MONTHYEARML20217K9681999-10-19019 October 1999 Ack Receipt of Transmitting Rev 40 to Physical Security Plan for Washington Nuclear Plant 2.Based on Determination That Changes Do Not Decrease Effectiveness of Plan,No NRC Approval Required ML17284A8981999-10-14014 October 1999 Forwards Rev 0 to WNP-2 Cycle 15,COLR 99-15, IAW Requirements of TS 5.6.5 ML17284A9061999-09-24024 September 1999 Forwards Final Rept for 990812 out-of-sequence Drills for Energy Northwest Washington Nuclear Power Project 2 (Lab, Food Control Point & Milk Sampling).No Deficiences & No Areas Requiring C/A Identified in Three Drills ML17284A8881999-09-24024 September 1999 Informs NRC of Change in Schedule Pertaining to Final Implementation of Reactor Stability long-term Solution for WNP-2 ML17292B7591999-09-24024 September 1999 Forwards Rev 24 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b), 50.54(q) & 10CFR50 App E.Detailed Synopsis of Changes,Encl ML17292B7581999-09-22022 September 1999 Forwards NRC Forms 396 & 398 for Nl Hancock,License SOP-50027-3,AR Herrington,License OP-50013-3,WH Sawyer, License SOP-50023-3 & Dl Strote,License SOP-50031-3,for Renewal of Licenses.Without NRC Forms 396 & 398 ML17284A8811999-09-0909 September 1999 Forwards Response to NRC 990623 RAI to Support Review of Pending Request for Amend to Reactor pressure-temp Limit Curve TS GO2-99-168, Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3)1999-09-0808 September 1999 Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3) ML17284A8711999-08-30030 August 1999 Informs Staff of Errors in world-wide-web Database Related to WNP-2 Reactor Vessel Structural integrity.Marked-up Pages Containing Errors or Omissions Will Be Forwarded by 991201 ML17284A8751999-08-30030 August 1999 Provides Correct Page from License NPF-21 Marked to Show Rev Addressed in 990729 Application for Amend,Which Included Page That Was Inadvertently Included as Attachment 4.Replace Attachment 4 with Attached Page & Disregard Attachment 5 ML17284A8721999-08-30030 August 1999 Forwards Proprietary Info to Support Review of Request for Amend to License NPF-21,re Min Critical Power Ratio Safety Limits Tss,As Requested During 990816 Conversation. Proprietary Encl Withheld ML17292B7531999-08-24024 August 1999 Requests That Eleven Individuals Listed Below Take BWR Generic Fundamentals Examination to Be Administered on 991006 ML17292B7511999-08-24024 August 1999 Forwards Fitness for Duty (FFD) Semiannual Performance Data Rept for Jan-June 1999,per 10CFR26.71(d) ML17284A8701999-08-19019 August 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee & NRC Form 398, Personal Qualification Statement - Licensee, for Jd Prescott (License SOP-50262-1).Without Encls ML17292B7501999-08-19019 August 1999 Informs Staff That Licensee Has Completed Review of NRC SER for B&Wog Util Resolution Guidance Document Addressing ECCS Suction Strainer Blockage ML17284A8681999-08-12012 August 1999 Submits Two ISI Program Plan Relief Requests for NRC Review & Approval,Per 10CFR50.55a(a)(3)(i).Proposed Alternatives Provide Acceptable Level of Quality & Safety ML20211A9501999-08-12012 August 1999 Discusses 990720-21 Workshop Conducted in Region IV Ofc,Re Exchange of Info in Area of Use of Risk Insights in Regulatory Activities.List of Attendees,Summary of Topic & Issues,Agenda & Copies of Handouts Encl ML20210L1461999-08-0303 August 1999 Informs That NRC Plans to Administer Gfes of Written Operator Licensing Exam on 991006.Requests Submittal of Ltr Identifying