s' e-ILLIN0/8 POWER COMPANY CLINTON POWER STATION, P.O. BOX 399, CLINTON, ILLINOIS 61727 January 26, 1983 Mr. R. A. Hartfield, Chief Management Information Branch Office of Management and Program Analysis United States Nuclear Regulatory Commission Washington, D.C.
20555
Reference:
Illinois Power Company Clinton Power Station Units 1 and 2 Construction Status Report (NUREG - 0030)
Dear Mr. Hartfield:
Enclosed please find status data as of December 31, 1982 for input to the referenced report.
The-status is noted on a marked copy of the NRC report compiled from data as of June 30, 1982.
As of December 31, 1982 construction of Unit 1 is estimated at 87.0% complete, with the target date for fuel load remaining at January 3,1984.
If there are any questions and/or comments, please contact us at (217) 937-1111 extension 2811.
w/ enclosure Sincerely,
.%A.
R.-P.
Rasho Director, Project Controls RPR/HST/jm cc:
Mr. H. Livermore - w/ enclosure Resident Inspector /Clinton NPS c/o Nuclear Regulatory Commission R.R. f3, Box 229-A Clinton, Illinois 61727
~
8504150224 840606 PDR FOIA KILLEFE84-367 PDR
a bec:
W. C. Gerstner (1/1)
D. P. Hall (1/1)
J. H. MacKinnon (1/1)
G. E. Wuller' (1/1) file (1/1)
I
C0N5TRUCTION
$TATUS REPQRT PAGE NO: 2-028 CLINTON 1 NUCLEAR POWER PLANT 5 STATUS A5 0F 96 h 8 PLANT CHARACTERI5 TIC 5:
KEY PER50NNELa DOCKET NO:
85000461 CORPORATE CONTACT:
W. C. GERSTMER. EXEC VICE PRESIDENT CP NO. 8 DATE ISSUED: CPPR-137/ 02-24-76 CP EXPIRATION DATE:
CORPORATE ADDRESS:
500 SOUTH 27TN STREET APPLICANT:
ILLINDIS POWER DECATUR. ILLINDIS 62525 PLANT LOCATION:
6 MI E OF CLINTON. ILL IE REGION:
3 CORPORATE PHONE NO (217) 137-1118 EXT, 28tt AE SARGENT 8 LUNDY NS$5 GENERAL ELECTRIC CortS T RUCT OR :
BALDWIN A550CIATES NRC LPM:
N. WILLIAMS REACTOR TYPE:
N. M. WESCOTT DER (r:WE):
0950 IE RESIDENT INSPECTOR:
M. LIVERt10RE IM5PECTION 5TATU5:
~
FUEL L0AD DATE CNANGE5 TIME PERIOD A5 REPQRTED 8Y UTILITY Arr. 1982 - Jun. 1982 REPORT HEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE SCHEDUL E REPORTED BY UTTLITY 18E1,813 0F INSP.
OF TNSP.
85-09-77 04-00-81 REEVALUATION OF CONSTRUCTION SCHEDULE.
8 15 06-02-81 02-05-82 06-23-78 04-00-82 TIME LOST DUE TO SEVERE WEATHER 8294 02-16-82 03-31-82 CONDITIONS.
8206 04-28-82 04-30-82 01-21-81 01-00-83 REEVALUATION OF CONSTRUCTION SCHEDULE.
8207 05-17-82 05-20-82 04-29-82 01-03-84 REEVALUATIDH OF CONSTRUCTION SCHEDULE.
8209 06-09-82 06-10-82 Inspection Reports are available at local PDRs.
STATUS TO BE PROV10E0 BY THE NRC.
f L0 CAL PUBLIC D0CUMENT R 0 0 M:
VESPASIAN WARNER PUBLIC LIBRARY 170 WEST JOI?HS0tl STREET CL Iti10:1 ILLIN0!$ 61727 I
I e
t
~
C0N5TRUCT ION 5TATU5 REP 0RT PAGE NO: 2-029 Ctit;Tn4 1 NUCLEAR POWER PLANT 5 STATUS A5 0F: e '
CDN5TRUCTION 5 i A T U 5:
- fPLICANT'S CURRENT ESTIMATED FUEL LOADING DATE:
01-03-84 APPLICANTS CONSTRUCTION CDMPLETION ESTIMATE AS ArPLICANT'S PREWIOUS ESTIMATED FUEL L0tDING DATE:
01-03-83 DEFINED IN CP (EARLIEST) 10-01-80 APPLIC AN T'S ESTITIATED FUEL LOADII:G DATE AT CP ISSUANCE:
IC-00-30 (LATEST)
APPLICA!!T'S CURRLui ESTIMATED CCMt1ERCIAL OPERATION DATE: 03-31-84 10-08-83 CURRENT LSTIMATED PERCCHT CONSTRUCTION COMPLETE:
s**
87.0 %
foi!1ENTS REGARDING CURRENT CONSTRUCTION STATUS:
1 i
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED.
