8 UNION ELECTRIC COMPANY 1901 GRATIOT STREET sT, Louis, MissouR October 28, 1983
'=a*fy,a;**-
oon.co,..c
~.cc
.r.6.wi......ouai.....
ULNRC-678 1
Chief, Management Information Branch /
Office of Management and Program Analysis U.S. Nuclear Regulatory Commission Washington, D.C.
20555
Dear Sir:
CONSTRUCTION STATUS REPORT CALLAWAY UNIT 1
. Enclosed is the Construction Status Report revised for a status date of September 30, 1983.
Construction of. Unit 1 is approximately 92.6 percent complete.
l f
This letter constitutes our report to be filed by October 31, 1983.
l l
Very truly yours, t
)
,h l
i 99 f.4 m / /. & /, e i A I i
j Donald F.
Schnell I
FLK/lw Enclosure cc Messrs.
H. M. Wescott E. K._Dille J. Neisler g 41 g 5 840606 KILLEFE84-367 PDR
l CONSTRUCTION STATUS REPORT Pcga No. 2-018 CALIARY -1 ~
NUCLEAR POWER PLANTS Status Ac of:
9-30-83' CONSTRUCTION STATUS:
Applicant's Current Estimated Fuel Applicants Construction Completion Estimate Loading Date:
04-02-84 As Defined in CP:
(Earliest) 06-30-81 Applicant's Previous Estimated Fuel (Latest) 12-31 Loading Date:
06-01-83 Applicant's Estimated Fuel Loading Date At CP Issuance:
06-01-81 i
Applicant's Current Estimated Commercial Operation Date:
Late 1984/Early 1985 Current. Estimated Percent Construction Complete:
92.6%
i Comments Regarding Current Construction Status:
Estimated Actual Estimated Actual Estimated
- Start Start Completion Completion
% Completr Mobilize and Prepare Site:
09-03-75 05-01-76 100%
Place Structural Concrete:
04-01 10-11-82 100%
Install Reactor Pressure vessel:
03-15-79 05-02-83 100%
i Install Large Bore Process Pipe:
01-12-78 05-16-83 100%-
Install Large' Bore Pipe Hangers, Restraints and Snubbers:
01-10-78 11-30-83 99%
Install Small Bore Pipe:
01-19-78 09-01-83 100%
Install Cable Tray:
07-09-78 05-09-83 100%
Install Exposed Metal Conduit:
07-01-78 01-31-84 984 i
t j
Install Power, Control, Instrumentation and Security Cable:
08-08-79 03-15-84 97%
j i
l
Estimated Actual Estimated Actual Estimated.
Start Start Completion Completion 4 Complete Install Electrical Terminations:
04-04-80 03-01-84.
90%
Conduct Reactor Cold Hydrostatic Test:
06-02-83 06-02-83' 100%-
Conduct Hot Functional Test:
11-15-83 12-30-83 0%
Conduct Preop and Acceptance Tests Necessary For Fuel Load:
10-30-81 02-02-84 63%
,