Individuals Taking Exam,Personnel Allowed Access to Exams & Mailing Address for Exams ML17284A8541999-08-0202 August 1999 Forwards Proprietary Addl Info to Support Review of Pending Request for Amend to MCPR Safety Limit Ts.Info Consists of Proprietary Ltr from Abb Combustion Engineering,Inc.Encl Withheld ML17284A8531999-07-30030 July 1999 Forwards Estimate of Number of Licensing Action Requests Planned for Submittal in Future,As Requested in Administrative Ltr 99-02.Twenty-nine Submittals Scheduled for Fy 2000 & Four for Fy 2001 ML17284A8301999-07-22022 July 1999 Clarifies Change of Licensee Name from Wpps to Energy Northwest & Change of Facility Name from Wppss Nuclear Project Number 2 to WNP-2,as Requested in 990719 Telcon with Js Cushing of NRC.Marked-up OL Pages,Encl ML17292B7451999-07-20020 July 1999 Forwards Rev 23 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b) & 50.54(q) & 10CFR50 App E.Rev 23 Provides Updated Description Re Establishment of Separate Emergency Operation Centers for Benton & Franklin Counties ML17292B7391999-07-16016 July 1999 Submits Withdrawal of Request for Amend to Secondary Containment & Standby Gas Treatment Sys Ts.Util Currently Plan to re-submit Amend Request in Entirety by 991112 ML17292B7381999-07-12012 July 1999 Forwards NRC Form 396 & NRC Form 398,for If Sumsion,License OP-50487 & Ga Westergard,License SOP-50415 for Renewal of Operator Licenses.Without Encls ML17292B7171999-07-0606 July 1999 Provides Notification of Early Completion on 990630 of Exception Noted in 990629 Ltr.Equipment within Scope of GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants, Evaluated & Y2K Ready ML17292B7181999-07-0202 July 1999 Responds to 990623 RAI to Support Review of Evaluation of Planar Indication Found on Weld Number 24RRC(2)A-1 During 1998 RO ML17292B7161999-06-30030 June 1999 Forwards Addl Info Requested in 990513 Ltr to Support Review of Pending Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves. ML17292B7131999-06-29029 June 1999 Forwards Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. ML17292B7091999-06-21021 June 1999 Forwards Proprietary Response to NRC 990603 RAI Re Licensee Request for Amend to MCPR Safety Limit Tss.Proprietary Info Withheld IAW Requirements of 10CFR2.790 ML17292B7041999-06-17017 June 1999 Forwards NRC Forms 396 & 398 for Three Individuals Listed Below for Renewal of Operator Licenses.Without Encls ML17292B7031999-06-10010 June 1999 Forwards Response to NRC 990511 RAI Re License Request for Amend to Secondary Containment & SGTS Tss.Results of Addl Benchmark of Gothic Computer Code Performed to Demonstrate Modeling Capability of Drawdown Response,Encl ML17292B6841999-06-0404 June 1999 Forwards Response to NRC 990326 RAI Re WNP-2 GL 96-05 Program for Periodic Verification of design-basis Capability of MOVs ML17292B6851999-06-0101 June 1999 Forwards 1999 Quality Audit of WNP-2 Emergency Preparedness Program, Per NUREG-0654,Section Ii,Criteria P.9.Seven Problem Evaluation Requests & Nine Recommendations for Improvement Were Issued as Result of Audit Activities ML17292B6831999-05-25025 May 1999 Informs That Request for NRC Approval of Changes to Emergency Plan Requesting Reduction in on-shift HP Staffing, Is Retracted.Util Will Resubmit Request with Required Addl Info at Later Date ML17292B6751999-05-25025 May 1999 Forwards Proprietary ABB-CE Ltr Re WNP-2 Cycle 15 SLMCPR & Core Reload Design Rept,Per Util Request for Amend Re MCPR Safety Limits.Proprietary Info Withheld,Per 10CFR2.790 