ML12091A049

From kanterella
Jump to navigation Jump to search
NRC Staff Pre-Filed Hearing Exhibit NRC000107, Indian Point Nuclear Generating Units 2 and 3 - NRC License Renewal Inspection Report 05000247/2008006 & 05000286/2008006
ML12091A049
Person / Time
Site: Indian Point  Entergy icon.png
Issue date: 03/31/2012
From: Conte R
Engineering Region 1 Branch 1
To: Joseph E Pollock
Entergy Nuclear Operations, Atomic Safety and Licensing Board Panel
SECY RAS
Shared Package
ML12091A044 List:
References
RAS 22176, 50-247-LR, 50-286-LR, ASLBP 07-858-03-LR-BD01 IR-08-006
Download: ML12091A049 (43)


See also: IR 05000247/2008006

Text

NRC000107

Submitted: March 31, 2012

August 1, 2008

Mr. Joseph Pollock

Site Vice President

Entergy Nuclear Operations, Inc.

Indian Point Energy Center

450 Broadway, GSB

P.O. Box 249

Buchanan, NY 10511-0249

SUBJECT: INDIAN POINT NUCLEAR GENERATING UNITS 2 AND 3 - NRC LICENSE

RENEWAL INSPECTION REPORT 05000247/2008006 & 05000286/2008006

Dear Mr. Pollock:

On February 14, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed the major

onsite portion of the Region I team inspection of your application for license renewal of your

Indian Point Nuclear Generating Unit Nos. 2 and 3, with additional followup inspections through

June 6, 2008. The enclosed report documents the results of the inspection, which were

discussed on June 18, 2008, with you, Fred Dacimo, and members of your staff in an exit

meeting open for public observation in Cortlandt Manor, NY.

The purpose of this inspection was to examine, on a sampling basis, the plant activities and

documents that support the application for a renewed license of the Indian Point Nuclear

Generating Unit Nos. 2 and 3. The inspection team reviewed the scoping of nonsafety-related

systems, structures, and components, as required in 10 CFR 54.4(a)(2). Further, the team

determined whether the proposed aging management programs are capable of reasonably

managing the effects of aging. These NRC inspection activities constitute one of several inputs

into the NRC review process for license renewal applications.

The team concluded that the scoping of nonsafety-related systems, structures, and components

was implemented as required in 10 CFR 54.4(a)(2). Further, the team concluded that the aging

management portion of the license renewal activities was conducted as described in the

License Renewal Application. The team concluded that the documentation supporting the

application was in an auditable and retrievable form. The team identified a number of areas that

resulted in changes to the application.

Overall, the inspection results support a conclusion of reasonable assurance that actions have

been identified and have been taken or will be taken to manage the effects of aging in the

systems, structures, and components identified in your application and that the intended

functions of these systems, structures, and components will be maintained in the period of

extended operation.

J. Pollock 2

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC=s document system

(ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Richard J. Conte, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-247 and 50-286

License Nos. DPR-26 and DPR-64

Enclosure: Inspection Report 05000247/2008006 and 05000286/2008006

J. Pollock 2

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRC=s document system

(ADAMS). ADAMS is accessible from the NRC Website at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Richard J. Conte, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-247 and 50-286

License Nos. DPR-26 and DPR-64

Enclosure: Inspection Report 05000247/2008006 and 05000286/2008006

SUNSI Review Complete: RJC (Reviewer=s Initials) ADAMS ACCESSION NO. ML082140149

DOCUMENT NAME: G:\DRS\Engineering Branch 1\Meyer\Indian Pt Insp Report\IP LR report FINAL -July 31-2008.doc

After declaring this document AAn Official Agency Record@ it will be released to the Public.

To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosu

"N" = No copy

OFFICE RI/DRS RI/DRS RI/DRP RI/DRS

NAME GWMeyer/cmm/RJC RJConte/RJC* MGray/MG* MKGamberoni/DJR

for* for

DATE 07/22/08 07/31/08 07/25/08 08/01/08

OFFICIAL RECORD COPY

  • See Previous Concurrence Page

J. Pollock 3

cc w/encl:

Senior Vice President, Entergy Nuclear Operations

Vice President, Operations, Entergy Nuclear Operations

Vice President, Oversight, Entergy Nuclear Operations

Senior Manager, Nuclear Safety and Licensing, Entergy Nuclear Operations

Senior Vice President and COO, Entergy Nuclear Operations

Assistant General Counsel, Entergy Nuclear Operations

Manager, Licensing, Entergy Nuclear Operations

P. Tonko, President and CEO, New York State Energy Research and Development Authority

C. Donaldson, Esquire, Assistant Attorney General, New York Department of Law

A. Donahue, Mayor, Village of Buchanan

J. G. Testa, Mayor, City of Peekskill

R. Albanese, Four County Coordinator

S. Lousteau, Treasury Department, Entergy Services, Inc.

Chairman, Standing Committee on Energy, NYS Assembly

Chairman, Standing Committee on Environmental Conservation, NYS Assembly

Chairman, Committee on Corporations, Authorities, and Commissions

M. Slobodien, Director, Emergency Planning

P. Eddy, NYS Department of Public Service

Assemblywoman Sandra Galef, NYS Assembly

T. Seckerson, County Clerk, Westchester County Board of Legislators

A. Spano, Westchester County Executive

R. Bondi, Putnam County Executive

C. Vanderhoef, Rockland County Executive

E. A. Diana, Orange County Executive

T. Judson, Central NY Citizens Awareness Network

M. Elie, Citizens Awareness Network

D. Lochbaum, Nuclear Safety Engineer, Union of Concerned Scientists

Public Citizen's Critical Mass Energy Project

M. Mariotte, Nuclear Information & Resources Service

F. Zalcman, Pace Law School, Energy Project

L. Puglisi, Supervisor, Town of Cortlandt

Congressman John Hall

Congresswoman Nita Lowey

Senator Hillary Rodham Clinton

Senator Charles Schumer

G. Shapiro, Senator Clinton's Staff

J. Riccio, Greenpeace

P. Musegaas, Riverkeeper, Inc.

M. Kaplowitz, Chairman of County Environment & Health Committee

A. Reynolds, Environmental Advocates

D. Katz, Executive Director, Citizens Awareness Network

K. Coplan, Pace Environmental Litigation Clinic

M. Jacobs, IPSEC

W. Little, Associate Attorney, NYSDEC

M. J. Greene, Clearwater, Inc.

R. Christman, Manager Training and Development

J. Spath, New York State Energy Research, SLO Designee

A. J. Kremer, New York Affordable Reliable Electricity Alliance (NY AREA)

J. Pollock 4

Distribution w/encl: (VIA E-MAIL)

S. Collins, RA

M. Dapas, DRA

S. Williams, RI OEDO

R. Nelson, NRR

M. Kowal, NRR

J. Boska, PM, NRR

J. Hughey, NRR

M. Gray, DRP

B. Bickett, DRP

T. Wingfield, DRP

G. Malone, SRI - Indian Point 2

P. Cataldo, SRI - Indian Point 3

C. Hott, RI - Indian Point 2

T. Koonce, RI - Indian Point 3

Region I Docket Room (w/concurrences)

ROPreport Resources

M. Gamberoni, DRS

D. Roberts, DRS

R. Conte, DRS

G. Meyer, DRS

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

Docket Nos: 50-247, 50-286

License Nos: DPR-26, DPR-64

Report Nos: 05000247/2008006 and 05000286/2008006

Licensee: Entergy Nuclear Operations, Inc (Entergy)

Facility: Indian Point Nuclear Generating Unit Nos. 2 and 3

Location: 450 Broadway, GSB

Buchanan, NY 10511-0249

Dates: January 28 - February 1, 2008

February 11 - 14, 2008

March 31 - April 2, 2008

June 2 - 6, 2008, and June 18, 2008

Inspectors: G. Meyer, Team Leader, Division of Reactor Safety (DRS)

M. Modes, Sr. Reactor Inspector, DRS

J. Richmond, Sr. Reactor Inspector, DRS

S. Chaudhary, Reactor Inspector, DRS

H. Jones, Reactor Inspector, DRS

B. Jose, Reactor Inspector, DRS, Region III

J. Lilliendahl, Reactor Inspector, DRS

D. Tifft, Reactor Inspector, DRS

H. Gray, Sr. Reactor Inspector, DRS

Accompanied by: B. Pham, NRR

Approved By: Richard J. Conte, Chief

Engineering Branch 1

Division of Reactor Safety

SUMMARY OF FINDINGS

05000247/2008006 and 05000286/2008006; January 28 - June 18, 2008; Indian Point

Nuclear Generating Unit Nos. 2 and 3; Scoping of Non-Safety Systems and the

Proposed Aging Management Programs for the Indian Point Application for Renewed

License.

This inspection of license renewal activities was performed by nine regional office

inspectors. The inspection was performed in accordance with NRC Manual Chapter 2516 and NRC Inspection Procedure 71002. This inspection did not identify any findings

as defined in NRC Manual Chapter 0612. The inspection team concluded scoping of

nonsafety-related systems, structures, and components was implemented as required in

10 CFR 54.4(a)(2). Further, the team concluded the aging management program

portions of the license renewal activities were conducted as described in the License

Renewal Application. The team concluded the documentation supporting the application

was in an auditable and retrievable form. The team identified a number of areas that

resulted in changes to the application.

Overall, the inspection results support a conclusion of reasonable assurance that actions

have been identified and have been taken or will be taken to manage the effects of aging

in the systems, structures, and components identified in your application and that the

intended functions of these systems, structures, and components will be maintained in

the period of extended operation.

ii

.

TABLE OF CONTENTS

Page

SUMMARY OF FINDINGS...ii

TABLE OF CONTENTS...iii

4. OTHER ACTIVITIES (OA).1

4OA2 Other - License Renewal1

a. Inspection Scope (IP 71002)...1

b.1 Scoping of Nonsafety-Related Systems, Structures,

and Components...1

b.2 Aging Management Programs.3

Containment Inservice Inspection Program...3

Fatigue Monitoring Program.4

Fire Protection Program4

Fire Water System Program.5

Nickel Alloy Inspection Program..5

One-Time Inspection Small Bore Piping Program6

Steam Generator Integrity Program7

Non-Environmentally Qualified Inaccessible Medium-Voltage

Cable Program...8

Environmental Qualification of Electric Components Program......8

Aboveground Steel Tanks Program9

Metal-Enclosed Bus Inspection Program...9

Non-EQ Bolted Cable Connections Program..10

Non-EQ Instrumentation Circuits Test Review Program...11

Non-EQ Insulated Cables and Connections Program...11

Buried Piping and Tanks Inspection Program.12

Service Water Integrity Program...13

Heat Exchanger Monitoring Program...13

Water Chemistry Control-Closed Cooling Water Program14

Diesel Fuel Monitoring Program15

Boric Acid Corrosion Prevention Program...16

External Surfaces Monitoring Program16

Flow-Accelerated Corrosion Program..17

Reactor Vessel Head Penetration Inspection Program.17

One-Time Inspection Program..18

Selective Leaching Program..18

Bolting Integrity Program19

Structural Monitoring Program..19

Masonry Wall Program...20

b.3 System Review.21

Auxiliary Feedwater System Review21

Unit 2 Station Blackout/Appendix-R Diesel Generator

(SBO/App-R DG) System Review...22

c. Overall Conclusions22

4OA6 Meetings, including Exit23

ATTACHMENT: SUPPLEMENTAL INFORMATION..A-1

iii

Report Details

4. OTHER ACTIVITIES (OA)

4OA2 Other - License Renewal

a. Inspection Scope (IP 71002)

This inspection was performed by NRC regional inspectors to evaluate the thoroughness

and accuracy of the scoping of nonsafety-related systems, structures, and components,

as required in 10 CFR 54.4(a)(2) and to evaluate whether aging management programs

will be capable of managing identified aging effects in an appropriate manner.

