Comments on Proposed Rev 2 to Reg Guide 1.100 Re Seismic Qualification of Electrical & Mechanical Equipment for Nuclear Power PlantsML20236Q799 |
Person / Time |
---|
Site: |
Point Beach ![NextEra Energy icon.png](/w/images/9/9b/NextEra_Energy_icon.png) |
---|
Issue date: |
11/09/1987 |
---|
From: |
Fay C WISCONSIN ELECTRIC POWER CO. |
---|
To: |
NRC OFFICE OF ADMINISTRATION & RESOURCES MANAGEMENT (ARM) |
---|
References |
---|
CON-NRC-87-111, FRN-52FR32980, REF-GTECI-A-46, REF-GTECI-SC, RTR-NUREG-0800, RTR-NUREG-800, RTR-REGGD-01.100, RTR-REGGD-1.100, TASK-A-46, TASK-OR 52FR32980-00005, 52FR32980-5, GL-87-02, GL-87-2, VPNPD-87-486, NUDOCS 8711200293 |
Download: ML20236Q799 (2) |
|
|
---|
Category:LEGAL TRANSCRIPTS & ORDERS & PLEADINGS
MONTHYEARNPL-97-0357, Comment Opposing Proposed NRC Bulletin 96-001,suppl 1, CR Insertion Problems1997-06-19019 June 1997 Comment Opposing Proposed NRC Bulletin 96-001,suppl 1, CR Insertion Problems DD-97-15, Director'S Decision DD-97-15 Re Petitioners Request That NRC Prohibit Loading of VSC-24 Until Coc,Sar & SER Amended Following Independent third-party Review of VSC-24 Design. No Adequate Basis Exists for Granting Petitioners Request1997-06-18018 June 1997 Director'S Decision DD-97-15 Re Petitioners Request That NRC Prohibit Loading of VSC-24 Until Coc,Sar & SER Amended Following Independent third-party Review of VSC-24 Design. No Adequate Basis Exists for Granting Petitioners Request ML20141B0451997-06-0909 June 1997 Requests Extension of Comment Period for NRC Bulletin 96-001,suppl 1 Re Control Rod Insertion Problems ML20198R1511997-03-0505 March 1997 Transcript of 970305 OI Interview of Aj Cayia in Two Rivers, Wi Re NRC Investigation Case 3-97-008.Pp 1-70 ML20198R1361997-03-0404 March 1997 Transcript of 970304 OI Interview of DF Johnson in Two Rivers,Wi Re NRC Investigation Case 3-97-008.Pp 1-37 ML20198R0931997-03-0404 March 1997 Transcript of 970304 OI Interview of Rj Harvey in Two Rivers,Wi Re NRC Investigation Case 3-97-008.Pp 1-28. Supporting Documentation Encl ML20198R1111997-03-0404 March 1997 Transcript of 970304 OI Interview of E Ziller in Two Rivers, Wi Re NRC Investigation Case 3-97-008.Pp 1-33.Supporting Documentation Encl ML20198R1281997-03-0404 March 1997 Transcript of 970304 OI Interview of T Malanowski in Two Rivers,Wi Re NRC Investigation Case 3-97-008.Pp 1-28 ML20134B7371997-01-27027 January 1997 Exemption from Requirements of 10CFR50.60 to Determine That Setpoint for LTOP Events Will Not Present Undue Risk to Public & Safety.Exemption Granted NPL-95-0321, Comment on Proposed 10CFR50.54(p) Re Process for Changes to Security Plans W/O Prior NRC Approval.Supports Proposed Clarification of Language in 10CFR50.54(p)1995-07-11011 July 1995 Comment on Proposed 10CFR50.54(p) Re Process for Changes to Security Plans W/O Prior NRC Approval.Supports Proposed Clarification of Language in 10CFR50.54(p) ML20085E6541995-06-13013 June 1995 Comment Re Draft NUREG/BR-0199, Responsiveness to Public. Expresses Concern on Dry Cask Storage W/Exemption Given to VSC-24 Cask & Procedures for Unloading & Transport at Plant ML20078F4831994-12-20020 December 1994 Comment on Proposed Rule 10CFR50 Re Shutdown & low-power Operations for Np Reactors.Informs That Util of Belief That NRC Already Has Appropriate Regulatory Authority Over Shutdown & low-power Operations,As Provided