ML20206U4501999-05-19019 May 1999 Ack Receipt of Which Transmitted Rev 39 to Physical Security Plan,Per 10CFR50.54(p).No NRC Approval Is Required,Since Changes Do Not Decrease Effectiveness of Security Plan ML17292B6661999-05-0707 May 1999 Requests Exemption to Requirement in 10CFR55.59(a)(2) Re Annual Operating Test requirements.One-time Exemption from Requirement to Period Not to Exceed 15-months from Last Date of Passing Operating Exam for Licensee at Facility ML17292B6531999-05-0303 May 1999 Forwards Response to NRC 990402 RAI Re Licensed Operator Positive Drug Test.Encl Withheld,Per 10CFR2.790 ML17292B6561999-04-29029 April 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Safe End & Calculation Mod Record CMR-98-0243, Fracture Mechanics Evaluation of N1A Nozzle Safe End, as Suppl Info to ISI Exam ML17292B6421999-04-19019 April 1999 Responds to NRC 990319 Ltr Re Violations Noted in Insp Rept 50-397/99-01.Corrective Actions:Provisions Are Presently in Place to Maintain Adequate Level of Security GO2-99-073, Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.7901999-04-19019 April 1999 Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.790 ML17292B6401999-04-13013 April 1999 Requests That WNP-2 Operator Requalification Program Be Granted one-time Extension Beyond Requirement in 10CFR55.59(a)(2) for Annual Operating Tests ML17292B6371999-04-12012 April 1999 Forwards Response to NRC 990211 RAI Re Util Request for Amend to Secondary Containment & SBGTS TS ML17292B6281999-04-0606 April 1999 Informs NRC That Insp Interval Ending Date for ISI Program Plan Has Been Extended by One Year to Dec 12,2005 Due to Changes in Plant Refueling Outage Schedule ML20196K6961999-03-30030 March 1999 Ack Receipt of ,Transmitting Rev 38 to Physical Security Plan for Plant.No NRC Approval Is Required,In Accordance with 10CFR50.54(p) GO2-99-060, Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1)1999-03-26026 March 1999 Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1) ML17292B6131999-03-24024 March 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Nozzle Safe End. Info Will Be Used to Assist NRC in Review of WNP-2 ISI Activities Associated with Evaluation of Planar Indication ML20204F0261999-03-19019 March 1999 Forwards Insp Rept 50-397/99-01 on 990201-04 & 0303-05.No Violations Noted.Areas of Physical Security Plan Effectively Implemented with Listed Exceptions ML17292B6001999-03-16016 March 1999 Responds to Weakness Noted in Insp Rept 50-397/98-24. Corrective Actions:Developed Document to Identify Areas Needing Improvement,Assigned Responsibility for Actions & Provided Milestones for Achievement ML17292B5941999-03-16016 March 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee, & NRC Form 398, Personal Qualification Statement - Licensee, for MD Comstock,Mc Naulty & RR Nelson.Without Encls 1999-09-09
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML17284A8981999-10-14014 October 1999 Forwards Rev 0 to WNP-2 Cycle 15,COLR 99-15, IAW Requirements of TS 5.6.5 ML17284A9061999-09-24024 September 1999 Forwards Final Rept for 990812 out-of-sequence Drills for Energy Northwest Washington Nuclear Power Project 2 (Lab, Food Control Point & Milk Sampling).No Deficiences & No Areas Requiring C/A Identified in Three Drills ML17292B7591999-09-24024 September 1999 Forwards Rev 24 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b), 50.54(q) & 10CFR50 App E.Detailed Synopsis of Changes,Encl ML17284A8881999-09-24024 September 1999 Informs NRC of Change in