The inspectors selected a number of systems, components, and structures for review to

determine if the methodology applied by Entergy appropriately addressed the non-safety

systems affecting the safety functions of a system, structure, or component within the

scope of license renewal.

The inspectors selected a sample of aging management programs to verify the

adequacy of Entergy guidance, implementation activities, and documentation. The

selected aging management programs were reviewed to determine whether the

proposed aging management implementing processes would adequately manage the

effects of aging.

The inspectors reviewed supporting documentation and interviewed Entergy personnel

to confirm the accuracy of the license renewal application conclusions. For a sample of

plant systems and structures, the inspectors performed visual examinations of

accessible portions of the systems to observe aging effects.

b.1. Scoping of Nonsafety-Related Systems, Structures, and Components

For scoping, the inspectors reviewed Entergy program guidance procedures and

summaries of scoping results for Indian Point to assess the thoroughness and accuracy

of the methods used to bring systems, structures, and components within the scope of

license renewal into the application, including nonsafety-related systems, structures, and

components, as required in 10 CFR 54.4 (a)(2). The inspectors determined Entergy

procedures to be consistent with the NRC-accepted guidance in Sections 3, 4, and 5 of

Appendix F to NEI 95-10, Industry Guideline For Implementing The Requirements of

10 CFR Part 54 - The License Renewal Rule, Revision 6 (3: nonsafety-related systems,

structures, and components within scope of the current licensing basis, 4: nonsafety-

related systems, structures, and components directly connected to safety-related

systems, structures, and components, and 5: nonsafety-related systems, structures, and

components not directly connected to safety-related systems, structures, and

components).

The inspectors reviewed the set of license renewal drawings, which had been color-

coded to indicate systems and components in scope for 10 CFR 54.4 (a)(1), in order to

evaluate the effects of (a)(2) systems on the (a)(1) systems, structures, and

2

components. The inspectors interviewed personnel, reviewed license renewal program

documents, and independently inspected numerous areas within Units 1, 2, and 3 to

confirm that appropriate systems, structures, and components had been included within

the license renewal scope, that systems, structures, and components excluded from the

license renewal scope had an acceptable basis, and that the boundary for determining

license renewal scope within the systems, including seismic supports and anchors, was

appropriate.

The in-plant areas and systems reviewed included the following:

$ Units 1, 2 & 3 Turbine Buildings*

$ Unit 1 Nuclear Service Building*

$ Unit 1 Fuel Handling Building*

$ Unit 1 Chemical Systems Building*

$ Unit 2 Primary Auxiliary Building

$ Unit 2 Fuel Storage Building

$ Unit 2 Reactor Building

$ Unit 2 & 3 Control Buildings

$ Units 2 & 3 Intake Structures

$ Units 2 & 3 Security Generators

$ Units 2 & 3 Diesel Generator Rooms

$ Unit 3 Auxiliary Feedwater Pump Room

$ Unit 3 480 V Switchgear Room

$ Unit 3 Cable Spreading Room

$ Unit 2 Station Blackout Diesel Generator

$ Unit 3 Instrument Air System

$ Units 2 & 3 Service Water Systems

and systems are addressed due to the potential effect on Units 2 and 3.

For systems, structures, and components selected regarding spatial interaction (failure

of nonsafety-related components adversely affecting adjacent safety-related

components), the inspectors determined that the in-plant configuration had been

accurately and acceptably categorized within the license renewal program documents.

The inspectors determined the personnel involved in the process were knowledgeable

and appropriately trained.

For systems, structures, and components selected regarding structural interaction

(seismic design of safety-related components dependent upon nonsafety-related

components), the inspectors determined that structural boundaries had been accurately

determined and categorized within the license renewal program documents. The

inspectors determined that Entergy had reviewed applicable isometric drawings to

determine the seismic design boundaries and had correctly included the applicable

components in the license renewal application, based on the inspectors= independent

review of a sample of the isometric drawings and the seismic boundary determinations.

3

In summary, the inspectors concluded that Entergy had implemented an acceptable

method of scoping of nonsafety-related systems, structures, and components and that

this method resulted in accurate scoping determinations.

b.2. Aging Management Programs

Containment Inservice Inspection Program

The Containment Inservice Inspection program is an existing program that manages the

aging affects on the containment, which is a reinforced concrete structure without post

tensioning. In the application, Entergy takes exception to NUREG 1801, Revision 1,

because containment seals and gaskets are in the Containment Leak Rate Program and

not in the Containment Inservice Inspection program. This conforms with the American

Society of Mechanical Engineers (ASME) Code applicable to Indian Point, which is an

edition later than that referenced in NUREG 1801, Revision 1.

The program specifies that all accessible surfaces receive a visual examination. The

procedure for visual containment inspection also requires that inaccessible areas

requiring inspection be separately identified. Painted surfaces are examined for

evidence of flaking, blistering, peeling, discoloration, and other signs of distress. Non-

coated areas are examined for evidence of cracking, discoloration, wear, pitting,

excessive corrosion, gouges, surface discontinuities, dents and other signs of surface

irregularities.

The inspectors reviewed the evaluation of concrete visual indications on the exterior of

the Unit 2 containment. Following an inspection during the March - June 2000 outage,

Entergy documented 22 indications of concrete pop-out, i.e., exposed rebar. The

exposed rebar and Cadweld had rusted, and in some cases rust stains had progressed

down the outside of containment. Entergy performed an analysis which compared the

indications against a structural analysis that divided containment into three zones of

importance, each indicating the amount of rebar margins that existed in each zone. The

analysis determined that no repairs were required and remediation would be ineffective

at arresting further aging effects. The NRC inspectors reviewed the analysis and did not

disagree with its determinations.

Entergys monitoring of the concrete pop-outs has consisted of periodic evaluation of

some pop-outs and making a qualitative determination of the amount of aging by

reviewing prior photographs of the pop-out. There were no measurements or

quantitative standards of acceptance applied. Without a method of consistent

measurement, the inspectors questioned the effectiveness of monitoring or trending.

Entergy agreed to correct this and issued CR-IP3-2008-00458 to establish baseline

measurements of the indications and compare them against future measurements.

During the spring 2008 outage, the NRC inspectors entered the Unit 2 containment and

reviewed some accessible areas of the containment liner to determine the visual

condition of the liner. The inspectors also visually inspected some accessible areas of

the liner-to-inside-sill seal and the areas previously ultrasonically thickness gauged.

4

For the Containment Inservice Inspection Program, the inspectors concluded that

Entergy had performed adequate evaluations, including reviews of industry experience

and plant history, to determine appropriate aging effects. Entergy provided adequate

guidance to ensure the aging effects are appropriately identified and addressed.

Fatigue Monitoring Program

The Fatigue Monitoring Program is an existing program that tracks the relevant

transients for selected reactor coolant system components. The components

considered include the reactor vessel, reactor vessel internals, pressurizer, steam

generators, and Class 1 piping and components. The program compares the transient

data with the analyzed fatigue transients in order to assure the actual effective number

of transients does not exceed the analyzed number of transients. The ratio of the

counted transients to the analyzed transients is the usage factor.

The inspectors noted the following site-specific program enhancements in IP-RPT-06-

LRD02, Section 4.2, Fatigue Monitoring:

Unit 2 Enhancements: Revise appropriate procedures to monitor steady state

cycles and feedwater cycles or perform an evaluation to determine monitoring is

not required. Review the number of allowed events and resolve discrepancies

between reference documents and monitoring procedures.

Unit 3 Enhancements: Revise appropriate procedures to include all the transients

identified. Assure all fatigue analysis transients are included with the lowest

limiting numbers. Update the number of design transients accumulated to date.

The inspectors reviewed the program elements and implementation. The inspectors

reviewed selected components and determined the adequacy of the process used to

maintain the transient count for the component.

For the Fatigue Monitoring Program, the inspectors concluded that Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance to

ensure the aging effects are appropriately identified and addressed.

Fire Protection Program

The Fire Protection Program is an existing program modified for the purpose of aging

management and is credited with managing the aging effects in the fire barrier system

and the diesel-driven fire pumps. The aging effects are managed by periodic inspection

of fire barrier penetration seals, fire barrier walls, ceilings, and floors; and periodic

inspection and testing of fire rated doors. Aging effects are also managed by the

periodic inspection and testing of the diesel-driven fire pumps to ensure that the fuel

supply line can perform its intended function.

5

The inspectors reviewed the existing fire protection program and supporting documents

to verify the effectiveness of the program. The inspectors conducted interviews and

performed walkdown inspections of various fire barriers throughout the plant to evaluate

the effectiveness of the existing program. The inspectors also performed a walkdown

inspection of the diesel-driven fire pumps and accessible portions of the associated fuel

supply line. Surveillance procedures were reviewed for completeness and compliance

with applicable codes. Also, program enhancements were reviewed for adequacy and

completeness.

For the Fire Protection Program, the inspectors concluded that Entergy had performed

adequate evaluations, including reviews of industry experience and plant history, to

determine appropriate aging effects. Entergy provided adequate guidance to ensure the

aging effects are appropriately identified and addressed.

Fire Water System Program

The Fire Water System Program is an existing program and is credited with managing

the aging effects in water-based fire protection systems. The aging effects are managed

by periodic testing and inspection of systems and components exposed to water,

including sprinklers, nozzles, fittings, valves, hydrants, hose stations, standpipes, and

above ground and underground piping and components.

The inspectors reviewed program basis documents and implementing procedures to

assess the effectiveness of the existing program. The inspectors reviewed the

implementing procedures and results of periodic flow testing. The inspectors also

conducted interviews and performed walkdown inspections of portions of the fire water

system to evaluate the effectiveness of the existing program. Program enhancements

were reviewed for adequacy and completeness.

For the Fire Water System Program, the inspectors concluded that Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance to

ensure the aging effects are appropriately identified and addressed.

Nickel Alloy Inspection Program

The Nickel Alloy Inspection Program is an existing program that manages aging effects

of alloy 600 components and alloy 82/182 welds in the reactor coolant system that are

not addressed by the Reactor Vessel Head Penetration Inspection Program or the

Steam Generator Integrity Program. The aging effect managed by this program, for

nickel alloys exposed to borated water at an elevated temperature, is primary water

stress corrosion cracking. The Nickel Alloy Inspection Program is a hybrid program

containing elements of the Inservice Inspection Program, the Boric Acid Corrosion

Control Program, and the Water Chemistry Control - Primary and Secondary Program.

Nickel alloy degradation also is currently the subject of NRC Orders, Bulletins and

Generic Letters and NRC-accepted industry guidelines, which form an integral part of

the program implementation at Indian Point.

