Letter Sequence Other |
|---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance...
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML110620203, ML11140A163, ML11172A096, ML11224A265, ML11230A003, ML11305A075, ML11318A121, ML11318A122, ML11318A123, ML11318A124, ML11318A125, ML11318A126, ML11318A127, ML11318A128, ML11318A129, ML11318A130, ML11318A131, ML11318A132, ML11318A133, ML11318A135, ML11318A136, ML11318A138, ML11318A139, ML11318A140, ML11318A141, ML11318A142, ML11318A143, ML11318A144, ML11318A145, ML11318A146, ML11318A147, ML11318A148, ML11318A149, ML11318A150, ML11318A151, ML11318A152, ML11318A153, ML11318A154, ML11318A155, ML11318A156, ML11318A157, ML11318A158, ML11318A159, ML11318A160, ML11318A161, ML11318A162, ML11318A163, ML11318A164, ML11318A165, ML11318A166... further results
|
MONTHYEARML1106202032011-03-17017 March 2011 License Renewal Application Online Reference Portal Project stage: Other ML1108309782011-04-14014 April 2011 Request for Additional Information for the Review of the South Texas Project, License Renewal Application, Fire Protection and Component Integrity (TAC Nos. ME4536 ME4637 Project stage: RAI ML1108907642011-04-14014 April 2011 Request for Additional Information for the Review of the South Texas Project, License Renewal Application-Electrical Branch Scoping Project stage: RAI ML1108205792011-04-14014 April 2011 Request for Additional Information for the Review of the South Texas Project, License Renewal Application -Section 2.4 Structural Project stage: RAI ML1112501472011-05-0505 May 2011 Notice of Withdrawal of Megan Wright in the Matter of South Texas Project, Units 1 and 2 Project stage: Request ML11130A0262011-05-0505 May 2011 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI ML11145A0902011-05-12012 May 2011 Response to Request for Additional Information for Licence Renewal Application Project stage: Response to RAI ML11137A0922011-05-24024 May 2011 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application Future Consideration of Operating Experience Project stage: RAI ML11140A1632011-06-0606 June 2011 Plan for the Aging Management Program Regulatory Audit Regarding the South Texas Project, Units 1 and 2 License Renewal Application Review Project stage: Other ML11172A0962011-06-16016 June 2011 Amendment 2 to the License Renewal Application Project stage: Other NOC-AE-11002681, Amendment 2 to the License Renewal Application2011-06-16016 June 2011 Amendment 2 to the License Renewal Application Project stage: Other ML11181A0372011-06-23023 June 2011 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI NOC-AE-11002683, Response to Request for Additional Information for License Renewal Application (TAC Nos. ME4936 and ME4937)2011-06-23023 June 2011 Response to Request for Additional Information for License Renewal Application (TAC Nos. ME4936 and ME4937) Project stage: Response to RAI ML11154A0132011-07-0606 July 2011 Summary of Telephone Conference Call Held on May 23, 2011, Between the NRC and STPNOC, Concerning Requests for Additional Information Pertaining to the South Texas Project, LRA-Future Consideration of Operating Experience Project stage: RAI ML11166A2392011-07-12012 July 2011 Letter Request for Additional Information for South Texas Project Electric Generating Station, Units 1 and 2 License Renewal Application - Scoping and Screening Balance of Plant Project stage: RAI ML11201A0552011-07-28028 July 2011 Requests for Additional Information for the Review of the South Texas Project, License Renewal Application - Scoping and Screening Audit Project stage: RAI NOC-AE-11002702, Response to Request for Additional Information for the Review of the South Texas Project License Renewal Application2011-08-0909 August 2011 Response to Request for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: Response to RAI ML11234A0452011-08-0909 August 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application Project stage: Response to RAI ML11245A1012011-08-0909 August 2011 Response to Request for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: Response to RAI ML11214A0052011-08-15015 August 2011 Requests for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application - Aging Management Programs Audit, Structures/Electrical Project stage: RAI ML11214A0272011-08-15015 August 2011 Requests for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application - Aging Management Programs Audit, Reactor Systems Project stage: RAI ML11214A0882011-08-15015 August 2011 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application - Aging Management Programs Audit, Plant Systems Project stage: RAI ML11238A0712011-08-18018 August 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application Project stage: Response to RAI ML1123000162011-08-18018 August 2011 License Renewal - Errata in AMP RAI Package Project stage: RAI NOC-AE-11002716, Response to Request for Additional Information for the South Texas Project License Renewal Application (TAC ME4936 and ME4937)2011-08-18018 August 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application (TAC ME4936 and ME4937) Project stage: Response to RAI ML11238A0722011-08-23023 August 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application