|
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML20024J2481994-10-0707 October 1994 LER 94-012-00:on 940907,discovered Failure to Perform TS Surveillance Requirements.Caused by Misunderstanding & Inadequate Technical Reviews.Ts Bases for 3/4.8.1 Will Be revised.W/941007 Ltr ML20029D9941994-05-11011 May 1994 LER 94-006-00:on 940415,determined That on 921103, Unidentified RCS Leak Rate of Greater than 1 Gpm Occurred. Caused by Error in RCS Mass Balance Equation.Approved Temporary Change to Procedure OP-903-024.W/940511 Ltr ML20045H4731993-07-15015 July 1993 LER 93-002-00:on 930615,reactor Tripped Due to High SG Level Caused by Failure of Feedwater Control Sys.Caused by Failure of Square Root Extractor in Feedwater Flow Circuit.Failed Components Replaced & Alarm Setpoints reviewed.W/930715 Ltr ML20042F7501990-05-0707 May 1990 LER 90-004-00:on 900408,partial Actuation of Emergency Feedwater Sys Occurred During Scheduled Test of Plant Protection Sys.Caused by Test Circuit Malfunction.Relay Hold Pushbutton Assembly replaced.W/900507 Ltr ML19332C5781989-11-20020 November 1989 LER 89-020-00:on 891031,containment Fan Cooler C Motor Ran in Reverse Direction Reducing Air Flow & Cooling Capacity. Caused by Personnel Not Performing Surveillance Testing. Motor Rewired for Correct Slow Speed operation.W/891120 Ltr ML19324C4611989-11-13013 November 1989 LER 89-019-00:on 891012,4.16-kV Bus 3A2 Metering Potential Transformer Fuse Door Inadvertently Opened,Causing Feeder Breaker & Supply Breaker to Open & Load Sequencer to Reset. Caused by Personnel Error.Drawers relabeled.W/891113 Ltr ML19327C1111989-11-13013 November 1989 LER 89-002-01:on 890125,discovered That Safety Classification of Instrument Air Tubing That Supplies Outlet Isolation Valves Installed as non-nuclear Safety.Caused by Use of Weld Filler Matl.Tech Spec Change Sent ML19327B3511989-10-23023 October 1989 LER 89-018-00:on 890921,while Testing Main Steam Safety Valve,Lift Pressure Found to Be Below Tech Spec Allowable Value.Caused by Error in Judgement by Plant Supervisors. Event Will Be Discussed by superintendent.W/891023 Ltr 1994-05-11
[Table view] Category:RO)
MONTHYEARML20024J2481994-10-0707 October 1994 LER 94-012-00:on 940907,discovered Failure to Perform TS Surveillance Requirements.Caused by Misunderstanding & Inadequate Technical Reviews.Ts Bases for 3/4.8.1 Will Be revised.W/941007 Ltr ML20029D9941994-05-11011 May 1994 LER 94-006-00:on 940415,determined That on 921103, Unidentified RCS Leak Rate of Greater than 1 Gpm Occurred. Caused by Error in RCS Mass Balance Equation.Approved Temporary Change to Procedure OP-903-024.W/940511 Ltr ML20045H4731993-07-15015 July 1993 LER 93-002-00:on 930615,reactor Tripped Due to High SG Level Caused by Failure of Feedwater Control Sys.Caused by Failure of Square Root Extractor in Feedwater Flow Circuit.Failed Components Replaced & Alarm Setpoints reviewed.W/930715 Ltr ML20042F7501990-05-0707 May 1990 LER 90-004-00:on 900408,partial Actuation of Emergency Feedwater Sys Occurred During Scheduled Test of Plant Protection Sys.Caused by Test Circuit Malfunction.Relay Hold Pushbutton Assembly replaced.W/900507 Ltr ML19332C5781989-11-20020 November 1989 LER 89-020-00:on 891031,containment Fan Cooler C Motor Ran in Reverse Direction Reducing Air Flow & Cooling Capacity. Caused by Personnel Not Performing