6

The inspectors reviewed Entergys implementation of NRC Orders, Bulletins, and

Generic Letters that form the basis for the Nickel Alloy Inspection Program. Entergy

credits the Water Chemistry Control - Primary and Secondary Program for minimizing

the potential for primary water stress corrosion cracking in susceptible materials by

maintaining an environment that is less conducive to initiating primary water stress

corrosion cracking. The Nickel Alloy Inspection Program detects degradation by using

the examination and inspection requirements of ASME Section XI, augmented in

response to NRC Orders, Bulletins and Generic Letters, or by the use of NRC-accepted

industry guidelines. The Nickel Alloy Inspection Program detects cracking due to

primary water stress corrosion cracking prior to loss of intended function.

The inspectors reviewed the current Electric Power Research Institute (EPRI) Materials

Reliability Program being developed to manage and mitigate primary water stress

corrosion cracking of nickel based alloy components. The main goal of this program will

be to provide short and long term guidance for inspection, evaluation, and management

of nickel alloy material and weld metal locations in pressurized water reactor primary

systems. Guidance developed by the Materials Reliability Program will be used by

Entergy to identify critical locations for inspection and augment existing inservice

inspections. This program and the implementation of NRC Orders, Bulletins and

Generic Letters are the subject of a separate inspection by the NRC: Temporary

Instruction 2515/172, Reactor Coolant System Dissimilar Metal Butt Welds.

For the Nickel Alloy Inspection Program, the inspectors concluded that Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance to

ensure the aging effects are appropriately identified and addressed.

One-Time Inspection Small Bore Piping Program

The One-Time Inspection Small Bore Piping Program is a new program credited with

managing the aging effects of cracking in small bore ASME Code Class 1 piping less

than 4 inches nominal pipe size (NPS 4), which includes pipe, fittings, and branch

connections. The ASME Code does not require volumetric examination of Class 1 small

bore piping.

The program will include a sample selected based on susceptibility, ability to inspect,

dose considerations, operating experience, and limiting locations of the total population

of ASME Code Class 1 small bore piping locations. When evidence of an aging effect is

revealed by a one-time inspection, evaluation of the inspection results will identify

appropriate corrective actions. Entergy states in its application that the inspections will

be performed prior to the period of extended operation.

This new program will be implemented consistent with the corresponding program

described in NUREG-1801,Section XI.M35, One-Time Inspection of American Society

of Mechanical Engineers Code Class I Small-Bore Piping, which is based on industry

operating experience. The program will use EPRI Report 1000701, Interim Thermal

Fatigue Management Guideline (MRP-24), January 2001, to determine which piping

7

less than 4" nominal pipe size is susceptible to potential effects of thermal stratification

or turbulent penetration.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

programs implementation.

For the One-Time Inspection Small Bore Piping Program, the inspectors concluded that

Entergy had performed adequate evaluations, including reviews of industry experience

and plant history, to determine appropriate aging effects. In program-level documents,

Entergy provided adequate guidance to ensure the aging effects are appropriately

identified and addressed.

Steam Generator Integrity Program

The Steam Generator Integrity Program is an existing program and includes processes

for monitoring and maintaining secondary side component integrity, including steam

generator tubes. Steam generator tubes, in general, have experienced aging caused by

corrosion, including primary water stress corrosion cracking, outside diameter stress

corrosion cracking, intergranular attack, pitting, and wastage. Steam generator tubes

have also experienced mechanically-induced aging, such as denting, wear, impingement

damage, and fatigue. Nondestructive examination techniques, such as eddy current

testing, are used to identify tubes that are defective and need to be removed from

service or repaired.

The Steam Generator Integrity Program is implemented in accordance with NRC-

approved guidance in NEI 97-06, Steam Generator Program Guidelines, and is

monitored by the NRC during every outage of each unit, using Inspection Procedure 71111.08, ISI Inspection. The inspectors had previously reviewed the eddy current

evaluations of tubes, the criteria used to determine if plugging was required, and

assessed the effectiveness of measures to mitigate degradation. The inspectors have

reviewed implementation regarding leakage monitoring, tube inspection scope and

frequency, plugging and repair criteria, and steam generator degradation management.

The inspectors reviewed the most recent Condition Monitoring and Operational

Assessment Reports for each unit to ascertain the current state of the generators. The

inspectors noted Unit 2 generators were replaced in December of 2000 with a W Model

44F Westinghouse design and the unit was uprated in November 2004. The inspectors

also noted the original Unit 3 generators were replaced in 1989 and underwent an uprate

in April of 2005.

For the Steam Generator Integrity Program, the inspectors concluded that Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance to

ensure the aging effects are appropriately identified and addressed.

8

Non-Environmentally Qualified Inaccessible Medium-Voltage Cable Program

The Non-Environmentally Qualified (non-EQ) Inaccessible Medium-Voltage Cable

Program is a new program that Entergy will implement prior to the period of extended

operation. The program will be comparable to that described in NUREG-1801, Section

XI.E3, Inaccessible Medium-Voltage Cables Not Subject to 10 CFR 50.49

Environmental Qualification Requirements. This program applies to inaccessible (e.g.,

in conduit or direct-buried) medium-voltage cables within the scope of license renewal

that are exposed to significant moisture simultaneously with applied voltage. This

program includes a commitment to test these cables at least once every 10 years to

provide an indication of the condition of the conductor insulation. The specific type of

test performed will be determined and implemented prior to the expiration of the current

license. The program also includes inspections for water accumulation in manholes at

least once every two years.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

implementation of this program. The inspectors reviewed program documentation,

condition reports, aging management review documents, and existing procedures, and

confirmed that Entergy had a commitment in place to enhance the program prior to the

period of extended operation. The inspectors also interviewed the engineer responsible

for the non-EQ inaccessible medium-voltage cable program regarding implementation of

particular test procedures to be developed under the program. The inspectors verified

that Entergy had performed adequate historical reviews of plant specific and industry

experience to determine aging effects.

Due to work control and planning constraints, Entergy was unable to open a manhole for

inspection during the inspection period. On June 2, 2008, the inspectors returned and

observed a scheduled quarterly preventive maintenance (PM) activity to open and

inspect Unit 3 manhole 36. The inspectors observed standing water with several cable

splices submerged. There were two 6.9 kV cables in the manhole, both associated with

the station blackout/fire protection diesel generator. Entergy pumped the water out of

the manhole, and assessed the condition of the cable jackets and splices as acceptable.

In addition, the inspectors reviewed the results of previous quarterly PMs, and noted that

water was typically found at a depth sufficient to submerge at least the lower cable

splices. These inspection results regarding manhole environmental conditions are under

evaluation by the NRC Office of Nuclear Reactor Regulation (NRR).

For the Non-EQ Inaccessible Medium-Voltage Cable Program, the inspectors concluded

that Entergy had performed adequate evaluations, including reviews of industry

experience and plant history, to determine appropriate aging effects. In program-level

documents, Entergy provided adequate guidance to ensure the aging effects are

appropriately identified and addressed.

Environmental Qualification of Electric Components Program

The Environmental Qualification of Electric Components Program is an existing program,

which is based on the program described in NUREG-1801,Section X.E1,

9

Environmental Qualification (EQ) of Electric Components. This program manages

component thermal, radiation, and cyclical aging through the use of aging evaluations

based on 10 CFR 50.49(f) qualification methods. As required by 10 CFR 50.49, EQ

components not qualified for the current license term are to be refurbished or replaced,

or have their qualification extended prior to reaching the aging limits established in the

evaluation. Aging evaluations for EQ components that specify a qualification of at least

40 years are considered time-limited aging analyses for license renewal.

The inspectors reviewed program documentation, condition reports, aging management

review documents and existing procedures to evaluate the capability of the program to

manage aging effects of EQ electric components. The inspectors also interviewed the

engineer responsible for the EQ program, and reviewed internal and external

assessments of the EQ program. The inspectors verified that Entergy had performed

adequate historical reviews of plant specific and industry experience to determine aging

effects.

For the Environmental Qualification of Electric Components Program, the inspectors

concluded Entergy had performed adequate evaluations, including reviews of industry

experience and plant history, to determine appropriate aging effects. Entergy provided

adequate guidance to ensure aging effects will be appropriately identified and

addressed.

Aboveground Steel Tanks Program

The Aboveground Steel Tanks Program is an existing program credited with managing

the loss of material from external surfaces of aboveground carbon steel tanks. The

aging effects are managed by periodic visual inspections of external surfaces and

thickness measurements of locations that are inaccessible for external visual inspection.

The inspectors reviewed program basis documents, plant procedures, and recent

aboveground tank inspection results, and interviewed personnel. The inspectors also

performed walkdown inspections of the Unit 2 and 3 condensate storage tanks, Unit 2

diesel fire pump water storage tank, and Unit 3 fire water storage tanks.

For the Aboveground Steel Tanks Program, the inspectors concluded Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance to

ensure aging effects will be appropriately identified and addressed.

Metal-Enclosed Bus Inspection Program

The Metal-Enclosed Bus Inspection Program is an existing program credited with

managing the aging effects on non-segregated phase bus. The aging effects are

managed by visually inspecting the enclosure assemblies and interior portions of the bus

for structural integrity, signs of cracking, corrosion, water intrusion, excessive dust

buildup, or foreign debris.

10

The inspectors reviewed drawings, reviewed completed maintenance documents, and

performed walkdown inspections to evaluate the capability of the program to manage

aging effects. The inspectors also had discussions with plant personnel regarding the

program and the current conditions of the non-segregated bus.

The inspectors questioned the completeness of acceptance criteria for the internal

inspection portion of the program. Entergy stated that the inspection procedures would

be revised to include more complete acceptance criteria and the License Renewal

Application (LRA) would be amended. The LRA was subsequently amended in LRA

Amendment 3 dated March 24, 2008.

The inspectors also noted that the program operating experience review did not identify

a 2004 example in which a bus connection was found less than hand tight and declared

inoperable. Entergy agreed to revise the operating experience review report to include

this example.

For the Metal Enclosed Bus Inspection Program, the inspectors concluded that Entergy

had performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance, as

amended, to ensure aging effects are appropriately identified and addressed.

Non-EQ Bolted Cable Connections Program

The Non-EQ Bolted Cable Connections Program is a new program credited with

managing the aging effects in bolted cable connections. The purpose of the program is

to inspect bolted cable connections for loosening of the connections due to thermal

cycling, ohmic heating, electrical transients, vibration, chemical contamination, corrosion,

or oxidation. The aging effects are managed by a one-time inspection of a

representative sample of in-scope connections.

The inspectors reviewed program documents, and had discussions with plant personnel

to assess the proposed program and its capability to manage aging effects. The

inspectors noted that the existing program document allowed visual inspection of the

connections, an approach which is not endorsed in the draft interim staff guidance, LR-

ISG-2007-02 (Changes to Generic Aging Lesson Learned Report Aging Management

Program XI.E6, Electrical Cable Connections Not Subject to 10 CFR 50.49

Environmental Qualification Requirements). Entergy stated that the inspection method

would be revised to comply with the final interim staff guidance, when issued, and the

LRA would be amended. The LRA was subsequently amended in LRA Amendment 3

dated March 24, 2008.

For the Non-EQ Insulated Cables and Connections Program, the inspectors concluded

that Entergy performed adequate evaluations, including reviews of industry experience

and plant history, to determine appropriate aging effects. In program-level documents,

Entergy provided adequate guidance, as amended, to ensure aging effects are

appropriately identified and addressed.