Project stage: Response to RAI NOC-AE-11002714, Response to Request for Additional Information for the South Texas Project License Renewal Application (TAC ME4936 and ME4937)2011-08-23023 August 2011 Response to Request for Additional Information for the South Texas Project License Renewal Application (TAC ME4936 and ME4937) Project stage: Response to RAI ML11230A0032011-09-0606 September 2011 Scoping and Screening Audit Report Regarding the South Texas Project, Units 1 and 2 Project stage: Other ML11266A0192011-09-15015 September 2011 Response to Request for Additional Information for License Renewal Application Project stage: Response to RAI ML11266A0202011-09-15015 September 2011 Response to Requests for Additional Information for License Renewal Application Project stage: Response to RAI NOC-AE-11002731, Response to Requests for Additional Information for License Renewal Application (TAC Nos. ME4936 and ME4937)2011-09-15015 September 2011 Response to Requests for Additional Information for License Renewal Application (TAC Nos. ME4936 and ME4937) Project stage: Response to RAI NOC-AE-11002730, Response to Request for Additional Information for License Renewal Application (TAC Nos. ME4936 and ME4937)2011-09-15015 September 2011 Response to Request for Additional Information for License Renewal Application (TAC Nos. ME4936 and ME4937) Project stage: Response to RAI ML1124402012011-09-21021 September 2011 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application - Aging Management Review, Set 2 Project stage: RAI ML11250A0432011-09-22022 September 2011 Requests for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application - Aging Management Review, Set 1 Project stage: RAI ML11224A2652011-09-22022 September 2011 Aging Management Programs Audit Report Regarding the South Texas Project, Units 1 and 2, Station License Renewal Application Project stage: Other ML11258A1612011-09-22022 September 2011 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application - Aging Management Review, Set 3 Project stage: RAI ML11272A1652011-10-0404 October 2011 Summary of Telephone Conference Call Held on September 28, 2011, Between the NRC and STP Nuclear Operating Company, Concerning Request for Additional Information Pertaining to the South Texas Project, LRA Project stage: RAI ML11291A1522011-10-10010 October 2011 Response to Requests for Additional Information for the License Renewal Application Project stage: Response to RAI NOC-AE-11002732, Response to Requests for Additional Information for the License Renewal Application2011-10-10010 October 2011 Response to Requests for Additional Information for the License Renewal Application Project stage: Response to RAI ML11291A1202011-10-10010 October 2011 10CFR50.59 Summary Report Project stage: Request ML11273A0172011-10-11011 October 2011 Requests for Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application - Aging Management Review, Set 5 Project stage: RAI ML11273A0082011-10-11011 October 2011 Requests for Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application - Aging Management Review, Set 4 Project stage: RAI ML11277A0472011-10-18018 October 2011 Requests for Additional Information for the Review of the South Texas Project, Units 1 and 2, License Renewal Application - Aging Management Program, Set 6 Project stage: RAI NOC-AE-11002737, Supplement to License Renewal Application (TAC Nos. ME4936 and ME4937)2011-10-18018 October 2011 Supplement to License Renewal Application (TAC Nos. ME4936 and ME4937) Project stage: Supplement ML11298A0822011-10-18018 October 2011 Supplement to License Renewal Application Project stage: Supplement ML11305A0762011-10-25025 October 2011 Response to Requests for Additional Information for License Renewal Application Project stage: Response to RAI NOC-AE-11002756, Contact Information Change, License Renewal Application (TAC ME4936 and ME4937)2011-10-26026 October 2011 Contact Information Change, License Renewal Application (TAC ME4936 and ME4937) Project stage: Other ML11305A0752011-10-26026 October 2011 Contact Information Change, License Renewal Application Project stage: Other ML11318A1772011-11-0303 November 2011 Drawing No. LR-STP-WL-7R309F90001 1, Rev. 1, Piping and Instrumentation Diagram Liquid Waste Processing System Project stage: Other ML11318A1722011-11-0303 November 2011 Drawing No. LR-STP-WL-5R309F05022 2, Rev. 1, Piping and Instrumentation Diagram Liquid Waste Processing System Project stage: Other 2011-06-16
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 16, 2012 Mr. D.W. Rencurrel Vice President, Technical Support and Oversight STP Nuclear Operating Company PO Box 289 Wadsworth, TX 77483
SUBJECT:
PLAN FOR THE ALUMINUM-BRONZE AGING MANAGEMENT PROGRAM REGULATORY AUDIT REGARDING THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW (TAC NOS. ME4936 AND ME4937)
Dear Mr. Rencurrel' By ietter dated October 25, 2010, STP Nuclear Operating Company (STPNOC or the applicant) submitted an application for renewal of operating licenses NPF-76 and NPF-80 for South Texas Project (STP), Units 1 and 2. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, "Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants."