Surveillance Testing. Motor Rewired for Correct Slow Speed operation.W/891120 Ltr ML19324C4611989-11-13013 November 1989 LER 89-019-00:on 891012,4.16-kV Bus 3A2 Metering Potential Transformer Fuse Door Inadvertently Opened,Causing Feeder Breaker & Supply Breaker to Open & Load Sequencer to Reset. Caused by Personnel Error.Drawers relabeled.W/891113 Ltr ML19327C1111989-11-13013 November 1989 LER 89-002-01:on 890125,discovered That Safety Classification of Instrument Air Tubing That Supplies Outlet Isolation Valves Installed as non-nuclear Safety.Caused by Use of Weld Filler Matl.Tech Spec Change Sent ML19327B3511989-10-23023 October 1989 LER 89-018-00:on 890921,while Testing Main Steam Safety Valve,Lift Pressure Found to Be Below Tech Spec Allowable Value.Caused by Error in Judgement by Plant Supervisors. Event Will Be Discussed by superintendent.W/891023 Ltr 1994-05-11
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217F2891999-10-13013 October 1999 Drill 99-08 Emergency Preparedness Exercise on 991013 05000382/LER-1999-014, :on 990910,reactor Shutdown Due to Loss of Controlled bleed-off Flow,Occurred.Caused by Rotating Baffle failure.Two-piece Rotating Baffle of Original Design Was Located & Installed,In Order to Repair RCP 2B1999-10-12012 October 1999
- on 990910,reactor Shutdown Due to Loss of Controlled bleed-off Flow,Occurred.Caused by Rotating Baffle failure.Two-piece Rotating Baffle of Original Design Was Located & Installed,In Order to Repair RCP 2B
ML20217G7211999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Waterford 3 Ses. with 05000382/LER-1999-013, :on 990825,exceeding TS Limits for RCS Cooldown Rate Was Discovered.Caused by Inadequate Content & Inadequate Implementation of TS Requirements.Page 2 of 2 in Attachment 2 of Incoming Submittal Not Included1999-09-23023 September 1999
- on 990825,exceeding TS Limits for RCS Cooldown Rate Was Discovered.Caused by Inadequate Content & Inadequate Implementation of TS Requirements.Page 2 of 2 in Attachment 2 of Incoming Submittal Not Included
05000382/LER-1999-012-01, :on 990812,potential Operation with Both Control Room Normal Outside Air Intakes Valves Inoperable Occurred.Cause for Event Was Indeterminate.Seat Leakage Requirements Calculated.With1999-09-13013 September 1999
- on 990812,potential Operation with Both Control Room Normal Outside Air Intakes Valves Inoperable Occurred.Cause for Event Was Indeterminate.Seat Leakage Requirements Calculated.With
ML20211Q2141999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for Waterord 3 Ses.With 05000382/LER-1999-011-01, :on 990801,with Plant Operating 100% Power, Lowering RCP Seal Pressures,Along with Dropping Controlled bleed-off (Cbo) & Increasing Cbo Temp Discovered.Caused by fatigue-induced Failure of Rotating Baffle of RCP 2B1999-08-31031 August 1999
- on 990801,with Plant Operating 100% Power, Lowering RCP Seal Pressures,Along with Dropping Controlled bleed-off (Cbo) & Increasing Cbo Temp Discovered.Caused by fatigue-induced Failure of Rotating Baffle of RCP 2B
05000382/LER-1999-010-01, :on 990726,discovered Inadequate Pumping Capacity in Dry Cooling Tower Area.Caused by Inadequate Design Control.Portable Pumps Were Installed in Each Dry Cooling Tower Areas to Ensure Sufficient Pumping Capacity1999-08-26026 August 1999