11

Non-EQ Instrumentation Circuits Test Review Program

The Non-EQ Instrumentation Circuits Test Review Program is a new program credited

with managing the aging effects in instrument cables exposed to adverse localized

equipment environments. The aging effects are managed by a periodic review of

instrumentation circuit calibration or surveillance results for in-scope components. Also,

cable testing on in-scope cables will be performed for cables that are disconnected

during the associated instrument calibration.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

implementation of this program. However, the inspectors interviewed plant personnel,

reviewed completed calibration results, and reviewed program documentation to assess

the capability of the proposed program to manage aging effects.

For the Non-EQ Instrumentation Circuits Test Review Program, the inspectors

concluded that Entergy had performed adequate evaluations, including reviews of

industry experience and plant history, to determine appropriate aging effects. In

program-level documents, Entergy provided adequate guidance to ensure aging effects

are appropriately identified and addressed.

Non-EQ Insulated Cables and Connections Program

The Non-EQ Insulated Cables and Connections Program is a new program credited with

managing the aging effects in insulated cables and connections exposed to adverse

localized environments caused by heat, radiation, and moisture. The aging effects are

managed by periodic visual inspections of a representative sample of in-scope cables

and connections for jacket surface anomalies.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

implementation of this program. The inspectors performed walkdown inspections, and

had discussions with plant personnel to assess the proposed program and its capability

to manage aging effects. The inspectors reviewed EPRI TR-109619, Guideline for the

Management of Adverse Localized Equipment Environments, the guidance document

that will be used to develop the program procedures. The inspectors noted that the

aging management review for electrical cables did not include the transite (fibrous

cement board) material used between cable trays for cable separation purposes.

Entergy agreed to revise the aging management review to address transite.

For the Non-EQ Insulated Cables and Connections Program, the inspectors concluded

that Entergy had performed adequate evaluations, including reviews of industry

experience and plant history, to determine appropriate aging effects. In program-level

documents, Entergy provided adequate guidance to ensure aging effects are

appropriately identified and addressed.

12

Buried Piping and Tanks Inspection Program

The Buried Piping and Tanks Inspection Program is a new program credited with

managing the effects of external corrosion on the pressure-retaining capability of buried

carbon steel, gray cast iron, and stainless steel piping components and tanks in a soil

environment. The aging effects will be managed by preventive measures (i.e., coatings

and wrappings) to mitigate corrosion and by visual inspections during planned

excavations. The program will be implemented by performing at least one inspection

within the 10 year period prior to the period of extended operation, either during an

excavation for other purposes or during an excavation planned for this inspection. An

additional inspection will also be performed during the first 10 years of extended

operation. The program will provide inspection and acceptance criteria, and will require

evaluation of the inspection results. Inspections will be performed in accordance with

approved station procedures.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

implementation of this program. The inspectors reviewed the program basis document,

including proposed scope, parameters to be monitored, method of monitoring, and

acceptance criteria, and system drawings, and interviewed the responsible plant

personnel regarding these documents and inspection criteria to be used. In addition, the

inspectors reviewed EN-DC-343, Entergy Buried Piping and Tanks Inspection and

Monitoring Program, which was an existing Entergy corporate level program not yet

approved for implementation at Indian Point. The inspectors also performed field

walkdown inspections of portions of the service water, auxiliary feedwater, and diesel

fuel oil systems in the vicinity of buried piping to independently assess the material

conditions and identify inconsistencies between the as-built plant configuration, and the

aging management evaluations and programs.

Entergy reviewed condition reports written in the last 5 years to identify whether any in-

scope buried piping component or tank inspections had been performed during

excavations performed for other reasons. The review did not identify any issues (i.e.,

surface corrosion, damaged coating) associated with in-scope buried components.

Entergy did identify several recent instances where buried piping had been excavated to

perform internal piping inspections, or to fix through-wall leaks due to internal corrosion.

In those instances, no formal inspection had been performed or documented, but

engineering and maintenance personnel involved with the excavations stated that the

external pipe coatings appeared to be in good condition. Therefore, Entergy concluded

there had been no significant degradation or failures of the existing protective coatings

on buried piping or tanks.

For the Buried Piping and Tanks Inspection Program, the inspectors concluded Entergy

had performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. In program-level documents, Entergy

provided adequate guidance to ensure the aging effects are appropriately identified and

addressed.

13

Service Water Integrity Program

The Service Water Integrity Program is an existing program credited with managing the

maintenance of internal protective coatings and piping, as well as the prevention of

excessive macro-fouling and biofouling, associated with the open cycle service water

system. The aging effects of material loss (corrosion) and fouling are managed by a

condition and performance monitoring program (e.g., visual inspections and/or non-

destructive examinations), and control techniques (e.g., chemical treatment), as

recommended by NRC Generic Letter 89-13. The program includes piping and

components in the service water system, emergency diesel generator system,

component cooling water system, containment cooling and filtration systems, various in-

scope nonsafety-related systems (i.e., instrument air), and the main control room

heating, ventilation and air conditioning system.

The inspectors reviewed the existing program, associated procedures, trending reports,

heat exchanger inspection records, eddy current examination results and trending

reports, heat exchanger tube plugging trends, buried piping internal inspection records,

intake structure inspection records, service water piping through-wall leakage logs, and

service water system health reports to evaluate the effectiveness of the existing

program. The inspectors interviewed the service water system engineer and the

engineer responsible for the service water program, and performed field walkdown

inspections to independently assess the material condition of the service water system,

and identify inconsistencies between the as-built plant configuration and the aging

management evaluations and programs.

The inspectors identified baffle racks in the Unit 3 intake structure, located immediately

below the service water pump suctions, which had not been included in Entergy's aging

management reviews. Entergy determined these components should have been within

the scope of license renewal and committed to perform an aging management review,

as required. Entergy preliminarily concluded these components would be managed by

the Structures Monitoring Program and stated that the LRA would be amended. The

LRA was subsequently amended in LRA Amendment 3 dated March 24, 2008.

For the Service Water Integrity Program, the inspectors concluded Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance, as

amended, to ensure aging effects are appropriately identified and addressed.

Heat Exchanger Monitoring Program

The Heat Exchanger Monitoring Program is an existing program, which will be enhanced

to manage the aging effects of material loss (corrosion) for heat exchanger tubes, for

those heat exchangers within the scope of license renewal that are not covered by other

existing periodic monitoring programs. The aging effects will be managed by periodic

visual inspections and non-destructive examinations. The enhancements will add

additional heat exchangers, within the scope of license renewal, to the existing program

and revise program procedures to (1) perform visual inspections when non-destructive

examinations cannot be performed, (2) consider material environment combinations

14

when determining sample selections, and (3) specify acceptance criteria for visual

inspections and minimum tube wall thickness.

The inspectors reviewed the existing program, heat exchanger inspection records, eddy

current examination results and trending reports, and heat exchanger tube plugging

trends to determine the effectiveness of the existing program. The inspectors

interviewed the heat exchanger program engineer and selected maintenance personnel,

performed field walkdown inspections, and observed portions of an on-going instrument

air closed cooling water heat exchanger inspection to independently assess the material

condition of selected heat exchangers, and identify inconsistencies between the as-built

plant configuration and the aging management evaluations and programs.

The inspectors identified that the Unit 2 instrument air closed cooling water heat

exchangers were included in an aging management review, but had been omitted from

an implementing procedure with heat exchangers to be added into the heat exchanger

monitoring program. Entergy agreed to add these heat exchangers to the program

implementing procedures, which already included the similar heat exchangers from

Unit 3.

For the Heat Exchanger Monitoring Program, the inspectors concluded Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance, as

revised, to ensure the aging effects are appropriately identified and addressed.

Water Chemistry Control - Closed Cooling Water Program

The Water Chemistry Control - Closed Cooling Water Program is an existing program,

which will be enhanced to manage the aging effects of material loss (corrosion),

cracking, and fouling for piping components and heat exchangers in closed cooling

water systems. The aging effects are managed by monitoring and controlling water

chemistry to minimize contaminant concentration and mitigate loss of material. The

enhancements will add additional closed cooling water systems into the existing water

chemistry program and revise the program procedures to monitor the appropriate

chemistry parameters. The added systems include the Unit 2 station blackout diesel,

and the Unit 2 and Unit 3 security generators.

The inspectors reviewed the existing water chemistry program and the associated

chemistry procedures, and interviewed water chemistry specialists to evaluate the

effectiveness of the existing program. In addition, the inspectors performed field

walkdown inspections and observed portions of an on-going instrument air closed

cooling water heat exchanger inspection to independently assess the material condition

of selected closed cooling water systems, and identify inconsistencies between the as-

built plant configuration and the aging management evaluations and programs.

The inspectors identified that (1) neither the existing procedures nor the specified

enhancements included monitoring glycol within specified limits for the Unit 2 and Unit 3

security generators, and (2) the Unit 2 and Unit 3 fire protection diesels had not been

included in the closed cooling water systems to be added to the existing program.

15

Entergy stated that the proposed enhancements would be revised to include these items

and the LRA would be amended. The LRA was subsequently amended in LRA

Amendment 3 dated March 24, 2008.

The inspectors identified that the reactor coolant pump motor lube oil coolers (i.e., heat

exchangers) had been incorrectly identified as short-lived components and screened out

of license renewal scope without an aging management review. Entergy committed to

perform an aging management review for these components. Entergy preliminarily

concluded these components would be managed by the Water Chemistry Control -

Closed Cooling Water Program and the Oil Analysis Program. This change was

subsequently addressed in Entergys response to NRC request for additional information

(RAI) 2.3.0-2 dated March 24, 2008.

For the Water Chemistry Control - Closed Cooling Water Program, the inspectors

concluded Entergy had performed adequate evaluations, including reviews of industry

experience and plant history, to determine appropriate aging effects. Entergy provided

adequate guidance, as amended, to ensure the aging effects will be appropriately

identified and addressed.

Diesel Fuel Monitoring Program

The Diesel Fuel Monitoring Program is an existing program, which will be enhanced to

manage the aging affects of material loss (corrosion) and fouling in fuel oil systems. The

aging effects are managed by a combination of periodic chemistry sampling and

analysis, and periodic fuel oil tank cleaning and inspection. The enhancements will

(1) add selected systems within the scope of license renewal that were not previously

included in the existing monitoring program, (2) add periodic cleaning and inspection of

fuel oil tanks, including thickness measurements of tank bottoms, and (3) revise fuel oil

chemistry sampling frequency, sample location, and monitored parameters, in

accordance with appropriate industry standards.

The inspectors reviewed the existing fuel oil monitoring program, associated chemistry

procedures, and recent fuel oil analysis results to evaluate the effectiveness of the

existing program. The inspectors reviewed tank inspection records to verify the results

were within the acceptable range. In addition, the inspectors interviewed engineering

and chemistry personnel, and performed field walkdown inspections of the diesel fuel oil

storage tanks, emergency diesel generators, station blackout diesels, and the

emergency fuel oil transfer trailer to independently assess the material condition of the

fuel oil systems and identify inconsistencies between the as-built plant configuration, and

the aging management evaluations and programs.

