Forwards Updated Const Status Rept as of 830930.Unit 1 Const Approx 92.6% Completed
ML20127D064
Person / Time
Site: 05000000, Callaway
Issue date: 10/28/1983
From: Schnell D
UNION ELECTRIC CO.
To:
NRC OFFICE OF RESOURCE MANAGEMENT (ORM)
Shared Package
ML082170543 List: ... further results
References
FOIA-84-367 ULNRC-678, NUDOCS 8504150055
Download: ML20127D064 (3)


Text

_

8 UNION ELECTRIC COMPANY 1901 GRATIOT STREET sT, Louis, MissouR October 28, 1983

'=a*fy,a;**-

oon.co,..c

~.cc

.r.6.wi......ouai.....

ULNRC-678 1

Chief, Management Information Branch /

Office of Management and Program Analysis U.S. Nuclear Regulatory Commission Washington, D.C.

20555

Dear Sir:

CONSTRUCTION STATUS REPORT CALLAWAY UNIT 1

. Enclosed is the Construction Status Report revised for a status date of September 30, 1983.

Construction of. Unit 1 is approximately 92.6 percent complete.

l f

This letter constitutes our report to be filed by October 31, 1983.

l l

Very truly yours, t

)

,h l

i 99 f.4 m / /. & /, e i A I i

j Donald F.

Schnell I

FLK/lw Enclosure cc Messrs.

H. M. Wescott E. K._Dille J. Neisler g 41 g 5 840606 KILLEFE84-367 PDR

l CONSTRUCTION STATUS REPORT Pcga No. 2-018 CALIARY -1 ~

NUCLEAR POWER PLANTS Status Ac of:

9-30-83' CONSTRUCTION STATUS:

Applicant's Current Estimated Fuel Applicants Construction Completion Estimate Loading Date:

04-02-84 As Defined in CP:

(Earliest) 06-30-81 Applicant's Previous Estimated Fuel (Latest) 12-31 Loading Date:

06-01-83 Applicant's Estimated Fuel Loading Date At CP Issuance:

06-01-81 i

Applicant's Current Estimated Commercial Operation Date:

Late 1984/Early 1985 Current. Estimated Percent Construction Complete:

92.6%

i Comments Regarding Current Construction Status:

Estimated Actual Estimated Actual Estimated

  • Start Start Completion Completion

% Completr Mobilize and Prepare Site:

09-03-75 05-01-76 100%

Place Structural Concrete:

04-01 10-11-82 100%

Install Reactor Pressure vessel:

03-15-79 05-02-83 100%

i Install Large Bore Process Pipe:

01-12-78 05-16-83 100%-

Install Large' Bore Pipe Hangers, Restraints and Snubbers:

01-10-78 11-30-83 99%

Install Small Bore Pipe:

01-19-78 09-01-83 100%

Install Cable Tray:

07-09-78 05-09-83 100%

Install Exposed Metal Conduit:

07-01-78 01-31-84 984 i

t j

Install Power, Control, Instrumentation and Security Cable:

08-08-79 03-15-84 97%

j i

l

Estimated Actual Estimated Actual Estimated.

Start Start Completion Completion 4 Complete Install Electrical Terminations:

04-04-80 03-01-84.

90%

Conduct Reactor Cold Hydrostatic Test:

06-02-83 06-02-83' 100%-

Conduct Hot Functional Test:

11-15-83 12-30-83 0%

Conduct Preop and Acceptance Tests Necessary For Fuel Load:

10-30-81 02-02-84 63%

,