d. Personnel Exposure
          10 CFR 20.103(a) requires that no licensee shall possess, use, or
          transfer licensed material in such a manner as to permit any
          individual in a restricted area to inhair a quantity of radioactive
          material in any period of one calendar quarter greater than the
          quantity which 'rould result from inhalation for 40 hours per week for
          13 weeks at uniform concentrations of radioactive material in air
          specified in Appendix B, Table 1, Column 1.         10 CFR 20.103(a)(3)
          requires that for purposes of determining compliance with the
          requirements of this section the licensee shall use suitable
          measurements of concentrations of radioactive materials in air for

' -

 .
                                     9
     detecting and evaluating airborne radioactivity in restricted areas'
     and in addition, . as : . appropriate, shall 'use measurements of
                                                                     ~
     radioactivity 'in .the body, measurements of radioactivity excreted
     from the body, ~ or any combination of such ' measurements as may be
     necessary for timely detection and assessment of individual intakes
     of radioactivity of exposed individuals.
     From discussion with cognizant licensee representatives and review of
     the. distribution and levels of -radioactive contamination, the.
     inspector determined that licensee personnel were potentially exposed
     to airborne radioactive contamination on August 18, 1987, during
     manipulation     of the experiment material and also- during
     decontamination activities conducted on August 19-20, 1987. The
     inspector reviewed and-discussed the licensee's' health physics survey
     and personnel monitoring procedures used to evaluate .. potential
     personnel exposure to airborne radioactive material.
     Licensee representatives stated that a . continuous air sample was
     collected in the reactor containment building during the week of
     August 17, 1987.       Licensee management stated that radiological
     analyses of daily air samples indicated that during .the week of
     August 17, 1987, levels of airborne radioactive contaminants were
     below 10 CFR Part 20 Appendix B concentrations for gross activity,
     air concentration averaging approximately 1 E-10 uC1/cc.
     Procedures and rnethodology used to conduct the samnling and
     subsequent analyses of airborne radioactive contamination were
     reviewed and discussed.      Licensee representatives stated that only
     one air sampler was located in the reactor building at the northeast
     area of the first floor beneath the control room.        The inspector
     noted that this sampler was not et the areas of the building where -
     the major contamination was identified.         Thus, the air samples
     analyzed were not representative of concentrations of radioactive
     material to which personnel were exposed. Furthermore, the licensee
     could not verify with data that the sampler was representative of the
     general air concentrations in the reactor building. The failure to
     use suitable measurements of concentrations of radioactive materials
     in the air for detecting and evaluating airborne radioactivity during
     the week of August 17, 1987, was identified as an apparent violation
     of 10 CFR 20.103(a)(3) requirements (50-160/87-08-04a).
     In addition, the inspector reviewed licensee procedure No. 9038, Air
     Sample Analysis. The procedure as written was inadequate in that if
     following initial analyses, samples which exceeded 10 CFR Part 20
     Appendix B limits for gross activity were not required to be
     maintained for a sufficient time period to allow decay of naturally
     occurring radon daughter products and then be recounted to accurately
     evaluate the actual radiation hazards present as a result of GTRR
     operations. The failure to have adequate procedures for air sampling
     analyses was identified as an additional example of TS 6.4.b(6)
     violation (50-160/87-08-01e).
 *

.