- on 990726,discovered Inadequate Pumping Capacity in Dry Cooling Tower Area.Caused by Inadequate Design Control.Portable Pumps Were Installed in Each Dry Cooling Tower Areas to Ensure Sufficient Pumping Capacity
05000382/LER-1999-009-01, :on 990727,discovered App R Noncompliance Condition Involving Inadequate Separation of Safe Shutdown Cables.Caused Design Analysis Deficiency.Compensatory Measures Were Established1999-08-26026 August 1999
- on 990727,discovered App R Noncompliance Condition Involving Inadequate Separation of Safe Shutdown Cables.Caused Design Analysis Deficiency.Compensatory Measures Were Established
ML20210Q6361999-07-31031 July 1999 Corrected Monthly Operating Rept for July 1999 for Waterford 3 ML20210S0581999-07-31031 July 1999 Monthly Operating Rept for July 1999 for Waterford 3.With 05000382/LER-1999-008-01, :on 990629,failure to Perform Testing of ESF Filtration Units Per TS Was Noted.Cause for Testing Charcoal Samples Contrary to TS Could Not Be Determined.All Future Analysis Will Be Performed IAW ASTM D3803-1989,per GL 99-021999-07-29029 July 1999
- on 990629,failure to Perform Testing of ESF Filtration Units Per TS Was Noted.Cause for Testing Charcoal Samples Contrary to TS Could Not Be Determined.All Future Analysis Will Be Performed IAW ASTM D3803-1989,per GL 99-02
05000382/LER-1999-007-01, :on 990625,operation Outside Tornado Missile Protection Licensing Basis for turbine-driven EFW Pump & Steam Supply Piping,Was Discovered.Caused Indeterminent. Entergy Will Submit 10CFR50.90 to NRC Staff1999-07-23023 July 1999
- on 990625,operation Outside Tornado Missile Protection Licensing Basis for turbine-driven EFW Pump & Steam Supply Piping,Was Discovered.Caused Indeterminent. Entergy Will Submit 10CFR50.90 to NRC Staff
ML20210D8951999-07-23023 July 1999 Safety Evaluation Accepting First 10-yr Interval Inservice Insp Plan Requests for Relief ISI-018 - ISI-020 05000382/LER-1999-006-01, :on 990614,plant Experienced Automatic Reactor Trip Following Loss of 7kV Bus.Caused by Spurious Actuation of Relay on Either RCP 1A or 2A.Personnel Performed Final Switchgear Walkdown with Indications Normal.With1999-07-14014 July 1999
- on 990614,plant Experienced Automatic Reactor Trip Following Loss of 7kV Bus.Caused by Spurious Actuation of Relay on Either RCP 1A or 2A.Personnel Performed Final Switchgear Walkdown with Indications Normal.With
ML20209H3781999-06-30030 June 1999 Monthly Operating Rept for June 1999 for Waterford 3 Ses. with 05000382/LER-1999-005-01, :on 980702,determined That Four Contacts in Control Circuits of EFW Control Valves Were Untested.Caused by Personnel Error.Untested Contacts Have Been Tested1999-06-24024 June 1999
- on 980702,determined That Four Contacts in Control Circuits of EFW Control Valves Were Untested.Caused by Personnel Error.Untested Contacts Have Been Tested
ML20195J8951999-06-17017 June 1999 Safety Evaluation Granting Relief for Listed ISI Parts for Current Interval,Per 10CFR50.55a(g)(5)(iii) ML20195J9741999-06-16016 June 1999 Safety Evaluation Supporting Amend 152 to License NPF-38 ML20207E8631999-06-0303 June 1999 Safety Evaluation Accepting Licensee 990114 Submittal of one-time Request for Relief from ASME B&PV Code IST Requirements for Pressure Safety Valves at Plant,Unit 3 ML20195D5491999-06-0303 June 1999 Safety Evaluation Supporting Amend 151 to License NPF-38 ML20195K3391999-05-31031 May 1999 Monthly Operating Rept for May 1999 for Waterford 3 Ses.With ML20195C3041999-05-28028 May 1999 Annual Rept on ABB CE ECCS Performance Evaluation Models 05000382/LER-1999-004-02, :on 990415,discovered That Complete Response Time for ESFAS Containment Cooling Function Had Not Been Performed.Caused by Response Time Testing Deficiency. Procedures Will Be Revised to Include Subject Testing1999-05-14014 May 1999
