ML20071E311

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in IE Insp Rept 50-461/81-15.Corrective Actions:Qa Manual Rewritten, Test Data Bank of Questions for QC Inspectors Developed & Bldg Arrangement & Grading Exam Process Changed
ML20071E311
Person / Time
Site: Clinton Constellation icon.png
Issue date: 06/04/1982
From: Gerstner W
ILLINOIS POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML20071E286 List:
References
U-0496, U-496, NUDOCS 8303140186
Download: ML20071E311 (7)


Text

-

q

, DESIGNATED ORIGINAL inh Certified By 7//p I

/

/LLINO/S POWER COMPANY 500 SOUTH 27TH STREET, DECATUR, ILUNOIS 62525 June 4, 1982 Mr. James C. Keppler Director, Region III Office of Inspection and Enforcement  %.% l h- %

U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, Illinois 61037

Dear Mr. Keppler,

This is in response to your Notice of Violation and In-spection Report Number 50-461/81-15. Illinois Power Company's response to the items of noncompliance cited are as follows:

1. The Notice of Violation states in part:

" Contrary to the above, activities affecting quality were not accomplished under suitably controlled conditions in that QC inspectors signed statements to the effect that, among other things, (3 ) answers to the certification ex-amination were provided prior to and during the examination, and (2) incorrect answers were allowed to be corrected."

With regard to Item 1 of the Notice of Violation, Illinois Power Company's response is as follows:

I. CORRECTIVE ACTION TAKEN AND THE RESULTS ACHIEVED The following actions were taken to ensure adequate controlled conditions during the certification examin-ing of QC inspectors:

a. The Quality Control training Manual was rewritten to strengthen the training and qualification program and to provide greater clarification regarding qualification requirements,
b. A test data bank of questions for Quality Control inspectors has been developed. The question bank is secured at all times to maintain confidential-ity. Prior to administering a test the Senior QC Discipline Engineer selects, at random, the questions to be included on ti.e test. This process ensures that each test is unique for each individual. After selection of the test question cards, the test is prepared and is sealed in an envelope by the Quality Control Manager. The r!303140186 830308 PDR ADOCK 05000461 0 PDR JUN 16 G82

1 J.C. Keppler June 4, 1982 NRC Page 2 envelope is then locked in a cabinet until the actual test is conducted. At the time of the test, the sealed envelope is opened by the Qd Training person proctoring the testing function.

Presently, a representative from Illinois Power Quality Assurance Department is nonitoring the QC Testing activity to verify that testing is accomplished under controlled conditions.

c. The Baldwin Associates QC Department has made physical changes to the building arrangement which has in turn improved the training and testing process. Certification examinations are no longer conducted in open office areas. The testing is conducted in a private room, with only the indi-vidual being tested, the test proctor, and the test monitor present.
d. The process of grading examinations with the person being tested present has been changed.

When the individual has completed the test, he is rading. The room asked to leave is closed and athe room sign is during postedg' Do Not Enter" until grading is completed. Upon completion of grading, the test is forwarded to the Senior QC Discipline Engineer who reviews the test and

' discusses the incorrect answers with the individual who took the test. The test is then filed in the individual's file in a locked cabi-net.

II. CORRECTIVE ACTION TAKEN TO AVOID FURTHER NONCOMPLIANCE The strengthened controls discussed above and the in-creased monitoring of Quality Control testing activ-ities by independent observers will preclude this condition from recurring.

III. DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED Actions taken to achieve full compliance were complete on June 1, 1982.

2. Example A The Notice of Violation states in part:

" Contrary to the above, in some cases, Nonconformance Reports are prepared by initiators in draft form and not on a Nonconformance Report. The nonconformance or suspected nonconformance is then documented on a Nonconformance Rep' ort at the discretion of personnel other than the initiator.

With regard to Item 2 Example A of the Notice of Violation, Illinois Power Company's response is as follows:

,J.C. Kcppler June 4,.1982 NRC Page 3 I. CORRECTIVE ACTION TAKEN AND THE RESULTS ACHIEVED Baldwin Associates Procedure BAP 1.0, "Nonconformances" has been revised to insure that nonconformances are identified, documented and processed in a controlled manner. The current program requires Baldwin Associ-ates Engineering, Quality Control, or Technical Ser-vices personnel to initiate the proper paper work (Nonconformance Report (NCR)) to report the nonconfor-mance. Furthermore, the Nonconformance Report origina-tor obtains a NCR number from Project Engineering prior to the NCR receiving any reviews by QC or Engineering personnel. This ensures that the NCR will be pro-cessed, since the program does not allow the voiding of Nonconformance Reports. The distribution list for NCRs has been changed to require that the originator of the NCR receive a copy of the NCR at initial distribution and after disposition of the NCR. This provides assurance to the originator that nonconformances reported have been properly processed.