Schedule Pertaining to Final Implementation of Reactor Stability long-term Solution for WNP-2 ML17292B7581999-09-22022 September 1999 Forwards NRC Forms 396 & 398 for Nl Hancock,License SOP-50027-3,AR Herrington,License OP-50013-3,WH Sawyer, License SOP-50023-3 & Dl Strote,License SOP-50031-3,for Renewal of Licenses.Without NRC Forms 396 & 398 ML17284A8811999-09-0909 September 1999 Forwards Response to NRC 990623 RAI to Support Review of Pending Request for Amend to Reactor pressure-temp Limit Curve TS GO2-99-168, Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3)1999-09-0808 September 1999 Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3) ML17284A8751999-08-30030 August 1999 Provides Correct Page from License NPF-21 Marked to Show Rev Addressed in 990729 Application for Amend,Which Included Page That Was Inadvertently Included as Attachment 4.Replace Attachment 4 with Attached Page & Disregard Attachment 5 ML17284A8721999-08-30030 August 1999 Forwards Proprietary Info to Support Review of Request for Amend to License NPF-21,re Min Critical Power Ratio Safety Limits Tss,As Requested During 990816 Conversation. Proprietary Encl Withheld ML17284A8711999-08-30030 August 1999 Informs Staff of Errors in world-wide-web Database Related to WNP-2 Reactor Vessel Structural integrity.Marked-up Pages Containing Errors or Omissions Will Be Forwarded by 991201 ML17292B7531999-08-24024 August 1999 Requests That Eleven Individuals Listed Below Take BWR Generic Fundamentals Examination to Be Administered on 991006 ML17292B7511999-08-24024 August 1999 Forwards Fitness for Duty (FFD) Semiannual Performance Data Rept for Jan-June 1999,per 10CFR26.71(d) ML17284A8701999-08-19019 August 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee & NRC Form 398, Personal Qualification Statement - Licensee, for Jd Prescott (License SOP-50262-1).Without Encls ML17292B7501999-08-19019 August 1999 Informs Staff That Licensee Has Completed Review of NRC SER for B&Wog Util Resolution Guidance Document Addressing ECCS Suction Strainer Blockage ML17284A8681999-08-12012 August 1999 Submits Two ISI Program Plan Relief Requests for NRC Review & Approval,Per 10CFR50.55a(a)(3)(i).Proposed Alternatives Provide Acceptable Level of Quality & Safety ML17284A8541999-08-0202 August 1999 Forwards Proprietary Addl Info to Support Review of Pending Request for Amend to MCPR Safety Limit Ts.Info Consists of Proprietary Ltr from Abb Combustion Engineering,Inc.Encl Withheld ML17284A8531999-07-30030 July 1999 Forwards Estimate of Number of Licensing Action Requests Planned for Submittal in Future,As Requested in Administrative Ltr 99-02.Twenty-nine Submittals Scheduled for Fy 2000 & Four for Fy 2001 ML17284A8301999-07-22022 July 1999 Clarifies Change of Licensee Name from Wpps to Energy Northwest & Change of Facility Name from Wppss Nuclear Project Number 2 to WNP-2,as Requested in 990719 Telcon with Js Cushing of NRC.Marked-up OL Pages,Encl ML17292B7451999-07-20020 July 1999 Forwards Rev 23 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b) & 50.54(q) & 10CFR50 App E.Rev 23 Provides Updated Description Re Establishment of Separate Emergency Operation Centers for Benton & Franklin Counties ML17292B7391999-07-16016 July 1999 Submits Withdrawal of Request for Amend to Secondary Containment & Standby Gas Treatment Sys Ts.Util Currently Plan to re-submit Amend Request in Entirety by 991112 ML17292B7381999-07-12012 July 1999 Forwards NRC Form 396 & NRC Form 398,for If Sumsion,License OP-50487 & Ga