                                 10
   Licensee representatives conducted an "in-vivo" chest survey analysis
   for the operator potentially exposed to airborne radioactive
   materials. The in-vivo chest survey was conducted on both August 19
   and August 20, 1987, using a 3 X 3-inch sodium iodide (NaI) detector
   held against the operator's chest for approximately 5 minutes.
   Licensee representatives indicated in a memorandum from R. Boyd,
   Manager of the Office of Radiation Safety (MORS), to R. Karam,
   Director GTRR, that the August 19, 1987, data of these surveys may
   have shown a "slight positive indication of Cd-115" however, the
   results were inconclusive as to whether it was external or internal
   contamination.    Furthermore, no indication of positive results was
   noted for the August 20, 1987 analysis.        These data were not
   retained. The failure to maintain records of the "in-vivo" chest
   surveys was identified as another example of a violatio1 of
   10 CFR 20.401(b) requirements (50-160/87-08-03b).
   Furthermore, the lower limits of detection for these chest tnalyses
   had not been calculated. The inspector noted that there was no
   procedure to provide guidance for calibration and operation of the
   NaI detector to specify analytical detection capabilities for the use
   of "in-vivo" chest surveys to meet 10 CFR 20.103 requirements. The
   failure to have adequate procedures for the "in-vivo" chest survey
   was identified as another example of a violation of TS 6.4.b(6)
   (50-160/87-08-01f).
   A urine sample was collected from the operator on August 20, 1987,.to
   evaluate potential uptake of radioactive materials. The sample was
   analyzed using liquid scintillation counting (LSC) methodology. The    '
   inspector reviewed the urine bioassay procedure 9036, E.ioassay
   Analysis Methodology, and results of radiological analysi!. of the
   operator's urine sample.     The LSC methodology had been established
   only for the analysis of tritium and other beta emitting isotopes,
   for example, Carbon-14. Although the licensee identified Cd-115 as
   the major airborne radioactive contamicant, the operator's urine
   sample was only analyzed for tritium as noted on the licensee's
   sample processing report. The failure to properly analyze the urine
   sample for the expected contaminants sas identified as another
   example of a violation of 10 CFR 20,201(b) survey requirements
   (50-160/87-08-02c).
   The inspector noted that quantitative results for a beta gamma
   emitting nuclide could not be conducted with the licensee's present
   methodology. The procedure failed to address standard practices in
   calibration of the LSC or use of other instrumentation for beta gamma
   quantitative analyses. The procedure also failed to addre ss standard
   methodology, for example, the use of distillation to minimize
   quenching in LSC analyses, to quantify       esults.   Furthermore the
   appropriate biological retention models (for example, Report of
   Committee II on Permissible Dose for Internal Radiation,1959 [ICRP
   II] methodology) to relate calculated body burdens to estimate a
   person's intake of airborne radioactive contaminants were not
   specified. The f ailure to have adequate urine bioassay analyses and
    internal exposure evaluation procedures were noted ts another example

-

      '
 .
                                            11
              of a violation of TS 6.4.b(6) (50-160/87-08-01g).      In addition, the
               failure to have adequate bioassay analyses, that is, whole body
              counting or urine bioassays, conducted to evaluate the operator's
              exposure to airborne radioactive contamination was identified as an
              additional example of a violation of 10 CFR 20.103 requirements
               (50-160/87-08-04b).
               External dose estimates for personnel involved in the August 1987
              event were discussed. For the measurement period of August 1-31,
               1987, the whole body dose as measured by film badge was 30 millirem
               for the operator involved in the contamination event.        For this
              operator an estimate and/or direct measurement of extremity doses was
              not conducted. For all other individuals involved in decontamination
              activities, film badge whole body dose measurements did not exceed
               30 millirem for the August 1-31, 1987 period.
         e.    Followup Activities
              On January 11, 1988, a radiological contamination survey was made by
               the licensee of the residence of the operator involved in the
              contamination event. Direct radiation measurements of selected areas
               and personal items, for example, floors, counter tops, personnel
               clothes and shoes, in the residence using a GM detector were at
              background levels. In addition, wipes (smears) using filter paper
              discs were taken of surfaces within the residence and then andlyzed
               for radioactive contamination using a low beta gas proportional
              counter. All smear results were at background levels.
   4.   Technical Specification Changes
         Independent of allegations discussed in Paragraph 6, and independent of
         the NRR review, the inspector audited several of the changes incorporated
         into the organization and plant operations for the proposed TS changes.
         The existing organization was reviewed with respect to the previous
         organization. The organizational change as made on July 1, 1987, and the
         TS change request was submitted on August 6, 1987. On December 7, 1987,
         NRR requested additional information or this change request.          As of
         January 22, 1988, the licensee had not responded to this request.
         Although NRR will make the final deciCon on this change request, the
         inspection focused on the existin ' struc'.ure without regard to the TS
         change request.
         The inspection identified one area in the new organization that did not
         appear to be functioning satisfactorily.      In the present structure, the
         position of Chairman, Nuclear Safeguards Committee and Radiation Safety
         Officer are held by the same individual and the organization chart shows
         that (old) position reporting to the facility Director.     This arrangement
         eliminated the independent facility oversight responsibility usually
         associated with this type of position.    It was clear from discustions with
         the RSO that the RSO was involved in oversight of activities at GTRR only
         on request of the Director, GTRR. The Director stated that a change to
      ~
 .
                                             12