These changes will ensure that nonconforming conditions will be documented and processed in a controlled manner.

II. CORRECTIVE ACTION TO AVOID FURTHER NONCOMPLIANCE Baldwin Associates has conducted training sessions on the new requirements of documenting and processing of Nonconformance Reports. This training was presented to Quality Control, Technical Services, and Engineering-personnel. Furthermore, a meeting was conducted by Mr.

L.J. Koch, Illinois Power Vice President with Quality Control and Technical Services personnel to discuss management's interest and concern on the NCR matter.

The main thrust of this meeting was to reiterate to Quality personnel that they had full support fron upper j management.

l III. DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED Actions taken to achieve full compliance were complete on June 1, 1982.

2. Example B The Notice of Violation states in part:

" Contrary to the above, activities affecting c uality were

!. not accomplished in accordance with prescribec instructions, in that the electrical fabrication shop was not inspected daily. Specifically, from February through June, 1981, only seven daily inspections of the electrical fabrication shop were made .

,J.C. Keppler June 4, 1982

, NRC Page 4 With regard to Item 2 Example B of the Notice of Violation, Illinois Power Company's response is as follows:

I. CORRECTIVE ACTION TAKEN AND THE RESULTS ACHIEVED Baldwin Associates Quality and Technical Services Department personnel performed an evaluation to determine if the work loads in this area were sufficient to require daily inspections. Due to the load work in the Electrical Fabrication area, the procedural requirements were changed to reflect random inspection. The procedure governing these inspections, QCI-401, Raceway Hanger / Support Fabrication /

Installation Inspection, further stipulates that these random inspections must be performed a minimum of twice a week. These random inspections will provide adequate inspection coverage in the Electrical Fabrication area.

To verify that inspections are being performed in accordance with requirements, Baldwin Associates Quality Assurance personnel reviewed Inspection Reports for the Electrical Fabrication Shops for the period of January 1 - March 31, 1982. The results of this review indicated that inspections are being performed at least twice a week.

II. CORRECTIVE ACTION TAKEN TO AVOID FURTHER NONCOMPLIANCES Baldwin Associates Quality Control Department conducted training sessions for Electrical QC inspectors which covered the requirements for performing inspections of the Electrical Fabrication shop.

III. DATE WHEN FULL COMPLIANCE UILL BE ACHIEVED Corrective action taken to achieve full compliance were complete on June 1, 1982.

3. The Notice of Violation states in part:

" Contrary to the above, Nonconformance Report No. 4055 was dispositioned "use-as-is" and closed (without reinspection to determine that the cable for radiation monitoring equip-ment had been enclosed in conduit) rather than being dispo-sitioned " rework" and being reinspected before being closed."

With regard to Item 3 of the Notice of Violation, Illinois Power Company's response is as follows:

. .J.C. Keppler June 4, 1982 NRC Page 5 4

1 4

I. CORRECTIVE ACTION TAKEN AND THE RESULTS ACHIEVED Nonconformance Report No. 4055 was revised and re-opened to require Quality Control verification that 4

subject cables were enclosed in conduit. This in-

!' spection was completed on July 3,'1981, and documented on Inspection Report No. 3715, which is attached to NCR

No. 4055. The results of this inspection indicated that subject cables were enclosed in conduit. The NCR was then re-closed based upon QC inspection results.

II. CORRECTIVE ACTION TAKEN TO AVOID FURTHER NONCOMPLIANCE Baldwin Associates Quality Assurance reviewed an additional fifty (50) Nonconformance Reports which were dispositioned by Sargent and Lundy as use-as-is to determine if similar conditions existed. These NCRs were selected at random and no instancas of the condi-tion as reported in the Notice of Violation were found.

Baldwin Associates Procedure BAP 1.0 is being revised to clarify use of use-as-is dispositions. The revised procedure will require reinspection for use-as-is

dispositions similar to NCR No. 4055.

III. DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED l

i Baldwin Associates will be in full compliance with the revised procedure requirements on or before July 15, 1982.