Westergard,License SOP-50415 for Renewal of Operator Licenses.Without Encls ML17292B7171999-07-0606 July 1999 Provides Notification of Early Completion on 990630 of Exception Noted in 990629 Ltr.Equipment within Scope of GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants, Evaluated & Y2K Ready ML17292B7181999-07-0202 July 1999 Responds to 990623 RAI to Support Review of Evaluation of Planar Indication Found on Weld Number 24RRC(2)A-1 During 1998 RO ML17292B7161999-06-30030 June 1999 Forwards Addl Info Requested in 990513 Ltr to Support Review of Pending Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves. ML17292B7131999-06-29029 June 1999 Forwards Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps. ML17292B7091999-06-21021 June 1999 Forwards Proprietary Response to NRC 990603 RAI Re Licensee Request for Amend to MCPR Safety Limit Tss.Proprietary Info Withheld IAW Requirements of 10CFR2.790 ML17292B7041999-06-17017 June 1999 Forwards NRC Forms 396 & 398 for Three Individuals Listed Below for Renewal of Operator Licenses.Without Encls ML17292B7031999-06-10010 June 1999 Forwards Response to NRC 990511 RAI Re License Request for Amend to Secondary Containment & SGTS Tss.Results of Addl Benchmark of Gothic Computer Code Performed to Demonstrate Modeling Capability of Drawdown Response,Encl ML17292B6841999-06-0404 June 1999 Forwards Response to NRC 990326 RAI Re WNP-2 GL 96-05 Program for Periodic Verification of design-basis Capability of MOVs ML17292B6851999-06-0101 June 1999 Forwards 1999 Quality Audit of WNP-2 Emergency Preparedness Program, Per NUREG-0654,Section Ii,Criteria P.9.Seven Problem Evaluation Requests & Nine Recommendations for Improvement Were Issued as Result of Audit Activities ML17292B6751999-05-25025 May 1999 Forwards Proprietary ABB-CE Ltr Re WNP-2 Cycle 15 SLMCPR & Core Reload Design Rept,Per Util Request for Amend Re MCPR Safety Limits.Proprietary Info Withheld,Per 10CFR2.790 ML17292B6831999-05-25025 May 1999 Informs That Request for NRC Approval of Changes to Emergency Plan Requesting Reduction in on-shift HP Staffing, Is Retracted.Util Will Resubmit Request with Required Addl Info at Later Date ML17292B6661999-05-0707 May 1999 Requests Exemption to Requirement in 10CFR55.59(a)(2) Re Annual Operating Test requirements.One-time Exemption from Requirement to Period Not to Exceed 15-months from Last Date of Passing Operating Exam for Licensee at Facility ML17292B6531999-05-0303 May 1999 Forwards Response to NRC 990402 RAI Re Licensed Operator Positive Drug Test.Encl Withheld,Per 10CFR2.790 ML17292B6561999-04-29029 April 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Safe End & Calculation Mod Record CMR-98-0243, Fracture Mechanics Evaluation of N1A Nozzle Safe End, as Suppl Info to ISI Exam ML17292B6421999-04-19019 April 1999 Responds to NRC 990319 Ltr Re Violations Noted in Insp Rept 50-397/99-01.Corrective Actions:Provisions Are Presently in Place to Maintain Adequate Level of Security GO2-99-073, Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.7901999-04-19019 April 1999 Forwards Rev 39 to WNP-2 Physical Security Plan,Per 10CFR50.54(p).Changes Do Not Decrease Effectiveness of Approved Plan.Encl Withheld IAW 10CFR73.21 & 10CFR2.790 ML17292B6401999-04-13013 April 1999 Requests That WNP-2 Operator Requalification Program Be Granted one-time Extension Beyond Requirement in 10CFR55.59(a)(2) for Annual Operating Tests ML17292B6371999-04-12012 April 1999 Forwards Response to NRC 990211 RAI Re Util Request for Amend