- on 990415,discovered That Complete Response Time for ESFAS Containment Cooling Function Had Not Been Performed.Caused by Response Time Testing Deficiency. Procedures Will Be Revised to Include Subject Testing
ML20206S7401999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for Waterford 3.With ML20205T2621999-04-22022 April 1999 LER 99-S02-00:on 990216,contract Employee Inappropriately Granted Unescorted Access to Plant Protected Area.Caused by Personnel Error.Security Personnel Performed Review of Work & Work Area That Individual Was Involved with ML20206A9641999-04-21021 April 1999 Safety Evaluation Supporting Amend 150 to License NPF-38 05000382/LER-1999-003-02, :on 990311,determined That Four Containment Vacuum Relief valves,CVR-101,CVR-201,CVR-102 & CVR-202,were Not Tested.Caused by Contractor Supply of Misinformation. Details of Event Discussed with Contractor.With1999-04-0909 April 1999
- on 990311,determined That Four Containment Vacuum Relief valves,CVR-101,CVR-201,CVR-102 & CVR-202,were Not Tested.Caused by Contractor Supply of Misinformation. Details of Event Discussed with Contractor.With
ML20205N9671999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for Waterford 3 Ses.With ML20205E8531999-03-30030 March 1999 Corrected Pages COLR 3/4 1-4 & COLR 3/4 2-6 to Rev 1, Cycle 10, Colr ML20205A6331999-03-25025 March 1999 SER Accepting Request to Use Mechanical Nozzle Seal Assemblies as an Alternative Repair Method,Per 10CFR50.55a(a)(3)(i) for Reactor Coolant Sys Applications at Plant,Unit 3 05000382/LER-1999-002-03, :on 990225,discovered RCS Pressure Boundary Leakage on Two Inconel 600 Instrument Nozzles.Caused by Axial Cracks Near HAZ of Nozzle Partial Penetration Welds Resulting from Pwscc.Leaking Nozzles Have Been Repaired1999-03-25025 March 1999
- on 990225,discovered RCS Pressure Boundary Leakage on Two Inconel 600 Instrument Nozzles.Caused by Axial Cracks Near HAZ of Nozzle Partial Penetration Welds Resulting from Pwscc.Leaking Nozzles Have Been Repaired
ML20204H1401999-03-23023 March 1999 Rev 1 to Engineering Rept C-NOME-ER-0120, Design Evaluation of Various Applications at Waterford Unit 3 ML20204H1231999-03-22022 March 1999 Rev 1 to Design Rept C-PENG-DR-006, Addendum to Cenc Rept 1444 Analytical Rept for Waterford Unit 3 Piping ML20204H2451999-03-22022 March 1999 Rev 2 to C-NOME-SP-0067, Design Specification for Mechanical Nozzle Seal Assembly (Mnsa) Waterford Unit 3 ML20204F0791999-03-17017 March 1999 Rev 1 to Waterford 3 COLR for Cycle 10 ML20207M9231999-03-12012 March 1999 Amended Part 21 Rept Re Cooper-Bessemer Ksv EDG Power Piston Failure.Total of 198 or More Pistons Have Been Measured at Seven Different Sites.All Potentially Defective Pistons Have Been Removed from Svc Based on Encl Results ML20207F3491999-03-0505 March 1999 LER 99-S01-00:on 990203,contraband Was Discovered in Plant Protected Area.Bottle Was Determined to Have Been There Since Original Plant Construction.Bottle