MONTHYEARML20133B2531984-03-20020 March 1984 Forwards Table Prioritizing Problems for Resolution According to Safety Significance.Review Requested Under TAC 54458 Complete Project stage: Other ML20132B8411984-03-21021 March 1984 Advises That Auxiliary Sys Branch Has Reviewed 248 Changes to Tech Specs & Prioritized 23 Changes Into Priority 1-3. Selection of Priority Based on Anticipated Risk to Health & Safety of Public.Effort on TAC 54458 Complete Project stage: Other ML20132B8201984-03-22022 March 1984 Forwards List of Items from Tech Spec Sheets for Which Reactor Sys Branch Has Responsibility.Each Item Assigned Priority Ranking Project stage: Other ML20133B2881984-03-22022 March 1984 Informs That Reactor Sys Branch Has Reviewed Tech Specs Problem Sheets Forwarded Under TAC 54458.List of Items for Which Branch Responsible Encl Project stage: Other ML20132B9251984-03-27027 March 1984 Comments on Prioritization of Tech Spec Problem Sheets. Twenty-five Problem Sheets Identified.Four Items of High Priority & 21 of Low Priority Project stage: Other ML20133B1311984-03-27027 March 1984 Informs of Completion of Containment Sys Branch Review of Tech Spec Problem Sheets.Recommends 21 Open Items Be Resolved Before Completion of First Refueling Outage Project stage: Approval ML20132B9641984-04-0909 April 1984 Informs of re-prioritization of Changes to Tech Specs,Per Div of Licensing Work Request Sheet.Categories 1 & 2 Items Listed.Tac 54458 Complete Project stage: Other ML20133B0441984-04-10010 April 1984 Forwards Comments Re Tech Spec Problem Sheets 292,293 & 306 Needing Resolution Before Low Power Operation Project stage: Other ML20132B9901984-04-12012 April 1984 Informs That No Addl Problem Areas within Instrumentation & Control Sys Branch Scope Require Resolution Prior to Next Criticality,W/Exception of Problem Areas Identified by Licensee,In Response to 840410 Memo Project stage: Other ML20133B2051984-04-13013 April 1984 Summarizes Results of Containment Sys Branch Review of Tech Spec Problem Sheets Needed for Low Power Operation. No Problem Sheets Identified for Resolution Prior to Operation Above 5% Full Power Project stage: Approval 1984-03-27
[Table View] |
Text
__
'o UNITED STATES
~,
E' NUCLEAR REGULATORY COMMISSION E
WASHINGTON, D. C. 20555 o
s., -
/
APR 12 B54 MEMORANDUM FOR:
Thomas M. Novak, Assistant Director for Licensing, Division of Licensing FROM:
L. S. Rubenstein, Assistant Director for Core and Plant Systems, Division of Systems Integration t
SUBJECT:
RE-PRIORITIZATION OF PROBLEM SHEETS ASSOCIATED WITH GRAND GULF TECHNICAL SPECIFICATIONS - AUXILIARY SYSTEMS BRANCH -
TAC NO. 54458 In ray memorandum to you dated April 9,1984, we reported the results of the
' Auxiliary Systems Branch's (ASB) re-prioritization of the proposed changes to the Grand Gulf Technical Specifications. Of the 341 changes to the Technical Specifications.39 changes were identified as falling into the ASB primary area of responsibility.
These 39 changes were further categorized into 23 Category 1 1,tems, which should be resolved prior to criticality, and 16 Category 2 items, which should be resolved prior to exceeding 5% power.
We pointed out in my memorandum that the intent of the changes was not always cleart This point was corroborated in a meeting with the applicant on April 11, 1984.
During our discussions with the applicant, it was determined that the 23 Category 1 items could be reclassified. Therefore, ASB has now concluded that there are no items which must be resolved prior to criticality.
Since there are no Category 1 items ASB will not provide an SER or SALP report as requested by your April 10, 1984 memorandum.
u_{dwL L. S. Ra nstein, Assistant Director for Core and Plant Systems Division of Systems Integration cc:
R. Mattson O. Parr J. Wilson J. Ridgely F. Clemenson E. Adensa L. Kintner
Contact:
J. Ridgely X29566 l
b 0
f 57