Advises That Fuel Load Date Revised from Jan 1984 to Jan 1986.Const Schedule Updates Will Continue to Be Submitted Quarterly.Next Update Planned for Jul 1983
ML20071J468
Person / Time
Site: Clinton Constellation icon.png
Issue date: 05/24/1983
From: Hall D
ILLINOIS POWER CO.
To: Harold Denton
Office of Nuclear Reactor Regulation
References
0982-L, 982-L, NUDOCS 8305270017
Download: ML20071J468 (1)


Text

ILLINOIS POWER COMPANY JP 500 SOUTH 27TH STREET, DECATUR,ILUNOIS 62525 0982-L May 24, 1983 Docket 50-461 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, D.C. 20555

Subject:

Clinton Unit I Construction Schedule Extension

Reference:

IP Letter 4/18/83, D. P. Hall to H. R. Denton, USNRC

Dear Mr. Denton:

The referenced letter states that your office will be ad-vised when new fuel load and commercial operation dates have been established for Clinton Unit I.

Today, the Company has announced that the fuel load date for Unit I has been revised from January, 1984 to January, 1986.

We will continue to submit quarterly updates of the con-struction schedule, with the next update planned for July, 1983.

Si cerely yours, D. P. Hall Vice President cc: Dr. H. Abelson, NRC Clinton Project Manager Mr. H. H. Livermore, NRC Resident Inspector Illinois Department of Nuclear Safety Mr. R. A. Hartfield, NRC Office of Management and Program Analysis Sool 8305270017 830524 PDR ADDCK 05000461 A PDR