in Maint Rule ML20077E8361994-12-0101 December 1994 Comment Opposing Proposed Rule 10CFR50 Re Shutdown & Low- Power Operations for Nuclear Power Reactors ML20059E9331993-10-27027 October 1993 Comment Supporting Proposed Rule 10CFR171 Re Restoration of Generic Exemption from Annual Fees for Nonprofit Educational Institutions ML20045D7331993-06-13013 June 1993 Comment on Proposed Rule 10CFR26 Re Mods to fitness-for-duty Program Requirements.Recommends That NRC re-evaluate Proposed Testing Frequency Due to Random Testing Rate of 50% Sufficient to Provide Continued Detection Effectiveness ML20127D7191992-09-0606 September 1992 Comment on Proposed Rule 10CFR72 Re Approval of Two Addl Dry Cask Storage Designs.Opposes Rule ML20127D6371992-09-0303 September 1992 Comment on Proposed Rule 10CFR72 Re Approval of Two Addl Dry Cask Storage Designs.Opposes Rule & Urges NRC to Extend Comment Period in Order for Concerned Citizens to Prepare Thorough List of Objections ML20114D2591992-08-24024 August 1992 Comment Opposing Proposed Rule 10CFR72 Re Proposal to Store Spent Nuclear Fuel in VSC-24 Storage Casks at Plant in State of Wi ML20073N1141991-05-10010 May 1991 Comment Supporting Proposed Rules 10CFR71,170 & 171, Rev of Fee Schedules;100% Fee Recovery ML20058D4831990-10-15015 October 1990 Comment Supporting Proposed Rules 10CFR2,50 & 54 Re Nuclear Power Plant License Renewal ML20235S8381989-02-22022 February 1989 Comment Opposing Proposed Rules 10CFR50 & 55 Re Degree Requirement for Senior Reactor Operator (Sro).Unless Grandfathered in Next 4-5 Yrs Author to Be Locked Out of Job & Does Not Intend Spending 20 Plus Yrs as Reactor Operator ML20235N8341989-02-17017 February 1989 Comment Opposing Proposed Rule 10CFR50 Re Effectiveness of Maint Programs for Nuclear Power Plants ML20148K5591988-03-18018 March 1988 Comment Supporting Proposed Rule 10CFR50,App J Re Mass Point Method of Data Analysis.Recommends Test Duration Criteria in ANSI/ANS-56.8-1987,Section 5.4 Be Accepted in Revised Regulations ML20236Q7991987-11-0909 November 1987 Comments on Proposed Rev 2 to Reg Guide 1.100 Re Seismic Qualification of Electrical & Mechanical Equipment for Nuclear Power Plants ML20235V8231987-10-13013 October 1987 Order Imposing Civil Monetary Penalty in Amount of $50,000 Based on Violations Noted During Special Physical Security Insp on 860718-0807 ML20136E0511985-11-20020 November 1985 Memorandum & Order Granting Licensee 850826 Request for Extension of Deadline for Environ Qualification of Electrical Equipment to 860525 for Unit 1 & 851231 for Unit 2.Served on 851120 ML20137C8601985-11-19019 November 1985 Transcript of Commission 851119 Affirmation/Discussion & Vote in Washington,Dc Re SECY-330(a) on Point Beach & SECY-225(a) on Sequoyah.Pp 1-5 ML20138M8711985-10-25025 October 1985 Transcript of 851025 Meeting in Washington,Dc Re Util Requests for Exemption from Environ Qualification.Pp 1-76 ML20078L1661983-10-17017 October 1983 Response Opposing Wisconsin Environ Decade 830923 Petition for Review of ALAB-739 Re Steam Generator Tubes Repaired by Sleeving.Nexus Between Sleeving & Tube Failure Shown. Certificate of Svc Encl ML20078C8801983-09-23023 September 1983 Petition for Review of Aslab 830907 Decision on Sleeving Degraded Steam Generator Tubes.Aslab Erroneously Denied Nexus Shown Between Sleeving & Tube Failure.Certificate