The staff plans to conduct a followup regulatory audit of your aluminum-bronze aging management program and associated issues at a RockvIlle, MD, location to be provided by STPNOC, on February 29, 2012. in accordance with the enclosed regulatory audit plan. If you have any questions, please contact me by telephone at 301-415-3873 or bye-mail at
&hn.daiIY@'1rc.gov.
lation Docket Nes 50-498 and 50-499
Enclosure:
As stated cc w/encL Ltstserv
Audit Plan Followup Audit on Aluminum-Bronze Aging Management Program for the South Texas Project, Units 1 and 2 License Renewal Application February 29,2012 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ENCLOSURE
- 2 License Renewal Aging Management Program Audit Plan South Texas Project
1. Background
By letter dated October 25, 2010, STP Nuclear Operating Company (STPNOC or the applicant),
submitted to the U.S. Nuclear Regulatory Commission (NRC or the staff) its application for renewal of Operating License Nos. NPF-76 and NPF-80 for South Texas Project (STP), Units 1 and 2, respectively. The applicant requested renewal of the operating licenses for an additional 20 years beyond the 40-year current license terms, which expires on August 20, 2027, for Unit 1 and December 15, 2028, for Unit 2. The staff from the Division of License Renewal will lead a followup regulatory audit to gain a better understanding of the applicant's Aging Management Program (AMP) B2.1.37, "Selective leaching of Aluminum Bronze" (aluminum bronze AMP) and associated aging management reviews, bases, and documentation as applicable.
- 2. Regulatory Audit Bases License renewal requirements are specified in Title 10 of the Code of Federal Regulations (10 CFR), Part 54 (10 CFR Part 54), "Requirements for Renewal of Operating Licenses for Nuclear Power Plants." Guidance is provided in NUREG-1800, Revision 2, "Standard Review Plan for Review of license Renewal Applications for Nuclear Power Plants" (SRP-lR), dated December 2010, and in NUREG-1801, Revision 2, "Generic Aging lessons learned (GAll)
Report," dated December 2010.
- 3. Regulatory Audit Scope and Methodology The scope of this audit is to: (a) examine the applicant's aluminum bronze AMP and supporting documentation for STP Units 1 and 2; and (b) determine the level of consistency with corresponding GAll program(s) and aging management review(s) (AMRs). As this program is a plant-specific AMP, it is evaluated on an individual basis for all 10 program elements, along with any associated issues. While portions of this review have been completed by the staff, this followup audit will examine issues as needed in order for the staff to complete its review.
Results of this audit will be ultimately documented in the staff's safety evaluation report (SER).
The SRP-lR allows an applicant's license renewal application (lRA) to declare its AMPs as being consistent with the AMPs described in the GAll Report. An applicant can also choose to establish one or more plant-specific AMPs. For a plant-specific AMP, it is incumbent on the applicant to ensure that the plant program contains appropriate descriptions and bases for all 10 elements of an aging management program, in accordance with Branch Technical Position RlSB-1 in the SRP-lR, Appendix A 1. The applicant's evaluations and bases for this program shall be documented and maintained in an auditable, retrievable form.
During this audit, the staff will utilize the following Scope and Agenda as a guide. The staff will also examine the applicant's program basis documents and related references for this AMP, review background calculations and evaluations as needed, and interview applicant representatives to obtain additional clarification related to the AMP.