Was Removed & Security Personnel Performed Search of Area.With ML20204B5141999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for Waterford 3.With ML20203H8151999-02-17017 February 1999 Safety Evaluation Supporting Amend 149 to License NPF-38 ML20203H8591999-02-17017 February 1999 Safety Evaluation Accepting Licensee Second Ten Year ISI Program & Associated Relief Requests for Plant,Unit 3 05000382/LER-1999-001, :on 990105,TS 3.0.3 Was Entered.Caused by Less than Adequate Chiller Thermostat Control.Placed Tamper Seal on Chiller Thermostat.With1999-02-0404 February 1999
- on 990105,TS 3.0.3 Was Entered.Caused by Less than Adequate Chiller Thermostat Control.Placed Tamper Seal on Chiller Thermostat.With
ML20202H9161999-02-0202 February 1999 Safety Evaluation Supporting Amend 148 to License NPF-38 ML20199H6261999-01-21021 January 1999 Safety Evaluation Accepting Classification of Instrument Air Tubing & Components for Safety Related Valve Top Works.Staff Recommends That EOI Revise Licensing Basis to Permit Incorporation of Change 05000382/LER-1998-020, :on 981204,determined That Certain Core Power Distribution SRs Had Been Incorrectly Scheduled.Caused by TS Change Implementation Error.Will Perform Final Review of TS SRs with 4.0.4 Exemption.With1998-12-31031 December 1998
- on 981204,determined That Certain Core Power Distribution SRs Had Been Incorrectly Scheduled.Caused by TS Change Implementation Error.Will Perform Final Review of TS SRs with 4.0.4 Exemption.With
ML20199C9101998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for Waterford 3.With ML20198F4691998-12-21021 December 1998 Safety Evaluation Supporting Amend 147 to License NPF-38 ML20196F4911998-12-0101 December 1998 SER Accepting Request for Relief ISI2-09 for Waterford Steam Electric Station,Unit 3 & Arkansas Nuclear One,Unit 2 ML20206N4131998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for Waterford 3.With ML20195C4841998-11-0606 November 1998 SER Accepting QA Program Change to Consolidate Four Existing QA Programs for Arkansas Nuclear One,Grand Gulf Nuclear Station,River Bend Station & Waterford 3 Steam Electric Station Into Single QA Program 1999-09-30
[Table view] |
Text
,=
f
+^- ,
- ,j }
o: ';
)
- k. .?
Ref: 10CFR50.73(a)(2)(iv) !
I
[]
,,. g Fz "#
L Louissama!
POWER & L1GHT WATUVORD 3 SES
I i
$NNIvsM W3A89-0204 f A4.05 l t
l-QA l
, November 13, 1989 l r
U.S. Nuc1 car Regulatory Commission ;
l ATTENTION: Document Control Desk '
- l. Washington, D.C. 20555 l
f
Subject:
Waterford 3 SES :
L Docket No. 50-382 i License No. NPF-38 Reporting of Licensee Event Report r Centlemen's i
- \
, Attached is Licensee Event Report Number LER-89-019-00 for Waterford :
Steam Electric Station Unit 3. This Licenst:e Event Report is submitted I putsuant to 10CFR50.73(a)(2)(iv). !
t Very truly yours. j (J.R.McGaha Plant Manager - Nuclear 1 f
-JRM/PTG/rk !
(w/ Attachment) ,
cci Messrs. R.D. Martin J.T. Wheelock - INPO Records Center !
E.L. Blake I W.M. Stevenson l D.L. Wigginton !
NRC Resident Inspectors Office !
, i 1 ;
(. I 1 ;
y .
i 8911170142 891113 i gDR ADOCK05000,g2 I
I t i
w p.e ans u s wucttu aaov617ony ConswsosiOes l . <* ovo o.. =o n . .
+ '
, LICENSEE EVENT REPORT ILER) 8 5 a ' * * **
$& cal 97V 4AML fli DUCT ti Nufitte n (at FAGE 4 Waterford Steam Electric Station Unit 3 ~ 0 l610 l0 l 01318 12 1 lMl O l4 v o 6 4 ..