of Svc Encl ML20076E1581983-08-22022 August 1983 Response Opposing Wisconsin Environ Decade 830811 Request to Respond to Hf Conrad Affidavit.Aslab Affirmed Dismissal of Decade Petition to Intervene.Decade Thus Lacks Party Standing.Certificate of Svc Encl.Related Correspondence ML20204G3481983-04-29029 April 1983 Brief Opposing Wisconsin Environ Decade Exceptions to ASLB 830204 Initial Decision Authorizing full-scale Sleeving. Exceptions Waived for Failure to Brief or Arguments W/O Merits ML20069K5951983-04-22022 April 1983 Answer Opposing Wisconsin Environ Decade 820407 Petition for Review of ALAB-719 Which Affirmed ASLB 821210 Special Prehearing Conference Order Dismissing Petition to Intervene.Matter Raised Not Reviewable.W/Certificate of Svc ML20073D6991983-04-11011 April 1983 Request for Extension Until 830427 to File Opposition to Wisconsin Environ Decade Brief on Exceptions.Counsel Has Numerous Obligations Before ASLB & Aslab.Certificate of Svc Encl ML20073B9701983-04-0707 April 1983 Petition for Review of Aslab 830322 Decision Denying Wisconsin Environ Decade 821220 Appeal of ASLB 821210 Prehearing Conference Order.Hearing on Steam Generator Tube Degradation Issue Should Be Held.Certificate of Svc Encl ML20069F6491983-03-16016 March 1983 Brief Supporting Wi Environ Decade 830211 Exceptions to ASLB Initial Decision.Aslb Refused to Make Prerequisite Findings on Degree of Assurance Necessary to Protect Public Safety. Affidavit of Mailing Encl ML20071A1311983-02-14014 February 1983 Exceptions to ASLB 830204 Initial Decision.Affidavit of Mailing Encl ML20064H4191983-01-10010 January 1983 Replacement P 2 of 821220 Proposed Findings of Fact & Conclusions of Law in Form of Proposed Initial Decision. Svc List Encl ML20070M0571983-01-0707 January 1983 Comments on Wi Environ Decade Statement of Inadequate Record.Statement Is Inconsistent W/Commission Regulations, Erroneous in Statement of Law,Untimely,Devoid of New Factual Info & Should Not Be Considered.Certificate of Svc Encl ML20028C3031983-01-0404 January 1983 Brief Opposing Wi Environ Decade 821220 Appeal of ASLB 821210 Special Prehearing Conference Order Denying Decade 820810 Petition to Intervene.Decade Willfully Failed to Attend Special Prehearing Conference.W/Certificate of Svc ML20028C3091983-01-0404 January 1983 Proposed Evidentiary Hearings Transcript Changes.Certificate of Svc Encl ML20070M0141982-12-30030 December 1982 Statement of Inadequate Record.Eddy Current Testing Not Proved Adequate for Sleeving Steam Generator Tubes.Record Must Be Reopened.Certificate of Svc Encl ML20070J0141982-12-20020 December 1982 Notice of Appeal from 821210 Special Prehearing Conference Order Dismissing Decade 820810 & 1105 Petitions to Intervene.Affidavit of Mailing Encl ML20070J0341982-12-20020 December 1982 Brief Supporting Appeal from 821210 Special Prehearing Conference Order Denying 820810 Petition to Intervene & Request for Extension of Time to Complete Brief.Dismissal of Petition on Stated Grounds Contrary to Law ML20070H4011982-12-20020 December 1982 Proposed Findings of Fact & Conclusions of Law in Form of Proposed Initial Decision Re Repair of Corroded Steam Generator Tubes by Inserting Sleeves.Certificate of Svc Encl ML20027E3171982-11-0505 November 1982 Contentions Re Steam Generator Replacement,Supplementing 820810 Petition to Intervene ML20027D4691982-11-0202 November 1982 Testimony of Wd Fletcher Re Adequacy of Eddy Current Testing.Certificate of Svc Encl.Related Correspondence ML20069J3451982-10-20020 October 1982 Notice of Appearance in Proceeding.Certificate of Svc Encl ML20065G3861982-09-28028 September 1982 Amend to Wi Environ Decade 820810 Petition to Intervene Including Affidavits Requesting Wi Environ Decade to Intervene on Affiant Behalf.Certificate of Svc Encl ML20063J4521982-08-31031 August 1982 Reply Brief Supporting Wi Environ Decade 820721 Motion Concerning Litigable Issues & in Response to Licensee 820809 & 24 & NRC 820812 Responses.Contentions Timely & Relevant. Certificate of Svc Encl 1997-06-09
[Table view] Category:PUBLIC COMMENTS ON PROPOSED RULES & PETITIONS FOR
MONTHYEARNPL-97-0357, Comment Opposing Proposed NRC Bulletin 96-001,suppl 1, CR Insertion Problems1997-06-19019 June 1997 Comment Opposing Proposed NRC Bulletin 96-001,suppl 1, CR Insertion Problems ML20141B0451997-06-0909 June 1997 Requests Extension of Comment Period for NRC Bulletin 96-001,suppl 1 Re Control Rod Insertion Problems NPL-95-0321, Comment on Proposed 10CFR50.54(p) Re Process for Changes to Security Plans W/O Prior NRC Approval.Supports Proposed Clarification of Language in 10CFR50.54(p)1995-07-11011 July 1995 Comment on Proposed 10CFR50.54(p) Re Process for Changes to Security Plans W/O Prior NRC Approval.Supports Proposed Clarification of Language in 10CFR50.54(p) ML20085E6541995-06-13013 June 1995 Comment Re Draft NUREG/BR-0199, Responsiveness to Public. Expresses Concern on Dry Cask Storage W/Exemption Given to VSC-24 Cask & Procedures for Unloading & Transport at Plant ML20078F4831994-12-20020 December 1994 Comment on Proposed Rule 10CFR50 Re Shutdown & low-power Operations for Np Reactors.Informs That Util of Belief That NRC Already Has Appropriate Regulatory Authority Over Shutdown & low-power Operations,As Provided in Maint Rule ML20077E8361994-12-0101 December 1994 Comment Opposing Proposed Rule 10CFR50 Re Shutdown & Low- Power Operations for Nuclear Power Reactors ML20059E9331993-10-27027 October 1993 Comment Supporting Proposed Rule 10CFR171 Re Restoration of Generic Exemption from Annual Fees for Nonprofit Educational Institutions ML20045D7331993-06-13013 June 1993 Comment on Proposed Rule 10CFR26 Re Mods to fitness-for-duty Program Requirements.Recommends That NRC re-evaluate Proposed Testing Frequency Due to Random Testing Rate of 50% Sufficient to Provide Continued Detection Effectiveness ML20127D7191992-09-0606 September 1992 Comment on Proposed Rule 10CFR72 Re Approval of Two Addl Dry Cask Storage Designs.Opposes Rule ML20127D6371992-09-0303 September 1992 Comment on Proposed Rule 10CFR72 Re Approval of Two Addl Dry Cask Storage Designs.Opposes Rule & Urges NRC to Extend Comment Period in Order for Concerned Citizens to Prepare Thorough List of Objections ML20114D2591992-08-24024 August 1992 Comment Opposing Proposed Rule 10CFR72 Re Proposal to Store Spent Nuclear Fuel in VSC-24 Storage Casks at Plant in State of Wi ML20073N1141991-05-10010 May 1991 Comment Supporting Proposed Rules 10CFR71,170 & 171, Rev of Fee Schedules;100% Fee Recovery ML20058D4831990-10-15015 October 1990 Comment Supporting Proposed Rules 10CFR2,50 & 54 Re Nuclear Power Plant License Renewal ML20235S8381989-02-22022 February 1989 Comment Opposing