Request for Extension of Construction Permit No. CPPR-93 Wppss Nuclear Project No. 2
ML18191A808
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 11/28/1976
From: Renberger D
Washington Public Power Supply System
To: Rusche B
Office of Nuclear Reactor Regulation
References
Download: ML18191A808 (8)


Text

NRC FORM 195 ~ U.S. NUCLEAR REGULATORY COMMISSION DOCKET NUM8ER I2-78I 50-397 FILE NUMSER NRC DISTRIBuTION FDR PART 50 DOCKET MATERIAL TO: B.C. RUSCHE FROM: WASHINGTON PUBLIC PWR SUPPLY DATE OF DOCUMENT SYSTEM 12/28/76 RICHLAND, WASHINGTON DATE RECEIVED D.L. RENBERGER ~, 1/5/77 OLETTER C3 NOTOR IZ 8 0 PROP INPUT FORM NUMSER OF. COPIES RECEIVED, ABORIGINAL E9 UN C LASS I F I E 0 OCOP Y ).

DESCRIPTION ENCLOSURE LTR. NOTARIZED 12/28/76...

LTR. REQUESTING EXTENSION OF AND INCLUDING DECEMBER1, 1981. 70R CONSTRUCTION PERMIT NO.

CPPR 93 ~ ~ ~ ~ ~ ~ ~

DONOT RZMOVR

( 1 SIGNED CY. RECEIVED)

( 3 PAGES)

ACKNOWLZDGZg PLANT NA1%: WPPS Sf/2 SAFETY FOR ACTION/INFORMATION or SAB 1 11 77 ASSXGNED AD:

NQH VARGA ROJECT lfANA E PROJECT MANAGER'XC LIC ASST SERVICE ASST INTERNAI DISTRIBUTION G FIL SYSTEMS SAFETY PLANT SYSTEMS SITE SAFE NRC PDR HEXtiEMAN TEDESCO I&E 2) SCHROEDER ENA 0 OELD GOSSICK & STAFF ENGINEERING XPPOLXTO MIPC HACARRY ERNST CASE KNXGHT BALLARD HANAUER SXHWEXL OPERATXNG REACTORS SPANGLER 1ARLESS PAWLICK STELLO SITE TECH PROJECT MANAGEMENT ACTOR SAFE OPERATXNG TECH GAl II IXLL BOYD ROSS EISENHUT STEPP PE COLLINS 1IULlfAN HOUSTON ROSZTOCZY PETERSON CHECK BVQ.E SXTE ANALYSIS I MELTZ VOLLlIER HELTEl IF.S AT& I BUNCH SKOVHOLT SALTZMAN J ~ COLLINS RUTBF.RG KREGER EXTERNAL OISTRII3UTION CONTROL NUMBER LPDR'D WASH NAT ~LAB WQMIAVEN~~AH TXC: REG V,I NSIC: 139 ASLB: CONS ULTANT ACRS CYS HeLBTHC/

t4Rc FDRM 188 (2.r8I

~ '

I\

j9 F ','I 1

';pl'~ / t(

L,4 I 4 \'

li )t e r-5 I

t ~ J W

pl/

~eZtl afory Washington Public Power Sugpjy+5ystern A JOINT OPERATING AGENCY CU P. O. BOX 968 3000 GL'O. A OTON WA ND, WASHINGTON 99352 PHONE(509) 946 16 l I ry O~a95I U

Docket No. 50-397 mber 28, 1976 0~ Qeh(

Mr. Benard C. Rus'che, Director Office of Nuclear Reactor Regula U. S. Nuclear Regulatory Commission Washington, D. C. 20555

Subject:

REQUEST FOR EXTENSION OF CONSTRUCTION PERMIT NO. CPPR-93 WPPSS NUCLEAR PROJECT NO. 2

Dear Mr. Rusche:

Washington Public Power Supply System (NWPPSSH) hereby requests that, pursuant to Section 185 of the Atomic Energy Act of 1954, as amended, and the Regulations of the Nuclear Regulatory Commission (10CFR Part 50),

the latest completion date for WPPSS Nuclear Project No. 2 (HWNP-2H),

currently specified in Construction Permit No. CPPR-93 as September 1, 1978, be extended to and including December 1, 1981.

At present, WNP-2 is approximately 36 percent complete. It is apparent that the facility cannot be completed by the date presently specified in the Construction Permit. Construction has not proceeded in accordance with the planned schedule due to several delaying factors beyond the control of WPPSS, principally a prolonged strike from June 1, 1976 to November 15, 1976 and an earlier strike of shorter duration. Other delaying factors included new NRC licensing requirements, poor labor productivity, increased project scope and complexity, additional and more stringent design criteria, and incorporation of modifications required as a result of operating experience at other plants. We believe that the foregoing constitutes good cause for the requested extension.

While our target date for completion is J~l, 1979, the December 1, 1981 latest completion date we are requesting for purposes of construction permit duration reflects a reasonable estimate of the time required plus a reasonable allowance for uncertainty, which is especially appropriate given the potential for further delays of the same nature as those noted above.

Since the requested extension of the completion dates involves no signif-icant hazards considerations not already evaluated and no undue risk to

0 0

~i N

1~

/

Jl

Mr. Renard C.'Rusche

'age 2 the health and safety of the public, it is respectfully requested that the Commission dispense with the notice and publication requirements as permited under Section 189(a) of the Atomic Energy Act of 1954.

Your prompt and favorable consideration of this request will be appreciated.

Very truly yours, D. L. RENBERGER Assistant Director Generation and Technology DLR:GCS:tm cc: Mr. D. Roe, Bonneville Power Administration

t e

4 4

4 j II 1

r P d r r

'L t A P 4 l I

r e* l l

P N

~ t

Letter from D..L'. Renberger to B. C. Rusche, "Request for Extension of Construction Permit No. CPPR-93 WPPSS Nuclear Project No. 2" STATE OF WASHINGTON )

) ss COUNTY OF BENTON )

D. L. RENBERGER, Being first duly sworn, deposes and says: That he is the Assistant Director, Generation and Technology, for the WASHINGTON PUBLIC POWER SUPPLY SYSTEM, the applicant herein; that he is authorized to submit the foregoing on behalf of said applicant; that he has read the foregoing and knows the contents thereof; and believes the same to be true to the best of his knowledge.

DATED 0 , l976 D. L. RENBERGER On this day personally appeared before me D. L. RENBERGER to me known to be the individual who executed the foregoing instrument and acknowledged that he signed the same as his free act and deed for the uses and purposes therein mentioned.