Loss of Voltage to a Safety Bus due to Personnel Error 8 WSNT patt ttl (la WynamiR (Si SteORT Datt 171 OTHE R f AClLlIlt $ thVOLVE D St MONTH Dav VfAR VtAM g' 'm' *S"e'Q MONTH I bay
. EAR 8 AC84ti t 8e&Me t DOC A41 NuY98 84tSt
^E N/A 0lbl0l0l01 l l 1 l0 1l 2 8 9 8l9 0l 1!9 0 l0 1l1 1l3 d9 N/A 0q6 to l0 iog l l
,,,,,,,,,, tMis alPont a suouitno evasuaNr vo tut niavialvtkn o, $o Ce n s ve .,,a. . +,i nu
" * * *' 6 ***2*' ro mm X so nwnine ta n ni no connuoi oo mmini se ni.nsn.i vi t u.i ggi _, _ _ _
noi o lo t o ao asuninsi so manni sets.nsn
_ g,H8 gs,7,7,ag.,g
,o .. n n, i .o n n.ni, .. n.n,n. n.i ~~
to enemuni..: Se n. nan. so ni. nan.. nei
) to sett.nin.i 60 taianen.ai tio f atainnat LICINtti COkt ACT SOA f ull tim nei NLME TILIPHONI Nvette A8'E4 G004 D.F. Packer, Assi' tant Plant Ma". ages - Operations & Maintenance 510 14 416 1 41-13 f. 1314 CD8A8Lif t 08vt L'h8 FOR 4 ACH N 8PONthf f altunt DischlSED IN THIS AGPOfit n3B CAU$8 $Ylf tM COMP 0'st NT #('y 0 "I#
gg gpp" C AV$t $v$Tt Y COMPONENT "l 0 g\"p?pp A6
! 1 1 I I I i 1 i i I i i t l I i i i I I I I I I i l i SUPPLlMINT AL REPORf E PPECTED tiet MONTH DAY . EAR Sv8Vis$ ION Tl5 (8' roe rempw'. f APFCfl0 Sve4'r$3s0N CA f(/ No g g
..in.C,u,.,,,,.x.m,...,,,...-,,,,....<.,..,....,n.,
At 1326 hours0.0153 days <br />0.368 hours <br />0.00219 weeks <br />5.04543e-4 months <br /> on October 12. 1989 Waterford Steam Electric Station Unit 3 was in Mode 6. Refueling, when an electrician inadvertently opened the 4.16 KV bus 3A2 metering Potential Transionner (PT) fuse drawer initiating a loss of voltage signal for the 3A2 electrical bus. The above indicated loss of voltage caused the feeder breaker from bus 3A2 and supply breaker to sciety bus 3A3S to open and Diesel Cenerator A Load Sequencer to reset.
The metering PT fuse drawer was closed and all breakers returned to the appropriate lineup by 1335 hours0.0155 days <br />0.371 hours <br />0.00221 weeks <br />5.079675e-4 months <br />. Because of the inadvertent actuation of an engineered safety feature (loss of voltage circuit), this event is reportable per 10 CFR 50.73(a)(2)(iv).
The root cause of this event is personnel error. Contributing to this event vere unnecessary work instructions and inadequate labeling and control of the notering pT fuse drawer. Because there was no loss of power to the operating shutdown cooling pump or other required safety related equipment, this e<ent did not threaten the health and safety of the public or plant personnel.
'
'Iffic Poe atta U S wLICLlam ht0 ult 0mv COMMISSI0lu~
UCENSEE EVENT REPORT (LE] TEXT G^NTINUATION ***aovioowsno mo-om -
, excents. e arm r enciuty haut n1 pocket utmean tai tan weveen ici paos tai ,
vtam D8d[, .)'jfN j Waterford Steam Electric Station Unit 3 o l5 lo g o g o l 3l g l,> nl 9 -
dd9 -
Ol0 012 Of 014 .
flKT s/ auswo apanse a recessesi, ease m #4C 7enn m W nh At 1326 hours0.0153 days <br />0.368 hours <br />0.00219 weeks <br />5.04543e-4 months <br /> on October 12, 1989 Waterford Steam Electric Station Unit 3 was in Mode 6, when an electrician and a Nucicar Auxiliary Operator (NAO) performed the preparatory lineup required by procedure ME-004-061, " Unit Auxiliary Transformer," for preventative maintenance on Unit Auxiliary Transformer (UAT) 3A (EIIS Identifier - XFMR). This procedure required the removal of the grounding Potential Transformer (PT) fuses (EIIS Identifier - FU) for UAT 3A in cubical 2 of the 4.16 KV Bus 3A2 switchgear (EIIS Identifier -
SWGR). The NA0 opened the grounding PT breaker (EIIS Identifier - BKR) then unlocked the drawer containing the grounding PT fuses. The electrician opened this drawer, removed the grounding PT fuses and then closed the drawer. The drawer above the grounding PT fuse drawer was marked "UV fuses". This drawer did not have either a lock or watning concerning opening the drawer. The electriciun did not know that these were the metering PT fuses for bus 3A2 and were not related to the UAT 3A grounding PT fuses. The electrician mistakenly unlatched the metering PT fuse drawer handle and opened the drawer. After a small amount of travel, the drawer electrical connection " fingers" were disconnected, deenergizing the bus voltage monitoring cirecit. Opening the drawer has the same effect as a loss of voltage on the 4.16 KV Bus 3A2 and ccused the feeder breaker and supply breaker to safety bus 3A3S from bus 3A?. to open and Diesel Generator A Load Sequencer to reset.
