Testimony of TR Campbell on Limerick Ecology Action Deferred & Respecified Offsite Emergency Planning Contentions.Related Correspondence
ML20100K180
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 12/03/1984
From: Tison Campbell
CHESTER COUNTY, PA
To:
Shared Package
ML20100K177 List:
References
OL, NUDOCS 8412100591
Download: ML20100K180 (4)


Text

-

RELATED CORREsp0NDENCE UNITED STATES OF AMERICA NUCLEAR REGULATORY ComlISSION Before the Atomic Safety and Licensing Board I 2 CXETED WC In the Matter of ) ,

)

Philadelphia Electric Company-' Docket Nos. 50-352,50-35g g g (Limerick Generating Station, )

0FF CE gr gcggg Units 1 and 2) ) DCCAEiitjG & sigyjcy

  1. ' AU TESTIMONY OF TIMOTHY R.S. CAMPBELL ON LIMERICK ECOLOGY ACfl0N s DEFERRED AND RESPECIFIED OFFSITE E)ERGENCY PLANNIl0 CONTEKrIONS 7 Introduction The purpose of this testimony is to respond to Limerick Ecolohy Action (LEA) of fsite emergency planning contentions admitted pursuant to the Licensing Board's Order dated October 26, 1984 relating to Cnester County.

LEA-1 The Risk Counties, Municipalities, School Districts, and Institutions haven't promulgated or adopted final radiological emergency resp 7nse plans, nor have they approved and adopted rians drawn up for them by Energy Consultants, Inc. , a Harrisburg firm hired by Philadelphia Electric Campany. There is no reasonabic assurance that the present state of planning is predictive of final approval, or that the plans are capable of being implemented.

1. The Conmissioners of Chester County are charged under the Pennsylvania Emergency Management Services Code ("P.L. 1332") with the response to and preparedness for energencies. They have established the Department of Emergency Services as the Icad agency for planning arti response at the county 1cvel urrier the act. Chester County officials are now reviewing i

Draft 9 of the Chester County Radiological Emergency B sponse Plan for l

T O

~i

. incidents at the Limerick Generating Station. This plan prepared by Department of Emergency Services staff, with assistance from Energy Consultants has incorporated Pennsylvania Emergency Management Agency (PEMA) and Federal Emer6ency Management Agency (FEMA) comments from plans review as well as the July 25, 1984 drill.

2. Subject to further changes resulting from observer comments on the July 25 drill and the November 20, 1984 scheduled supplemental drill, the plan represents the intended response of Chest er County Government to Limerick Generating Station incidents. When appropriate, the final version will be presented to the County Commissioners, as was the Chester County Radiological Emergency Response Plan for incidents at the Peach Bottom Atomic Power Station in December of 1981.
3. The plan will be implementable in the final version which will be presented to the Board of Conmissioners for adoption. It will outline the county role as the coordinating agency of the response of the schools, municipalities and health care agencies in the Emergency Planning Zone as well as the response of county government agencies.
4. In addition to passirc unmet needs to PEMA, discussions and negotiations are underway with public private agencies, such as the Southeastern Pennsylvania Transportation Authority (SEPTA) and Philadelphia Electric Company pursuant to P.L. 1332 to obtain the resources needed for emergency response. As these resources become available they will be incorporated into the plans and exercised in the next drill. These negotiations include not only equipment but also assistance and training.

LEA-2 The unadopted RERP's fail to provide reasonable assurance that each principal response organization has sufficient staff to respond to and to augment its initial response on a 24-hour continual basis, or that the assigned staff can respond in a prompt manner in case of a radiological emergency at Limerick.

5. Chester County has sufficient staff for 24-hour response.. The July 25, 1984 drill revealed some training needs, which are in the process of being addressed by Chester County Department of Emergency Services and Energy, Consultants. The staff's July 25 experience, along with four ac.hvcahto vd pattial ar*i-itize over the past two years and three Peach Bottom Atomic Power Station drills since 1982, demonstrate that the staff can respond in an appropriate fashion.

LEA-5 The Emergency Response Organizations (including federal, state, and local governments and support organizations) have failed to fully document the existence of appropriate letters of agreement with support orgenizations and agencies. Thus, there is no reasonable assurance that the emergency plans can be implemented.

6. Although Ictters of agreement are not a requirement of P.L.1332, and although many verbal commitments of aid have been made, Chester County Department of Emergency Services is continuing to attempt to obtain written commitments from support agencies and organizations.

Where this does not occur, the need for support is being passed on to PEMA as an unmet need under P.L.1332. Agreements are not required for agencies of the County or those charged by law or by contract with emergency responsibilities.

Y

LEA-23 The draft ccunty plans are de'icient because they do not contain reliable evacuation time estimates.

1

7. The Chester County Radiological Emergency Response Plan contains evacuation time estimates by the Pennsylvania Department of Transportation

-- and HMM Associates commissioned by Philadelphia Electric Company.

Both of these estimtes, along with information from the National Weather Service, PEHA, the Pemsylvmia Bureau of Radiation Protection and Philadelphia Electric Company will be reviewed by Chester County officials if indepedent action is required. Normally guidance as to the choice of protective action will be given to Chester County by the Governor via PEHA.