ML20127D423
Text
'
G PublicUrvin ElIctric and G:s Company 80 Park Plaza, Newark, NJ 07101/ 201430 7000 MAILING ADDRESS / P.O. Box 97s,.tk;7 ark f(LD7 Lot,,
January 20, 1984 Mr.
R.
A.
Hartfield Chief, Management Information Branch Office of Resource Management United States Nuclear Regulatory Commission Washington, D.C.
20555
Dear Mr. Hartfield:
HOPE CREEK GENERATING STATION UNIT NO. 1 DOCKET NO. 50-354 LICENSE NO. CPPR-120 CONSTRUCTION STATUS REPORT AS OF DECEMBER 31, 1983 Attached is the construction status report for Hope Creek Unit 1 statused as of December 31, 1983.
very truly yours,
~,
P.-R.
H.
Landrieu Project Manager - Hope Creek Engineering and Construction HPC:srd Attachments CC:
Mr.
L.
E.
Tripp - IE, Region 1 8504150242 840606 PDR FOIA KILLEFE84-367 PDR M P 82 117/11 The Energy Peopc man a
CONSTRUCTION STATUS REPORT PAGE NO:
2-065 NUCLEAR POWER PLANTS HOPE CREEK 1 STATUS AS OF:
12/31/83 PLANT CHARACTERISTICS:
KEY PERSONNEL:
DOCKET NO:
05000354 CORPORATE CONTACT:
T. J. MARTIN - VICE PRESIDENT CP NO. & DATE ISSUED:
CPR-120 / 11/04/74 ENGINEERING AND CONSTRUCTION CP EXPIRATION DATE:
12/31/86 CORPORATE ADDRESS:
80 PARK PLAZA APPLICANT:
PUBLIC SERVICE ELECTRIC & GAS CO.
NEWARK, NEW JERSEY 07101 PLANT LOCATION:
IE REGION:
1 CORPORATE PHONE NO:
(201) 430-8316 AE BECHTEL NRC LPM:
D. WAGNER NSSS:
GENERAL ELECTRIC IE PRINCIPAL INSPECTOR:
CONTRACTOR:
BECH1EL
-CONSTRUCTION:
W. H. BATEMAN (RESIDENT INSPECTOR)
REACTOR TYPE:
-TEST AND STARTUP:
DER (MWE):
1067 IE RESIDENT INSPECTOR:
INSPECTION STATUS:
FUEL LOAD DATE CHANGES AS REPORTED BY UTILITY:
TIME PERIOD REPORT NEW REASON FOR CHANGE DATE SCHEDULE REPORTED BY UTILITY JULY 1983 - SEPTEMBER 1983 04-00-75 06-00-82 DELAY IN OBTAINING STATE OF NEW JERSEY COASTAL AREAS FACILITY PERMIT.
REPORT BEG DATE END DATE NUMBER OF INSP.
OF INSP.
05-00-76 12-00-82 REEVALUATION OF DELAY CAUSED BY N. J.
COASTAL AREAS FACILITY PERMIT.
83-13 08-18-83 10-16-83 83-16 10-17-83 12-04-83 10-00-76 11-00-83 RE-EXAMINATION OF THE EFFORT REQUIRED TO 83-17 12-20-83 12-23-83 CONSTRUCT THE PLANT.
02-00-80 11-00-84 NO REASON GIVEN.
08-00-80 06-00-86 LOWER THAN ANTICIPATED ELECTRICITY SALES GROWTH, CONTINUED INFLATION, AND RECESSIONARY TRENDS IN ECONOMY.
08-00-82 01-00-86 TARGET FUEL LOAD DATE.
LOCAL PUBLIC DOCUMENT ROOM:
SALEM FREE PUBLIC LIBRARY 112 WEST BROADWAY SALEM, NEW JERSEY 08079 M P83 11/04 1-sed a
CONSTRUCTION STATUS REPORT PAGE NO:
2-066 NUCLEAR POWER PLANTS HOPE CREEK I STATUS AS OF:
12/31/83 CONSTRUCTION STATUS:
APPLICANT'S CURRENT ESTIMATED ' FUEL LOADING DATE:
01-00-86 APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS' APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
11-00-84 DEFINED IN CP: (EARLIEST)
APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP lSSUANCE:
06-00-81 (LATEST) 12-31-86 APPLICANT'S CURRENT ESTIMATED COMMERCIAL OPERATION DATE:
12-00-86 CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE: 815 COMMENTS REGARDING CURRENT CONSTRUCTION STATUS: NONE 1
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED i
START START COMPLETION COMPLETION
$ COMPLETE MOBILIZE AND PREPARE SITE:
02/76 03/76 08/77 08/77 1005 PLACE STRUCTURAL CONCRETE (REACTOR BLDG. TO RPV PEDESTAL):
07/77 08/77 10/79 09/79 1005 INSTALL REACTOR PRESSURE VESSEL:
11/80 11/80 12/80 12/80 1005 INSTALL LARGE BORE PROCESS PIPE:
04/79 04/79 07/85 965 79%
lNSTALL LARGE BORE PIPE HANGERS, RESTRAINTS, AND SNUBBERS:
04/79 04/79 06/85 605
' INSTALL SMALL BORE PIPES-12/81 07/81 08/85 99$
INSTALL CABLE TRAY:
08/79 08/79 07/85 INSTALL EXPOSED METAL CONOUlT:
09/81 05/81 07/85 755 INSTALL POWER, CONTROL, INSTRUMENTATION, AND SECURITY CABLE:
02/83 11/82 09/85 33%
20%
INSTALL ELECTRICAL TERMINATIONS:
03/83 02/83 11/85 CONDUCT REACTOR CODE HYDROSTATIC TEST:
04/85 05/85 05 Of 12/85 CONDUCT COLD FUNCTIONAL TEST:
12/85 05 01/86 CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD:
09/85 M P83 11/04 2-srd