Upon hearing the operation of the feeder breaker, the NA0 directed the electrician to shut the metering PT fuse drawer. The NA0 then contacted the ,
control room to report the incident. All breakers were returned to the proper lineup by 1335 hours0.0155 days <br />0.371 hours <br />0.00221 weeks <br />5.079675e-4 months <br /> (event duration - nine minutes).
P 8d C FORM 394A 'L' S . CPU s 1 08 520-589 et.a ll'
M
=ac . . m. uo avettu ateve.voay et umio i
UCt!NSEE EVENT REPORT (LER) TEXT CONTINUATK)N m:ovin ove wo mo-om
, exeints: swee 9 ActLif v Isaae6 ett Ducatt teve. Dam tai St. NLuetta 406 t&OS (31 Wterford Steam
- m. "ew :":.n mi 0 Electric Station Unit 3
. < aw Aec s.,.maa mi 0 p l 0 l 0 l 0 l 3 lg l 2 gl 9 -
Ol1l 9 -
Ob 0l3 M 0l4 The root cause of this event was personnel error. The electrician mistakenly performed actions, opening the metering PT fuse drawer, not in the work package, lie did not know the difference between the metering and ground PT fuse drawers and did not know the offccts on the electrical distribution system of opening the drawers. Of larger consequence, he did not stop and get more information before prcceeding. A contributing cause was that the preparatory steps in procedure ME-004-061, " Unit Auxiliary Transf ormer," which called for removal of the UAT 3A grounding PT fuses were not required. These steps should not have been in the procedure. Additional contributing causes were: lack of a locking mechanism on the metering PT fuse drawer; imprecise labeling of the drawers, and no cautionary warnings on the drawer stating that opening the drawer could cause loss of voltage to safety bus 3A3S.
In response to the root cause, the electrician was counselled on proper conduct of maintenance ar.d proper action, in the event he does not understand a procedure step. Procedure compliance is being covered with maintenance personnel in individual counseling sessions to be completed by January 1, 1990.
In response to the contributing causes, procedure ME-004-061, " Unit Auxiliary Transformer" will be revised to remove steps not actually required. This will be completed by October 31, 1990. In addition, the metering and grounding PT fuse circuit drawers have been relabeled. Cautions have been added concerning opening of these drawers, l
l kdCFOmw3esa ep... m. 19sa g das N C a31
ne 5 . anna u s. =uctea o evaron, m.s io.
UCENSEE EVENT REPORT (LER) TEXT C3NTINUATION u*aove n owe wo. mo-oim
. tarines own f actitTv esaalt t3 09Catt 8#uMel 626 gga wuusta tai tADt tai Waterford Steam "'" '
"Delt' "'IAU Electric Station Unit 3 0 l6 l0 l0 l0 l3 l 8l2 8] 9 -
0l1l9 -
0l0 0 l4 0F 0l4 vent v . w =c == =v nn Because there was no loss of power to the operating shutdown cooling pump or other required safety related equipment, this event did not threaten the health and safety of the public or plant personnel.
SIMILAR EVENTS NONE PLANT CONTACT D.F. Packer. Assistant Plant Manager. Operations & Hafntenance. 504/464-3134.
NicPERW&#A ou,3, cPos 1909 520 689 00079
.,, . - . , - , - ~