The inspectors identified that the Unit 2 security diesel fuel oil storage tank was not

included in the program enhancement to perform fuel oil chemistry sampling. Entergy

stated that the proposed enhancements would be revised to include this item and the

LRA would be amended. The LRA was subsequently amended in LRA Amendment 3

dated March 24, 2008.

16

The inspectors identified that the existing procedure for fuel oil transfer using the

emergency fuel oil transfer trailer did not specify a chemistry oil sample be taken at the

tank bottom, and did not provide specific acceptance criteria as to when tank flushing

would be required. Entergy stated that the transfer trailer procedure would be revised to

sample and flush in accordance with the existing requirements for fuel oil receipt

inspections and the LRA would be amended. The LRA was subsequently amended in

LRA Amendment 3 dated March 24, 2008.

The inspectors identified that for the Unit 3 emergency diesel fuel oil storage tanks, the

existing procedure for tank bottom verification relied on techniques which would not be

capable of determining bottom thickness, and did not specify appropriate acceptance

criteria. Entergy stated that the existing procedure would be revised to specify wall

thickness measurement using appropriate techniques and include appropriate

acceptance criteria, and the LRA would be amended. The LRA was subsequently

amended in LRA Amendment 3 dated March 24, 2008.

For the Diesel Fuel Monitoring Program, the inspectors concluded Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine appropriate aging effects. Entergy provided adequate guidance, as

amended, to ensure the aging effects will be appropriately identified and addressed.

Boric Acid Corrosion Prevention Program

The Boric Acid Corrosion Prevention Program is an existing program credited with

managing the aging effects of structures and components that are susceptible to boric

acid corrosion. The aging effects are managed by performing periodic visual inspections

of systems containing borated water and adjacent structures, components, and supports

for leakage, and implementing appropriate corrective actions.

The inspectors reviewed relevant license renewal program documents, implementing

procedures, the boric acid leakage database, and corrective action program documents,

and interviewed the boric acid coordinator. Additionally, the inspectors performed a

walkdown inspection of the Unit 2 and Unit 3 safety injection pump rooms and

containment spray pump rooms.

For the Boric Acid Corrosion Prevention Program, the inspectors concluded that Entergy

had performed adequate evaluations, including reviews of industry experience and plant

history, to determine the appropriate aging effects. Entergy provided adequate guidance

to ensure aging effects are appropriately identified and addressed.

External Surfaces Monitoring Program

The External Surfaces Monitoring Program is an existing program that will be enhanced

for the purpose of aging management. The aging effects are managed by performing

periodic visual inspections by system engineers of components subject to aging

management. The program is also credited with managing loss of material from internal

17

surfaces for situations in which internal and external material and environment

combinations are the same, such that external surface condition is representative of

internal surface condition.

The inspectors reviewed relevant license renewal program documents, implementing

procedures, system walkdown reports, and condition reports, and performed a walkdown

inspection of the Unit 2 and Unit 3 safety injection pump rooms and residual heat

removal pump rooms with the system engineer.

For the External Surfaces Monitoring Program, the inspectors concluded that Entergy

had performed adequate evaluations, including reviews of industry experience and plant

history, to determine the appropriate aging effects. Entergy provided adequate guidance

to ensure aging effects are appropriately identified and addressed.

Flow-Accelerated Corrosion Program

The Flow-Accelerated Corrosion Program is an existing program credited with managing

the corrosion aging effects in all carbon steel and low alloy steel components in systems

containing high-energy fluids carrying two-phase or single-phase high energy fluid

greater than 2% of plant operating time. The aging effects are managed by performing

non-destructive examinations (e.g., ultrasonic testing) to detect wall thinning and by

predicting wear rates to support the proactive replacement of system piping. In addition,

the program provides for the performance of follow-up inspections to confirm predictions

and to determine the need for repairs or replacements, as necessary.

The inspectors reviewed relevant license renewal program documents, implementing

procedures, calculations, past flow-accelerated corrosion reports, and condition reports

generated during previous inspections. In addition, with the engineer responsible for the

flow-accelerated corrosion program, the inspectors performed a walkdown inspection of

past inspection points and scheduled inspection points to confirm the configuration

matched the plant drawings.

For the Flow-Accelerated Corrosion Program, the inspectors concluded that Entergy had

performed adequate evaluations, including reviews of industry experience and plant

history, to determine the appropriate aging effects. Entergy provided adequate guidance

to ensure aging effects are appropriately identified and addressed.

Reactor Vessel Head Penetration Inspection Program

The Reactor Vessel Head Penetration Inspection Program is an existing program

credited with managing the aging effect of primary water stress corrosion cracking

(PWSCC) of nickel-based alloy reactor vessel head penetrations exposed to borated

water. Entergy developed this program in response to NRC Order EA-03-009. The

aging effects are managed by performing bare metal visual examinations of the external

surfaces of the reactor vessel head and non-visual examinations on the underside of the

head.

18

The inspectors reviewed relevant license renewal program documents, implementing

procedures, calculations of effective degradation years, videos of past reactor vessel

head inspections, and reports documenting the results of past reactor vessel head

inspections. The inspectors also reviewed Entergys written responses to NRC Bulletins

and NRC Order EA-03-009, and interviewed the assistant outage manager regarding the

reactor vessel head penetration program.

For the Reactor Vessel Head Penetration Inspection Program, the inspectors concluded

that Entergy had performed adequate evaluations, including reviews of industry

experience and plant history, to determine the appropriate aging effects. Entergy

provided adequate guidance to ensure aging effects are appropriately identified and

addressed.

One-Time Inspection Program

The One-Time Inspection Program is a new aging management program intended to

verify the effectiveness of other aging management programs, including Water

Chemistry, Oil Analysis, and Diesel Fuel Monitoring Programs, by reviewing various

aging effects for impact. Where corrosion resistant materials and/or non-corrosive

environments exist, the One-Time Inspection Program is intended to verify that an aging

management program is not needed during extended operations by confirming that

aging effects are not occurring or are occurring in a manner that does not affect the

safety function of systems, structures, and components. These verifications will be

accomplished by non-destructive evaluation performed by qualified personnel using

procedures and processes consistent with the ASME Boiler and Pressure Vessel Code

and 10 CFR 50, Appendix B. The One-Time Inspection Program will be implemented

prior to the period of extended operation.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

implementation of this program. The inspectors reviewed the program description and

implementing procedures, and discussed the planned activities with the responsible

staff.

For the One-Time Inspection Program, the inspectors concluded Entergy had performed

adequate evaluations, including reviews of industry experience and plant history, to

determine appropriate aging effects. In program-level documents, Entergy provided

adequate guidance to ensure aging effects are appropriately identified and addressed.

Selective Leaching Program

The Selective Leaching Program is a new program that is credited with managing the

aging of components made of cast iron, bronze, brass, and other alloys exposed to raw

water, treated water, soil or other environments that may lead to selective leaching of

material constituents. The program will include a one-time visual inspection and

hardness measurement of selected components that may be susceptible to selective

leaching to determine whether loss of material due to selective leaching is occurring, and

whether the process will affect the ability of the components to perform their intended

19

function for the period of extended operation. The Selective Leaching Program will be

implemented prior to the period of extended operation.

At the time of the inspection, Entergy had not completed many of the actions identified in

the program. Therefore, the inspectors were unable to assess the effectiveness of the

implementation of this program. The inspectors reviewed the program description and a

listing of components covered by the program, and discussed the planned activities with

the responsible staff. Also, the inspectors reviewed condition reports for some

applicable components and visually examined the condition of these components.

The inspectors noted that the program description specified a selected set of

components to be inspected but provided no details as to how the set would be

determined. Subsequently, Entergy stated that the program description would be

revised to base the sample selection on a 90% confidence that 90% of the component

population has not experienced degradation, and the LRA would be amended. The LRA

was subsequently amended in LRA Amendment 3 dated March 24, 2008.

For the Selective Leaching Program, the inspectors concluded Entergy had performed

adequate evaluations, including reviews of industry experience and plant history, to

determine appropriate aging effects. In program-level documents, Entergy provided

adequate guidance, as amended, to ensure aging effects are appropriately identified and

addressed.

Bolting Integrity Program

The Bolting Integrity Program is an existing program which applies to the bolting and

torquing practices for bolting on pressure retaining components, component supports,

and structural joints. The program includes periodic inspections for signs of leakage due

to cracking, loss of material, and loss of preload. The program has preventive measures

to preclude or minimize loss of preload and cracking.

The inspectors reviewed program basis documents and plant procedures, and

interviewed applicable personnel. The inspectors also performed walkdown inspections

of various systems to evaluate the effectiveness of the existing program.

For the Bolting Integrity Program, the inspectors concluded Entergy had performed

adequate evaluations, including reviews of industry experience and plant history, to

determine appropriate aging effects. Entergy provided adequate guidance to ensure

aging effects are appropriately identified and addressed.

Structural Monitoring Program

The Structural Monitoring Program is an existing program that will be enhanced for the

purpose of aging management of structures and structural components. The program

had been developed based on guidance in Regulatory Guide 1.160 Revision 2,

Monitoring the Effectiveness of Maintenance at Nuclear Power Plants, and NUMARC 93-01 Revision 2, Industry Guidelines for Monitoring the Effectiveness of Maintenance

at Nuclear Power Plants, to satisfy the requirements of the Maintenance Rule. The

20

scope of the program also includes condition monitoring of masonry walls and water-

control structures. The program enhancements will expand the program to include

additional structures and components (such as diesel generator foundations, fire

pumphouses, water and oil storage tanks, manholes and duct banks, cable trays and

supports, cranes, crane rails, gaskets, seismic joint filler, and roof elastomers) that are

not monitored under the existing program but require monitoring during the period of

extended operations. Also, guidance will be added to the program to perform an

engineering evaluation of groundwater samples to assess the aggressiveness of

groundwater to concrete on a periodic basis (at least once every five years).

Aging effects are managed by periodic visual inspections by qualified personnel to

monitor structures and components for applicable aging effects. Specifically, concrete

structures are inspected for loss of material, cracking, and changes in material

properties. Steel components are inspected for loss of material due to corrosion.

Masonry walls are inspected for cracking, and elastomers will be monitored for a change

in material properties. Earthen structures associated with water-control structures will be

inspected for loss of material and loss of form (such as subsidence, settlement, leaks,

and bowing). Component supports will be inspected for loss of material, reduction or

loss of isolation function, and reduction in anchor capacity due to local concrete

degradation. Exposed surfaces of bolting are monitored for loss of material due to

corrosion, loose nuts, missing bolts, or other indications of loss of pre-load.

The inspectors reviewed the program description, program basis documents, station

procedures, and results of prior inspections, interviewed cognizant personnel, and

visually examined accessible structural items, including reinforced concrete and

structural steel members, components, and systems to assess the effectiveness of the

current program.

The inspectors also reviewed station procedures, maintenance history, inspection

findings and followup of inspection findings, and inspection schedules. Planned

inspection frequency was every five (5) years for accessible areas. The program

contained provisions for more frequent inspections to ensure that observed conditions

that have the potential for impacting an intended function are evaluated or corrected in

accordance with the corrective action process.

For the Structural Monitoring Program, the inspectors concluded Entergy had conducted

adequate evaluations, including reviews of industry experience and plant history, to

determine appropriate aging effects. Entergy provided adequate guidance to ensure

aging effects are appropriately identified and addressed.