4. The Notice of Violation states in part:

" Contrary to the above, measures were not properly estab-lished to preclude inadvertent bypassing of inspections, in i

that, anchor bolts and straps used to hang electrical I

conduit were torqued to prescribed values and painted green to indicate that they had been inspected and accepted prior f

to installing the conduit which requires loosening the 1

anchor bolts without benefit of re-torquing and j re-inspection."

i j With regard to Item 4 of the Notice of Violation, Illinois Power Company's response is as follows:

I. CORRECTIVE ACTION TAKEN AND THE RESULTS ACHIEVED

, To ensure that all completed expansion anchor bolt installations are satisfactorily inspected, Baldwin i Associates has revised Procedures BAP 2.16, " Concrete Expansion Anchor Work", BAP 3.3.1, " Exposed Conduit

! Installation", and BAP 3.3.6, " Electrical Raceway

Support Installation". These procedures now require 1

,J.C. Keppler Junc~4, 1982

, 5, NRC Page 6

re-torquing and re-inspection of concrete anchors if
the nut is loosened for any reason. The re-inspection l

I of the concrete anchors will be' documented on the applicable final inspection form (JV-688, Electrical Hanger Inspection: JV-550, Anchor Bolt Installation Inspection; or JV-489/JV-776, Conduit Inspection Package). We are confident that the procedural re-quirement now in place will preclude the inadvertent bypassing of inspections on anchor bolts which have been loosened after initial torquing and inspection.

II. CORRECTIVE ACTION TAKEN TO AVOID FURTHER NONCOMPLIANCE 4

Baldwin Associates has conducted extensive training sessions on the new requirements concerning re-torquing and re-inspection of concrete anchors which are loosened after initial torquing and inspection were complete. This training was presented to Baldwin Associates Engineering, Quality Control, Quality Assurance and craft personnel.

III. DATE WHEN FULL COMPLIANCE WILL BE ACHIEVED Actions taken to achieve full compliance were complete on June 1, 1982.

b!gg) In regards to your concern, expressed in cover letter dj(lf' bg to Report No. 50-461/81-15, as to the adequacy of the Awnapected, prior to the retesting on May z-4, 1981, Illinois Power Company's response is as follows:

I An evaluation was performed by Illinois Power Company

' and Baldwin Associates to determine the areas of completed and inspected work that could possibly be

, affected by the questionable Quality Control Inspector -

Certifications. This evaluation resulted in a determination that a re-inspection program was required in the area of electrical nangers aHH PGCC rioor -

s~eetions. ---

1

, The reinspection of the electrical hangers was 3 accomplished using a sample plan developed by the 1

Baldwin Associates Quality Control Manager. The reinspection was completed on September 9, 1981. The results of these reinspections provided no indication of inspection deficiencies that would degradate the Quality Control Program for acceptance of electrical hangers during the period of time in question. The results of the evaluation were reviewed by Illinois Power Company Quality Assurance. The results of this review were satisfactory, however, there was a statistical disparity with respect to reinspection i

5

J.C. Keppler June 4, 1982 2U0: Page 7 percentages. As a result, Baldwin Associates Quality Control performed additional reinspections. The subsequent reinspections did not reveal any inspection deficiencies that would degradate the Quality Control Inspection program.

During August 17, 1981 to August 20, 1981, an independent verification of 100% of the PGCC floor sections was performed by an ad hoc task force which was composed of representatives from IP Quality Assurance, IP Plant Staff Compliance, IP Start-up and IP Nuclear Station Engineering Departments. Prior to performing the evaluation each participant in the verification effort attended a training program conducted by IP Start-up. The results of the verification revealed one (1) cable not routed correctly and not discovered by BA Quality Control '

during the inspection process. Since this represents one case in approximately 4000, this represents an error by the inspector rather than an indication of lack of qualification or knowledge. This cable was subsequently rerouted to correct the problem.

Based upon actions taken, we have concluded that the adequacy of the work inspected by Baldwin Associates Quality Control Electrical Inspectors, prior to the retesting on May 2-4, 1981, was adequate.

I trust that our response is satisfactory to allow closure of items of noncompliance. I hereby affirm that the information contained in this letter is correct to the best of my knowledge.

Sincerely o

W.C. Gerstner Executive Vice President cc: NRC Resident Inspector Director-Quality Assurance Illinois Department of Nuclear Safety Director, Office of I&E, USNRC, Washington, DC 20555 i

I