.

                      '
         the reporting level within Georgia Tech for 'these positions would be
         considered.
         Also, a portion. of the TS change involving a change from a helium to a
         nitrogen reactor vessel cover gas is discussed in Paragraph 7.b.
         No violations or deviations were identified.
   5.    Personal Interviews
         During the inspection, interviews were conducted with the facility staff
         to evaluate working relationships with respect to the August 1987 event
         and also to evaluate the effect of changes made to the facility since the
         enforcement conference of May 4, 1987. Although the interviews did
         generate numerous comments and personal opinions of those ' interviewed,
         .several general observations can be made:
         -
               All personnel appeared to be conscientious in wanting to perform
               their job in a safe manner.
         -
               Working attitudes between health physics and operations have
               continued to deteriorate.         .
         -
               The facility relies on informal training in lieu of procedures for
               many routine tasks.
         -
               The Deput/ Diractor position is a positive change to the facility.    !
         -
               Operations personnel appear satisfied with the Director's management
               efforts.
         -
               Health physics personnel appear to believe that the Director is
               involved too much in day-to-day health physics activities to the
               detriment of those activities.
         The interviews, although not identifying any regulatory concerns, did
          reveal that overall performance at the facility appears to have degraded
          since the May 4, 1987 enforcement conference.
         No violations or deviations were identified.
   6.   Allegation Followup (99014)
         a.    Allegation (RII-87-A-0090)
               The alleger stated that the management reorganization made in regard
               to the Neely Nuclear Research Center, Georgia Institute of Technology
               Research Reactor (GTRR) program on or about July 1, 1987, was in
               violation of NRC regulations. The specific concerns were as follows:
                                                                                ._

, ...

 ,
                                        13
          (1) An amendment to incorporate the administrative changes int : ;he
               licensee Technical Specifications (TS) was not-submitted at the
               time the changes were implemented and thus, the subsequent
               approval from the proper regulatory group (NRC) was not received
               prior to implementing the reorganization.
          (2) The GTRR health physics group does not have the ability to
               terminate work at the facility which could . lead to potentially .
               dangerous conditions.
          (3) A new Radiological Safety Officer (RS0) was appointed and the
               previous RSO demoted to the position of Manager of-the Office of
               Radiation Safety (MORS). The actual duties of the new RSO did
               not meet the professionally defined criteria for a RSO.
          (4) The Office of Radiological Safety was renamed the Radiation
                Safety Office without proper approval.
          (5) The Nuclear Safeguards Committee (NSC) has been disbanded.
          (6) The Director of the GTRR, a licensed isotope user, has authority
               over the group meant to keep uses of radioactive materials in
                check. Only this person can terminate work being done for his
                own uses.
          (7) The Radiation Protection Committee no longer controls the use of
                isotopes on campus. The Director of the GTRR r.ow has that
                responsibility,
       b. Discussion and Findings
          The   inspector discussed the above concerns with the GTRR
          management and staff, and interviewed the campus RSO.          Current  ,
                                                                                  '
          licensee procedures regarding authority to address potential
          radiological health and safety issues at the GTRR also were reviewed.
          In addition, licensee correspondence sent to the NRC, and management
          issues discussed during an enforcement conference held with NRC
          Region II personnel were reviewed and discussed.          Information
          collected as a result of personnel interviews, and the procedure and
          correspondence reviews, was audited against applicable regulatory
          codes, licensee TSs and the GTRR Safety Analysis Report (SAR).
          (1) TS 6.2 and the GTRR SAR Section 6.1 detail the licensee
                management organization. A proposal to change the GTRR
                management organization was discussed during an enforcement
                conference    conducted    on  May 4,    1987    (IE Report
                No. 50-160/87-06). At that time, NRC Region II management was
                informed that the GTRR organization would be changed on or about
               July 1, 1987. The licensee implemented the change on July 1,
                1987, and provided the proposed TS change to the NRC Region II
                staff in a letter dated July 6, 1987. A formal application to
 .