Masonry Wall Program

The Masonry Wall Program is an existing program which will be enhanced to include the

Unit 1 intake structure within the scope of the program due to potential effects on Unit 2

electrical equipment. The scope of the program includes all masonry walls that perform

intended functions in accordance with 10 CFR 54.4 and were covered by IE Bulletin 80-

11. Additionally, the program includes masonry walls covered by 10 CFR 50.48 (Fire

Protection), radiation shielding, and walls with potential to affect safety-related

21

components. The program is credited with managing the aging effects in masonry walls

by a program of inspection for deterioration on a frequency of 5 years to assure that the

established evaluation basis for each masonry wall remains valid during the period of

extended operation. If any crack or deterioration is found, the inspection frequency is to

be increased to monitor and assess the cause and effect of the degradation.

The inspectors reviewed the program description, program basis documents, station

procedures, and results of prior inspections. The inspectors also interviewed cognizant

personnel and performed a visual examination of accessible masonry walls to assess

the effectiveness of the current program. The inspections are implemented through

station procedures. A review of maintenance history indicated that any degradation

(such as cracks) of masonry block walls was identified and addressed, providing

evidence that the inspection program is effective in identifying and correcting

deficiencies, so that walls continue to perform their intended function.

In response to IE Bulletin 80-11, Masonry Wall Design," and Information Notice 87-67,

Lessons Learned from Regional Inspections of Licensee Actions in Response to IE

Bulletin 80-11," various actions have been taken. Actions have included program

enhancements, follow-up inspections to substantiate masonry wall analyses and

classifications, and the development of procedures for tracking and recording changes to

the walls. These actions have addressed all concerns raised by IE Bulletin 80-11 and

Information Notice 87-67, namely unanalyzed conditions, improper assumptions,

improper classification, and lack of procedural controls. The inspectors review of Indian

Point operating experience demonstrated that the program has been effective in

managing aging effects of masonry walls.

For the Masonry Wall Program, the inspectors concluded Entergy had performed

adequate evaluations, including reviews of industry experience and plant history, to

determine appropriate aging effects. Entergy provided adequate guidance to ensure

aging effects are appropriately identified and addressed.

b.3 System Review

Auxiliary Feedwater System Review

The inspectors selected the auxiliary feedwater system for a focused review to

determine whether the aging management programs were adequate to effectively

manage aging effects related to this system. The aging effects requiring management

for the auxiliary feedwater system are loss of material, cracking-fatigue, fouling,

cracking, and loss of material due to wear. The following aging management programs

are credited with managing aging effects of the auxiliary feedwater system:

Aboveground Steel Tanks; Bolting Integrity; Buried Piping and Tanks Inspection,

External Surfaces Monitoring; Flow-Accelerated Corrosion; Water Chemistry Control -

Auxiliary Systems; and Water Chemistry Control - Primary and Secondary.

The inspectors interviewed the auxiliary feedwater system engineer, performed

walkdown inspections, and reviewed various aging management program documents to

verify that the existing programs credited with managing the effects of aging in the

auxiliary feedwater system have been comprehensive and effective. (All programs

22

except Buried Piping and Tanks Inspection are existing programs.) Specifically, the

inspectors evaluated the existing aging management programs by reviewing system

health reports, condition reports, plant procedures, and NDE inspection reports.

For the auxiliary feedwater system, the inspectors concluded that the physical condition

of the system and the results of tests and inspections of the various existing aging

management programs demonstrated that aging effects on the auxiliary feedwater

system have been appropriately identified and addressed. Also, the inspectors

concluded that the auxiliary feedwater system was appropriately addressed within the

applicable aging management programs.

Unit 2 Station Blackout/Appendix-R Diesel Generator (SBO/App-R DG) System Review

Entergy modified the facility, and placed the new Unit 2 SBO/App-R DG in-service on

April 30, 2008. (See LRA Amendment 4 dated April 30, 2008, for additional information.)

The inspectors performed a focused review to determine whether the scoping and

proposed aging management programs were adequate to effectively manage aging

effects of this system. The aging effects requiring management for the SBO/App-R DG

system are loss of material, cracking-fatigue, fouling, cracking, and loss of material due

to wear. The following aging management programs are credited with managing aging

effects: Bolting Integrity; External Surfaces Monitoring; Oil Analysis; Periodic

Surveillance and Preventive Maintenance; Water Chemistry Control - Closed Cooling

Water; Heat Exchanger Monitoring; and Selective Leaching.

The inspectors interviewed the SBO/App-R DG system engineer, performed walkdown

inspections, and reviewed various aging management program documents to verify that

the programs credited with managing the effects of aging in the SBO/App-R DG system

will be comprehensive and effective. Because the SBO/App-R DG system is new, with

no operating experience, the inspectors evaluated the existing aging management

programs by reviewing similar system and component health reports, condition reports,

and NDE inspection reports.

For the SBO/App-R DG system, the inspectors concluded that for license renewal

purposes Entergy had accurate scoping determinations for the system and its

components. Also, the inspectors concluded that the SBO/App-R DG system was

appropriately addressed within the applicable aging management programs and that

these programs were capable of managing SBO/App-R DG system aging effects.

c. Overall Conclusions

Overall, the inspection results support a conclusion that the proposed activities will

reasonably manage the effects of aging in the systems, structures, and components

identified in the application and that the intended functions of these systems, structures,

and components will be maintained in the period of extended operation. The inspection

concluded that the documentation supporting the application was in an auditable and

retrievable form.

23

40A6 Meetings, Including Exit Meeting

The inspectors presented the inspection results to Joe Pollock, Site Vice President; Fred

Dacimo, Vice President, License Renewal; and members of their staffs in an exit

meeting that was open for public observation on June 18, 2008, in Cortlandt Manor, NY.

Entergy had no objections to the NRC observations and presented the status of Entergy

actions to address the NRC observations. Slides from the exit meeting are located in

ADAMS within package ML081850595, which addresses inspection-related documents,

including NRC slides under ML081840487 and Entergy slides under ML082130530.

No proprietary information was provided to the inspectors during this inspection.

A-1

ATTACHMENT

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

F. Dacimo Vice President, License Renewal

J. Pollock Site Vice President

R. Ahrabli Structural engineer

T. Beasly System engineer

A. Bokhari Design engineer

C. Caputo License renewal team

J. Cottam Fire protection programs engineer

A. Cox License renewal team

J. Curry License renewal project manager

R. Dolansky Program engineer

D. Fronabarger License renewal team

J. Goebel Assistant outage manager

R. Herrmann Program engineer

J. Hill Design engineering, I&C supervisor

T. Ivy License renewal team

L. Loubrano Component engineer

W. Mahlmeister Design engineer

I. Mew Program engineer

D. Pennino, Program engineer

J. Pinada System engineer

C. Pistol Program engineer

H. Robinson System engineer

R. Rucker License renewal team

D. Shah System engineer

M. Stewart Electrical maintenance

A. Taylor License renewal team

M. Tesorioro NSSS supervisor

J. Timone Component engineer

J. Whitney System engineer

LIST OF DOCUMENTS REVIEWED

License Renewal Application Drawings

Complete set, including four Unit 1, 73 Unit 2, and 60 Unit 3 drawings

Other Drawings

A202382, Conduit Details for Manholes 35 & 36, Rev 8

A-2

617F645, IP3 Main One Line Diagram, Rev 18

A208377-09, IP2 Main One Line Diagram, Rev 9

A250907-21, IP2 Electrical Distribution and Transmission System, Rev 21

9321-2018, Flow Diagram - Condensate & Boiler Feed Pump Suction

9321-2019, Flow Diagram - Boiler Feedwater

9321-F-2012, IP2 Intake Structure General Arrangement, Rev 5

9321-F-40573, IP3 Flow Diagram for Auxiliary Steam Supply and Condensate Return

System, Rev 27

9321-F-51773, Pipe Trench Area - Restraint and Support Design, Rev 7

9321-L-60129, Sht 6, Restraint SA-H&R-505-U

License Renewal Program Basis Documents

IP-RPT-06-LRD01, System and Structure Scoping Results, Rev 0

IP-RPT-06-LRD02, Aging Management Program Evaluation Report, Rev 3:

Section 3.1, One-time Inspection - Small Bore Piping Program

Section 4.1, Nickel Alloy Inspection Program

Section 4.2, Fatigue Monitoring Program

Section 4.6, Reactor Vessel Head Penetration Inspection Program

Section 4.8, Steam Generator Integrity Program

IP-RPT-06-LRD05, Operating Experience Review Report, Rev 1

IP-RPT-06-LRD07, Aging Management Program Evaluation Report, Rev 3:

Section 3.1, Buried Piping and Tanks Inspection Program

Section 3.2, One-Time Inspection Program

Section 3.3, Selective Leaching Program

Section 4.1, Aboveground Steel Tanks Program

Section 4.2, Bolting Integrity Program

Section 4.4, Boric Acid Corrosion Prevention Program

Section 4.5, Diesel Fuel Monitoring Program

Section 4.6, External Surface Monitoring Program

Section 4.7, Fire Protection Program

Section 4.8, Fire Water System Program

Section 4.9, Flow Accelerated Corrosion Program

Section 4.12, Service Water Integrity Program

Section 4.15, Water Chemistry Control - Closed Cooling Water Program

Section 4.17, Heat Exchanger Monitoring Program

IP-RPT-06-LRD08, Aging Management Program Evaluation Report, Rev 3:

Section 3.2, Containment Inservice Inspection Program

Section 3.3, Structures Monitoring Program

Section 3.4, Masonry Wall Program

IP-RPT-06-LRD09, Aging Management Program Evaluation Report, Rev 3:

Section 3.1, Non-EQ Bolted Cable Connections Program

Section 3.2, Non-EQ Inaccessible Medium-Voltage Cable Program

A-3

Section 3.3, Non-EQ Instrumentation Circuits Test Review Program

Section 3.4, Non-EQ Insulated Cables and Connections Program

Section 4.1, Environmental Qualification (EQ) of Electric Components Program

Section 4.2, Metal Enclosed Bus Inspection Program

Aging Management Review Technical Basis Documents (all preceded by IP-RPT-06-)

AMC04, Aging Management Review of Bulk Commodities, Rev 1

AME01, Attachment 4, Inaccessible Medium-Voltage Cable Screening, Rev 0

AMM14, Aging Management Review of the Compressed Air Systems, Rev 0

AMM16, Aging Management Review of Fire Protection Water System, Rev 0

AMM20, Aging Management Review of IP2 SBO and Appendix R Diesel Generator

System, Rev 0

AMM24, Aging Management Review of the Auxiliary Feedwater Systems

AMM30, Aging Management Review of the Nonsafety-related Systems and Components

Affecting Safety-Related Systems, Rev 2 & Rev 3

Plant Procedures

EN-DC-147, Alloy 600 Program Plan, Rev 3

EN-DC-159, System Monitoring Program, Rev 2

EN-DC-178, System Walkdowns, Rev 1

EN-DC-315, Flow Accelerated Corrosion Program, Rev 0

EN-DC-317, Entergy Steam Generator Administrative Procedure, Rev 2

EN-DC-319, Inspection and Evaluation of Boric Acid Leaks, Rev 2

EN-DC-343, Entergy Buried Piping and Tanks Inspection & Monitoring Program, Rev 0