to Secondary Containment & SBGTS TS ML17292B6281999-04-0606 April 1999 Informs NRC That Insp Interval Ending Date for ISI Program Plan Has Been Extended by One Year to Dec 12,2005 Due to Changes in Plant Refueling Outage Schedule GO2-99-060, Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1)1999-03-26026 March 1999 Submits Rept of Status of WNP-2 Decommissioning Fund as of 981231,IAW 10CFR50.75(f)(1) ML17292B6131999-03-24024 March 1999 Forwards Rev 0 to Calculation ME-02-98-04, Fracture Mechanics Evaluation of N1 Nozzle Safe End. Info Will Be Used to Assist NRC in Review of WNP-2 ISI Activities Associated with Evaluation of Planar Indication ML17292B5991999-03-16016 March 1999 Informs That Listed Property & Liability Insurance Coverage for WNP-2 Is in Force,In Compliance with Licensing Responsibilities Delineated in 10CFR50.54(w)(3) ML17292B5911999-03-16016 March 1999 Forwards 1998 Environ Operating Rept, Per Reporting Requirements of Section 5.4.1 of WNP-2 Epp.No Design or Operational Changes or Tests in 1998 Involved Unreviewed Environ Question ML17292B5941999-03-16016 March 1999 Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee, & NRC Form 398, Personal Qualification Statement - Licensee, for MD Comstock,Mc Naulty & RR Nelson.Without Encls ML17292B6001999-03-16016 March 1999 Responds to Weakness Noted in Insp Rept 50-397/98-24. Corrective Actions:Developed Document to Identify Areas Needing Improvement,Assigned Responsibility for Actions & Provided Milestones for Achievement ML17292B5901999-03-11011 March 1999 Forwards Hard Copy of Addl Occupational Exposure Data Requested in GL 94-04,per 990303 e-mail.Original Electronic Version Was Corrupted ML17292B5681999-03-0101 March 1999 Forwards Radioactive Effluent Release Rept for 1998, IAW 10CFR50.36a(a)(2) & TS 5.6.3 & Complete Copy of WNP-2 ODCM Per TS 5.5.1 ML17292B5651999-02-22022 February 1999 Forwards Relief Request 2ISI-20,proposing Alternate Exam Expected to Reduce Dose Significantly & Still Provide Adequate Safety & Quality.Attached Relief Request Will Be Used to Support ALARA Dose Reduction Efforts During Maint ML17292B5581999-02-0404 February 1999 Requests Change to Co Which Modified WNP-2 OL to Reflect Schedule for Implementing Thermo-Lag 330-1 Fire Barrier C/As.Change Requested to Reflect That Final Implementation of C/As Will Be Completed During Fall 1999 Not Spring 1999 1999-09-09
[Table view] |
Text
PRIDRI EY (ACCELERATED RIDS PROCI;SSIXG REGULATORY INFORMATION DISTRIBUTXON SYSTEM (RXDS)
ACCESSION NBR:.9412220098 DOC.DATE: 94/12/09 NOTARIZED: NO DOCKET FACIL:50-.39/ WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH. NAME AUTHOR AFFILIATION PARRISH,J.V. Washington Public Power Supply System RECIP.NAME RECXPIENT AFFXLIATXON P Document Control Branch (Document Control Desk)
SUBJECT:
Informs that GL 89-10 6 suppls outline recommendations for R
testing 6 evaluating MOVs.
DISTRIBUTION CODE: A064D COPIES RECEIVED:LTR J ENCL ~ SIZE:
I TITLE: Response to Generic Ltr 89-10, "Safety-Related MOV Testing 6 Surveill NOTES:
RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD4-2 PD CLIFFORD,J INTERNAL: ACRS AEOD/SPD/RAB
~"LEi CENT-ER~ 1 NRR/DE/EMEB ERR/IDIS P/I PXPB NRR/DOPS/OECB NRR/PD111-3 RES/DSIR Y RES/DSIR/EIB/B EXTERNAL'OAC NRC PDR p
0',
C U
N NOTE TO ALL"RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE iVASTE! CONTACT'I'IIE DOC! 'Nf EYT CONTROL DESK, ROOhf Pl-37 IEXT. 504-20S3 ) TO ELIXIINATEYOUR XAifE PROil DISTR(DU'I'IOY, LISTS I:OR DOCL'z IEY.'I'S YOI.'Oi'"I'I.:ID!