,

                                 14
        change the licensee Technical Specifications to reflect - the
        present management structure was submitted to the NRC, Office of
        Nuclear Reactor Regulation (NRR), by letter - dated- August 6,
        1987.
        The GTRR organizational change was . made on July 1, 1987, as
        stated. Currently, the new GTRR management organization, its
        functional responsibilities and adequacy to protect public
        health and safety are being reviewed by NRR.         This review
        includes evaluation of the adequacy of the present GTRR
        management organization and staff to meet the TS and - SAR
        criteria.
   (2) TS 6.4.b(6) requires written procedures to be provided and
        utilized for radiation and radioactive contamination control.
        The Georgia Institute of Technology (GT) Radiation Safety-
        Manual, Section III, dated July 1987, indicates that the Director
        of the GTRR has the authority to terminate any experiment which
        uses radiation sources if the methods and/or procedures used in
        such experiments are declared unsafe and contrary to
        regulations. In addition, Section It/ authorizes the Manager of
        the Office of Radiation Safety to supervise the campus
        health physics program. The manual specifies that the MORS can
        suspend on a temporary basis, any operation causing excessive
        radiation hazards as rapidly as possible.      From interviews of
        reactor facility personnel and from review of research conducted
        at the GTRR, no examples were identified where health physics
        had recommended cessation of work and were overruled.
   (3) TS 6.1.c details that the RSO, organizationally independent of
        the GTRR operations staff, advises the director of the nuclear
        research center in inatters pertaining to radiological safety at
        the GTRR. The GTRR SAR, Section 6.1, details that all health
        physics personnel are responsible to the campus RSO.       Further,
        the RSO is directly responsible to the President of the
        Institute.
        A new RSO was appointed on July 1, 1987. The recently appointed
        RSO is not a member of the iRR staff but he reports directly to
        the Director, GTRR, for RSO functions according to the new
        organizational chart.    Thus, TS requirements and SAR criteria
        describing the RS0's independence from the GTRR organization and
        his functional control over the health physics staff were not
        met.    This organizational change of TS and the apparent
        deviation from SAR commitments concerning the lack of health
        physics staff independence from the current GTRR management
        structure is being reviewed by NRR.
      _
 .
                                                                               i
   ..

,

                                       15
        (4) The GTRR TS do not require an Office of Radiological Safety.
             However, licensee SAR Sections 6.1 and 6.4 specify that the
             Office of Radiological Safety authority is derived from the~'
             President of. the Institute and is, responsible -for radiation
             safety _ training, radioactive materials inventory, surveys,
             effluent releases and personnel monitoring at the reactor
             facility.
             The Office of Radiological Safety was abolished and renamed the
             Office of Radiation Safety on July 1,1987.        This office was
             integrated as a functional unit into the GTRR organization and
             mandated to conduct required training, monitoring, and survey
             requirements.      However, the current GTRR administrative
             authority over the Office of Radiation Safety does not appear
             meet the intent of the GTRR SAR. This change in organization
             currently is being reviewed by NRR.
        (5) TS 6.2 details the licensee responsibilities and requirements
             for a Nuclear Safeguards Committee (NSC). The GT Radiation
             Safety Manual, dated July 1987, requires the Committee to meet
             quarterly and as circumstances warrant.
             Interviews with selected GTRR personnel and the campus RSO
             indicated that the NSC is operational and has met as required by
             the licensee's TSs.
        (6) The GTRR TSs and SAR do not prohibit the Director of the reactor
             research center from utilizing the nuclear research reactor
             facilities or isotopes. However, the licensee SAR, Section 6.1,
             details that the operating staff is completely dhorced from the
             research programs and the Reactor Supervisor is in charge of the
             reactor operations group.
                                                                         '
             The Director of the GTRf, has conducted gem irradiation research
             experiments through the reactor operations staff. The Director
             has authority over the GTRR operations.         Thus, use of the
             operations staff to conduct research for the Director of the
             reactor facility apparently deviates from the intent of the GTRR
             SAR.   The GT Radiation Safety Manual, Sections III and IV,
             authorize that either the Director of the GTRR center or the
             MORS can suspend any operation causing unsafe or excessive
             radiation hazards.      The present organization structure in
             relation to its intended safety function is presently undergoing
             review by NRR.
        (7) The licensee's TS criteria and SAR specifications do not require
             establishment of a Radiation Protection Committee nor prevent
             the Director of the GTRR from having authority over use of
             radioactive materials regulated by the state license.