EN-LI-102, Corrective Action Process, Rev 8

EN-LI-102, Corrective Action Process, Rev 9

EN-MS-S-011-MULTI, Conduct of System Engineering, Rev 2

ENN-CS-S-008, Pipe Wall Thinning Structural Evaluation, Rev 1

ENN-DC-150, Condition Monitoring of Maintenance Rule Maintenance, Rev 2

ENN-EP-S-001, IWE General Visual Containment Inspection, Rev 0

ENN-EP-S-003, IWL Visual Containment Inspection, Rev 0

ENN-NDE-2.12, Certification of Visual Testing (VT) Personnel, Rev 2

ENN-NDE-9.05, Ultrasonic Thickness Examination, Rev 1

ENN-NDE-10.1, VT-1 Examination, Rev 3

0-MS-411, Rev 1 Torquing of Mechanical Fasteners

2-PT-R075, Rev 13 RCS Integrity Inspection

3-PT-R131, Rev 11 RCS Integrity Leak Test

Engineering Report IP-RPT-07-00093, Boric Acid Corrosion Control Program, Rev 0

HTX-006-IAC, Instrument Air Compressor Closed Cooling Water HX Maint., Rev 1

IP-SMM EV-103, Petroleum Bulk Storage Tank Program, Rev 0

PFM-116, Motor Monitoring Program Procedure, Rev 0

PT-EM19, Procedure for Testing Cable Spreading Room Halon System, Rev 10

SAO-703, Fire Protection Impairment Criteria and Surveillance, Rev 24

SEP-SW-001, Generic Letter 89-13 Service Water Program, Rev 1

0-CY-1500, Chemistry Sampling Locations, Rev 6

0-CY-1810, Diesel Fuel Oil Monitoring, Rev 5

A-4

0-CY-2510, Closed Cooling Water Chemistry Specifications and Frequencies, Rev 4

0-CY-2515, Adding Chemicals to Closed Cooling Systems, Rev 6

0-CY-3318, Water and Sediment in Fuel Oil, Rev 3

2-PI-Q001, Inspection Procedure for Fire Separation Barriers (Unit 2), Rev 8

2-PT-2Y015, Revision 1, Thermal Cycle Monitoring Program, Rev 0

2-PT-2Y017, Procedure for Penetration Fire Barrier Seal Inspections (Unit 2), Rev 0

2-PT-W005, Weekly Surveillance Procedure for Diesel Fire Pump (Unit 2), Rev 18

2-PT-M040, Procedure for Testing Diesel Fire Pump (Unit 2), Rev 23

2-PT-Q092, Containment Building Inspection, Rev 3

2-PT-R156, RCS Boric Acid Leakage and Corrosion Inspection, Rev 1

2-PT-R203, Visual Examination of Reactor Vessel Head Penetrations and Head Surface

for Leakage, Rev 2

2-PT-R204, Visual Examination of Reactor Vessel Bottom Mounted Instrument

Penetrations for Leakage, Rev 1

2-SOP 29.20, Emergency Fuel Oil Transfer Using the Trailer, Rev 0

3-CY-2615, Adding Chemicals to Auxiliary Systems, Rev 0

3-PT-M042B, Procedure for Testing Unit 3 Diesel Fire Pump, Rev 3

3-PT-M051, Revision 9, Plant Operation Information, Rev 2

3-PT-R100A, Procedure for Unit 3 Controlled Barrier Inspection, Rev 1

3-PT-R102, Procedure for Fire Barrier Wrap/Radiant Energy Shield Inspection, Rev 4

3-PT-2Y004, Unit 3 CO2 System Test for Cable Spreading & Switchgear Rooms, Rev 2

3-PT-Q137, Containment Building Inspection, Rev 4

3-PT-R203, Visual Examination of Reactor Vessel Head Penetrations and Head Surface

for Leakage, Rev 2

3-PT-R204, Visual Examination of Reactor Vessel Bottom Mounted Instrument

Penetrations for Leakage, Rev 1

3-PT-CS032B, Flow Test of SW Header Check Valve and Underground Portions of Line 408,

Rev 9

2-RPT-00003, Containment Inservice Inspection Program First Containment Inspection

Interval (09/09/96 - 05/09/08), Rev 1

3-RPT-UNSPEC-03499, IP 2&3 Eddy Current Program, Rev 1

IP-RPT-04-00206, Indian Point 2 Steam Generator Program, Rev 1

IP-RPT-04-01796, Indian Point 3 Steam Generator Program, Rev 7

IP-RPT-06-00055, Condition Monitoring and Operational Assessment of

Indian Point 2 Steam Generator Tubing for Cycles 18 and 19, Rev 0

IP-RPT-07-00031, 3R14 Condition Monitoring and Operational Assessment of Indian

Point 3 Steam Generators, Rev 0

IP3-RPT-VC-03071, Containment Inservice Inspection, First Ten Year Class MC and CC

Program, 09/10/99-07/20/09, Rev 5

System Health Reports

IP3 Heat Exchangers, 2nd Quarter 2007

IP3 Service Water, 1st Quarter 2007

IP2 Auxiliary Feedwater, 1st Quarter 2007

IP2 Auxiliary Feedwater, 3rd Quarter 2007

IP3 Auxiliary Feedwater, 1st Quarter 2007

IP3 Auxiliary Feedwater, 3rd Quarter 2007

IP2 Cycle 18 Generic Letter 89-13 Leakage Logs

A-5

IP2&3 Service Water System Leakage History 1991 to Present, Dated Jan 2008

IP3 Cycle 15 Generic Letter 89-13 Leakage Logs

Condition Reports (CRs)

IP2-2000-04864

IP2-2000-07403

IP2-2001-07815

IP2-2002-03598

IP2-2003-02364

IP2-2004-05296

IP2-2004-05748

IP2-2005-02690

IP2-2006-01485

IP2-2006-01798

IP2-2006-01929

IP2-2006-01965

IP2-2006-02146

IP2-2006-02161

IP2-2006-02290

IP2-2006-02553

IP2-2006-02639

IP2-2006-02712

IP2-2006-02780

IP2-2007-03749

IP2-2008-00124

IP2-2008-00517*

IP3-1995-00044

IP3-2000-01898

IP3-2000-00561

IP3-2001-04270

IP3-2005-02634

IP3-2005-03202

IP3-2005-04563

iP3-2006-00583

IP3-2006-02270

IP3-2007-01388

IP3-2007-01399

IP3-2007-00309

IP3-2007-01852

IP3-2007-02984

IP3-2007-03497

IP3-2008-00285*

IP3-2008-00442*

IP3-2008-00444*

IP3-2008-00457*

IP3-2008-00517*

A-6

IP3-LO-2005-00117

  • CRs written as a result of the NRC inspection

Maintenance Requests & Work Orders

WO IP2-02-32382

WO IP2-03-10707

WO IP2-04-14606

WO IP2-04-14609

WO IP2-06-01525

WO IP3-98-484002

WO IP3-02-20718

WO IP3-05-21828

WO IP3-05-19497

WO IP3-05-24529

WO IP3-06-13173

WO IP3-06-16430

WO IP2-02-48724

WO IP3-06-23446

WO IP3-06-23450

WO 51345229-01

WO 51434864

WR IP2-02-32987

WR IP2-02-60313

WR IP2-04-23003

WR IP3-02-22223

WR IP3-02-22224

WR IP3-03-19544

WR IP3-03-19545

I3-000261300

I3-000277700

I3-010166600

I3-980309200

I3-980309300

I3-990116600

IP2-01-21964

IP2-02-31080

IP2-02-31082

IP2-02-31084

IP2-02-31085

IP2-02-33308

IP2-03-21948

IP2-98-97215

IP3-02-16871

A-7

IP3-02-21957

IP3-02-21958

IP3-02-21984

IP3-02-22487

IP3-02-22488

NP-92-58250

NP-93-66966

NP-95-81537

NP-98-97215

Completed Surveillance Tests

2-PC-2Y72A, Source Range Neutron Flux N-31 Channel Calibration, performed 4/19/06

2-PC-2Y72B, Source Range Neutron Flux N-32 Channel Calibration, performed 4/20/06

2-PC-2Y73A, Intermediate Range Neutron Flux N-35 Channel Calibration, performed 5/9/06

2-PC-2Y73B, Intermediate Range Neutron Flux N-36 Channel Calibration, performed 4/25/06

2-PC-4Y74B, Nuclear Instruments Power Range N-42 Channel Calibration, performed 5/5/06

2-PC-4Y74D, Nuclear Instruments Power Range N-44 Channel Calibration, performed 5/4/06

2-PC-R38-2, High Range Containment Area Radiation Monitor R25, performed 4/14/06, 5/16/06

2-PC-R38-4, High Range Containment Area Radiation Monitor R26, performed 5/6/06

2-PI-M009, Aboveground Petroleum Storage Tanks, Performed 1/16/08

3-PC-Q109A, Nuclear Power Range Channel N-41 Axial Offset Calibration, performed 5/31/07

3-PC-Q109B, Nuclear Power Range Channel N-42 Axial Offset Calibration, performed 5/31/07

3-PC-Q109C, Nuclear Power Range Channel N-43 Axial Offset Calibration, performed 6/1/07

3-PC-Q109D, Nuclear Power Range Channel N-44 Axial Offset Calibration, performed 6/1/07

3-PC-R45, Calibration Procedure for the Gamma-Metrics Excore Nuclear Instrumentation

System, performed 3/25/05

3-PC-R46A, Containment High Range Radiation Monitor Calibration (R-25), performed 3/13/07

3-PC-R46B, Containment High Range Radiation Monitor Calibration (R-26), performed 3/13/07

3-PC-R72A, Nuclear Instruments Source Range N-31 Channel Calibration, performed 3/8/07

3-PC-R72B, Nuclear Instruments Source Range N-32 Channel Calibration, performed 3/8/07

3-PC-R73A, Nuclear Instruments Intermediate Range N-35 Channel Calibration, performed

3/10/07

3-PC-R73B, Nuclear Instruments Intermediate Range N-36 Channel Calibration, performed

3/10/07

EBD-B-002-N, Westinghouse 6.9KV Cubicle and Bus Cleaning and Inspections, performed

2/25/93, 7/14/94, 5/15/97, 11/2/04

EBD-P-004-A, Westinghouse Station Service Transformers and Buses (480VAC), performed

4/24/00, 11/8/02

ELC-013-BUS, Inspection, Cleaning, and Testing of Medium Voltage Switchgear, performed

9/17/99, 5/7/01, 4/9/03, 3/18/07, 3/21/07

ELC-014-BUS, Inspection, Cleaning, and Testing of 480V Load Center, performed 9/17/99,

4/8/03, 3/17/07

IP2-04-30541, High Range Containment Area Radiation Monitor 26, performed 3/24/06

PC-M-1, Nuclear Power Range Channels Axial Offset, performed 9/13/04

PI-SA-2, Atmospheric Tanks, Performed 9/7/07

2-PT-3Y009, Flow Test for underground SE Line 409, Completed 08-09-2005

2-PT-3Y010, Flow Test for underground SE Line 409, Completed 09-10-2005

A-8

3-PT-CS032A, Flow Test of SW Header Check Valve and Underground Portions of Line 408,