START 11ARl_
COMPLETION COMPLETTON ]LCOMPLETE M30ILIZE AND PREPARE SITE:
10-06-75 03-16-76 100%
FLACE STRUCTURAL CONCRETE:
02-25-76 01-00-83 bets 99.9%
INSTALL REACTOR PRESSURE VESSEL:
10-06-79 10-15-79 1004 INSTALL LARGE 80RE PROCESS PIPE:
05-01 87-15-83 tSt-97.3%
INSTALL LARGE 802E PIPE HANGERS, RESTRAINTS AND SHUBBERS:
05-08-76 08-15-83 444 9J.J{
INST ALL SMALL SCRE PIPET 06-08-77 09-01-83 33x 97.61 INSTALL CAOLE TRAY 06-01-78 02-18-83 44x 93.2%
INSTALL'Exr05ED METAL CONDUIT:
06-01-78 02-29-83 23x 85.9%'
- IH5T ALL PO!JER, CCNTROL. INSTRUMENTATION AHD SECURITY CABLE:
12-12-79 10-03-83
+4x 57.3% -
INSTALL ELECTRICAL TERMINATI0HS:
04-01-80 11-08-83 44x 49,gg i
CONDUCT REACTOR CCLD HYDRDSTATIC TEST:
02-23-83 04-03-83 0%
i C0t:CUCT H3T FUNCTIONAL TEST:
N/A N/A N/A N/A N/A CONDUCT PRECP AND ACCEPTANCE TESTS HECESSARY TOR FUEL LOAD:
03-06-81 11-28-83 awe 4.5%
6
C0C5YRUCTIOO 5TATUS REPORT PAGE
- 2-3 CLINTON 2 N U C L E A'R POWER P L A N T'S STATUS A5 0F:
96-59-44 PLANT C H A R A C T E R'I 5 T I C 5:
KEY. PERS0NNEL*
DOCRET NO:
85088462 CORPORATE CONTACT:
~ W. C. GERSTNER EXEC VICE PRESIDENT
'CP 100. 4 DATE ISSUED:. CPPR-134/ O2-24-76 CP EXPIRATION DATE:
CORPORATE ADDRESS:
-500 50*JTN 27TN STREET-APPLICANT:
. ILLINOIS POWER DECATUR, ILLINOIS 62525 PLANT LOCATION:
6 MI E OF CLINTON, ILL IE REGION:
3 CORPORATE PHONE NO:
(217) 937-1118 EXT. 2411 AE SARGENT 4 LUNDY N555*
-GENERAL ELECTRIC CONSTRUCTOR:
SALDWIN ASSOCIATES NRC LPM:
M. WILLIAMS REACTOR TYPE
M. M. WESCOTT-DER (f1WE):
8950 IE RESIDENT INSPECTOR:
N. LIVEttt0RE IN5PECTION 5 T A T U 5:
FUEL L0AD DATE CHANGE 5 TIME PERIOD A.5 REP 0RTED EY UTILITY Anr. 1982 - Jun. 1982 REPORT NEW REASON FOR CHANGE REPORT BEG DATE END DATE DATE 1GHERE.E REPORTED BY UTILITY NUMBER OF INSP.
OF INSP.
83-24-77 10-08-87 FINANCIAL CONSIDERATIONS AND UNCERTAINTY OVER FEDERAL NUCLEAR GENERATION AND FUEL POLICIES.
11-28-88 N#5 REDUCED LOAD GROWTN RATE.
STATUS TO BE PROV10E0 BY
.THE NRC.
e z.
L 0 C-A L PUBLIC D0CUMENT R00M VESPA5!AN WARNER PUBLIC LIBRARY 12e WEST JOHNSON STREET CLINTON, ILLINOIS 68727 e
e 0-9
C0N$TRUC7 ION' STATU$
REP 0RT PAGE No 2-03 CLINTON 2 NUCLEAR P0WER PLANTS
-STATUS AS OF
'4 ~
L C 0 N.S T R U C T I C N
'S T A T U 5:
APPLICANT'S CURRENT ESTIMATED FUEL LDADING DATE:
N/S APPLICANTS CONSTRUCTION COMPLETION ESTIMATE AS l
APPLICANT'S PREVIOUS ESTIMATED FUEL LOADING DATE:
10-00-87 DEFINED IN CP: (EARLIEST) 18-08-83 APPLICANT'S ESTIMATED FUEL LOADING DATE AT CP ISSUANCE:
10-00-83 (LATEST) 10-01-a5 APPLICANT'S CURRENT ESTIMATED ConMERCIAL OPERATION DATE: N/S CURRENT ESTIMATED PERCENT CONSTRUCTION COMPLETE:
1%
i CDMMENTS REGARDING CURRENT CONSTRUCTION STATUS: UNIT 2 CONSTRUCTION DEFERRED INDEFINITELY.
ESTIMATED ACTUAL ESTIMATED ACTUAL ESTIMATED START
}IAR1 COMPLETION Lor *PL QIO3 It Cor*P_Lfg MOBILIZE AND PREPARE SITE:
10-06-75 05-86-76 100%
PLACE STRUCTURAL CONCRETE:
INSTALL REACTOR PRESSURE VESSEL:
INSTALL LARGE BORE PROCESS PIPE:
l INST ALL LARGE BORE PIPE MANGERS. RESTRAINTS AND $NUBBERS:
INSTALL SMALL BORE PIPE:
INSTALL CABLE TRAY:
INSTALL EXPOSED METAL. CONDUIT:
INSTALL POWER. CONTROL. INSTRUMENTATION AND SECURITY CABLE:
INSTALL ELECTRICAL TERMINATIONS:
CONDUCT REACTOR COLD HYDROSTATIC TEST:
CONDUCT NOT FUNCTIONAL TEST:
CONDUCT PREOP AND ACCEPTANCE TESTS NECESSARY FOR FUEL LOAD: