ML20055B411

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-454/82-05 & 50-455/82-04 on 820329-0511. Noncompliance Noted:Failure to Assure Contractors Are Operating W/Qa Organization Described in QA Manual & Failure of Site Contractors to Control Documents
ML20055B411
Person / Time
Site: Byron  Constellation icon.png
Issue date: 06/16/1982
From: Danielson D, Forney W, Keshishian P, Love R, Nightingale E, Peschel J, Wescott H
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML20055B409 List:
References
50-454-82-05, 50-454-82-5, 50-455-82-04, 50-455-82-4, NUDOCS 8207220171
Download: ML20055B411 (74)


See also: IR 05000454/1982005

Text

a

e

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

i

Report Nos. 50-454/82-05(DETP); 50-455/82-04(DETP)

Docket Nos. 50-454; 50-455 License Nos. CPPR-130; CPPR-131

Licensee: Commonwealth Edison Company

P. O. Box 767

Chicago, IL 60690 1

Facility Name: Byron Station, Unit 1 and 2

Inspection At: Byron Site, Byron, IL

Inspection Conducted: March 29-31, April 1-2, 5-9, 12-14, and May 11, 1982.

Inspectors:

.lwin.. i/f~

D. H. D ielson l/ [#'

??

//@. M. Peschel d[/4/PL

d

R. S. Love S/;2.//9'A.,

W47176baf

H. M. Wescott d' g ,ffa

'

ogL..n/h -

d ## *

I,dE.H. Nightingale

.

M9A,aJun

W. Forney

(SRI Byron)

. 6/lu

l-

210 8

shishian 6//4/87__

E Headquarters) '

Approved By:

47 8i A llo-

D. Danielson, Chief 0!/0l'l'

.

Materials and Processes Section

Inspection Summary

Inspection on March 29-31, April 1-2, 5-9, 12-14, and May 11, 1982 (Reports

No. 50-454/82-05(DETP); 50-455/82-04(DETP))

8207220171 820624

PDR ADOCK 05000454

O PDR

.. - . - - - =.- --._ - _ - - . .

.

.

,

Areas Inspected: QA Program interfaces and overview; corrective action

systems; design change control; material traceability of installed struc-

tures and components; electrical cable installation; inprocess inspections;

QC inspector ef fectiveness. The inspection involved a total of 662 in-

spector-hours onsite by seven NRC inspectors.

Results: Of the areas inspected nine apparent violations were identified

(failure to assure contractors are operating with a QA organization as

described in their QA manual and to assure that QA is sufficiently inde-

pendent from cost and schedule - paragraphs b.(6).(b), b.(8).(b), and

b.(10).(b); failure of site contractors to control the issuance of docu-

ments - b.(10).(b); failure of site contractors to follow their procedures

paragraphs b.(10).(b), and c.(2),(d).2; failure of site contractors to

, accomplish activities in accordance with procedures paragraphs b.(10).(b),

i

c.(2).(e).1, and f.(2).(a); failure to include certain ANSI N45.2.12

criteria in CECO audit reports of contractors - paragraph b.(10).(b);

failure of a site contractor to meet certain security standards established

l by ANSI N45.2.9 for storage of records - paragraph b.(10).(b); failure to

I meet ANSI N45.2.6 qualification, certification and training requirements

for contractor QC inspectors - paragraph h.(2); failure to specify complete

and adequate corrective actions on nonconformance reports - paragraph

c.(2).(a).4; failure to accomplish welding in accordance with applicable

codes paragraph g.(2).(d).

i

d

l

l

i

1

4

3

2

. - _ , -

. _ -. _ _ _ _ - .

.

.

DETAILS

1. Persons Contacted

Commonwealth Edison Company (CECO)

  • W. Stiede, Assistant Vice President
  • L. DelGeorge, Director of Nuclear Licensing
  • V. I. Schlosser, Project Manager
  • W. J. Shewski, Quality Assurance Manager
  • G. Sorensen, Project Superintendent
  • R. Tuotken, Assistant Project Superintendent
  • M. A. Stanish, QA Superintendent, Byron

R. J. Farr, QA Supervisor

K. J. Hansing, QA Supervisor

T. R. Sommerfield, QA Superintendent, Braidwood

J. J. Mihovilovich, Structural Supervisor, PCD

R. B. Klingler, QA Qupervisor, PCD

G. F. Marcus, Director of QA, Engineering / Construction

J. O. Binder, Electrical Supervisor, PCD

M. E. Lohmann, Mechanical Supervisor, PCD

C. J. Tomashek, Startup Coordinator

H. J. Kaczmarek, QA Engineer

A. A. Jaras, Project Operations Analysis Supervisor

  • T. Tramm, Nuclear License Administrator

P. Donavin, Project Engineering Department

R. E. Querio, Startup Superintendent

  • J. T. Westermeier, Project Engineer

R. Gruber, QA Engineer

J. Klink, QA Inspector

P. Nodzenski, QA Engineer

J. Toney, Engineering Assistant

P. Macuiba, QA Engineer

K. Key, Senior Buyer

L. Channell, Material Coordinator

R. Schwartz, QA Engineer

Sargent and Lundy Engineers (S&L)

R. Rabin, Senior QA Coordinator

D. Demoss, Engineer, PMD

  • T. B. Thorsell, Senior Electrical Project Engineer

V. Crisci, Project Leader

J. Kelnosky, Electrical Project Leader

Westinghouse (W)

D. R. Fraser, Manager, SAMU

S. Stahl, QA Engineer, NTD

Y. Kau, Associate Engineer, PIDG

3

.

.

Hatfield Electric Company (HECo)

G. Vanderhei, Project Manager

J. Buchanan, QA Hanager

A. Koca, QC Supervisor

R. Barzeloski, QA Supervisor

D. Stoner, QC Foreman

L. Broege, QC Inspector

J. Mulrene, QC Inspector

Powers-Azco-Pope (PAP)

R. Larkin, QA Manager

M. Donahoe, Engineering Manager

C. Cremer, QC Supervisor

A. Limia, QC Inspector

Blount Brothers Corporation (BBC)

R. H. Bay, QA/QC Manager

W. Wills, QC Inspector

Ebasco Services, Inc.

R. Detommaso, NDE Supervisor

Johnson Controls, Inc.

B. Shah, QA Manager

S. Pearson, QC Inspector

Pittsburgh Testing Laboratory (PTL)

J. Troutman, Site Manager

J. Chasm, Calibration Technician

G. Mohammad, Site Auditor

Mi_dway Industries Contractor, Inc.

M. Windsor, Site Manager

Nuclear Installation Services Company (NISCo)

J. Pruitt, QA/QC Manager

Nuclear Power Services (NPS)

W. Whitaker, Project QA Engineer

Relleable Sheet Metal Works, Inc.

A. M. Schlegel, QA Supervisor

4

_ - _ _ ____-_- _ -_

'

.

.

a

Hunter Corporation

M. Somsag, QA Supervisor

L. Haddick, QC Inspector

D. Corasani, Piping Engineer

L. Hill, Auxiliary Building Superintendent

W. Evertt, Containment Building Superintendent

D. Askland, Warehouseman

J. Morrison, Project Engineer

J. Young, Hanger Engineer

A. Simon, Administrative Supervisor, QA

R. Irish, Administrative Assistant, QA

H. Lundquist, Material Control Supervisor

U.__S. Nuclear Regulatory Commission (Region III)

  • C. E. Norelius, Director, Division of Engineering & Technical Programs

W. S. Little, Chief, Engineering Inspection Branch

L. McGregor, Senior Resident Inspector, Braidwood

L. Cox, Secretary

  • Denotes those presonnel attending the exit meeting held at the USNRC

Region III office on May 7, 1982. During the inspection at the Byron

Station exit meetings were held on a daily basis in order to keep the

licensee informed of any findings.

The inspectors also contacted and interviewed other licensee and

contractor personnel during this inspection.

2. Function or Program Areas Inspected

a. General Background

The purpose of this special team inspection was to determine if

there are indications of existing or potential construction

problems similar to some of those identified at a number of other

plants under construction. The scope of the assessments included

quality assurance program interfaces and overviews, corrective

action systems, design change control, material traceability of

installed structures and components, electrical cable installa-

tion, inprocess inspections, and effectiveness of quality control

inspectors.

5

.. .. . ..

_- __ - _ _ _ _ _ _ _ - - _ _ _ -

____ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ __ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _

.

.

.

-

.

-

~

o

Prepared By: J. M. Peschel

P. Keshishian

b. QA Program Interfaces and Overview

(1) Quality Assurance Manuals Reviewed

Pittsburgh Testing Laboratory Quality Assurance Manual

  1. QA-M-1, Revision 4, September 21, 1979

Powers-Azco-Pope Quality Assurance Manual, Revision 3,

! December 7, 1981

l

Commonwealth Edison Topical Report, Revision 20,

February 17, 1982

Johnson Controls, Inc., SECD Quality Assurance Program,

Revision 0, June 29, 1978

Hatfield Electric Company Quality Assurance Manual,

Revision 9, August 13, 1979

Ebasco Nuclear Quality Assurance Program Manual, Revision 10,

September 30, 1981

Hunter Corporation Quality Assurance Manual, Revision 5,

August 1, 1981

Nuclear Power Services, Inc., Quality Assurance Manual,

Fevision 1, January 13, 1981

Reliable Sheet Metal k'orks, Inc. , Quality Assurance Manual,

July 21, 1981

(2) Procedures Reviewed

(a) Commonwealth Edison Company

Byron Quality Instruction (BQI)

BQI-1, Revision 2, March 22, 1982

Generating On-Site Quality Instructions

BQI-7.1, Revision 2, March 22, 1982

On-Site Contractor Non-Conformance Reports

BQI-7.2, Revision 5, March 22, 1982

QA Handling of CECO Non-Conformances

BQI-9, Revision 4, March 22, 1982

QA Handling of Field Change Requests

BQI-10, Revision 4, February 25, 1982

Site QA Handling and Review of On-Site

Contractor Procedures

6

_ _ _ _ _ _ _ _ - _ - - _ - - _ _ - - - _ _ _ - _ - _ _ _ _ _ _ _ _

.. - .- _ . _ _- _ _ - .- - . . .

.

a

'

BQI-11.1, Revision 4, March 22, 1982

Byron Site QA Audits

BQI-12.1, Revision 1, March 22, 1982

Installed Equipment Surveillance Instructions

, BQI-24, Revision 1, March 22, 1982

Byron QA Training Program

Byron Site Instruction (BSI)

BSI-5, Revision 5, October 20, 1980

Material and Equipment Receiving, Receiving

Inspection Storage, and Removal from Storage

- Instruction

Quality Procedure (QP)

. QP, 2-1, Procedure for the Revision of the Quality

Assurance Manual - Engineering, Construction

and Operation, Revision 63, February 24, 1982

QP, 2-2 Training of Personnel to meet Quality Assurance

Requirements, Revision 63, February 24, 1982

QP, 3-3, Classification of System, Components, Parts

and Materials, Revision 63, February 24, 1982

1

QP, 4-2, Evaluation of Contractor's Quality Assurance

Program, Revision 63, February 24, 1982

QP , 5 - 1, Quality Instruction and Procedures,

i Revision 63, February 24, 1982

QP , 7 - 1, Control of Procured Material and Equipment,

Receiving and Inspection, Revision 63,

February 24, 1982

QP, 12-1, Calibration Control of Commonwealth Edison

Test and Measurement Equipment, Revision 63,

February 24, 1982

QP, 15-1, Reporting Quality Nonconformance during

Construction and Test, Revision 63,

February 24, 1982

I QP, 15-2, Reporting Incidents and Deficiencies that

occur during Construction and Test, Revision

63, February 24, 1982

QP, 16-1, Corrective action for Reportable Deficiencies

and Quality Nonconformances that occur during

Construction and Tests, Revision 63,

-February 24, 1982

QP, 17-1, Quality Assurance Records, Revision 63,

February 24, 1982

QP, 4- 1, Request for Bid, Proposed Evaluation, and

Recommendation, Revision 63 February 24, 1982

QP, 18-1, Quality Program Audits, Revision 63,

February 24, 1982

QP, 18-2, Surveillance of Contractor Quality Assurance

Control Activities, Revision 63, February 24,

1982

!

7

l

__ ., _ . . . . . . _ __ .,,

_. __ . . .

.

&

General Procedure

General Procedure No. 738, Site Buying, February 2, 1981

(b) Hatfield Electric Company Procedures

Procedure #6, Revision 6, January 15, 1982

Reporting of Damaged or Nonconforming

Material or Equipment

Procedure #8, Revision 2, Issue 1, July 6, 1981

Audits

Procedure #9E, Revision 6, Issue 1, January 23, 1981 ,

Class I Cable Pan Identification

Procedure #11, Revision 12, February 2, 1982

Class I Cable Termination and Splicing

Procedure #17, Revision 2, October 10, 1981

Qualification of Inspection and Audit

Personnel

Procedure #19, Revision 4, Issue 1, January 24, 1981

Equipment Turnover Reporting

Procedure #20, Revision 8, November 20, 1981

Class I Exposed Conduit System

Identification

Procedure #23, Revision 8, Issue 1, January 22, 1981

Concrete Expansion Anchor Installation

Procedure #24, Revision 1, Issue 2, January 28, 1980

Control and Calibration of Meters and

l

'

Instruments

Procedure #29, Revision 5, November 20, 1981

Field Initiated Request for Design

Changes

(c) Hunter Corporation Site Implementation Procedures

'

4.201 Revision 4, January 19, 1982

Installation Verification

7.502 Revision 7, Augast 20, 1981

Control of Measuring and Testing Equipment

11.101 Revision 4, April 28, 1981

Nonconformance Processing

12.301 Revision 5. March 19, 1981

Internal and External Site Quality Assurance

Audits

i 20.513 Revision 9 June 8, 1981

Installation of Concrete Expansion Anchors

(d) Powers-Azco-Pope Procedures

QC-4 Revision 7, September 30, 1981

Nonconformance Control

QC-5 Revision 5, December 17, 1981

Site Audit

8

.-. .- -

. - , - -

.

o O

.

FP-3 Revision 9, December 22, 1981

Material Receiving-Inspection Controls . ,

FP-4 Revision 5, September 30, 1981 ,

-

Material Storage .

> ,

FP-11 Revision 7, January 21, 1982 , e " ,-

'

Calibration and Control of Measuring,and Test ,- , .

Equipment (M&TE) , ' '3 'I . ;_ m ,

. ..  ; n. ,< /

l, ~

(e) Pittsburgh Testing Laboratory-Procedure ,  ; . , ,

y

.

- -

Resident Internal Quality Assurance Audit, I'lan, *

', - l.

,

Revision 4, November 17, 1981 , i  % -

..

7

>

f 1'

(f) Johnson Controls Inc., Procedures , ,

'-

. n . ,. ,

, . . . , ,

.-

. .~,

QAS-210-BY Revision 2, January 28, 1980 ,

/

Auditor Training and Qualification , ,

,

'

V'.

QAS-211-BY Revision 2, February 5, 1980 , , '

/s ,

Training and Indoctrination, Procedure , ,,...

QAS-710-BY Revision 1, September 19, 1979 -

-

-

On-Site Document Control Procedure ,.

'

's

'

QAS-1011-BY Revision 3, January 10;- 1980. . <-

Weld Rod Control ""b '

<

QAS-1310-BY Revision 1,'Ocotober 30, 1979 , /, ' < e /-

Calibration Cctitrol 9f, Measuring and Test M

Equipment / 1 ,-

.

l ~

[ ,

QAS-1510-BY Revision 0, Ap311-D , 1979-- -

'

ss

Status Tag Usage Procedure .

.f

QAS-1610-BY Revision 0, February 13,,1979 - **

f

Nonconformance Control Procedure j >

-

'

QAS-1710-BY Revision 0, September 16,. 1,9/9 , , -j

Corrective Action -

'

7 -

QAS-1910-BY -Revision 1, November 8, 1979 .

.-

s ~ -; 'g

Audit Procedure '

s

SP-611-BY Revision 1, April 3, 1981 h '

Field Change Control Procedure ,

!

(3) Audits and Miscellar.cous Documentation Reviewed M

(r.) Commonwealth Edison Comp'any re *

, e- , .

Audit Reoorts  ?' *

l .

,,,j

  1. 6-82-4 . , /
  1. 6-82-08 -

-

  1. 6-81-300 , , , ,
  1. 6-81-308 , .
  1. 6-81-309 .

'

>

  1. 6-81-330 '+O.. , / - ,'
  1. 6-81-331

" '

) > '

f / .

  1. 6-81-336

~

.

~

~ "

  1. 6-81-340 '

j ,s

,,

J, o

,

s .' , .

<

-

. , , - -' 7

/ i  !

'

.- , 3

-

]

e

.

.. .,

e .s

_ _ . . . .

..

.

.

  1. 6-81-344
  1. 6-81-354
  1. 6-81-357
  1. 6-81-360

.

General Office Audit of Byron Construction Site,

~

April 30, 1981.

'

General Office Audit of Byron Construction Site,

November 8, 1981.

General Office Quality Assurance Audit of Byron

Station, April 30, 1981.

'

Gene ~ral Office Quality Assurance Audit of Byron

-

Station, Noveraber 8, 1981.

Management Audit at LaSalle, Byron, and Braidwood

Construction Sites and the LaSalle Operating Station,

April, 1981, by Energy Incorporated.

Miscellaneous Documentation

c. Site Mechanical Organization Chart, March 16, 1982.

L Site Electrical Organization Chart, March 16, 1982.

n g. Site Structural Organization Chart, March 16, 1982.

'

Site Project Construction Organization Chart, March 16,

1982.

1981 Byron Site QA Audit Schedule, Revision 0 and

/,< Revision 9.

'

[' 198'l-Byron Site QA Survie11ance Schedule.

-

../ Byron Quality Assurance Organization Chart, March 22,

F

' . 1982.

'

Byron Quality Assurance Status Reports, January 5, 1982

and February 4, 1982.

'

. Byron Site Quality Assurance Semi-Monthly Report for

. December 1981.

,

,

1982 Byron Site Quality Assurance QP Training Schedule.

'** (b) Hatfield Electric Company

-

.- Audit Reports

'

-

~v #81-OR

,

  1. S1-18

,

, , #81-19

"

7 #81-20

< , ,

  1. 82-04

.. . -

' ~~ ~

-r Audit Report of Byron Site Procedure 5, 6 and 22 by

'{i

~

"

Energy Incorporated, September 21, 1981.

- E Follow-up' Management Audit Report by Energy Incorporated,

-

September 21, 1981.

-

.

h.

10

_ _ _ _ _ _ _ _ _ .

_ -__- _ - - _ _ - - - - _ - _ _ _ _ . _ _ _ _ _ _ _ _ _ -

.

Trend Analysis Reports

  1. 2, July 24, 1981, 2nd Quarter of 1981
  1. 3, November 6, 1981, 3rd Quarter of 1981
  1. 4, 4th Quarter of 1981

, #1, March 25, 1982, 1st Quarter of 1982

Miscellaneous Documentation

Discrepancy Reports, " Trouble Letters" No.'s 640 - 670,

680 - 720.

1981 Audit Schedule

1982 Audit Schedule

Quality Assurance Audit Log

Memorandum from C. Van Lyssel to W. Brock concerning

Quality Assurance Organization, March 17, 1982.

(c) Hunter Corporation

Audit Report

No. 084-4

l

l Miscellaneous Documentation

!

Audit Summary

Fourth Quarter Audit Report

Follow-up Audit #1

Hunter Audit Summary Report for Fourth Quarter, 1981.

Hunter Corporation, Byron Site Quality Assurance Audit,

June 3, 1981.

Hunter Corporation Quarterly Nonconformance Report (NR)

I

Summary and Trend Analysis, December 29, 1981.

(d) Powers-Azco-Pope

Audit Reports

  1. 52 September 29, 1981
  1. 53 October 1, 1981
  1. 54 November 12, 1981
  1. 55 November 12, 1981
  1. 56 November 16, 1981
  1. 57 November 15, 1981.
  1. 58 November 25, 1981
  1. 59 December 3, 1981
  1. 60 December 29, 1981
  1. 61 January 27, 1982

Management Review Audit, Byron, March 17, 1982

11

1

__-_N

_ .

.

Miscellaneous Documentation

Weekly Storage Surveillance Report, March 10, 1982

Weekly Storage Surveillance Report, March 17, 1982

Weekly Storage Surveillance Report, March 24, 1982

Weekly Storage Surveillance Report, March 30, 1982

(e) Pittsburgh Testing Laboratory

1

Audit Reports

  1. 81-21
  1. 81-22
  1. 81-23
  1. 81-24
  1. 81-25
  1. 81-26
  1. 81-27
  1. 81-28
  1. 81-29

Internal QA Audit #BY-3

Internal QA Audit #BY-4

'

Miscellaneous Documentation

Pittsburgh Testing Laboratory Organization Chart

Pittsburgh Testing Laboratory Inspectors Eye Examination

Records

(f) Jchnson Controls, Incorporated

Audit Reports

Yearly QA Program Audit No. 00501, May 16, 1980

Yearly QA Program Audit No. 10801, August 5, 1981

Audit Report, Bensenville Office, September 15, 1981

Nonconformance Reports

  1. 001BY November 14, 1980
  1. 002BY November 14, 1980
  1. 003BY December 4, 1980
  1. 004BY August 19, 1981
  1. 005BY February 23, 1982
  1. 006BY March 25, 1982
  1. 007BY April 2, 1982

(4) Interviews with Site Personnel

Interviews were conducted with sixteen personnel from Common-

wealth Edison Company, six personnel from Hunter Corporation,

three personnel from Powers-Azco-Pope, three personnel from

12

._ _-- - _ - _-__- _- ___-- - __--_ - ____ - _ _ _ . - - - _ _ - _ _

.

Hatfield Electric Company, two personnel from Pittsburgh

Testing Laboratory and one person from Johnson Controls,

Incorporated.

(5) Licensee's Quality Assurance Program

(a) Objective

The objectives of this assessment were to determine:

. that the licensee's Quality Assurance Program,

including all amendments, has been approved by NRR.

. if the licensee has control of changes to the

submitted Quality Assurance Program.

. if the Quality Assurance Manual is consistent with

the approved Qualit: Assurance Program.

(b) Discussion

The inspectors reviewed:

1. the licensee's Topical Report, CE-1-A, Revision 20,

and determined that the original program and all

subsequent revisions have been approved by NRR.

The licensee submits all changes to NRR and

includes minor or typographical changes at the

same time as substantive changes are submitted.

2. the licensee's Quality Requirements and Quality

Procedures and determined that the licensee

initiated and controlled changes to the program

through QP-2-1. The procedure requires the same

level of review for a QA Program change as the

original program received. The program has pro-

visions to input a change due to feedback of

experience, regulatory requireLents, codes and

standards, audits, and reviews.

3. the licensee's Quality Assurance Manual and referenced

documents to determine whether adequate QA plans and

procedures have been established (written, reviewed,

approved, and issued) to implement the docketed QA

program. The reivew indicated that the 18 Criteria

of 10 CFR 50, Appendix B were addressed by the

Quality Procedures of the Quality Assurance Manual.

The inspectors reviewed 6 of the 25 Quality Assurance

Manuals assigned to Byron Station to determine they

were of the latest revisions. The following manuals

were reviewed and no problems were detected.

13

1

. - . , - . _ , - , . , ,

. _- . _ _

-

I

l

4

  • l

Manual No. Assigned To

111 Project Construction Superintendent

208 Byron Station Superintendent

177 CECO OAD Supervisor

191 Byron Station Maintenance Supervisor

62 Byron Station Technical Staff Supervisor

115 Byron Station Quality Assurance Super-

intendent '

(6) Quality Assurance Program of Contractors

(a) Objectives

The objectives of this assessment were to determine

if the licensee has approved and routinely audits the

Quality Assurance Programs of contractors for consistency

with 10 CFR 50, Appendix B, and to determine the current

status and effectiveness of licensee management of the

on-site Quality Assurance Programs.

(b) Discussion

The inspectors reviewed documentation, conducted extensive

interviews with licensee and site contractor personnel,

and reviewed portions of the licensee's and contractor's

QA manuals to determine levels of staffing, organizational

independence from cost and schedule, position descriptions,

and to determine if the status and adequacy of the QA

Programs were_ regularly reviewed by the licensee and

contractor's management.

At the time of inspection the licensee had 13 contractors

on site and each was performing safety related work under

their own specific Quality Assurance Programs (QAPs).

These QAPs had been submitted to the licensee for review

and approval. The licensee had reviewed and approved

j the QAPs prior to the contractors start of work. The

,

licensee was fully aware of its ultimate responsibility

i for site Quality Assurance and had its own QA organiza-

tion on site to monitor the activities of the various

site contractors through the mechanisms of surveillances-

and audits.

Table 1 is a matrix of licensee and on-site contractors

performing safety-related work indicating the areas

checked and compliance with these areas.

1

'

Noncompliance (454/82-05-01a; 455/82-04-01a)

10 CFR 50, Appendix B, Criterion I, requires that "Such

persons and organizations performing quality assurance

functions shall report to a management. level such that

14

- -

__ ,. ._ - .. . . _ . _ _ - _ . ~ .

.

.

this required authority and organizational freedom,

including sufficient independence from cost and schedule

when opposed to safety considerations, are provided."

Contrary to this requirement, the inspectors found that

the QA Managers of both Hatfield Electric Company and

Powers-Azco-Pope (PAP) reported directly to on-site

managers who had direct responsibilities for cost and

schedule for their respective contracts. The Hatfield

QA Manager reported to the Vice-President and the PAP

QA Manager reported to the Project Manager.

Unresolved Item (454/82-05-02; 455/82-04-02)

In addition to the foregoing, it appeared that the QA

Representative for Johnson Controls had production

responsibilities that also conflicted with organizational

independence. A review of the activities of Pittsburgh

Testing Laboratories (PTL) indicates that there is no

PTL on-site QA organization other than a site auditor

and that for a substantial period of time each week PTL

activities are not under surveillance. This condition

occurs because there are two shifts for PTL inspectors

and only one auditor.

The questions regarding Johnson Controls and PTL could

not be resolved during the current inspection and are

an unresolved item.

(7) Licensee Management Assessment of the Quality Assurance Program

(a) Objective

The osjective of this assessment was to determine if a

periodic assessment of the licensee's Quality Assurance

Program is conducted by Commonwealth Edison Company

upper level management.

(b) Discussion

The inspectors reviewed audits of the Byron Construction

site conducted by a General Office Audit Team. These

semi-annual audits are supplemented'by a biennial audit

conducted by an independent auditing organization. The

audits cover the entire scope of the Quality Assurance

Program and are reviewed by upper level management.

The licensee's Quality Assurance organization is headed

by a site QA Superintendent. He is assisted by two

Supervisor's who direct the activities of thirteen QA

Engineers and Inspectors in monitoring and auditing

the activities of the site contractors. In addition

four Pittsburgh Testing Laboratory personnel are

assigned to the organization for specific documentation

related assignments.

15

.- . .. _ - _ _ _ _ _ ___ . _ _ _ _ _ _ _ - _

.

.

Each engineer and inspector is assigned a specific list

of responsibilities so that all contractor activites and

other QA monitoring systems are fully covered. This

type of organization should be able to effectively

monitor site QA activities. However, the execution of

the program is not satisfactory, as evidenced by the

many problems uncovered by the inspectors. One factor

,

affecting the execution is the stability of service for

the QA personnel.

A key individual in a QA Program is the on-site super-

intendent. He has the direct responsibility for the

QA performance of the contractors and other plant

related activities. It is he who anticipates problem

areas, sees to the training of his staff, directs the

activities of his staff and is instrumental in producing

a quality product. Since January 1976 there have been

five QA Superintendents at the Byron Site:

J. Pizzica January 1976 to May 1976

D. Jeritz May 1976 to August 1977

R. Gousden Augu.t 1977 to May 1978

T. McIntere May 1978 to January 1981

M. Stanish January 1981 to Present

In addition to this undesirable condition, the QA

Engineers and Inspectors have an average on-site s rvice

time of approximately fourteen months and have limited

prior QA experience. Part of this on-site time was

spent in training and qualifying for various QA duties.

In addition to this problem, manpower is currently being

sent to other sites so that the QA effort is substantially

weakened. Out of a staff of sixteen, three men have been,

and currently are at other assignments:

R. J. Schwartz La Salle Station 12/7/81 to 2/19/82;

3/19/81 to Present

J. S. Hale La Salle Station 1/8/81 to 2/26/8?;

3/19/82 to Present

P. J. Nodgenski Quad-Cities Station 9/14/81 to 9/25/81;

l Byron Pre-op Testing 4/5/82 to Present

The constant change over of personnel resulting in a

minimum experience level and transfer of personnel could

hinder the QA organization in meeting its obligation

of effectively implementing a QA program.

In contrast to the experience level of the QA organ-

ization the inspectors made a review of the stability

of the supervisory and engineering personnel in the

construction organization. The key individuals and

service time at the Byron Station are:

16

_ _ _ _ _ _ _ _ - _ - _ _ _ - _ _ - _ _

.

.

Title Name On Site Since

Project Superintendent G. Sorensen 1976

Assistant Project R. Tuetken 1977

Superintendent

Lead Civil Engineer J. Mihovilovich 1975

Lead Mechanical Engineer M. Lohmann *1981

Lead Electrical Engineer J. Binder 1978

  • Six years prior experience as a Mechanical Engineer at

La Salle County Station.

The pronounced difference in site time and experience

level indicates there is the potential for a problem

with QA personnel continually being transferred. In

an effort to determine the cause of this potential

problem a meeting was held with the Corporate Manager

of Quality Assurance, W. J. Shewski, on April 16, 1982.

His explanation was the the transfer of the QA Superin-

tendents was for promotional opportunities in four

cases and a death in the case of one superintendent.

His explanation for the large turnover and inexperience

level of the QA Engineers and Inspectors was that he

desired to seed the licensee departments with QA

experienced personnel and also not deny them promotional

opportunities.

This constant change over of QA personnel as contrasted

to the stable and experienced work force of the construc-

tion group indicates the need to create greater promo-

tional opportunities in the QA organization, or the need

to have some sort of system instituted to require QA

personnel to acquire minimum service time at nuclear

sites.

The inspectors reviewed the training that was given to

CECO QA personnel after they had completed corporate

quality assurance training. The Byron QA training is

an on-the-job type training and is intended to supple-

,

ment the corporate training and enhance the development

of new QA personnel.

A review of BQI-24. Revision 1, Byron QA Training

Program, revealed that although the stated purpose of

the instruction was to provide the necessary training

to appropriate personnel as quickly as possible, there

was no specified length of time in which the training

was to be completed. A lack of prompt training was a

finding annotated by the General Office Audit of

November 1981. A review of on-the-job training records

revealed that prompt training was still not being

accomplished and that the corrective action to prevent

17

_

_ _ _

.

.

recurrance, stated in the audit response, was not being

effectively implemented. The on-the-job training

system had no provision to alert supervisory personnel

when a new employee's training was lagging.

BQI-24 also states, "It is the new employees respons-

ibility to obtain and maintain the required training."

It is our belief that the training of new employees is

a management responsibility and cannot be delegated to

the new employee. *

Attachment A to BQI-24 lists fourteen areas of training,

and specific individuals are designated as authorized

trainers in each area. There are no lesson plans or

other types of written guidance for the required train-

ing. The lack of a formalized training program is not

conducive to the maintenance of a skilled, trained,

and competent Quality Assurance Department. With some

of the more experienced personnel assigned to duties

at other locations the training of the QA department

suffers.

Open Item (454/82-05-03; 455/82-04-03)

The inability of the licensee to dedicate resources to

the Quality Assurance organization to see that their

experience base is equivalent to other organizations,

leads the inspectors to question the licensee's

effectiveness in staffing the Quality Assurance Program

Organization. In addition, there is no evidence of a

Management Policy Statement emphasising the dedication

of the Company to Quality Assurance and quality in

general. The licensee's position is that the Company

policy is stated in the Quality Requirements of the

Quality Assurance Manual. It is our belief that these

are an explanation of the Quality Assurance Manual

and not a statement of policy.

(8) Licensee Quality Assurance Organization

(a) Objective

l The objective of this assessment was to determine if

the Quality Assurance Program provides sufficient

independence from cost and schedule.

l

(b) Discussion

The inspectors reviewed the organization charts in the

licensee's Topical Report and they indicate adequate

independence for the CECO Quality Assurance Organization.

Further inspection resulted in concern regarding the

activities of the Project Construction Department that

18

i

.

,

appear to be centrary to 10 CFR 50, Appendix B, Criterion-

I, regarding the independence of the Quality Assurance

effortWfrom production.

The licensee's site-Project Construction Department

is organized with a Manager, Technical Staff, Project

Engineers and Field Engineers. The inspectors inter-

viewed four supervisors and the assistant superin-

tendent of the construction group and found each of

them to be knowledgeable and experienced engineers

fully capable of meeting their respective respons-

ibilities. They all fully recognized the importance

of quality assurance and control and were determined

to build a quality plant.

The responsibilities of this group include:

. Advisor to Engineering for design suitability for

constructability.

. Coordinate requests for field revisions.

. Receipt and storage of materials.

. Assist Project Engineering in development of

overall schedule.

. Verify conformance and completeness of contractor's

installation to specification requirements.

. Supervise and approve mechanical and structural

construction tests.

. Coordinate and provif essistance for electrical

construction tests.

. Coordinate preoperation tests.

The Project Construction QC Supervisor and Project

Construction Electrical Supervisor have engaged in

Quality Assurance activities independent of the Byron

Superintendent of Quality Assurance and the offsite

Manager of Quality Assurance. The licensee could

not produce a position description for the areas of

responsibilities and the duties of the Project

Construction QC Supervisor. An example of specific

QA activities engaged in by these supervisors is:

. Letter of November 13, 1981 from the Electrical

and QC Supervisors to the on-site Vice President

of Hatfield Electric Company suggesting duties

and responsibilities of the QA/QC Manager and a

suggested organization chart.

The activities of the two supervisors in QA activities

i

appears to be contrary to 10 CFR 50, Appendix B, Criter-

-

ion 1, that requires independence of QA supervisors from

cost and schedule. In addition, it seriously undermines

the effectiveness of the incumbent QA Superintendent

r

l

19

L

.

.

to monitor the activities of the site QA organizations.

The activities of these two supervisors resulted in a

reorganization of the Hatfield Electric Company QA/QC

Department that was not described in the QA Manual.

We believe that CECO QA should, at a minimum, be in-

volved in a review and concurrence capacity when such

suggestions are made to contractors.

In addition to the foregoing, a further problem with

QA independence from cost and schedule arises in that

the site Project Superintendent has final contractual

approval for some contractor QA organizations concerning

salary increases, promotions, and hires for QA non-manual

personnel increases. The requests for such action from

Hatfield Electric Company and Powers-Azco-Pope do not

have a concurrence from the contractors Quality Assurance

Department and come from the project construction manage-

ment.

,

The following list indicate salary changes or promotions

of QA inspectors for site contractors that were approved

by the site Project Superintendent.

Date Contractor Position

2/24/82 Powers-Azco-Pope QA Specialist

12/8/81 Hunter Corporation QA Inspector

11/23/81 Hunter Corporation QA Inspector

11/3/81 Hunter Corporation QA Inspector

11/5/81 Hunter Corporation QA Inspector

The inspectors recognize that the Project Superintendents'

responsibility for contract administration requires his

final approval for contractors staff size and changes in

compensation, however, a question of satisfying the re-

quirements of 10 CFR 50, Appendix B, Criteria I relative

to QA independence arises. Mechanisms are currently now

in effect for such independence in that the Pittsburgh

Testing Laboratory contract is administered by the

Corporate Quality Assurance Manager who is independent

of cost and schedule.

Noncompliance (454/82-05-01b; 455/82-04-01b)

The lack of independence between the Quality Assurance

Department and the Project Construction Department is

in violation of 10 CFR 50, Appendix B, which states

in part, "Such persons and organizations performing

quality assurance functions shall report to a manage-

ment level such that this required authority and

organizational freedom, including sufficient inde-

pendence from cost and schedule when opposed to safety

considerations, are provided.

20

-_

.

.

Open Item (454/82-05-04; 455/82-04-04)

The involvement of the Project Construction Department

in Quality Assurance Activities indicates the need for

an Interface Document or Interface Procedure to explain

the interaction of the licensee's Quality Assurance

Organization with the Contractor's Quality Assurance

Organizations, and the relation of the Project Con-

struction Department to all on-site Quality Assurance

Organizations.

(9) Quality Assurance Responsibility

(a) Objective

The objective of this assessment was to determine if

the licensee has the prime responsibility for establish-

ing and executing the Quality Assurance Program.

(b) Discussion

The inspectors reviewed the Topical Report and the

Quality Assurance Manual and interviewed the licensee's

Corporate and Site Quality Assurance Managers and the

Quality Assurance Manager of selected contractors.

The documentction review and the interviews showed

that the responsibility of the licensee was established,

documented and understood by responsible personnel in

both the }1censee's and contactor's organizations.

The inspectors were concerned about the lack of a policy

statement from upper management that went beyond the

explanation provided in Quality Requirement 1.0 and pro-

vided assurance that upper management of CECO supported

the Quality Assurance Program and it objectives.

i (10) Licensee Oversight of Contractor Activities

l (a) Objective

t The objectives of this assessment were to determine

l if the licensee has effective oversight of contractor

' activities and has detailed knowledge of those

activities.

(b) Discussion

The inspectors conducted interviews with Quality Assurance

personnel from the licensee, Hatfield Electric Company,

[ Hunter Corporation, Powers-Azco-Pope, Johnson Controls,

} Inc., and Pittsburgh Testing Laboratory. These interviews

were supplemented by the review of related quality assur-

ance procedures, audits and documentations; tour of work

l

,

21

l

= _ _ _ .

..

.

areas, warehouses and field offices; and discussions with

licensee and contractor personnel. -As a result of the

above the inspectors determined that the licensee has a .

program that should provide an effective oversight of

contractor activities. The ability of the licensee to

provide this oversight is questionable due to the man-

power limitation discussed in the " Licensee Assessment

of the Quality Assurance Program" section of this report

and the findings noted below.

Contractor QA Manuals

A review of the operating organization of two contractors,

Hatfield Electric Company and Johnson Controls, .Inc.,

revealed that the present organizations were not described

in the latest Quality Assurance Manual revisions.

Johnson Controls, Inc., changed the title of the Senior

QA Representative associated with Byron from the Quality

Assurance Representative to the Quality Assurance Manager

and did not update their Quality Assurance Manual.

Johnson Controls operated for approximately five months

with this discrepancy, and Commonwealth Edison Company

Quality Assurance was not aware of the discrepancy.

Hatfield Electric Company was operating with a Quality

Control Supervisor and a Quality Assurance Supervisor,

both of whom report to the Quality Assurance Manager

and who are not reflected in the Quality Assurance

Manual. The reason for this disparity is a letter

from the licensee's Project Construction Department to

the Hatfield Electric Company Vice-President suggesting

an organization change.

Noncompliance (454/82-05-01c; 455/82-04-01c)

10 CFR 50, Appendix B, Criterion I states, "The

authority and duties of persons and organizations

l performing activities affecting the safety-related

I

functions of structures, systems, and components

shall be clearly established and delineated in

writing."

The failure of Hatfield Electric Company to have its

I

,

'

Quality Assurance Manual reflect the actual Quality

Assurance Organization is contrary to the above and is

an item of noncompliance.

The failure of Johnson Controls, Inc. , to have its

Quality Assurance Manual reflect the actual Quality

Assurance Organization is contrary to the above and

is an item of noncompliance.

22

- - - -

.

_- - _

.

.

The licensee has indicated that the above conditions

have been corrected. These items will be examined

during future inspections.

Safekeeping of Quality Records

A tour was made of the combined vault used by Johnson

Controls, Westinghouse-SAMU, Midway Industrial Con-

tractors, Ebasco Services, Inc., and Reliable Sheet

Metal. The safes of Westinghouse SAMU and Midway

Industrial Contractors were found unlocked and with no

attendant at the door of the vault. The Westinghouse

safe contained computer tapes which were described to

be non-safety-related and the Midway safe contained

quality records.

Noncompliance (454/82-05-05; 455/82-04-05)

10 CFR 50, Appendix B, Criterion XVII states, " Sufficient

records shall be maintained to furnish evidence of act-

ivities affecting quality." ANSI N45.2.9-1974 states,

"A full time security system shall be established to

preclude the entry of unauthorized personnel into the

storage area. This system shall guard against larceny

and vandalism."

The failure of Midway Industrial Contractors to lock

a safe containing quality records is contrary to the

above and is an item of noncompliance.

The licensee has indicated that this situation and the

condition of the Westinghouse-SAMU safe have been

corrected. This item will be examined during a future

inspection.

During tours of the combined vault, the Powers-Azco-Pope

,

vault, the Hatfield Electric Company vault and the li-

'

censee's vault, the inspectors noted that entrance holes

for conduit and other such piping had not been sealed

and possible air paths from the exterior existed.

Unresolved Item (454/82-05-06: 455/82-04-06)

ANSI N45.2.9-1974 states that permanent and temporary

l records storage facilities shall be constructed to

protect the contents from possible destruction by fire.

The inspectors are concerned that with the possible air

paths around conduits and pipes that the Halon System

may not be able to extinguish a fire.

The 'icensee has indicated that action has been taken

to correct this condition. This item will be examined

during a future inspection.

,

23

-_ . .. _ _ _ _ _ _ __

'

e

.

Surveillances

The inspectors reviewed the licensee's Quality Assurance

Department 1981 surveillance schedule and noted that

approximately seven percent of the scheduled surveil-

lances were not conducted and there was no documented

reason for their omission. The licensee did conduct

approximately 800 more surveilla_ces than were scheduled

with an increase being made in some areas due to problems

discovered or to follow up on audit findings. We

recognize that such increased attention is necessary,

but are concerned about the omission of surveillances

without substantiating documentation, as surveillances

are one of the intergal methods by which the Quality

Assurance Organization provides an oversight of con-

tractor activities.

Open Item (454/82-05-7; 455/82-04-7)

The inspectors are concerned about the omission of

scheduled surveillances without substantiating docu-

mentation.

The licensee indicated that this item will be corrected.

This item will be examined during a future inspection.

Drawing Control

The inspectors reviewed selected drawings in the on-site

office of Johnson Controls, Inc., and at Hunter Corpora-

tion's Document Station 1-H, at the 426 level in the

containment.

Twelve drawings were chosed at Johnson Controls, and of

those chosen one was not the latest revision as indicated

on the Sargent and Lundy master drawing list located in

the CECO Quality Assurance office. Drawing M3393, Page

4 of 12, was Revision B and should have been Revision C,

which was issued February 12, 1982. The M3393 drawing

series is not marked to indicate how many drawings are

in the series but are annotated as 1 of " blank".

Ten drawings were reviewed at Hunter Corporation's

Document Station 1-H, at the 426 level in the contain-

ment, and of these two drawings, CS-58 and RH-15, were

not the proper revisions according to the Hunter

Engineering Department master list. Hunter Corporation

personnel explanined that the drawings in question were

for work on the Unit 2 containment, which had been

stopped, and all related drawings were supposed to have

been recalled to document control. Hunter instituted

an immediate recall of these drawings.

24

_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

.

Noncompliance (454/82-05-08; 455/82-04-08)

10 CFR 50, Appendix B, Criterion VI states, " Measures

shall be established to control the issuance of docu-

ments, such as instructions, procedures, and drawings,

including changes thereto, which prescribe all activities

affecting quality." The failure of Johnson Controls, Inc.,

and Hunter Corporation to control the issuance of drawings

is contrary to the above and an item of noncompliance.

The licensee indicated that the condition has been

, corrected. This item will be examined durfug a future

'

inspection.

Process Traceability

The inspectors accompanied two CECO Quality Engineers,

one electrical and one welding, on inspections in the

containment, auxiliary building and the turbine building

to determine if they could trace the installation and

inspection process on welds, conduit hanger installation,

and cable pan installation. No problems were identified.

Quality Assurance Procedures

Inspection identified that two on-site contractors per-

forming safety related work were using forms which were

not controlled by procedures.

Hatfield Electric Company is utilizing a Discrepancy

Letter, also known as a Trouble Letter, for documenting

incomplete construction, non-conforming contruction,

requirements for Field Change Requests and other dis-

crepant items found during quality control inspections.

These Trouble Letters have been in use for approximately

the last 18 months and about 800 have been generated

in this time frame. The Trouble Letters are used as an

intermediate document during inspections prior to

corrective work or preparation of FCRs and NCRs and do

not become part of the quality records. Trouble Letters

numbers 640 thru 670 and 680 thru 720 were examined and

l It was found that in the inspectors opinion Trouble

Letters 658, 662, 664, 669, 679, 696, 697, 700 and 721

should have been documented as non-conformance reports.

As an example, in Trouble Letter 679, a Hatfield Electric

Company QC Inspector reports a conduit strap backing

j plate that is not welded to a hangar. The failure to

have a procedure for this Trouble Letter is contrary

i

to Appendix B.

! A similar condition exists with the instrumentation

piping installer, Powers-Azco-Pope. k' hen making Quality

i

25

l

.. - .- -

____ __

.

..

.

.. .

.

.

Control inspections a Fabrication Installation Surveil-

lance form, for which there is no prescribed procedure

is used for purposes identical to the Hatfield Trouble

Letter.

The inspectors examined FIS numbers 180 through 216

and in their opinion a number of the FIS's should have

resulted in NCRs. As an example, FIS 186 reported items

that were installed but did not have the required heat

numbers.

We are not against the use of trouble letters or speed

letters to expidite some contractor functions, however,

when these documents are used to document inspection

discrepancies they must be procedurally controlled.

Noncompliance (454/82-05-09a; 455/82-04-09a)

10 CFR 50, Appendix B, Criterion V states, " Activities

affecting quality shall be prescribed by documented

instructions, procedures, or drawings, of a type appro-

priate to the circumstances and shall be accomplished

in accordance with these instructions, procedures, or

drawings."

The failure of Hatfield Electric Company to utilize a

procedure to control their Discrepancy Records is contrary

to the above and is an item of noncompliance.

The failure of Powers-Azco-Pope to control their

Fabrication Installation Surveillances is contrary

to the above and is an item of noncompliance.

The licensee has indicated that these conditions have

been corrected. These items will be examined during

a future inspection.

Audits

The inspectors reviewed audits that were conducted by

the corporate and site quality assurance organizations

of Commonwealth Edison Company, Hatfield Electric

Company, Hunter Corporation, Powers-Azco-Pope, Johnson

Controls, Incorporated, and Pittsburgh Testing Laboratory.

The audits were conducted according to an audit schedule

and the scope and content of the audits was acceptable.

The audit reports consistently failed to include a list

of persons contacted during the conduct of the audit

and a summary of audit results, including an evaluation

statement regarding the effectiveness of the quality

assurance program elements which were audited, as

required by ANSI N45.2.12.

26

.

..

.. - -- - ____ - ____ _ - -___________ - _ __-

.

.

Noncompliance (454/82-05-10; 455/82-04-10)

10 CFR 50, Appendix B, Criterion XVIII states tha; a

comprehensive system of planned and periodic audits

shall be carried out to verify compliance with all

aspects of the quality assurance program and to deter-

mine the effectiveness of the program.

ANSI N45.2.12-1977 states that audit reports shall pro--

vide a list of persons contacted during audit activities

and shall have a summary including an evaluation statement

regarding the effectiveness of the quality assurance pro-

gram elements which were audited.

.

Contrary to the above, the audit reports of the licensee,

Hatfield Electric Company, Hunter Corporation, Powers-

Azco-Pope, Johnson Controls, Inc., and Pittsburgh Testing

Laboratory consistently failed to include persons con-

tacted during the audit and an evaluation statement re-

garding effectiveness of the program elements as indicated

in the examples listed below:

List of Evaluation

Auditor Audit # Persons Contacted Statement

CECO 6-81-330 Yes No

CECO 6-81-308 Yes No

CECO 6-81-336 No No

CECO 6-81-357 Yes Yes

CECO 6-81-309 Yes No

CECO 6-81-344 Yes No

CECO 6-81-340 Yes No

CECO 6-81-300 No No

CECO 6-82-08 No No

Hatfield 81-02 No No

Hatfield 81-18 No No

Hatfield 81-19 No No

Hunter 84-4 No No

Hunter None July 9, 1981 No No

Johnson 00501 No Yes

Johnson 10801 No Yes

PAP 52 No No

PAP 54 No No-

PAP 55 No No

PTL 81-21 No No

PTL 81-23 No No

PTL 81-25 No No

The licensee has indicated that action has been taken

to correct this situation in future audits. This item.

will be examined during a future inspection.

I

27

i

. . _ _ _ -._ ... - -

_ _ _ _

.

.

Measuring and Test Equipment

The inspectors reviewed the procedure and methods for

control of Measuring and Test Equipment used by Hunter

Corporation, Hatfield Electric Company, Powers-Azco-Pope,

Johnson Controls, Inc., and Pittsburgh Testing Laboratory

and inspected various instruments in office and field

locations.

The inspectors identified no problems with Hunter

Corporation, Johnson Controls, Inc., and Pittsburgh

Testing Laboratory (PTL).

During a review of torque wrenches in the Hatfield

Electric Company Quality Assurance office and the

Powers-Azco-Pope Quality Assurance office the following

items were identified.

. Hatfield Electric Company: The storage of torque

wrenches was not according to Hatfield Procedure

  1. 24 as the wrenches that were past the calibration

date were not red tagged and they were stored on

the same shelf as wrenches currently in calibration.

HE-151, HE-142, and HE-135 are some of the untagged,

uncalibrated torque wrenches stored with calibrated

wrenches.

. Powers-Azco-Pope: One torque wrench, TW-4, was

marked as defective, but did not have a Reject Tag

as required by Section 5.15 of Powers-Azco Pope

Procedure FP-11, Calibration and Control of

Measuring and Test Equipment (M&TE).

Noncompliance (454/82-05-11a; 455/82-04-11a)

10 CFR 50, Appendix B, Criterion V states, " Activities

affecting quality shall be prescribed by documented

instructions, procedures, or drawings, of a type

appropriate to the circumstances and shall be accomp-

lished in accordance with these instructions, procedures,

or drawings."

The failure of Hatfield Electric Company to follow its

procedure #24, with regard to tagging torque wrenches,

is contrary to the above and is an item of noncompliance.

The failure of Powers-Azco-Pope to follow its procedure

No. FP-11, with regard to tagging torque wrenches, is

contrary to the above and is an item of noncompliance.

The licensee has indicated that these conditions have

been corrected. These items will be examined during a

future inspection.

28

- -- ___

.

.

Purchasing, Receiving and Storage

The inspectors reviewed the process used to obtain safety

related material starting with a material request gen-

erated by a contractor and culminating with storage in

a warehouse. The inspectors noted no discrepancies in

the requesting, purchasing and receiving portions of

the project, but during tours of warehouse areas the

following items were noted:

. In Warehouse No. 1, safety-related equipment was

stored on shelves that also contained lumber,

boxes of paper, scraps of rubbish and food in a

housekeeping atmosphere that did not meet the

requirements of Section 6.2 of ANSI N45.2.2.

. In Warehouse No. 5, a pallet of bags containing

charcoal type compound was stored above safety

related valves. One of the bags had broken and

the material had spilled onto the valves, shelving-

and floor, and the housekeeping was not in accord-

ance with Section 6.2 of ANSI N45.2.2.

Noncompliance (454/82-05-11b; 455/82-04-11b)

10 CFR 50, Appendix B, Criterion V states, " Activities

affecting quality shall be prescribed by documented

instructions, procedures, or drawings, of a type

appropriate to the circumstances and shall be accomp-

lished in accordance with.these instructions, procedures,

or drawings."

The conditions maintained by the licensee in Warehouses

No. I and No. 5 were contrary to Quality Procedure 13-1

,

and to the requirements of ANSI N45.2.2-19?2, and are

'

an item of noncompliance.

The licensee has indicated that action has been taken

to correct the warehouse conditions. This item will

be examined during a future inspection.

. In Warehouse No. 4, Powers-Azco-Pope is storing

material that is tagged Rejected next to Accept

and Hold material and is not segregated as re-

quired by Section 5.6 of Powers-Azco-Pope Pro-

cedure No. FP-3, Material Receiving Inspection

Control.

>

. Powers-Azco-Pope is attaching a red tag that says

" Safety-Related" to material that has also been

tagged with PAP's Accept Tag. The red tag is not

referenced in any PAP or CECO procedure.

29

.

.

.

Noncompliance (454/82-05-11c; 454/82-04-11c)

10 CFR 50, Appendix B, Criterion V states, " Activities

affecting quality shall be prescribed by documented in-

structions, procedures, or drawings, of a type appro-

priate to the circumstances and shall be accomplished

in accc.-dance with these instructions, procedures, or

drawfu4s."

The failure of Powers-Azco-Pope to store rejected

material in accordance with their procedure No. FP-3

is an item of noncompliance.

The licensee has indicated that this condition has been

corrected. This item will be examined during a future

inspection.

(11) Quality Assurance Staffing

(a) Objective

The objective of this assessment was to determine if

the Quality Assurance Organizations of the licensee

and contractors are adequately staffed.

(b) Discussion

The inspectors interviewed personnel involved in the

management of the licensee's and selected contractor's

Quality Assurance Organizations; and approximately 14

percent of the Quality Control inspectors employed by

the contractors. Based on the interviews and a review

of scheduled and completed audits and surveillance

the inspectors were able to conclude that the Quality

Assurance Organizations were supplied with sufficient

manpower. The auditors of the selected organizations

were found to be adequately qualified. Qualifications

of Quality Control inspectors are discussed in detail

in the "QC Inspector Effectiveness" section of this

report.

The inspectors do not believe that the Quality Control

Supervisor for Powers-Azco-Pope was qualified to be a

Level II Supervisor on the day she was appointed to the

position, as she did not have the one year of Level I

experience as required by ANSI N45.2.6-1978. This is

discussed in greater detail in section h., QC Inspector

Effectiveness.

The CECO Quality Assurance Organization at Byron is

fully staffed with 16 personnel, but the effectiveness

of Quality Assurance section is being weakened by the

30

. _ _ _ _ _ _ .

.

.

deployment of Byron Quality Assurance personnel at

<

La Salle and Quad-Cities. This is discussed in more

detail in pargarph b.(7), Licensee Assessment of Quality

Assurance Program. In addition to the above, one

Quality Engineer was transferred to the Operations Quality

Assurance section during our inspection and a replacement

is not scheduled to arrive until June 1982.

The transfer of the Quality Assurance personnel to sup- i

port other programs is an area of concern.

(12) Trend Analysis Program

(a) Object f.ve

The objective of this assessment was to determine if

the licensee has an effective trend analysis program.

(b) Discussion

The inspectors reviewed the trend analysis reports of

the licensee and Hatfield Electric Company. Licensee

trending of NCR's is discussed in detail in section c.,

Corrective Action Systems. The licensee publishes an

annual Trend Analysis Report which is s summary of

NCR's by problem area for each contractot during the

previous year, and the Corrective Action System is

scheduled to be audited semi-annually.

(13) Compliance History

(a) Objective

The objectives of this assessment were to review the

licensee's compliance history and the effectiveness

of the associated corrective action.

(b) Discussion

The inspectors reviewed the licensee's history of

noncompliances, unresolved items, 10 CFR 50.55(e)

Reports, NCR's, IE Bulletins, IE Circulars, and IE

Information Notices and reviewed the systems used to

assign responsibility and to track the resolution of

the problem. A review of all 10 CFR 50.55(e) reports

and 30% of the noncompliances showed that the corrective

action was appropriate, with the cause identified and

! action taken to prevent recurrence. NCR's and their

resolution are discussed in detail in section c.,

'

Corrective Action Systems.

Except as noted, within the areas inspected, no items of non-

compliance or deviations were identified.

i

I

31

l

!

i

.

.

Prepared By: R. S. Love

c. Corrective Action Systems

(1) Objective

The objective of this assessment was to determine if:

(a) corrective action procedures are adequate.

(b) responsibilities have been adequately defined and that

the affected personnel have been trained and understand

the procedures.

(c) procedures are being effectively implemented. This

includes the areas of tracking and closeout, trending

of nonconformances, and upper management's involvement.

(2) Discussion

(a) Commonwealth Edison Company (CECO)

1. Procedure Review

A review of CECO Quality Procedures QP No. 15-1,

Revision 5, dated January 20, 1981, and QP No. 16-1,

,

Revision 5, dated December 29, 1980, indicates that

they appear to be adequate as relating to Corrective

Action.

Adverse trends and problem areas are brought to the

attention of the Vice President (Nuclear Operations),

Manager of Projects, Project Manager and Manager cf

Quality Assurance.

2 Review of NCR Log

The inspector reviewed CECO's Nonconformance Report

(NCR) log for the years 1979, 1980, and 1981. It

was observed that for the year 1981, 101 NCRs were

prepared and Hold Tags were applied in 96 instances.

In the 5 instances where Hold Tags were not applied,

the item was controlled by a Subcontractors tag or

the NCR was generic in nature.

3. Review of Open NCRs

.

The inspector reviewed eleven open NRCs that

were prepared during 1980. The following.is a

status of these NCRs.

a. F-491, dated April 7, 1980. There is an open

50.55(e) report on this item.

32

- _ _ _ _ _ _ _ _ _ _ _ _ _ _ _

.

I

.

b. F-488, dated March 27, 1980. This NCR was

sent to Project Construction Department (PCD)

on May 15, 1980, for implementation of the

disposition.

c. F-526, dated June 27, 1980. This NCR is

still at Station Nuclear Engineering Depart-

ment (SNED) undergoing evaluation.

d. F-539 dated July 22, 1980. This NCR is still

at SNED undergoing evaluation, but, from infor-

mation received by the NRC inspector, the subject

cables have been terminated and energized based

on a " Work can Proceed" notation on the NCR.

e. F-544, dated August 8, 1980. This NCR is still

at SNED undergoing evaluation.

f. F-546, dated August 11, 1980. There is an

open 50.55(e) report on this item.

g. F-563, dated October 22, 1980. This NCR was

sent to PCD on August 27, 1981, for implementa-

tion of the disposition.

h. F-565, dated November 5, 1980. This NCR is

still at SNED undergoing evaluation.

i. F-575, dated November 26, 1980. This NCR

was sent to PCD on January 28, 1981, for

impicmentation of the disposition.

J. F-577, dated December 8, 1980. This NCR

was sent to PCD on February 13, 1981, for

implementation of the disposition.

k. F-582, dated December 12, 1980. This NCR

was sent to PCD on July 14, 1981, for imple-

mentation of the disposition.

Open Item (454/82-05-12: 455/82-04-12)

The NRC is concerned about NCRs that remain open

for an extended period of time in that as the

fuel-load date approaches, there may be a tendency

to accept items without proper engineering evalua-

tion, including back-up data, or to accept items

that should be reworked or repaired. Pending review

of the action taken to close the NCRs listed above,

this is an open item.

33

_ _ _ _ _ _ _ _ _

.

.

4. Review of Voided NCRs

The inspector selected six voided NCRs for review.

The subject procedures do not address voiding NCRs

, but this is an accepted practice in the industry,

when the-NCR is voided for just cause.

a. NCR F-597 was missing from the QA Records

Vault. The NCR log indicated that the NCR

was prepared on January 27, 1981 to document

that Pump Motor OCC01P terminations were

leaking. The log indicates this NCR was '

voided on April 13, 1981. l

b. NCR F-600 was missing from the QA Records

Vault. The NCR log indicated that the NCR

was prepared on February 6, 1981 to document

some damaged cables. The log indicates this

NCR was voided on April 3, 1981.

c. NCR F-634, dated March 23, 1981, was prepared

to document a minimum bend radius violation

on cable IRH119 and to point out that the

cause of the bend radius violation was that

the weight of the cable pulled the loop out

of cable tray. ECN 1992 was issued to add

a device to prevent cable slippage. The NCR

was voided on July 24, 1981, without an

evaluation of the subject cable. The licensee

had an inspection / evaluation performed on the

cable on April 7, 1982. Cable was acceptable,

d. NCR F-645, dated May 7, 1981, was prepared

to document that Westinghouse furnished watt-

meters installed on various panels supplied

by Systems Control did not meet the 1% toler-

ance requirements. The NCR was voided on

June 3, 1981. Systems Control letter to

Commonwealth Edison Company, dated August 19,

1981, stated in part, "The wattmeters will be

returned to Westinghouse for repair at their

expense."

e. NCR F-650, dated May 18, 1981, was prepared

to document certain nonconforming hangers.

This NCR was voided on June 3, 1981, because

it was being tracked on Hatfield NCR #298.

f. NCR F-682, dated October 28, 1981, was pre-

pared to document that concrete had been

placed next to a pipe, resulting in a weld

on the pipe becoming unaccessible for inspec-

i

34

.

.

tion under ASME Section XI. ECN 2336, dated

December 8, 1981, was issued to enlarge the

opening around the pipe so the weld would be

accessible for inspection. The NCR was voided

on December 16, 1981, because the ECN resolved

the problem.

Noncompliance (454/82-05-13a; 455/82-04-13a)

The items listed in peragraph1 ci d and f1 above

are exempics of improperly voided nonconformance.

For item c 2the issuance of the ECN 1992 was a

good corrective action to prevent recurrence but

did not resolve the bend radius violation. For

item d2 the return of the instruments to Westing-

house for repair was a good resolution to the

problem, net reasoning for voiding. Again, the

issuance of the ECN 2336 was satisfactory resolution

to the problem identified in item f2 not a reason

to void the NCR. Improper voiding of the NCRs.is

an item of noncompliance with Criterion XV of 10

CFR 50, Appendix B.

5. Review of Closed NCRs

On April 1, 1982, the Region III inspector reviewed

the following NCRs for proper closure and for cor-

rective action to prevent recurrence:

F-562, dated October 14, 1980, closed January 6, 1982

F-627, dated March 24, 1981, closed January 6, 1982

F-635, dated March 24, 1981, closed June 22, 1981

F-656, dated June 12, 1981, closed July 21, 1981

F-673, dated August 17, 1981, closed January 19, 1982

F-687, dated January 8, 1982, closed February 16, 1982

F-683, dated October 2, 1981, closed February 11, 1982

6. Review of Trend Analysis

On April 1, 1982, the Region III inspector reviewed

the trend analysis of NCRs prepared by CECO. This'

trend analysis is prepared by the Projects Engineer -

ing Department (off-site). Reports dated January 8,

1981, March 19, 1981, September 17, 1981, October 21,

1981, November 12, 1981, December 17, 1981,

January 12, 1982, January 20, 1982, and February 17,

1982 were reviewed during this inspection. All of

the aforementioned reports had the notation, "No

trends are evident" or "No trends could be identified."

CECO QA (on site) does perform a trend analysis on

contractor's nonconformances. On the trend anhlysis

reviewed, they agreed with the analysis being per-s

formed by the individual contactors. J )

35

t

s

~

.

.

7. Interviews with Personnel

Interviews with Ceco personnel indicate that they

appeared to be knowledgeable in their own procedures

on Corrective Action as well as their contractor's

procedures.

(b) Blount Brothers Corporation (Blount)

1. Procedure Review

Blount utilizes a Deviation Report (DR) System

versus an NRC system. If a DR requires CECO

Project Engineering approval, CECO transcribes

the information from Blount's DR onto a CECO NCR

which is then forwarded to Project Engineering

for approval.

A review of Blount's procedure number 4, Inspection

Nonconformances and Corrective Action, Revision 8,

Issue 9, dated February 12, 1981, indicates that

it appears to be adequate as relating to correction

action.

2. 2w of NCRs

The inspector selected several DRs from the DR

log for a detailed review for proper closure and

corrective action to prevent recurrence. Following

is a status of these DRs:

a. Q3-485, dated July 7, 1980. Closed October 14,

1980.

b. Q3-508, dated November 22, 1980. Closed

January 22, 1981.

c. Q3-505, dated December 1, 1980. Closed

February 23, 1981.

d. Q3-494, dated August 25, 1980. Closed June 2,

1981.

e. Q3-545, dated October 19, 1981. As of April 2,

1982, this DR was at CECO for final approval

for closure.

On all DRs reviewed, for years 1980, 1981, and

1982, che action to resolve the nonconformance and

the steps taken to prevent recurrence appeared to

be adequate.

36

,

-<

,3- r - 3 y

'

,

-

. .. , ;u . ~,# .:

w i V ,

.

'

.

,

> -

'

'-

V, ,

  • -

,

,,

u a

,

,

- ,

- , .

,

3. Review of Trend An41ysis / o ' *

, . ~

ys , _ ,.

-

Per Blount's procedure, tread smalysis are desu- '

mented annually but a runni'ngf9 Eunt of DRs 'is made /

in each deviation area wb16hf rese.Its in a continuous

trend analysis. The tredds'nuted by the inspector... -

had been documented on Blount's trend analysis'.

"

report. These reports appear -to be given side "'

distributica.and includes a copy to CECO. 4, ,

?

4. Interviews wit _h Persor.hel

"

,

Interviews =with Blount personnel indicate that

the QA Manager was relatively new on the project /

but appeared to have an adequate knowledge of 'W

the procedures. The inspector was inpressed by

the knowledge displayed by the QC Inspector as _ ~

pertaining to the DRs reviewed and the corrective , . . .

action system in general. ,

,

(c) Hunter Corporation (Hunter)

s- ,

-

1. Procedure Reviews -

'

,,

-

~

/-

A review of Hunters S'ite Impler'neitt'ation/ Procedures '

/

Number 11.101, Nonconfec$ance Processing,NRevision '

4, dated April 28, 1981, indicates tha~t it; appears ,

to be adequate as relating to correct,1vp,ections. , . ,

2. Review of NCRs t #

% ^-

,4  %

'

. ,1 ,.

The inspector made a genaral review of approximately '

30 NRs and a detailed review of 10 hTis for proper

closure and for corrective action to prevent *rsturr-

ence. Following is a status.of the NCRs that were

reviewed in detail: f

.- y' .

a. NR-099, dated May 5, 1980. Closed Septebber"16, '

1980.

b. NR-132, dated July 22, 1980. This NR' was pro-

perly voided on August 4, 1980.

""

c. NR-119, drited July 15, 1980. Closed on

December 15, 1980.

d. NR-193, dated January 28, 1981. Closed on

March 18, 1981.

e. NR-263, dated September 17, 1981. Closed on

October 14, 1981.

L NR-151, dated August 4, 1980. Closed on f

February 26, 1981.

E NR-159, dated July 3, 1980. This NR was pro-

perly voided on December 2, 1980.

L NR-204, dated March 17, 1981. Closed on

April 15, 1981.

37

- - -

_ _ .

.

  • l

.

.

'

i. NR-231, dated June 5, 1981. Closed on

August 21, 1981.

-

1 NR-262, dated September 11, 1981. Closed on

November 24, 1981.

'

,

3. Review of Trend Analysis

The inspector reviewed the nonconformance (NR)1og

for the years 1980, 1981 and 1982. It was observed

that with the way the NR log was prepared, a trend

, would be observed. The inspector selected two

attributes (unqualified welders and hold points

bypassed) and performed a trend analysis for the

years 1980 and 1981. A review of Hunters trend

'

analysis for the same period of time indicated

'

that the two analysis (Hunter's and the inspector's)

were compatable for the two attributes selected.

'i . Through training, unqualified weld NRs dropped from

, 11 in 1980 to 2 in 1981 and bypassing of hold points

, sf dropped from 23 in 1980 to 11 in 1981. Hunter

'

recognizes that they still have problems with hold

+

points.

,

-

4. Interviews with Personnel

Interviews with Hunter personnel indicate that they

<

appeared to have a good working knowledge of their

system and procedures. Their system and applicable

procedures appear to be adequate.

(d) Powers-Azco-Pope (PAP)

1. Procedure Review

A review of PAP Field Operating Procedure Number

QC-4, Nonconformance Control, Revision 7, dated

September 30, 1981 and PAP Quality Assurance

j Manual, Section B-8, Nonconforming Material and

Parts, Revision 1, dated October 22, 1981, indicates

that they appear to be adequate as relating to

Corrective Action.

2. Review of NCRs

The inspector performed a general review of approx-

imately 30 NCRs and a detailed review of 13 NCRs

and 11 Corrective Actions Requests (CARS). The

following is the status of the NCRs reviewed in

detail:

38

.

.

a. NCR 14, dated July 25, 1980. Closed August 1,

1980

b. NCR 19, dated September 18, 1980. NCR was un-

acceptable, with the note - see NCR 20.

c. NCR 20, dated September 30, 1980. Closed

October 1, 1980.

d. NCR 23, dated September 21, 1980. Closed

June 24, 1981.

f. NCR 44, dated April 3, 1981. Closed April 24,

1981.

g. NCR 39, dated February 27, 1981. Closed

March 4, 1982.

h. NCR 55, dated June 1, 1981. Closed August 13,

1981.

i. NCR 71, dated February 13, 1981. Closed

November 16, 1981.

J. NCR 73, dated July 15, 1981. Closed July 24,

1981.

k. NCR 81, dated July 31, 1981. Closed

November 9, 1981. Re-instruction was required

as part of corrective action.

1. NCR 90, dated September 10, 1981. Closed

January 6, 1982.

m. NCR 117, dated November 20, 1981. Closed

December 28, 1981.

Noncompliance (454/82-05-11d; 455/82-04-11d)

Of the 13 Powers-Azco-Pope NCRs reviewed in detail,

12 of the NCRs did not contain any corrective action

to prevent recurrence which is in violation of PAP's

Quality Assurance Manual, Section B-8, Revision 1,

dated October 7, 1981, Paragraph 13-8.8.2. The li-

censee was informed that this was an item of non-

compliance with Criterion V of 10 CFR 50, Appendix B.

3. Review of CARS and Trend Analysis

Of the 11 CARS generated by PAP as a result of

their trend analysis, the corrective action

appeared to be adequate.

4. Interviews with Personnel

Interviews with PAP personnel indicate that they

appeared knowledgeable in their system and procedures.

j (e) Hatfield Electric Company (HECol

1. Procedure Review

l

l The inspector reviewed HECo Procedure #6, Reporting

i of Damaged or Nonconforming Material or Equipment,

i

l

39

!

.

.

Revision 6, dated January 15, 1982, and Section XVI,

Corrective Action, Revision 5, of the QA Manual.

During review the following observation was made.

Noncompliance (454/82-05-09b; 455/82-04-09b)

The only reference to corrective action to prevent

recurrence in the above mentioned procedures is in

Section XVI, Paragraph 2.4, of the QA Manual. This

paragraph discusses corrective action for adverse

audit findings. The NCR form in use at the Byron

Station, as contained in procedure 6 has a section

titled " Action to Prevent Recurrence" but there is

no directions in the body of the procedure for this

section.

Failure to assure that applicable regulatory require-

ments are correctly translated into procedures and

instructions is an item of noncompliance with Criter-

ion V of 10 CFR 50, Appendix B.

2. Review of NCRs

The inspector reviewed approximately 180 NCRs for

proper closure and for corrective action to prevent

recurrence. The NCR log in use when most of the

NCRs were prepared did not provide a description

of the nonconformance, resulting in a larger number

of NCRs reviewed. The following observations were

made,

a. NCRs 98, 99, and 100 were prepared to docu-

ment a violation of concrete expansion anchor

(CEA) edge distance. The NCRs were voided on

February 25, 1980, because an FCR was or will

be issued to accept the CEAs as installed.

One FCR (2500) was not issued until July 16,

1980. By voiding the NCRs, they were removed

from the trending system. After this was

pointed out by the NRC, the contractor pre-

pared NCR 432, dated April 9, 1982, to docu-

ment the items originally contained in NCRs

98, 99, and 100,

b. NCR 168, dated March 2, 1981, documented that

a cable was deformed at routing point 1899B.

CECO engineering evaluated the cable and dis-

positioned the NCR as " Remove, Damaged Cable"

and pull a nec cable. Hatfield made the

decision, without CECO's concurrence, that

the subject cable did not need to be replaced.

The NCR was closed on August 22, 1981.

40

_ __

_ _ . _ _

.

.

i

c. NCR 154, dated February 24, 1981, documents

that cables 1FW441, 1FW482, and 1DC198 were

damaged and the disposition was to replace the

cables. Review of records indicate that cable

IDC197 was pulled out and scrapped on June 4,

1981 instead of cable IDC198. The NCR was

closed on June 4, 1981. A review of cable pull

cards for cables IDC197 and 1DC198 indicated

that IDC197 had been pulled and scrapped on

June 4, 1981, and that 1DC198 was initially

pulled on July 24, 1981. On April 6, 1982,

the HECo QA Manager corrected the subject NCR

and the attached documentation.

d. NCR 107, dated March 21, 1980. Closed

November 21, 1980.

e. NCR 97, dated February 20, 1980. Closed

August 21, 1981.

f. NCR 152, dated February 23, 1981. Closed

June 24, 1981.

g. NCR 164, dated March 2, 1981. Closed

August 15, 1981.

h. NCR 160, dated February 16, 1981. Closed

September 3, 1981.

i. NCR 103, dated March 6, 1980. Closed

January 8, 1981.

1 NCR 184, dated March 4, 1981. Closed June 8,

'

1981.

k. NCR 177, dated March 4, 1981. Closed March 23,

1981.

The inspector reviewed 42 NCRs generated between

1

September 15, 1981 and February 15, 1982. The

,

following is a status of the disposition of the

subject NCRs:

J 23 - Use-as-is, FCR issued

I

4 - Repair the item

4 - Open as of April 7, 1982

3 - Voided

2 - Replace the item

1 - FCR issued to add side rails

1 - Reject the item

1 - Reorder replacement item

1 - Retrain the cables

41

- . - _ . - -- .- - . _ -

. ..

.

.

.

1 - Closed - Being tracked by CECO NCR

1 - Clean the item

42

Noncomplainee (454/82-05-13b; 455/82-04-13b

The licensee was informed that items a and b

above are additional examples where NCRs were

improperly closed / voided and is an item of non-

compliance with Criterion XV of 10 CFR 50,

Appendix B.

3. Review of Trend Analysis

A review of Hatfields trend analysis .for 1981 and

1982 indicates that it was adequate.

4. Interviews with Personnel

Interviews with HECo personnel indicate that they

appeared knowledgeable in theie procedures and

system.

Except as noted, within the areas inspected, no items of

noncompliance or deviations were identified.

l

42

-

.

.

Prepared by: H. M. Wescott

d. Design Change Control

(1) Objectives

The objectives of this assessment were to ascertain that,

site design change interfaces are clearly defined and im-

plemented, design change control is adequate, personnel

understand and use appropriate procedures, and that the

procedures are being implemented to assure the timely

revising and distribution of drawings.

(2) Discussion

(a) Review of QA Manuals and Procedures

The inspector examined QA Manuals and Implementing

Procedures as follows:

1. Nuclear Power Services, Section No. 3, Revision 1,

dated December 30, 1980, " Design Control".

2. Powers-Azco-Pope QA Manual, Section B.1, Revision

1, dated October 7, 1981, " Design and Document

Control".

3. Hunter Corporation QA Manual, Section 2, Revision 5,

dated August 1, 1981, " Drawing and Specification

Control".

4. CECO QA Manual, Quality Requirement, QR No. 30,

Revisions 1, 3, 13, and 18, dated December 29,

1980, December 29, 1980, September 9, 1980, and

December 29, 1980 respectively, " Design Control".

5. CECO QA Manual, Quality Procedure, QP No. 3-2

thru Revision 13, dated November 12, 1981, " Design

Change Control".

l 6. Johnson Controls, Inc., QA Manual, Section 4,

'

Revision 0, dated June 29, 1978, " Design Control".

7. Byron Site Instruction No. 20, Revision 8, dated

December 17, 1981, " Instruction for Site Design

Document Receipt, Distribution and Control".

8. Byron Site Instruction No. 21, Revision 0, dated

i

July 13, 1978, "ECN Routing".

9. Westinghouse Policy / Procedure, WRD-OPR 3.0,

Revision 2, dated March 20, 1981, " Design Control".

l

43

_ _ . , _- ._ . - . _ , . _ - . . . . . _ . _ , .__ ,__ . . _ _ - - _ - - - , _ -. _ _ _ _

.

.

10. Westinghouse WRD-OFR 3.1 " Reactor Coolant System

Design Definition (Power Capability Working Group)"

Revision 3, dated March 22, 1981.

11. Westinghouse Instruction / Guidance SMD 1.4, Revision

4, dated January 18, 1982, " Byron Unit 1 Engineering

Change Notice".

12. Westinghouse Instruction / Guidance SMD 1.5, Revision

0, dated October 31,^1980, Byron Unit " Field Change

Requests".

13. AZCO Field Procedure FP-9, Revision 6, dated

December 21, 1981, " Design Change Control".

(b) Review of Audits of Site Contractors

The inspector reviewed CECO's audits of site contractors

concerning design change control as follows:

1. Sargent and Lundy Nos. 6-81-301, 6-81-314, 6-81-339

and 6-28-07.

2. Westinghouse SAMU No. 6-81-317.

3. Powers-Azco-Pope Nos. 6-81-326, 6-80-247 and

6-82-10,

4. Nuclear Installation Service Company Nos. 6-81-311

and 6-80-281.

5. Hatfield Electric Company Nos. 6-80-254 and 6-81-331.

6. Hunter Corporation Nos. 6-82-09 and 6-81-350.

7. Blount Brothers Corporation Nos. 6-80-248, 6-81-294

and 6-82-02.

8. Johnson Control, Inc. No. 6-80-250.

9. Hunter Corporation, Hatfield Electric Company,

Reliable Sheet Metal Works, Inc., Powers-Azco-Pope

Services, Inc., Blount Brothers Corporation,

Westinghouse SAMU, Pittsburgh Testing Laboratory,

and Nuclear Installation Services Company

No. 3/8-10/82.

(c) Review of Design Specifications

The inspector reviewed design specifications as follows:

4L

--. _

'

.

.

1 Certified piping design specification for the

" Outdoor Essential Water System" dated February 19,

1982.

! 2. Certified piping design specification for the

" Indoor Essential Water System" dated December 14,

1981.

3. Certified design specification for the " Reactor

Vessel" dated May 15, 1972.

. 4. Design Criteria for Category 1 Cable Tray, Cable

Tray Supports, Bus Duct Supports, HVAC Duct Supports,

Conduit and Conduit Supports, DC-51-03 BY/BR.

It is noted that item 2. above did not have the Pro-

fessional Engineer's Seal for Certification. Sargent

and Lundy further researched ten piping design specifi-

cations and found threa that did not have the required

'

seal. These were to be revised to include the seal by

April 23, 1982.

(d) Review of Control of Field Change Requests (FCR's) and

Engineering Change Notices (ECN's)

The inspector randomly selected fifteen (15) FCR's and

three (3) ECN's at Powers-Azco-Pope, seven (7) FCR's

at Hatfield Electric Company, and three (3) ECN's at

Westinghouse SAMU. They were verified to be under CECO

control. Additionally five (5) traveller packages for

in-process welding were verified to have the correct

drawing revisions in place.

'

The following are the totals of FCR's and ECN's issued

as of this inspection:

Electrical FCR's 4,492

Mechanical FCR's 13,702

Structural FCR-s 101

  • Mixed FCR's 4,999

ECN's 2,454

TOTAL 25,746

  • Mixed FCR's contain all disciplines prior to separation

by discipline.

(e) Review Site Design Change Interface

i

The inspector reviewed the following:

45

_ - - __ . _ _ _ _ _ __ ._ _ _ _ _ _ _ _ _ _ . _ _ _ _ . _ _ _ _ _

-

i

i

i

1. Interface Control Agreement, Westinghouse Piping

and Structural Evaluation Program for the Byron

Station Unit 1, dated October 13, 1980. Paragraph

'

4.3 states that, "The Byron Project Engineering

Organization,-as the Owner, has overall responsi-

! bility for the activities described in this

agreement."

2. Flow Chart for routing CECO Field Change Request,

Byron Site Instruction No. 10, Revision 5, dated

March 25, 1982.

! (f) Personnel Interviewed

The inspector interviewed personnel from CECO, Westing-

house, Powers-Azco-Pope, Sargent & Lundy, Hatfield

Electric Company, and Hunter Corporation.

i Within the areas inspected no items of noncompliance or

l deviations were identified.

1

4

,i

l

f

i

,

d

)

e

1

46

i

- . , _ . _ . _ . , _ - . _ _ . - , . _ , - - _ _ - _ - , _ _ _ . -m. .,, ., _ _._, -. . . _ , . _ . . _ . - . _ _ . - _ _ . _ _ _ . ,

. - --- -. -

.

.

Prepared By: E. H. Nightingale

4

c. Material Traceability of Installed Structures and Components

(1) Objective

The objective of this assessment was to determine that

material traceability was maintained from procurement

through installation for structural beams, small bore

piping and welding materials.

(2) Discussion

The following contractors were involved and their areas of

responsibility are as indicated:

Hatfield Electric Company: Cable Trays

Hunter Corporation: Small Bore Pipe Systems

Powers-Azco-Pope: Small Bore Piping Systems

Blount Brother Corporation: Structural *

,

(a) Hatfield Electric Company

1. Review of Procedures

,

The following site procedures were reviewed:

  1. 5, Class I Materials and Equipment, Receiving

and Inspection

  1. 13AA, Class I Shielded Metal Arc Field Welding

(S.M.A.F.W.)

  1. 13AB, Class I S.M.A.F.W. (Procedure Qualifica-

tion)

  1. 13AC, Qualification of Welders

i

  1. 13AD, Arc Welding Electrode Control

'

2. Review of Records

The documents reviewed for material traceability  ;

were as follows:

. Weld Material Request

. Material Certification

. Weld Rod Request

. Weld Data Sheet

. Weld Material Issue Tag

47

. . _ . -_ _ - - , . - - _ _ _ , -__ __ _. .

_ _ - - .-_

-.

.

.

3. Review of Welder Qualification

The review of welder qualification records consisted

of reviewing the original qualification records as

well as the supportive documents pertaining to

their "up-date" qualification records. Hatfield

,

Electric Company welding efforts are to AWS Code

which requires six (6) month re-qualification

periods.

The following welders had their certification and

qualification records reviewed:

'

Name Welder ID#

N. Larrabee WW

C. W. Werner W

J. A. Dickson -MM

Greene CG

R. S. Glenny CF

C. Stagg CS

W. McVay BM

D. Gavin DG

T. Whitcomb TV

F. Plegge FP

These ten (10) welders are representatives of the

sixty (60) welders qualified by Hatfield and are

presently on site.

3

4. Review of Weld Material Control

!

The review of weld material control procedures and

direct observation of in process activities

indicate that sufficient efforts are being im-

plemented to assure material traceability and

, control.

Open Item (454/82-05-14; 455/82-04-14)

The Hatfield daily weld rod issue log did not

indicate the actual time weld rod was issued and

returned. The log only noted "a.m." or "p.m.".

The licensee has provided information to indicate

that Hatfield form HP-13AD-1 has been revised to

i

include provisions for the actual rod issue and

return times. This item will be reviewed during

j a future inspection.

(b) Hunter Corporation-

e

1. Review of Procedures

.

'

48

. ._ . - - , -_ ., -, ..- -. - , - ,

.

.

The following site implementation procedures were

reviewed:

1.601, QA Procedures and Instructions

3.102, Material and Services Procurement

3.602, Material Received and Inspected

5.101, Weld Filler Material Control

5.201, Welding Procedure Qualification Control

5.301, Welding Qualification

5.501, Weld Material Issuance

6.002, Visual Exaaaaation and Verification

6.501, NDE

2. Review of Records

The inspector selected three (3) safety related

small bore piping systems for review of material

traceability. The review of the data packages

consisted of documentation from the purchase order

to installation of the item. The systems involved

were as follows:

. Safety Injection (3)

Reactor Coolant (2)

.

Chemical Volume (4)

The documents reviewed were as follows:

. Material / Services Request

. Material Receiving Report

. Receipt Inspection Checklist

. QA Documentation Requirements List

. Material List

. Requisition

. Shipping Order / Packing Slip

. Material Certificate

. NDE Request

. Process Sheet

. Weld Record

. Material List

. Material Certification

. Weld Material Issue Report

The inspector reviewed data packages for the

following small bore piping systems:

SYSTEM SPOOL PC ITEM HT # MATERIAL REPORT

1016-S-CV-001 2 2" sch/160 462460 MSR 4967

1016-S-RC-001 1 2" sch/160 462460 MSR 4967

CECO-S-RC-001 105 3/4" sch/160 483245 MRR 9575

1016-S-SI-001 5 2" sch/160 462460 MSR 4967

1016-S-SI-001 16-5 2" sch/160 462460 MSR 4967

49

.

.

SYSTEM SPOOL PC ITEM HT # MATERIAL REPORT

1018-S-CV-100 1-5 3/4" sch/40 462224 MSR 4967

1016-S-CV-100 8-7A 2" sch/160 462460 MSR 4967

1016-S-CV-100 9-8 2: sch/160 462717 MSR 4967-

1065-S-SI-100 29-10 1" sch/160 HD7123 MSR 4967

The total footage involved consisted of 19,884'.

An expanded study of small bore piping was made

to include valves and fittings. Data packages

for the following items were reviewed:

NAME LOCATION SYSTEM SPOOL MRR

Globe Valve IRC8039B S-RC-001-51 2 10084

M.O.V. IRC8037B S-RC-001-51 2 10062

M.O.V. 1-SI-8871 S-SI-001 33 10144

NAME TYPE HT # SPOOL MRR

CPLG Fitting 2.0" 6000# S.S.-S.W. TL 2 496h

CPLG Fitting 3/4" 6000# S.S.-S.W. EGJ 2 5338

3. Review of Welder Qualification

The review of welder qualification records consisted

of reviewing the original qualification record as

well as the supportive documents pertaining to their

"up-date" qualification record. Hunter Corporation

welding efforts are conducted to the ASME Code which

requires three (3) month re-qualification periods.

Hunter Corporation routinely re-certifies their

wolders in two (2) month periods to preclude any

loss of certifications due to vacations, illness,

etc.

The following welders had their certification and

qualification records reviewed:

NAME WELDER ID #

R. Sturm D40

l B. Strom B17

'

D. Colby E52

R. Decker ,

A38

D. Upstone F19

, E. Baker E56

B. Burns

'

E82

1 R. Bilyeu B91

4

1

50

,

-_. ., m., _ - . . ._ --- _ - . . . ~ . _ - - -

.

.

NAME WELDER ID #

A. Arnold E48

V. Burdene C19 l

D. Radke A12 l

L. Anderson F3

These twelve (12) welders are representative of

the 237 welders qualified by Hunter Corporation

and are presently on site.

4. Review of Weld Material Control

The review of weld material control procedures and

direct observation of in-process activities indicate

that sufficient efforts are being implemented to

assure material traceability and control.

The documents reviewed for material traceability

are as follows:

. Weld Material Stores Requisition

. Purchase Requisition

. Materials / Services Request

. Material Receiving Report

. Receipt and Inspection Checklist

. Material Certificate

(c) Powers-Azco-Pope

1. Review of Procedures

The following procedures were reviewed:

. QC-4, Nonconformance Control

. FP-2, Control of Procurement and Requisitioning

of Material and Services

. FP-3, Material Receiving, Inspection Control

. FP-5, Weld Filler Material Control

. FP-6, Material Handling

. FP-7, Transfer Package and Weld Record Control

. WE-2, Welders Performance Qualification and

Control

2. Review of Records

The inspector selected three (3) safety related

small bore piping systems for material traceability

review. The review of the data packages consisted

of documentation from the purchase order to in-

sta11ation of the item involved. The systems

selected were as follows:

51

.

.

.

. Feedwater

. Containment Spray

. Reactor Coolant

The documents involved for review were as follows:

. Weld Filler Material Requisition

. Receiving Inspection Check List

. Final As-Built Isometric (Supplement Weld and

Inspection Record)

. Material Certification

. Weld Rod Issue Tag

. P.O. (CECO Responsibility)

. NDE Records

A study of the data packages, for the systems

selected, consisted of the following items:

SYSTEM PIPE SIZE HT # REC. & INSP. ISO #

Report #

RX Coolant 0.50" 462,444 MRR# 7074 IF1S-418B

Feed Water 0.50" M81,577 RIR# 040 ILT-542

Feed Water 0.50" D85,772 RIR# 040 1LT-542

Feed Water 0.50" E89,871 RIR# 040 ILT-542

Containment 0.50" 744-783 MRR# 7074 IFT-CS011

Spray

Total footage of piping involved consisted of 27,900'.

The suppliers of weld material for the Byron facility

is Hunter Corporation. The pipe materials are

supplied to the small bore piping contractors by

CECO. Therefore, purchase orders are originated

from these two (2) sources. This system of pur-

chasing in large quantities by one contractor /

l licensee enhances material traceability.

An expanded study of small bore piping was made to

include valves and fittings. Data packages for

the following items were reviewed:

FIELD REC & INSP.

i

ITEM HT# WELD # REPORT # ISO #

<

, Coupling EGJ 41 057 IPT-RC009

90 Elbow OZ 52 131 1PT-403

Valve 1RV048 N/A 20049 11J-461

S/N N11591

Valve IRC025E N/A 230 1FT-415

S/N N11526

52

.-- _

.

.

.

, 3. Revieu of Welder Qualification

The review of welder qualification records con-

sisted of reviewing the original qualification

record as well as the sLpportive documents per-

taining to their "up date" qualificiation record.

PAP welding efforts are conducted to the ASME

Code which requires three (3) month re qualifica-

tion periods.

The following welders had their certification and

qualification records reviewed:

Name Welder ID#

B. Strom CS

R. Sutherland AF

H. Arteaga DU

L. Flynn DX

D. Tucker BH

H. Mitchell AJ

R. Boyle BM

D. Shurely CE

P. Meyers DE

W. Meyers DG

These ten (10) welders are representative of the

46 welders qualified by PAP and are presently on

site.

4. Review of Wold Material Control

The review of weld material control procedures

and direct observation of in process activities

indicate that sufficient efforts are being impli-

, mented to assure material traceability and control.

The documents reviewed for material traceability

are as follows:

. Weld Filler Material Requisition

i

. Receiving Inspection Check List

. Material Certification

l . Weld Rod Issue Tag

. Weld and Inspection Record

(d) Blount Brothers Corporation

1. Review of Procedures

, The following procedures were reviewed:

I

53

,

- ~ - - - - - , - , - - _ , - , . - . . , - - - , , ,-- ,- , - -

.

.

,

. QC 3385 #1, Document Control

. QC 828 #2, Procurement Control

. QC 3012 #4, Inspection (Nonconformance

and Corrective Action)

. QC 3262 #7, Calibration of Tools, G@uges

and Instruments Concrete)

. QC 835 #10, Receiving, Storage and Handling

. QC 3333 #11, Welding - (AWS D1.1) 1974

i . QC 845 #21, Structural Steel Erection

. QC 1992 #33, Personnel Qualification and

Certification

2. Review of Records

The inspector selected nine (9) structural beams

for material traceability. Beams selected were

three from Unit #1 containment building and three

beams from Unit #1 auxiliary building. Three

'

more beams were selected from Unit #2 containment

building.

Beams selected were as follows:

Beam I.D. Building Unit # Drawing #

a A220B2 Containment 2 E-205

A230BB3 Containment 2 E-205

A240BB1 Containment 2 E-205

A132B5 Containment 1 E-102

B111BB2 -Containment 1 E-102

B104BB1 Containment 1 E-102

333B3 Auxiliary 1 E-201

326G1 Auxiliary 1 E-201

603B1 Auxiliary 1 E-201

The inspector reviewed the data packages for the

following structural steel for material traceability.

Beam # 326G1 -

Film Roll 3 -

Dr. #326

Index # Heat # S&L Letter Date

440 2R6969 12-28-76

j 435 J-31694 11-30-76

464 96266 12-28-76

474 96723 11-29-76

461 63062 11-08-76

i

Mill B8 L511159 02-28-77

Beam # 333B3 -

Film Roll 3 -

Dr. #333

54

- , __ . - _-, -

- _--. _-

.

.

Index # Heat # S&L Letter Date

351 K-24080 11-10-76

474 96723 11-19-76

Beam #B104BB1 -

Film Roll 1 -

Dr. #B104

Index # Heat # S&L Letter Dale

11133 69C076 06-29-77

11127 69C050 07-01-77

90126 66C242 07-01-77

90127 69C167 08-10-77-

80123 63729 05-26-77

Beam #A230BB3 -

Film Roll 1 - Dr. #A230 - 80230

-

Index # Heat # S&L Letter Date

38 70C576 02-07-78

62 K58219 02-06-78'

K58377 02-06-78

573 T47512 06-26-78

S-22 87495 06-27-78

Beam #B111BB2 -

Film Roll 1 -

Dr. #B111B

Index # Heat # S&L Letter Date

11113 VY4703 07-01-77

11106 70C266 07-01-77

90126 66C242 07-01-77

90127 69C167 08-10-77

80123 63729 05-26-77

Beam #A220B2 -

Film Roll 1 -

Dr. #A220

Index # Heat # S&L Letter Date

B-9 J-51717 12-13-77

S-43 44B489 07-19-78

B-1 A-325 Bolts 09-12-78

B-2 A-325 Bolts 06-09-78

Beam #A132B5 -

Film Roll 1 -

Dr. #A132

Index # Heat # S&L Letter Date

80135 24456 05-26-77

C-80119 W35079 07-11-77

A-80190 B-34009 08-10-77

55

.

.

Beam #603B1 -

Film Roll 3 -

Dr. #603

Index # Heat # S&L Letter Date

l

1407 10005 03-04-77

287 18216 10-12-76

Beam #A240BB1 - Revised to Beam #E144-1

S&L Drawing S-1001, Revision H. , Dated 3-16-78,

Note 10. Fabricated by Midcity Architectural

Iron Company (on-site contractor).

Heat # K62702 and #83833

A-325 Bolts - C6810; 4048

,

3. Review of Welder Qualifications

The review of welder qualification records consisted

of reviewing the original qualification reccrd as

well as the supportive documents pertaining to

their "up-date" qualification records. Blount

Brothers Corporation welding efforts are to AWS

Code which require six.(6) month re qualification

periods.

The following welders had their certification and

qualification records reviews:

j Name Welder ID #

K. Knaub K-5

R. Long K-4

P. Fadness P-4

1

R. Sullivan B-4

D. Lower L-4

W. Thompson V-4

K. Flosi W-3

R. Schusler V-18

K. Todo Y-4

D. S. Wielan D-5

The ten (10) welders are representative of the

fifteen (15) welders qualified by Blount Brothers

Corporation and are presently on site.

4. Review of Weld Material Control

The review of weld material control procedures and

direct observation of in process activities indicate

that sufficient efforts are being implemented to
assure material traceability and control.

i

56

.- . . - _ _ _ , _ - . _ .

.

.

The documents reviewed for material traceability

are as follows:

. Material Requisition

. Receiving Inspection Report

. Material Certification

. Weld Material Issue Sheet

. Weld Data Report

Within the areas inspected, no items of noncompliance or

deviations were identified.

57

- _ _ .

,

.

, .

Prepared By: R. S. Love

f. Electrical Cable Installation

(1) Objective

The objectives of this assessment were to determine if:

. cable installation procedures are in accordance with

FSAR commitments and that they are adequate for con-

trolling cabic installation activities.

. the cable installation personnel and QC inspectors have

been adequately trained in this activity.

. safety related cables are routed, separated, and loaded

in accordance with procedure requirements.

(2) Discussion

(a) Review of Electrical Procedures

The inspector reviewed the following Hatfield Electrical

Company procedures:

1. Procedure No. 5, Class I Material and Equipment

Receiving and Inspection, Revision 4, Issue 1,

3 dated January 26, 1981. This procedure was

l reviewed and accepted by Sargent and Lundy on

l January 27, 1981.

2. Procedure No. 6, Reporting of Damaged and Noncon-

forming Material or Equipment, Revision 6, dated

January 15, 1982. This procedure was reviewed and

accepted by Sargent and Lundy on February 11, 1982.

3. Procedure No. 9-A, Class I, Cable Pan Hanger Instal-

lation, Revision 11, dated November 20, 1982. This

procedure was reviewed and approved by Sargent and

Lundy on December 23, 1981.

i

4. Procedure No. 9-B, Class I, Cable Pan Installation,

Revision 9, dated November 20, 1981. This procedure

was reviewed and approved by Sargent and Lundy on

l December 23, 1981.

5. Procedure No. 9-E, Class I, Cable Pan Identification,

Revision G, Issue 1, dated January 23, 1981. This

,

'

procedure was reviewed and approved by Sargent and

Lundy on January 26, 1981.

,

58

I

l

,- - , .

. . - - - _ _ -- , .-. ,- , --

.

.

6. Procedure No. 10, Class I, Cable Installation,

Revision 14, dated February 8, 1982. This proce-

dure was reviewed and approved by Sargent and Lundy

on February 18, 1982.

Open Item (454/82-05-15; 455/82-04-15)

Procedure No. 9-B, Class I, Coble Pan Installation,

Revision 9, dated November 20, 1981, did not address

the installation of cable pan and riser covers. The

inspector was informed that Procedure No. 9-C would

address the installation of covers as required by

the Byron /Braidwood FSAR. This is an open item.

Unresolved Item (454/82-05-16; 455/82-04-16)

During review of Procedure 9-E, Class I, Cable Pan

Identification, Revision G, Issue 1, dated January 23,

1981, the inspector observed that paragraph S.3.1

of the subject procedures states in effect that the

requirements to apply segregation identification to

raceway at a minimum of every 15' does not apply to

risers. This is contrary to the requirements stated

in paragraph 5.1.2 of IEEE 384-1974. Pending a review

of installed riser identification markings for compli-

ance to requirements, this item is an unresolved item.

Noncompliance (454/82-05-09c; 455/82-04-09c)

During review of Procedure No. 10, Class I, Cable

Installation, Revision 14, dated February 8, 1982,

the inspector observed that the subject procedure

does not address:

a. the requirements to calculate electrical cable

sidewall pressure. Maximum cable sidewall pres-

sures are specified by the cable manufacturers,

b. electrical cable rework. Example - An electrical

cable has been installed per Revision A of the

cable pull card and Revision B of the pull card

requires that the cable be " pulled back" to a

given point in the raceway system and re-routed

to a different landing point. What precautions

are taken to prevent damage to the cable being

" pulled back" and to the cables remaining in

the raceway. This would be especially important

when the cable was installed in conduit or duct

banks. Another example would be that as a result

of an NCR, a cable had to be removed (Ref.

Hatfield NCR's 164, 154, 107).

Failure to provide adequate instructions or procedures

to accomplish activities affecting quality in accord-

ance with Quality Assurance Program provisions is an

59

1

.

.

item of noncompliance with Criterion V of 10 CFR 50,

Appendix B.

(b) Review of Storage Facilities - Cable Yard

The inspector toured the Hatfield Electric Company

cable reel yard to verify proper storage and to select

several cable reel numbers for follow-up review of

material receiving reports and vendor documentation.

The cable reels were stored on dunnage (plywood),

identified, and separated as to cable type. Electrical

cable reel numbers 02146-409, 04146-215, 03367-7, and

01135-43 were selected for records review.

(c) Review of Electrical k'ork Activities

1. During a tour of the power block the inspector

observed that the weld heat affected zone inside

cable tray 11774J-C2E, located at the 439' eleva-

tion of the cable spreading room, had not been

touched-up with zinc rich paint in accordance with

Hatfield Electric Company Procedure No. 9-B, Class

I, Cable Pan Installation, Revision 9, dated

November 20, 1981.- The licensee took immediate

action to have the subject area cleaned and galva-

noxed. This was the only area identified where

the weld or heat affected zone had not been

touched-up.

2. The inspector observed that non-safety related

pipe number FP-41-4-10" was installed 3 1/2" from

safety related cable tray number 11461J-C2E.

These items are located in the Auxiliary Building

between column lines 17 and P at the 426' eleva-

tion. Further investigation indicates that the

fire protection (FP) system is classified as

moderate energy piping and is seismically supported

in the area observed. This appears to meet the

intent of Regulatory Guide 1.29, Seismic Design

Classification.

3. The inspector verified that electrical cable

i number IVX105 was routed in accordance with the

cable pull card, Revision A. The subject cable

is a 12c/14, 600V and was pulled from cable reel

12146-201. The cable extends from 1AP32E (MCC

j 132X5) to IVX02J (Vent System Local Control Panel).

l

The cable was physically verified in routine points

11461J-C2E, 1R369-C2E, 1910F-C2E, IR353-C2E,

11375M-C2E, and verified that the cable entered

, the conduit to the equipment,

i

l

60

_-- -

2 *

.

The raceway was accepted on January 18, 1982, and

cable pulled on January 19, 1982.

! 4. During discussions with an electrical foreman and

one electrical craftspersor., the inspector observed

that, with respect to cable pulling, they were very

knowledgeable and proud of their work. The subject

craftsperson assisted the inspector in verifying

the routing of electrical cable IVS105 (Ref. Para-

graph (c)3 above).

(d) Review of Procurement Documentation - Class IE Cable

The inspector reviewed the procurement documentation

relative to 600V and SKV electrical cable. The inspector

reviewed the cable specifications, Material and Equip-

ment Receiving and Inspection Reports (MRR), and vendor

documentation. The following observations were made:

1. The licensee purchased the following electrical

cable from Okonite Company to Sargent and Lundy

specification F-2823.

a. Cable reel number 02146-409 containted 2500

feet of 2c/14, 600V cable and was received

May 11, 1981 on MRR 50217.

I

b. Cable reel number 04146-216 contained 3124

feet of 4c/14, 600V cable and was received

April 22, 1980 on MRR 8569.

c. Cable reel number 03356-7 contained 2060 feet

of 3c/350 MCM, 600V cable and was received

October 4, 1978 on MRR 4187.

The following data was included in the on-site

i

documentation packages for the above listed cables:

. Certificate of Compliance

. Certificate of Conformance

. Certified Test Report

. Results of Water Absorption Test

. Results of Ozone Resistance Test

. Results of High Potential Voltage Test

. Sargent and Lundy letter, dated June 20, 1980,

that accepted the results of Flame Tests and

Tests for Design Basic Events.

2. The licensee purchased electrical cable, reel

number 01115-43 from Okonite Company to Sargent

and Lundy specification F2851. This reel contained

1094 feet of Ic/1000 MCM, SKV cable and was received

61

1

,m- - - , .- . ,. - . - - p , . _ , , . ~ ~ . - ,- - - < - - - -

- _ . - - .- - .-. .

,

,

!

July 11, 1979 on MRR 7032. The following data was

included in the on-site documentation package for

this cable:

. Certificate of Compliance

. Certificate of Conformance

<

. Certified Test Report

. Results of Water Absorption Test

. Results of Ozone Resistance Test

. Results of High Potential Voltage Test

'

. Sargent and Lundy letter, dated June 20, 1980,

that accepted the result of Flame Tests and

Tests for Design Basic Events.

(c) Review of Class 1E Cable Pull Cards

The inspector reviewed 20 completed cable pull cards

to verify that correct cable type was installed,

raceway was inspected prior to pulling cable, and that

QC accepted the cable pull. The following typical

observations were made:

1. Cable IVX105 was pulled on January 19, 1982 from

Cable Reel 12146-201. Revision A to the cable

pull card indicates the cable type code as 12146

which is 12/c-14, 600 volt cable. The raceway

was accepted on January 18, 1982, and the cable

pull was accepted January 19, 1982. This was a

complete pull.

2. Cable IRC223 was pulled on April 9, 1981 from

Cable Reel 02166-41. Revision A to the cable

pull card indicates the cable type code as 02166

which is one twisted pair, #16 (shielded), 600

volt cable. The raceway was accepted on

!

March 27, 1981, and the cable pull was accepted

April 9, 1981. This was a complete pull.

3. Cable IVC 019 was pulled on June 23, 1981 from

Cable Reel 09146-84. Revision A to the cable

pull card indicates the cable type code as 09146

which is 9/c-14, 600 volt cable. The raceway

was accepted on June 22, 1981 and the cable pull

was accepted on June 23, 1981. This was a

j complete pull.

Except as noted, within the areas inspected, no items of

noncompliance or deviations were identified.

i

1

62

__. _

.. _ _ _ - _ - - . - - - . - ~ _ - - - - . - -

l k 1

'

. 't

i ( $-

l G-

-

.

1

Prepared By: H. H. Wescott

'

i

g. In-Process Inspection ,

j

j (1) Objectives (3l

The objective of this assessment was'to ascertain that ,

, in-process inspection procedures are adequate and properly

implemented. ,

(2) Discussion .

.

j (a) Review of Procedures  ;

The inspector reviewed procedures concerning in-process .i

"

inspection as follows:

,

1. Powers-Azco-Pope Quality Control Field Procedure

j FP-7, Revision 6, dated October 16, 1981, " Traveller

j Package and Weld Record Control PAP Isometric and

j

i

Installation Control".

2. Powers-Azco-Pope QC-6, Revision 6, dated

i September 30, 1981, " Quality Assurance Documen-

tation".

4 ,

3. Hatfield Electric Company Procedure 9-A, Revision

11, dated November 20, 1981, " Class I, Cable Pan

Hanger Installation".

! 4 Hatfield Electric Company Procedure 9-B, Revision

9, dated November 20, 1981, " Class I, Cable Pan

Installation".

i

i- 5. Hatfield Electric Company Procedure 20, Revision

8, dated November 20, 1981, " Class I, Exposed

'

Conduit System Installation". '

6. Hunter Corporation, Site Implementation Procedure

, SIP No. 1.601, Revision 1, dated March.3, 1981,

j " Quality Assurance Procedures and Instructions". '

! 7. Hunter Corporation, SIP No. 4.201, Revision 4,

i

dated January 19,.1982, " Installation Verification".

I

!

(b) Observation of Work Activities ,

j The inspector accompanied two Hatfield Electric

i Company QC inspectors and observed their inspection

{ of conduit hangers located in the control room.

i

f.

'

The inspector also observed the inspection and torquing m,

of four concrete expansion anchors.

.

'

! 63

!

l

!

_ _ , _ _ _ _ _ _ . _ _ , . . . . _ - . _ , . . . _ _ _ . , , _ _ _ . . _ __-_ _ _ . . _ _

. _ _ . . , _ . , _ , . . _ , , , , , , , , _ , .

. -. . . - _ _ . -

. _ _ . _ _ - . - . .. _ .__ _

._ ,

.

T

. i.

,

.

(c) Review of Records

, The inspector reviewed records as follows:

.

1. Hunter Corporation completed traveller packages

t  ? for welds Numbered 45, Part No. 1-SA-76-AD-3;

, ,

3

4 565, Part No. 1-CC-50-B-4"; Numbr.r 571, Part No.

i '

,' 1-CC-50-C-6"; Number 1608, Part No. 1-CC-50-C-6"

rework; Number 1171 and 1178, Line No. 1-D-0-33-CA-

t

3l4".

2. idunter Corporation Field Order JTP No 's 5-PS-100-

i *

78, 5-PS-10-77, HOG-72-1, S-NT-100-2-15-A, and

'

i OG-61-7.

3. Hatfield Electric Company QA Process Sheet File

'

No. 13.09B.1, Class I, Cable Pan Inspection

1

Checklists (approximately 33 checklists).

4. Hatfield Electric Company Concrete Expansion

.< Ancnor File No. 13.25.02, Travellers 1901 thru

i 1950'.

.,

5. Hatfield Electric Company Conduit Inspection

Reports; File No. 13.20.01, 766 thru 850.

\

(d) Personnel Int'rviewed e

'

The inspector interviewed two QC inspectors from

j Hatfield Electric Company.

i Noncompliance (454/82-05-17; 455/82-04-17)

'

The inspector interviewed four welders performing

in-process safety related welding (two from Hunter

J Corporation and two from Powers-Azco-Pope). Three

) of the welders did not have the welding procedure

,

1 specification (WPS) with the traveller packages.

When the inspector asked where the WPS was, two

i

welders did not appear to know what a WPS was and

I one-stated that he knew the WPS should be in the

j weld materia 1' issue point but stated that he had

l not seen it.

r

This item is considered to be in noncompliance with

the requirements of' 10 CFR 50, Appendix B, Criterion

IX.

l

l Except as noted, within the areas inspected, no items of

noncompliance or deviations were identified.

l

.

l

64

. . _ _ . - - _ _ _ _. _ . .. . ~ . _ , _ _ . _ _ _ . _ - . - _ - _ _

.

.

Prepared By: W. Forney

h. QC Inspector Effectiveness

(1) Objective

The objectives of this assessment were to determine if:

(a) any problems exist that inhibit an inspector from

properly executing his assigned functions.

(b) the training, qualifications, and certification of

QA/QC personnel working for contracting organizations

to the licensee are in compliance with 10 CFR 50,

Appendix B, ANSI N45.2.6-1978; ANST SNT-TC-1A, USNRC

Regulatory Guides 1.58, USNRC Generic Letter 81-01;

CECO Quality Assurance Program Manual; CECO Response

to Generic Letter 81-01 (L. O. De1 George to

D. G. Eisenhut-August 17, 1981); and Contractor Quality

Assurance Manuals.

(2) Discussion

Individuals selected for interview were chosen at random

by the NRC inspector. All contractors utilizing QA/QC

personnel to monitor and accept production activities at

the site were selected. The organizations selected, pro-

duction function monitored by the inspectors, number of

inspectors in the organization, number of inspectors inter-

viewed and percentages are identified in Table 2. Each

inspector interviewed was asked a standard set of questions.

The answers provided were summarized and are provided as

Table 3.

Individuals selected for QA/QC inspector interview were

requested to provide the record of their training, qualifi-

cation and certification to the inspector. Tne inspector

reviewed each of the training, qualifications and certi-

fication records to verify compliance with applicable

, regulatory requirements, standards and commitments. In

'

verifying the implementation of the approved requirements

emphasis was placed on (1) determination of initial cap-

ability by suitable evaluation (2) evaluation of perform-

ance/ reevaluation (3) written certification in appropriate

form (4) physical requirements identified and examined yearly,

and (5) qualification criteria followed and (6) records of

qualification established and maintained.

Table 3 is provided as a summary of inspector answers to the

standard set of interview questions. Answers to questions

1, 2, 4, 5 are self evident and do not require further

definitions. However, the answers to remaining questions

require further clarification and conclusions.

, 65

i

- - - . .

.

.

Question 3 - relates to the number of inspectors that in-

dicated during their answer to Question 2 that they had

prior inspection experience. Of the 30 inspectors inter-

viewed 47% indicated prior inspection experience; however,

only 27% had prior inspection experience in nuclear work

related activities.

Question 6 - of the 19 inspectors interviewed that regularly

worked frequent or excessive overtime one worked less than

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> weekly, fourteen worked from 8 to 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> weekly,

and four work greater than 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> weekly. The two

inspectors that provided qualified answers _ indicated the

overtime was intense at times based upon fluctuations of

production activities. All of the inspectors that answered

yes or qualified their answer were asked if the frequent or

excessive overtime caused the accuracy of their inspections

to be deminished. Without exception, none of the inspectors

felt the accuracy of their inspections were affected.

Question 7 and 8 - the inspectors that provided a qualified

answer to these questions indicated that the lack of adequate

staff and/or failure to conduct inspections promptly were a

result of fluctuations in production activities.

Open Item (454/82-05-18; 455/82-04-18)

Question 9 - indicates that inspectors generally do not

feel they have the authority to stop an activity in their

contractor's work that is not being properly performed,

nor have they been provided written management policy in

this area. The inspectors that provided qualified answers-

indicated that they would inform the area supervisor.

The inspectors were also asked if they felt they could

immediately stop the work activity of another contractor

worker who was performing work that was hazardous to

safety related equipment. The majority of inspectors

indicated they did not have that authority.

The licensee management committed to take actions to

re-emphasize to all inspectors their responsibility to

stop an activity which does not conform to applicable

quality requirements. This item will be examined during

a future inspection.

Question 10 - the majority of inspectors interviewed

indicated that the training they received was adequate

for the work activity they are required to perform. One

inspector did not feel his training was adequate and the

remaining inspectors felt that although their training

was not the best, that if they needed additional guidance

or clarification that management would provide the infor-

mation immediately.

66

O

.

i

Question 11 - indicates that inspectors do not feel that a

lack of inspection personnel is the cause for construction

activities to come to a stop and is consistent with the answers

provided in Question 8.

Question 12 - the inspectors that qualified their answer gener-

ally indicated that their activity did not require a check list

but was normally accomplished utilizing a combination of in-

sta11ation plans and/or procedures.

Question 13 - the inspectors that qualified their answer indi-

cated that they would have to follow the chain-of-command which

could be untimely.

When asked to discuss their opinion of how their management

portrays the relationship of quality to production the majority

of inspectors stated that quality was first and production

second, a number of inspectors stated that quality and produc-

tion were on an equal basis, and a few of the inspectros (pre-

dominately from one contractor) stated that production was

first and quality second.

When asked to discuss their opinion of the overall finished

product of their contractors activities the majority of in-

spectors stated that the work generally exceeded minimum

acceptable standards, a few stated the work generally met

minimum standards, and no inspectors felt that the work did

not meet minimum acceptable standards.

Noncompliance (454/82-05-19; 455/82-04-19)

Based on a review of training qualification and certification

records of a minimum of ten percent of the QA/QC personnel

working for contractors performing safety-related work it is

apparcat that an effective program does not exist to ensure

that a suitable evaluation of initial capabilities is performed,

that written certification is provided in an appropriate form,

and that qualification criteria is established.

Certain contractor QA/QC supervisors and inspectors were not

adequately qualified and/or trained to perform safety-related

inspection functions. The following examples of apparent non-

compliance were identified:

a. Contractor - Reliable Sheet Metal Works, Inc.

(1) The contractor Quality Assurance Manual did not require

inspection personnel to be trained and certified to

ANSI N45.2.6-1978.

(2) The certification record for the QA/QC supervisor did

not contain a satisfactory basis for certification.

(3) The certification record for the QA/QC supervisor did

not contain the level of capability.

67

.

__ __ _ _ . . - _

.

.

b. Contractor - Johnson Controls, Inc.

(1) The certification records reviewed did not contain a

determination of initial capability.

(2) The certificaticn records reviewed did not contain a

copy of the individuals high school diploma or veri-

.

fication of prior work history.

(3) The certification records reviewed did not support

adequate testing prior to certification. It is noted

that testing was accomplished by oral examination

consisting of 25 questions to determine the individuals

knowledge of 26 procedures. The oral examination noted

the individual was weak in ability to work with draw-

ings. However, there is no record to indicate addi-

tional training was provided or that the individual

was subsequently tested and found to be proficient in

his ability to work with drawings.

c. Contractor - Powers-Azco-Pope

(1) The certification records for the QC Supervisor did not

provide an adequate determination of initial capability.

(2) The certification records for the QC Supervisor did not

contain a high school diploma, or verification of pre-

vious employment.

(3) The certification records for the QC Supervisor did not

contain adequate evaluation and justification for certi-

fication to Level I or subsequent certification to

Level II Supervisor.

(4) The certification records for three (3) QC inspectors

did not contain a high school diploma.

(5) The certification folder for three (3) QC inspectors

did not contain verifications of prior employment.

(6) The certification records for the QC Supervisor and

three (3) QC inspectors contain open book examinations

that do not provide an adequate icvel of knowledge

prior to certification. The records did not contain

results of a capability demonstration to support certi-

fication.

(7) The certification records for three (3) QC inspectors

did not contain adequate evaluation and justification

for certification to Level I and subsequent certifica-

tion to Level II inspector.

68

[

.

.

d. Contractor - Hunter Corporation

(1) The certification records for two (2) of the seven (7)

QC inspector qualifications reviewed did not provide

determination of equivalent inspection experience to

support the level of certification.

e. Contractor - Hatfield Electric Company

(1) The certification records for three (3) of the nine

(9) inspector qualifications reviewed did not contain

c Certification Evaluation Sheet.

(2) The certification record for one (1) of the nine (9)

QC inspector qualifications reviewed did not have

records of examinations or work samples.

(3) The certification records for two (2) of the nine (9)

QC inspector qualifications reviewed did not provide

complete evaluation and justification for certification

to perform the level of inspection identified.

f. Contractor - Blount Brothers Corporation

(1) The certification record for one (1) of the two (2)

QC inspector qualifications reviewed did not indicate

the expiration date of certification as a Level I lead

auditor.

g. Contractor - Midway Industrial Contractor, Inc.

-

(1) The certification record for the QC inspector quali-

fications reviewed did not indicate the activities

certified to perform.

,

h. Contractor - Pittsburgh Testing Laboratory

(1) The certification record for one of the three (3)

QC/QA inspector qualification records reviewed did

not have an evaluation of prior work experience.

Based on a sample review of CECO audits conducted in the

area of training Tsalification and certification for the

period 1979-19Fa i+ . 2 determined that a program exists

to routinely review the acceptability of QA/QC personnel.

It was noted that many audit findings were identified and

resulted in notable improvements of contractor adherence

to ANSI N45.2.6-1978. During the meeting conducted April 9,

1982, CECO management committed to develop an alternate plan

for certification of contractor QC inspectors when the

recommendations of ANSI N45.2.6.-1978, Section 3.5 are not

complied with. Additionally, a commitment was made to

require each contractor to verify inspectors education and

experience.

69

_ . . . .. _. . _. . . . . .

. . ,

__

..

.

TABLE 1

Licensee and On-site Contractors

QA/QC Periodic QA/QC

Services # Cract QA/QC Organ. Review of Supv.

Organization Performed Workers Staff Indep. QA Program Pos. Des.

Commonwealth Licensee N/A 16 Yes Yes Yes

Edison

Blount Brothers Plant 220 5 Yes Yes Yes

Structures

Ebasco Services Inservice 10 2 Yes Yes Yes

Inspection

Hatfield Electric Electrical 555 83 No Yes No

l Company Installation

l

Hunter Corp. Piping 944 71 Yes Yes Yes

Systems

Johnson Controls HVAC 47 2 (2) Yes Yes

Controls .

Midway Indust. Field Finish 10 2 Yes Yes Yes

NISCO Mechanical 10 2 Yes Yes Yes

Erector

Nuclear P.S. Mechanical *96 1 Yes Yes Yes

Design

Pittsburgh Testing #28 1 Yes Yes Yes

Test Lab

Powers-Azco-iope Instrumenta- 135 11 No Yes Yes

tion

Reliable Sheet HVAC 37 2 Yes Yes Yes

Metal

Sargent & Lundy A. E. Firld *72 0 (1) Yes (1)

Group

Westinghouse Mechanical *47 0 (1) Yes (1)

SAMU Design

  1. - Testers * - Engineers

(1) - Not reviewed (2) - Unresolved item

6

70

-. . _. _

.

, TABLE 2

QA/QC INSPECTCR INTERVIEW SUMMARY

Total Inspectors

Organization Function Inspectors Interviewed 1

EBASCO Services Inservice Inspection 2 1 50

NISCO Erect miscellaneous 2 1 50

mechanical equipment,

final setting and

erection of NSSS

equipnent.

Reliable Sheetmetal HVAC 2 1 50

Johnson Controls HVAC Controls 2 1 50

, Powers Azco Pope Instrumentation 11' 4 36.36

(PAP)

Hunter Corporation Piping System 71 7 9.86

Hatfield Electrical Installation 83 9 10.84

Blount Brothers Plant Structures 5 2 40

Pldway Field Finish Coating 2 1 50

Pittsburgh Testing Lab Onsite NDT 28 3 10.71

, TCrrALS 208 30 14.42

!

._ - - - . - - ~ -

--

--

y

.

TABLE 3

.

SUMMARY OF QUESTIONS ASKED

QC/QA INSPECTORS DURING INTERVIEWS

1. How long employed as an inspector 3 mo. 6 mo. 6 no.-l yr.

onsite?

2 4 8

1-2 yr. 2-3 yr. 4 yr.

7 4 5

Yes pig,

2. Prior inspection experience? 14 16

Nuclear Non-Nuclear

3. What discipline (s)? 8 6

Implemented

Qualified

Yes pict Qualified Answer

4. Is there a sense of intimidation 29 1

.

based upon the neeo/ requirement

to keep up with construction?

5. Is there a reluctance to make 29 1

adverse findings if they will

impact on the construction or

audit schedule?

6. Is it routine for QC inspectors 19 9 2

to be working frequent and/or

excessive overtime?

7. Do the inspectors feel that their 19 2 9

particular section is adequately

staffed?

8. Do they feel the required inspections 18 2 10

are being conducted promptly?

9. Do the QC inspectors have stop work 13 3 14

. and/or stop process authority?

Have they ever used this authority? 13 9 8

If so do they feel they were supported 19 1 3 7

or will heve the support of manage-

ment in the event of a stop work?

v

.

"

o

Implemented

Qualified

Yes o

N_o Qualified Answer

10. Do the inspectors feel the 24 1 5

training they have been provided

is adequate?

11. Do situations arise where the 1 27 2

lack of a QC inspector causes

construction activities to come

to a stop?

12. Are the QC inspectors provided 15 15

adequate check lists for all

activities they are inspecting

or are they sometimrs using

vague guidelines?

13. Do they feel that they have an 28 2

avenue to management if they

come across a problem?

Do they feel management will get 27 3

, involved or just pay lip service?

.

o

O