', TOTAL NUMBER OF COPIES REQUIRED: LTTR 13 ENCL
r 1"
I
)
I
WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968 ~ 3000 Geotge Washington Way ~ Richland, Washington 993S2-0968 ~ (509) 372-SOOO December 9, 1994 G02-94-275 Docket No. 50-397 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 Gentlemen:
Subject:
WNP-2, OPERATING LICENSE NPF-21 GENERIC LETTER 89-10 AND SUPPLEMENTS
Reference:
Letter GO2-93-217, dated August 31, 1993, JV Parrish (SS) to NRC, same subject Generic Letter (GL) 89-10 and its supplements outline the recommendations for testing and evaluating motor operated valves (MOVs), In the referenced letter, the Supply System committed to complete testing of the remaining GL 89-10 Program MOVs listed in Table 2 of the letter during the Spring 1995 (R-10) Maintenance and Refueling Outage. Included in the Table were 16 Main Steam Isolation Valve Leakage Control System (MSLC) valves, which had previously been baseline tested, but were scheduled to be retested using revised setpoints and a different testing methodology. Three of the valves have been retested, and the 13 remaining valves were to be retested during the R-10 outage.
Subsequent to submittal of the referenced letter, the Supply System decided to pursue a design change, similar to that implemented at Hatch 1 and 2, which will functionally deactivate the MSLC system. Subject to Technical Specification amendment submittal and NRC approval, the design change is planned for implementation during the Spring 1996 (R-11) Maintenance and Refueling Outage. As a result, the 13 MSLC MOVs scheduled to be retested during the R-10 outage are to be functionally deleted during the R-11 outage.
// /
94i2220098 94i209 PDR ADOCK 05000397 P PDR
'll
~ ~
II I' II t~ II V
0
- jP Page 2 GENERIC-LETTER 89-10 AND SUPPLEMENTS V
It has been estimated that the Supply System would benefit from a one time savings of approximately $ 103,000 in refurbishment, engineering, and testing costs by not retesting the 13 MSLC MOVs during the R-10 outage. In addition, based on previous experience, not having to retest the valves could significantly reduce personnel radiation exposure and unplanned impacts on critical path outage work. Moreover, the Supply System can focus its resources on issues that are more beneficial to plant safety and reliability in the longer term. For the foregoing reasons, the Supply System does not intend to retest the remaining 13 MSLC MOVs from Table 2 of the referenced letter during the R-10 outage. However, normal MOV maintenance and inspections will continue to be performed. In the event that the MSLC system design change is not implemented as planned, the valves willbe retested during the R-11 outage.
In other words, retesting of the 13 MSLC MOVs will be essentially postponed by at most one year, at which time they will be either functionally deactivated or retested. This information is provided as an update to the WNP-2 MOV program status.
The Supply System has evaluated the effects of the postponement of retesting on the 13 MSLC MOVs involved and determined that there will be no impact on valve operability or functional reliability. The following discussion is provided in support of this conclusion.
The 16 MSLC MOVs listed in Table 2 of the referenced letter have been baseline tested in accordance with GL 89-10 guidance (circa 1992) using the ITI-MOVATS thrust measuring device (TMD) methodology. Subsequently, ITI-MOVATS (pursuant to 10 CFR 21.21(b)) and NRC Information Notice 92-23 notified the industry of concerns relating to the accuracy of the TMD methodology for MOV close stroke stem thrust measurements. The Supply System responded by re-evaluating the baseline test results for each MOV, including the MSLC MOVs, in accordance with the latest industry standards. In addition, the Supply System elected to reperform the baseline tests on the GL 89-10 Program MOVs where the TMD methodology had been used, regardless of the evaluation results. The retesting schedule was based on acceptability of the evaluations and the importance of the valve. Because of the generally acceptable evaluation results, 13 of the 16 MSLC MOVs listed in Table 2 of the Reference letter were scheduled for retesting during the R-10 outage, just prior to GL 89-10 Program close-out.