Proposed Rules 10CFR50 & 55 Re Degree Requirement for Senior Reactor Operator (Sro).Unless Grandfathered in Next 4-5 Yrs Author to Be Locked Out of Job & Does Not Intend Spending 20 Plus Yrs as Reactor Operator ML20235N8341989-02-17017 February 1989 Comment Opposing Proposed Rule 10CFR50 Re Effectiveness of Maint Programs for Nuclear Power Plants ML20148K5591988-03-18018 March 1988 Comment Supporting Proposed Rule 10CFR50,App J Re Mass Point Method of Data Analysis.Recommends Test Duration Criteria in ANSI/ANS-56.8-1987,Section 5.4 Be Accepted in Revised Regulations ML20236Q7991987-11-0909 November 1987 Comments on Proposed Rev 2 to Reg Guide 1.100 Re Seismic Qualification of Electrical & Mechanical Equipment for Nuclear Power Plants 1997-06-09
[Table view] |
Text
- - .__
- v .Q$Of _ __
Q '
) k f );y.}sVf'q A
I f k-DOCKETED USNRC -
L L RULES & PROCEDURES BR -
ORP:ADM WNSCORSin POWER COMPANY 231 W. MICHIGAN, P.O. BOX 2046, MILWAUKEE, WI 53201 17 NOV .13 A10 :34 - em 277 234s ge. m be l 17')
lE"87Ni86 8
5g m Wllo November 9,.1987 Rules & Procedures Branch Division of Rules and Records.
Office of Administration and Resources Management US NUCLEAR REGULATORY COMMISSION Washington, DC 20555 Gentlemen:
COMMENTS ON PROPOSED REVISION 2 TO REGULATORY GUIDE 1.100, SEISMIC QUALIFICATION OF ELECTRICAL AND MECHANICAL EQUIPMENT FOR NUCLEAR POWER PLANTS In response to your letter of August 14, 1987, which forwarded proposed Revision-2 of the subject regulatory guide, the following comments.are offered:
- 1. The subject regulatory guide requires case by case approval for qualification of equipment, 'using earthquake experience. This is in' conflict with NRC Generic Letter 87-02, which permits generic qualification of_ equipment based on data obtained from earthquake sites,-using a. methodology developed by the Seismic Qualification Utility Group (SQUG). The regulatory
. guide should endorse the SQUG methodology being reviewed by the NRC Staff.
- 2. The proposed Regulatory Guide 1.100 applies IEEE-344-1987 to pipe supports, snubbers, restraints and hangers.
This proposed qualification method is inappropriate for these ,
devices and is not consistent with NUREG-0800, Standard Review J Plan, Sections 3.9.2, 3.9.3, 3.9.4 and 3.10. The ASME, ANSI and AISC codes have been demonstrated by experience to adequately address these components. For example, a hydraulic snubber's lockup velocity, bleed velocity and displacement prior to lockup are important for it to perform its design function during an earthquake. These variables are not addressed by the proposed regulatory guide. The regulatory guide should be revised to remove mechanical equipment from the scope.
8721200293 871109 PDR 01,100REcco PDR
- _ - kh sauz"///n/7
L p. .
NRC, Rules & Records Div.
November 9, 1987 Page 2
- 3. IEEE-344-1987 requires justification of similarity of each equipment item to be seismically qualified by experience.
SQUG experience in resolution of Unresolved Safety Issue A-46 indicates that a broad and diverse data base applicable to generic types of equipment is the preferred approach. The regulatory guide should explicitly endorse the SQUG methodology now being reviewed by the NRC Staff for twenty classes of equipment.
We will be pleased to discuss these comments with you.
Very truly yours,
,v f l'wf'y C. W.
Vice / President Fay Nuclear Power l