_

      *
 .                                                                                     ;
                                             16
                    The Radiation Protection Committee was abolished and the.
                    Director, GTRR, was authorized responsibility for all nuclear
                    research and safety issues on July 1, 1987. The Health Physics
                    Manual, dated July 1987, Section III, lists the responsibilities
                    of the Director of the Neely Nuclear Research Center,- including
                    the direction and operation of the GTRR and all nuclear research
                    and radiation safety issues on the GT campus.
        c.    Conclusion
              Several of the issues in the allegation were substant'.ated in that
              the administrative, organizational and management changes occurred as
              stated. These management and organizational changes to the GTRR TS
              requirements and SAR commitments were made by the licensee. These
              changes. currently are being reviewed by NRR.           Other issues
              identified, that is, disbandenment of the NSC and only the Director
              of the GTRR having control of experiments were not substantiated.-
        No violations were identified.
   7.   Licensee Action on Previous Enforcement Matters (92702)
        Violaticns identified in Inspection Report 50-160/87-01 and responded to
        in licenAee 'etters dated May 25, 1987, and July 15, 1987, were reviewed.
        The identification of the violation in the discussion is consistent with
        that used in the Notice of Violation enclosed with the report.
        a.    (0 pen) Violation 50-160/87-01-01, Failure to Provide or Utilize
              Procedures.
              (1) A.1.a:     There was no approved procedure to measure excess
                    reactivity to assure it cid not exceed the limits ~ of
                    Technical Specification 3.1.e.     Procedure 7246, Control Element
                    Reactivity Worth, was revised on October 30, 1987.         Step V
                    established an excess reactivity calculation, using the measured
                    worths, on the Reactivity Worth Report Form (Page 3 of the
                    procedure), and stated an acceptance criterion that excess
                    reactivity be less than 11.9% delta-K/K. The procedure did
                    require a plot of the integral control element worth curves, but
                    did not provide data sheets to capture the reactor period and
                    associated reactivity worth data obtained in the measurements
                    and used to plot the data and to satisfy the acceptance
                    criteria.   Review of some of the completed procedures in the
                    files revealed that general purpose data sheets, appropriately
                    headed and filled out, had been used to capture the data and
                    were attached to the completed procedures. This portion of the
                    violation is closed.
               (2) A.1.b:    There was no approved procedure to measure the 0,
                    concentration in the cover gas to assure it was less than 2% by
                    volume before making the reactor critical as specified in
         -.