Completed 03-28-2007

WR 51478836-01, Perform 3-PT-Q137, Rev 4, Containment Building Inspection

WR 51550475, Perform 2-PT-Q092, Rev 3, Containment Building Inspection

WR IP2-02-17652, Perform 2-PT-R203, Rev 0, Visual Examination of Reactor Vessel Head

Penetrations and Head Surface for Leakage

WR IP3-06-10035, Perform 3-PT-R203, Rev 1, Visual Examination of Reactor Vessel Head

Penetrations and Head Surface for Leakage

WR IP3-06-12801, Perform 3-PT-R204, Rev 0, Visual Examination of Reactor Vessel Bottom

Mounted Penetrations for Leakage

Inspection Reports

IP3-UT-07-096

IP2-UT-07-053

IP2-UT-07-047

IP2-UT-07-043

IP2-UT-07-037

Maintenance Rule Inspections (Structural):

  • Reactor Building: Twenty-three reports
  • Turbine Building: Eight reports
  • Radwaste Building: Four reports
  • Miscellaneous Structures: Sixty reports

Visual Inspection Photographs

IP2 408 SWP:

408 header exc Nov 04, 021 - 10 photographs

IP2 buried flng to header by river - 3 photographs

IP2 SWP 408 buried flng to PAB Bldg - 4 photographs

IP2 SWP 24/25/26 408 - 5 photographs

1st tee @ 30' - 4 photographs

Upper 90 vert elbow - 1 photographs

IP2 414 HDR:

Debris @10' east of access - 1 photograph

Debris @15' east of access - 1 photograph

IP2 840 Vlv:

840 flng - 1 photograph

1103 pipe connection to main from swn 46 - 1 photograph

1105 left side close up - 1 photograph

1105 right side close up - 1 photograph

1105 upstream - 4 photographs

Flow restrictor - 1 photographs

A-9

Main Pipe to 1103 (SWN45) connection - 1 photograph

Tee crotch near 840 - 1 photograph

Weld @ tee down stream of 1105 (2) - 1 photograph

Weld @ tee down stream of 1105 left side - 1 photograph

Weld @ tee down stream of 1105 right side - 1 photograph

Weld @ tee downstream (4) - 1 photograph

Weld @ tee downstream of 1105 (3) - 1 photograph

Excavation of flange 408 - 12 pictures

SWN 40:

2nd Reducer from access - 1 photograph

Debris @ Vert 90 elbow - 3 photographs

Photos of Reactor Vessel Head Cleaning from 2R16

Photos of Reactor Vessel Head Cleaning from 2R17

Miscellaneous Documents

IP2-DBD-222, Electrical Separation Design Basis Document, Rev 2

Letter No. 20407.002, from Normandeau Associates, to IP3, Zebra Mussel Monitoring Program

June Results, dated 06-22-2007

Letter from Hunting Pipeline Services, to IP3, Evaluation of As-found Condition of SW

Mechanical Seals, dated 03-17-2005

2R17 Flow Accelerated Corrosion Monitoring Program, Spring 2006

3R14 FAC Examination Report for Indian Point Unit 2 for Entergy Nuclear, March 2007

IP-RPT-05-00407, IPEC 3R14 FAC Scope Review, Rev 0

IP-RPT-06-00070, Alloy 600 Program Plan, Rev 0

IP-RPT-MULT-03162, Unit 3 Flow-Accelerated Corrosion Susceptibility Review and Small-Bore

and Augmented Monitoring Program, Rev 2

IP2 Boric Acid Database

IP2 Flow Accelerated Corrosion Program Plan Supplement, April 28, 2003

IP2 Reactor Vessel Examination, Examination Summary dated May 5, 2006

IP3 Boric Acid Database

ER IP2-06-26282, Flow Accelerated Corrosion Inspection Points for 2R18, Rev 0

ER IP3-05-24045, Flow Accelerated Corrosion Inspection Points for 3R14, Rev 1

IP2-02-50626, Reactor Vessel Head Penetration Contingency Repair

Maintenance Rule Basis Document for Structures

Monitoring Reports for 10CFR50.65 Maintenance Rule Structures

A02-07I, 12/23/2003, QA Audit Report on EQ Program.

A03-12-I, 10/21/2003, Fire Protection Program Audit

GT-1 North & South Fuel Oil Storage Tanks Inspection Report, Dated June 2001

GT-2/3 Fuel Oil Storage Tank Inspection Report, Dated April 2002

IP-2 Service Water Intake Pump Bay Silt Mapping Report, Dated 05-04-2007

IP-2 Service Water Intake Pump Bay Silt Mapping Report, Dated 11-28-2007

IP-2 Remote Visual Inspection of Service Water Piping Report, Dated 11-10-2004

QA-09-2005-IP-1, 12/12/2005, IPEC Fire Protection Program Audit.

QA-09-2006-IP-1, 01/19/2006, IPEC Fire Protection Program Audit.

IPEC Self Assessment Report - Leak Management Program Implementation

A-10

Listing of Components Covered by Selective Leaching Program

Email from Charles Caputo on August 14, 2006; Results from site walkdown of the

chlorination system for IP2 and IP3

WCAP-12191, Transient and Fatigue Cycle Monitoring Program Transient History

Evaluation Final Report for Indian Point Unit 2, July 1999, Rev 2

WCAP-12937, Structural Evaluation of Indian Point Units 2 and 3 Pressurizer Surge

Lines, Considering the Effects of Thermal Stratification, May 1991

Calculations

FCX-00538, Estimation of EDYs for IP2 Reactor Vessel Head by 2R17 and 2R18

IP-CALC-04-01634, Assessment of the Impact of Power Uprate on the EOL Degradation

Years (EDY's) for the IP3 Vessel Head, Rev 0

IP-CALC-06-00100, Wall Thinning Evaluation for Flow Accelerated Corrosion at 2R17

Locations, Rev 0

IP-CALC-06-00175, Evaluation of FAC Inspection Point LPFW22B-1N for Local Wall

Thinning, Rev 0

IP-CALC-06-00297, Wall Thinning Evaluation and R.S.L. for Flow Accelerated Corrosion at

2R17 Locations, Rev 0

IP3-CALC-RV-03720, Estimation of Effective Degradation Years (EDY) for IP3 Reactor Vessel

Head, Rev 2

Entergy Letters/Correspondence

Indian Point 2 Response to NRC Generic Letter 89-08 Erosion/Corrosion - Induced Pipe

Wall Thinning, July 20, 1989

Indian Point Unit 2, Response to NRC Bulletin No. 87-01, Thinning of Pipe Walls in

Nuclear Power Plants, September 11, 1987

IP3-87-055Z, Indian Point 3. NRC Bulletin No. 87-01 Thinning of Pipe Walls in

Nuclear Power Plants, September 15, 1987

IPN-89-044, Indian Point 3 Nuclear Power Plant Response to NRC Generic Letter 89-08,

Erosion/Corrosion - Induced Pipe Wall Thinning, July 21, 1989

Letter from Entergy to NRC dated March 11, 2004, Indian Point 2 and 3 Answer to

2/20/04 Revised NRC Order Regarding Interim Inspection Requirements for

Reactor Pressure Vessel Heads

Letter from Entergy to NRC dated March 27, 2003, IP3 NRC Order EA-03-009

Relaxation Request Regarding Inspection of Reactor Pressure Vessel Head

Nozzles

Letter from NRC to Entergy dated October 15, 2004, Relaxation of First Revised Order

on Reactor Vessel Nozzles, Indian Point Unit Number 2

NL-05-001, Letter from Entergy to NRC dated January 17, 2005, Reactor Vessel Head

Inspection Results: IP2, Fall 2004 Refueling Outage (2R16)

NL-05-044, Letter from Entergy to NRC dated May 31, 2005, Reactor Vessel Head

Inspection Results: IP3, Spring 2005 Refueling Outage (3R13)

NL-06-028, Letter from Entergy to NRC dated May 31, 2006, License Amendment

Request for Adoption of TSTF-449, Regarding Steam Generator Tube Integrity

NRC Letter to Entergy Nuclear Operations, Inc. August 18, 2005

Entergy Nuclear Northeast Letter to NRC, NL-05-002, January 17, 2005

Entergy Nuclear Northeast Letter to NRC, NL-05-063, May 31, 2005

A-11

NRC Documents

BL 2002-01, Reactor Pressure Vessel Head Degradation and Reactor Coolant Pressure

Boundary Integrity

BL 2002-02, Reactor Pressure Vessel Head And Vessel Head Penetration Nozzle

Inspection Programs, August 9, 2002

BL 2003-02, Leakage From Reactor Pressure Vessel Lower Head Penetrations And

Reactor Coolant Pressure Boundary Integrity, August 21, 2003

EA-03-009, Issuance Of Order Establishing Interim Inspection Requirements For

Reactor Pressure Vessel Heads At Pressurized Water Reactors, February 11,

2003

EA-03-009, Issuance Of First Revised NRC Order (EA-03-009) Establishing Interim

Inspection Requirements For Reactor Pressure Vessel Heads At Pressurized

Water Reactors, February 20, 2004

GL 88-05, Boric Acid Corrosion Of Carbon Steel Reactor Pressure Boundary

Components In Pwr Plants (Generic Letter 88-05), March 17, 1988

GL 89-13, Service Water System Problems Affecting Safety-related Equipment

IN 2002-11, Recent Experience With Degradation Of Reactor Pressure Vessel Head,

March 12, 2002

IN 2002-13, Possible Indicators Of Ongoing Reactor Pressure Vessel Head

Degradation, April 4, 2002

IN 2003-02, Recent Experience With Reactor Coolant System Leakage And Boric Acid

Corrosion, January 16, 2003

IN 86-108, Degradation Of Reactor Coolant System Pressure Boundary Resulting From

Boric Acid Corrosion, December 29, 1986

NUREG-1801, Generic Aging Lessons Learned (GALL) Report, Rev 1

RIS 2003-13, NRC Review Of Responses To Bulletin 2002-01, Reactor Pressure

Vessel Head Degradation And Reactor Coolant Pressure Boundary Integrity

Industry Documents

EPRI TR 1042135 Bolted Joint Maintenance & Applications Guide

EPRI TR-107396, Closed Cooling Water Chemistry Guideline, Rev 1

EPRI TR-107514, Age-Related Degradation Inspection Method and Demonstration

EPRI Report 10000701, Interim Thermal Fatigue Management Guideline (MRP-24),

January 2001

NEI 95-10, Industry Guidelines for Implementing the Requirements of 10 CFR Part 54 -

The License Renewal Rule, Rev 6

NSAC-202L-R3, Recommendations for an Effective Flow-Accelerated Corrosion

Program, May 2006

United Engineers & Constructions Inc. Specification No. 9321-01-248-18

A-12

LIST OF ACRONYMS

ADAMS Agencywide Documents Access and Management System

ASME American Society of Mechanical Engineers

CR Condition Report

DRS Division of Reactor Safety

EPRI Electric Power Research Institute

EQ Environmental qualification, i.e., 10 CFR 50.49

IE Office of Inspection & Enforcement, NRC

ISG Interim Staff Guidance

ISI Inservice Inspection

LRA License Renewal Application

NEI Nuclear Energy Institute

NPS normal pipe size

NRC U.S. Nuclear Regulatory Commission

NRR Office of Nuclear Reactor Regulation, NRC

PARS Publicly Available Records

PM preventive maintenance

PWSCC primary water stress corrosion cracking