ML20070F750

From kanterella
Jump to navigation Jump to search
Exemption from 10CFR55.45(b)(2)(iii) to Permit Submittal of Simulation Facility Certification After 910326 Deadline in Rule But No Later than 910724
ML20070F750
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/05/1991
From: Boger B
Office of Nuclear Reactor Regulation
To:
WISCONSIN ELECTRIC POWER CO.
Shared Package
ML20070F752 List:
References
NUDOCS 9103110032
Download: ML20070F750 (5)


Text

.._ _

e, l

UNITED STATES OF AMERICA i

NUCLEAR REGULATORY COMMISSION In the Matter of WISCONSIN ELECTRIC POWER Docket Nos. 50-266 COMPANY-and 50-301 (Point Beach Nuclear Plant, Units No. I and No. 2)

EXEMPTION I.

Wisconsin Electric Power Company (Wisconsin Electric or the licensee) is the holder of facility Operating ~ License Nos. DPR-24 and DPR-27, which authorize operation of the Point Beach Nuclear Plant, Unit Nos.1 and 2.

The licenses provide, among other things, that the Point Beach Plant is subject to all rules, regulations, and orders of the Commission now or htreafter in effect. The facility consists of two pressurized water reactors located on the licensee's site in Manitowoc County, Wisconsin.

The revision to 10 CFR Part 55, " Operators' Licenses," which becane effective on May 26, 1987, established requirenents for the administration of operating tests on nuclear power plant simulators. These regulations, in conjunction with-10 CFR 50.54(1-1), require facility licensees to use

simulation facilities when administering operating ?ests for initial licensing and.requalifica tion. These regulations further require that a certified or NRC-approved simulation facility must be used tc administer operating tests after May 26,.1991.

By letter dated December 17, 1990, Wisconsin Electric l

l l

9103110032 010300 ADOCK0500g6 3DR

. _. - _. _ -. ~. -., - -. -.. -,, -. - - - - - - - - - - - - - - -

-2 requested an exemption from the schedular requirements for :ertification of a plant-referenced simulator.

]

11.

The licensee intends to comply with 10 CFR 55.45(b) by certifying a

_ plant-referenced simulator.

Section 55.45(b)(2)(iii) of 10 CFR Part 55 requires that facility licensees proposing to use a simulation facility consisting solely of a plant-referenced simulator submit Form NRC-474,

" Simulation Facility Certification," no later than 46 months after the e

effective date of this rule, that is, by March 26, 1991. On December 17, 1990, Wisconsin Electric requested an exemption from this filing requirement to allow for the submittal of NRC Form-474 after March 26, 1991, but no later than July 24, 1991.

-Wisconsin Electric began writing the specifications for the purchase of a plant-referenced simulator in early 1986. These specifications were issued to prospective bidders in December 1986. Af ter extensive negotiations with qualified bidders, the contract for the construction of the Point Prach Plant simulator was let on April 15, 1988.

In accordance with 10 CFR 55.45(b)(5)(vi), any certification report must include, among other things, a description of perfonnance testing completed for the simulation facility.

It has always been the intent of Wisconsin Electric to use the Factory Acceptance Testing (FAT) of th'e plant-referenced-simulator as the testing portion of the certification process. The FAT of the

simulator was originally scheduled for a 90-day period beginning on September 3, 1990. Due to delays in hardware delivery cnd software development, i

the FAT was not actually commenced until October 9,1990.

L

_. _ _., -. _ _ _ _ _.... ~.... _ _.. _.. _. _. - _. _. _. _... - -.. _ _ _,

'.i.

This 5-week delay, of itself, would not have necessitated a late submittal l

of NRC Form-474 However, once the Flit began, the simulator did not perform as well as expected. Wisconsin Electric, therefore, augmented its staff at the sinulator vendor's site by three people in order to better support test administration and documentation. The licensee also increased the testing schedule from one shif t a day, 5 days a week, to two shif ts a day, 6 days a week. These actions have achicved some positive results, but the resolution of some of the test discrepancies and failures still requires the attention of expert vendor technical personnel.

Additional resources of this nature have not been available.

Secause of the late testing start and the unexpectedly poor performance of the simulator, Wisconsin Electric has concluded that the point Beach Plant simulator will not be ready for certification until af ter the March 26, 1991 deadline.

Wisconsin Electric proposes to comply with 10 CFR 55.45(b) for the point Beach Plant by certifying a plant referenced sinulator by July 24, 1991.

During the period from May 26, 1991 until certification of the simulator, no initial or requalification operating tests are scheduled, 111.

The Commission has determined, pursuant to 10 CFR 55.11, that this exemption is authorized by law and will not endanger life or property and is otherwise in the public interest.

Furthermore, the Commission has determined, pursuant to 10 CFR 50.12(a), that special circumstances of 10 CFR 50.12(a)(2)(v) are applicable in that the exemption would provide only temporary relief from the applicable regulation and the licensee has n.ade good faith efforts to ccmply with the regulation.

This exemption grants a temporary relief period

\\

-4 of 4 months from the March 1991 date for submittal of the Point Beach Plant simulation facility certification. Good faith efforts to comply with the regulation were made as follows:

(1) Wisconsin Electric began writing specifications for a plant-referenced simulator in early 1986 and issued invitations for bids in December 1986.

(2) On April 15, 1988, Wisconsin Electric entered into contract for construction of a plant-referenced simulator. The simulator was originally scheduled for delivery by December 1990 and was to be ready for training by February 1991.

(3) Wisconsin Electric has kept the NRC informed of the status of the Point Beach Plant simulator project.

In letters dated OctoDer 11, 1989, and March 13, 1990, the licensee provided updated estimated certification dates. On April 10, 1990, in a meeting at NRC headquarters, Wisconsin Electric presented the details of the project and its status.

(4) Upon identifying unexpectedly poor performance during simulator testing, Wisconsin Electric allocated additional resources to the project. Three people were added to the licensee's staff at the simulator vendor's site and testing was increased from five to twelve shifts per week.

(5) Wisconsin Electric intends to comply with 10 CFR 55.45(b)(2)(iv) by not administering the simulation facility portion of the operating test on other than a certified simulator after May 26, 1991.

l l

The Commission hereby grants an exemption from the schedular requirements of 10 CFR 55.45(b)(2)(iii) for submittal of NRC Form-474, " Simulation Facility Certification." This exemption is effective until July 24, 1991.

Pursuant to 10 CFR 51.21, 51.32 and 51.35, an environmental assessment 3

and finding of no significant impact has been prepared and published in the Federal Register on March 5,1991 (56 FR 9238 ).

Accordingly, based upon the environmental assessment, the Commission has determined that the issuance of this amendment will not have a significant effect on the quality of the human environment.

The licensee's exemp. ion request dated December 17, 1990 is available for public inspection at the Commission's Public Document Room, 2120 L Street, N.W., Washington, D.C. and at the local public document room located at the Joseph P. Mann Public Library,1516 Sixteenth Street, Two Rivers, Wisconsin.

This exemption is effective upon issuance.

FOR THE NUCLEAR REGULATORY COMMISSION Bruce A. Boger, Director Division of Reactor Projects - lil/IV/V Office of Nuclear Reactor Regulation Dated at Rockville, Maryland this 5th day of March 1991.