in Response to 781201 Ltr,Forwards Suppl Implementation Schedule for Fire Protection Commitments Re Equipment Installation
ML19274D850
Person / Time
Site: Beaver Valley
Issue date: 02/21/1979
From: Dunn C
DUQUESNE LIGHT CO.
To: Schwencer A
Office of Nuclear Reactor Regulation
References
TAC-6405, NUDOCS 7902260456
Download: ML19274D850 (3)


Text

.

86,

'A@

Duquesne Ufit < m ,. ,, sco

.35 Sixth Avenue QHsburgh, Pennsylvania February 21, 1979 Director of Nuclear Reactor Regulation United States Nuclear Regulatory Commission Attention: A. Schwencer, Chief Branch No. 1 Division of Operating Reactors

' Washington, D. C. 20555

Reference:

Beaver Valley Power Station, Unit No. 1 Docket No. 50-334 Response to December 1, 1978 letter on Fire Protection Gentlemen:

Enclosed are four signed originals of a supplemental response to our letter of January 11, 1979 on Fire Protection Commitments.

The schedule for implemer.tation of equipment installation previously furnished to you excluded several items for which commitments were made in our prior response which addressed compliance with APCSB 9.5-1 Appendix A.

This supplemental response and schedule covers those items excluded in our January ll,1979 submittal.

Please note that this list excludes any commitments provided in the response to APCSB 9.5-1 Appendix A that were superseded by our January 11 s ubmi t tal.

Very truly yours ,

f }l [

C. N. Dunn u >u ~~

Vice President, Operations Enclosure cc: Messrs.: Ralph Paolino - NRC, Region I Robert Dodds - NRC, Region V Ingenar Asp - Gage, Babcock & Assoc., Inc.

7 9 0.2 2 6 0 e/25'le

SUPPLEMENTAL IMPLEMENTATION SCHEDULE BEAVER VALLEY POWER STATION - UNIT 1 Fire Protection Program Commitments AREA MODIFICATION SCHEDULE Cable Tunnel Add fire detection and rapid Oc t. 31, 1980 access hatchway.

Add CO2 fire extinguisher. April 30, 1979 Charging Pump Add smoke detectors in each Dec. 31, 1979 Cubicle charging pump cubicle.

Intake Struc- Add smoke detectors in Intake June 30, 1980 ture structure cubicles.

Control Room Add temporary smoke detectors. Oct. 31, 1979 BV-2 Misc. Areas Replace unlabled doors with UL Oct. 31, 1979 approved three hour fire rated doors.

Reactor Con- Add oil drip pans to Reactor Implementation tainment Coolant Pumps. during refuel-ing outage in 1981 or 1982 9

(CORPORATE SEAL)

Attest:

v[

l bC W H.W. Staas Secretary COMMONWEALTH OF PENNSYLVANIA'

) SS:

COUNTY OF ALLEGHENY )

On this 2/ day of /2~EBN s A 4 / , 1979, before me, DONALD W. SFAWNON , a Notary Public in and for said Common-wealth and County, personally appeared C. N. Dunn, who being duly sworn, deposed, and said that (1) he is Vice President of Duquesne Light, (2) he is duly authorized to execute and file the foregoing Submittal on behalf of said Company, and (3) the statements set forth in the Submittal are true and correct to the test of his knowledge, information and belief.

l /d ..-

DONALD W. SHANNON. Notary Puttic Pdtsburd. AHegbeny Co.. Pa.

J//Comtriseien Expires JJne 7,1379