-

     .
       *
                                           17
                 Technical Specification 3.6.e.      The licensee purchased a- gas
                 chromatograph and prepared Procedure 4400, '03 Analysis in
                 Reactor Cover Gas (issued October 30, 1987) for its use. The
   ,             procedure had been performed once, and the measured
                 concentration was much less than the limit. The procedure
                 specified an annual performance frequency, but no technical
                 justification of that frequency was provided by the licensee.
                 The reactor operated for less than 200 megawatt hours in the
                 recent year, but.is capable of thousands of megawatt hours of
                 operation in a year.     Increased operation and other activities-
                 not considered by the licensee may affect the rate of Da
                 production. Although no longer surveillance interval is
                 acceptable, other considerations may dictate a shorter interval
                 is necessary to maintain confidence Technical Specification
                 3.6.e is always satisfied. The licensee agreed to perform a
                 quantitative    evaluation    of the frequency of cover gas
                 surveillance (Inspector Followup Item 160/87-08-05).         This
                 portion of the violation is closed.
            (3) A.1.c:     The requirement of TS 3.5.b.6 that the containment
                  isolation valve closing time.be less than five seconds was not
                 addressed'in a surveillance procedure. Procedure 7220, Building
                  Isolation Test,. was revised to include Step D to measure the
                 valve closing time and an acceptance criterion of less.than five   i
                  seconds was specified.      The procedure did not include data
                 sheets for recording the measurements, nor did it specify the
                 method used to determine valve closing time. Discussion with
                 management and the operator who performed the test confirmed
                  that the measurement was based upon observing stem travel time.
                 Management agreed to revise the procedure accordingly. This
                 portion of the violation remains open.
            (4) A.2.a: Procedures 2350 and 2400 referred to helium as the cover
                 gas although nitrogen is currently oeing used (see also
                 violation D).     The procedures have been changed to indicate
                  nitrogen as the cover gas. This portion of the violation is
                  closed.
            (5) A.3.a: The operators failed to log data required by procedure.
                  The operators were counselled by management on the requirements
                  to follow procedures.       Audits of the operators'    log by
                 management have confirmed acceptable log keeping. This portion
                  of the violation is closed.
            (6) A.3.b:     Procedure 2210 was not performed with the required
                  frequency.   Review of the procedure and its requirement to run
                  water through the cooling tower weekly led licensee management
                  to the conclusion that neither were required in the current and
                  anticipated modes of operation. The procedure was deleted with
                  the approval of the NSC. This portion of the violation is
                  closed.
 _
 .
   o
                                       18
     b.  (0 pen) Violation 50-160/87-01-04, (Violatien 0) The licensee changed
        .the cover gas specified in TS .3.6.e from helium to nitrogen without
         first obtaining the appropriate change to the specifications. The
         lice'nsee   subsequently   submitted  a   proposed- change    to  the.
         specifications, but has yet to submit an acceptable safety evaluation.
         to justify the change.    Nevertheless, the licensee' continues to use
         nitrogen as the cover gas. The NRC has requested additional
         infornation regarding this proposal in a letter dated December 7,
         1987.
     c.  Part B.1 of Violation 50-160/87-01-02 stated that, contrary to the
         requirements of Technical Specification 6.3.a(1),         estimates of
         isotopic activities were not being entered in the space provided on
         Request for Minor Experiment Approval. form. In their letter of
         July 15, 1987, the licensee denied the violation with the argument
         that it was not the intent of the form to require calculation of the
         activities expected from all irradiations.       Region II management
         concurred in the licensee's position and deleted the violation in a
         Region II letter of August 31, 1987. In the event of the week of
         August 17, 1987, that same form was filled out inaccurately in that all

-

         activities were listed as "nil" when in fact they were not
         (Paragraph 3.b). In further review of minor experiment forms
         emoleted since August 1987, the inspector determined that many of
         tit    were filled out inaccurately. Only the activity of interest to
         the experimenter was listed and the other activities, from other
          isotopes of the same element, that would be produced were not
         calculated in many cases. Clearly the form is not being used in a
         manner that would promote safe handling of the irradiated package,
         and there appears to be no other control imposed by tne licensee to
         accomplish that end. This activity will continue to be reviewed
         during    subsequent   inspections to further assess the safety
          significance of providing the calculations.
         The procedures reviewed, including those revised to respond to
         violations, were barely acceptable. Only an experienced person could
          hope to complete the procedures satisfactorily.      They would be of
          limited use in training new operators for the facility, particularly
          those enge;ed in self study.

}}