- 3 SCOPE AND AGENDA
- 1. Entrance, introduction of personnel, review overall purpose of meeting
- 2. Overview of current aluminum bronze management programs, operating experience, repair and replacement activities, inservice inspection results, and current status of components (by Applicant)
- 3. Review the methodology, inputs, assumptions, and conclusions for the flaw calculations that demonstrate structural integrity of welded joints and large castings affected by selective leaching, with an emphasis on:
- a. modeling of flaw dimensions and orientation, crack growth, and crack stability
- b. how material properties were obtained
- c. Acceptance criteria in STP calculations versus ASME Sections III and XI requirements
- 4. Review and discuss (this could be a breakout session if needed), with technical personnel, the metallurgical factors which appear to cause the observed selective leaching to be associated with weld heat affected zones. This discussion should include cracking in aluminum bronze throttle valve(s) as described in LER 499/2005 004. The staff is also interested in any micrographs of heat affected zones (both cracked and uncracked) and of selective leaching/cracked areas.
- 5. Review the latest results of sectioned material specimens removed from the plant including having pictures available at the meeting
- 6. Review the aging management strategy for buried pipe welds where there could be multiple leak sites that have not yet been identified
- 7. Review adequacy of the number and timing of destructive examinations in relation to confirming degree of selective leaching prior to and during the period of extended operation
- 8. Align on what documents need to be provided on the docket and general outline of followup RAI questions 9, Exit and wrap-up
- 4. Information and Other Material Necessary for the Regulatory Audit The project team will review the LRA, the AMPs, the AMP basis documents, and other applicant supporting documentation as appropriate. The project team would like for at least one hard copy set of the aluminum bronze AMP, AMP basis documents, condition reports that are related to degradation of the aluminum bronze components, documents on repair/replacement of the subject components, flaw evaluation reports, and all other supporting background documentation (including but not limited to items such as calculations, engineering evaluations, 10 CFR 50.59 evaluations, and so on) to be available in the team's work room.
-4
- 5. Special Requests The staff emphasizes that, for a successful outcome, the applicant should make every effort to have available at the audit site: (a) copies of relevant materials; (b) management; and (c) technical personnel and expertise knowledgeable in aluminum bronze issues; so as to minimize the need for the applicant to contact the site, realizing that some contact, of course, may be necessary.
- 6. Team Assignments NRC Staff participation is projected as follows (some deletions, additions or substitutions may occur on an as-needed basis):
Area ofReview ASSigned Auditor Project Manager John Daily Branch Chief Dennis Morey Technical Lead William Holston Technical Reviewer David Alley Technical Reviewer John Wise Technical Reviewer John Tsao Technical Reviewer Robert Hardies
- 7. Logistics The audit will be conducted at a location near NRC HQ in Rockville, MD, at a place to be supplied by STPNOC. The deSignated location is NPOC Office (NEI), Suite 230, 11426 Rockville Pike (above the Chili's Restaurant), Rockville, MD 20852. A map is attached below.
Work space and team support logistics:
- Audit timeframe: 8:00 AM - 3:30 PM.
- One general team work area with seating and laptop space for up to 10 people.
- One break-out room for question/answer/small group sessions and meetings, so that work in the main room will not be disrupted.
- Telephone access for outside business-related calls. The break-out rooms should also have speaker phone capability for conference calls. External internet access as applicable.
- Access to printers for printing out drafts, draft requests for additional information (RAls),
review comments, schedules, and so on.
- Access to a copier for making duplicates for team use, meeting agendas.
- 8. Deliverables RAI(s) may be issued as deemed necessary by the staff.
An audit summary report will be issued to the applicant, normally within 90 days from the end of the audit. Final evaluation of the aluminum bronze AMP and related issues will be presented in the staffs SER for the STP license renewal application.
'.. ML12039a054
- concurrence via email OFFICE LA: RPB1 :DLR*
PM: DLR/RPB1 BC: DLR/RPB1 PM: DLR/RPB1 NAME YEdmonds JDaily DMorey JDaily/DMorey for DATE 02/1512012 02/16/2012 2116/2012 02/1612012
Letter to D.W. Rencurrel from John W. Daily dated February 16, 2012
SUBJECT:
PLAN FOR THE ALUMINUM-BRONZE AGING MANAGEMENT PROGRAM REGULATORY AUDIT REGARDING THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW (TAC NOS. ME4936 AND ME4937)
DISTRIBUTION:
HARDCOPY:
DLR R/F E-MAIL:
PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRpb2 Resource RidsNrrDlrRerb Resource RidsNrrDlrRpob Resource RidsOgcMailCenter JDaily TTran DMclntyre,OPA BSingal, DORL WWalker, RIV JDixon, RIV BTharakan, RIV WMaier, RIV VDricks, RIV NO'Keefe, RIV GPick, RIV