Because the accuracy of the TMD methodology is a concern for close stroke stem thrust measurements, the 16 MSLC MOVs listed in Table 2 of the Reference letter were evaluated for safety function and operability. Based on the evaluation, only four of the valves have a close safety function. As previously mentioned, three of the 16 MSLC MOVs have already been retested, and one of the four MOVs identified as having a close safety function was included in the valves that were retested. Since the retests incorporated the currently acceptable torque thrust cell and stem mounted strain gage methodologies for stem thrust measurement, only three MSLC MOVs have minimum required thrust baseline test data that could be affected by the measurement accuracy of the TMD methodology. The measured thrust data for the three MOVs were compared to the setpoint, which uses conservative assumptions for Rate of Loading, Stem Factor Degradation, and Valve Factor. In each case, sufficient thrust margin exists to assure
~ ~
>q")f>)~< fly>>I>Ir> 4>>>p>>'4 jap+,~t~>>" <- tp>g'> <<>>,'4 gggr>>~<ij(~f> j'~ -t>jgtf)> )tying f>;~>, jk~ef>jj )plfg >rq'.>~ >so>,ff}
,'yftf <>;lfr,'..lPy',:v" p >I>,'>4 '->'j',r'fQ imp >'y fi)0 fp J 'i.f> l))ff)y) Q.'>)KJ>> J)>>851 ) >4') f>I >VOV ~f " '~4 af)>
ffl!JP'I: y!"'- '<<ft ~5*'PV: > At .>y.'f'%~9. >'.)'!)~J.'!f ')'>>'. flf~zfr. l)')Blf "N; Al>>)8 >)I: > I >') O'>':SUt'> "
4'4-' >'>4 rNI f ";>>I~ y-f II Ift ~)4..4 > "y > rw>f > Ir > r ~
>j N>t>f ~ I lI >II
~ >f ~ p,f >f " ill r>~ '
' >g" 4>.
(4 4'IlI 4, >4" 4 ~ yy >I C>'
4 4
I 4 4 .,r ~ >fl Iy> 4>4 ff>> Ily 4
~ 4, ~ ~ r
~,
"f > 4 > ' t')>4> >i~
I Jyr f>> ~ 4<<y> ~ '->> >X A I )l">y>. >>'4 >fy ".1
>r~}F~ "> ~, 4r4 Jl>f.I."*f '...."~":e
>4 '4>
y,l y V 4
I'4
~ > 4>>4 ~
~
Il.", f fr >'>4)2 ~ I'8 '4
Page 3 GENERIG LETTER 89-10 AND SUPPLEMENTS operability and functional reliability. Additionally, the thrust values and torque switch settings for the 13 MOVs to be retested were compared to those of the three MOVs retested using the torque thrust cell and stem mounted strain gage methodologies. In every case, the maximum measured thrust/torque values were below the design limits of the retested MOVs, and the torque switch settings were below the maximum allowed settings. Furthermore, since all 16 of the MSLC MOVs are limit open, the valves are not backseated and the open thrust design limits are not a concern.
The MSLC MOVs were identified as Graded Approach MOVs in the referenced letter. The MOVs classified as Graded Approach are considered to have conditions which do not require differential pressure testing to verify open/close capability. The criteria is applied to MOVs that are expected to have low maximum differential pressures, and a differential load less than the estimated packing load. Therefore, the effect of the differential pressure on the MOV is small and not significantly greater than static conditions.
Since the measured thrust values for the 16 MSLC MOVs listed in Table 2 of the referenced letter were found to provide sufficient thrust margin using the TMD methodology, further baseline retesting was not required. The Supply System had elected to reperform the baseline tests solely in an effort to update the test data to the latest industry standards prior to GL 89-10 Program close-out. There was no safety significance associated with the decision. Hence, the one year postponement of retesting willhave no impact on the operability or functional reliability of the 13 MSLC MOVs that remain to be retested.
Should you have any questions or desire additional information regarding this matter, please call me or D.A. Swank at (509) 377-4563.
Sincerely,
. V. Parrish (Mail Drop 1023)
Assistant Managing Director, Operations CD M/ml cc: LJ Callan - NRC RIV KE Perkins, Jr. - NRC RIV, Walnut Creek Field Office NS Reynolds - Winston & Strawn JW Clifford - NRC DL Williams - BPA/399 NRC Sr. Resident Inspector - 927N