|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21025A1752021-01-26026 January 2021 License Amendment Request to Adopt TSTF-505 - Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Pre-Application Meeting, January 26, 2021 (Slides) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML19298A9552019-10-29029 October 2019 License Amendment Request for a Revision to the Dose Consequence Analysis for a Loss of Coolant Accident - Pre-Application Meeting, October 29, 2019 ML19165A0062019-06-18018 June 2019 (SSES) License Amendment Request for Proposed Changes to Emergency Response Organization Staffing Augmentation. Pre-Submittal Call Meeting June 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML19099A0162019-04-0909 April 2019 Pre-application Meeting for Framatome Fuel - Slide ML18305B0582018-11-0505 November 2018 Emergency Service Water Piping Replacement LAR - NRC Pre-Application Meeting ML18129A4242018-05-10010 May 2018 Advanced Framatome Methods LAR - NRC Pre-Application Meeting ML15264A6872015-09-21021 September 2015 SSES Slide Presentation in Support of 9/23 Public Meeting EAL Scheme Change LAR ML14182A3222014-06-10010 June 2014 Presentation in Support of PPL Meeting with NRC Staff License Transfer Pre-Application Meeting to Be Held July 2, 2014 ML14100A3712014-04-0909 April 2014 Susq 2014 Aam Slides ML13107B1962013-04-10010 April 2013 Slide Presentation for Susquehanna 2012 EOC Annual Assessment Meeting, on April 10, 2013 ML12296A6702012-10-16016 October 2012 SCCI Public Meeting - Slides, 10-16-12 ML12089A4302012-03-21021 March 2012 Aam 95002 Slide Presentation ML12089A1342012-03-21021 March 2012 Annual Assessment Meeting NRC Slide Presentation ML1014500762010-05-25025 May 2010 Susq NRC Slides for Aam, April 27, 2010 ML1014503572010-05-25025 May 2010 PPL Slides for Susquehanna Annual Assessment Meeting, April 27, 2010 ML0919402082009-07-13013 July 2009 PPL Slides for Susquehanna SCWE Public Mtg July 6, 2009 ML0919401892009-07-0606 July 2009 Meeting Slides, NRC Susquehanna Safety Conscious Work Environment (SCWE Public Meeting ML0913906312009-06-0404 June 2009 ACRS Meeting with the U.S. Nuclear Regulatory Commission, - June 4, 2009, Slides ML0900903402009-01-26026 January 2009 Transmittal of Summary of Telephone Conference Call Held on January 5, 2009, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, Llc. Concerning the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Applicat ML0828807292008-05-31031 May 2008 Draft Comprehensive Plan for the Water Resources of the Susquehanna River Basin ML0915201302008-05-19019 May 2008 Annual Assessment Meeting Slides for 5/19/09, 2008 Reactor Oversight Process ML0808103392008-03-18018 March 2008 Meeting on March 18, 2008 (NON-Proprietary Version) Presentation (Tac No. MD8099) ML0725600652007-08-10010 August 2007 Susquehanna Meeting Presentation, ATWS and Stability Implementation ML0719802842007-07-19019 July 2007 Meeting Slides for Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Asension Test Plans ML0717104272007-06-13013 June 2007 Summary of June 13, 2007, Category 1 Working -Level Meeting with PPL to Discuss the Licensee'S Proposed License Amendment Request Regarding Electrical Distribution Systems Dated March 2, 2007 ADAMS Accession No. ML070720545 ML0733409182007-05-31031 May 2007 05/31/2007 Presentation by J. Cudsworth NRC Treatment of Issues Other than Category 2 Issues for License Renewal ML0715101782007-05-30030 May 2007 Attachment 2 to PLA-6211, Steam Dryer Replacement, NRC Meeting ML0714401792007-04-24024 April 2007 EOC 2006 Meeting Slides (PPL) ML0714401562007-04-24024 April 2007 EOC Meeting Slides (NRC) on NRC Annual Performance Assessment of Susquehanna Steam Electric Station - 2006 Reactor Oversight Program ML0703804702006-11-15015 November 2006 License Renewal Scoping Meeting Handouts: Public Input by Sue Fracke ML0609602842006-04-0606 April 2006 Public Meeting, Susquehanna, Slides on Reactor Oversight Program - Cy 2005 ML0602602402006-01-19019 January 2006 Enclosure 2 - Meeting Handouts from 1/19/06 Meeting with PPL Susquehanna, LLC to Discuss an Impending Exemption Request to CoC 72-1004 ML0536201842005-11-21021 November 2005 NRC-PPL Extended Power Uprate Pre-Submittal Meetings. Start-Up Testing/Large Transient Testing Process Topics ML0514403502005-04-0606 April 2005 NRC Annual Assessment Meeting, PPL Susquehanna LLC Team (PPL Slides) ML0513704462005-04-0606 April 2005 Annual Assessment Meeting Notice, Slides ML0315307242003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F4 - Hubert J. Miller - Region I Breakout ML0314906962003-04-16016 April 2003 April 16, 2003 - RIC 2003 Presentation - W8 - Bryce L. Shriver - Safety Management - Promoting Safety Culture to Achieve Safe Performance ML0210903772002-04-16016 April 2002 NRC - Region I Susquehanna Steam Electric Station Annual Assessment Meeting Slides ML18025A2921975-08-25025 August 1975 Letter Attaching the Outline of the BWR Mark II Containment Supporting Program ML17037B8491975-08-23023 August 1975 08/21/1975 Summary of Meeting with Mark II Owners, Sargent & Lundy, Bechtel, Stone & Webster, Burns & Roe, and the NRC Staff to Discuss Load Factors and Load Combinations Proposed by the Mark II Owners and Their Architect ... 2023-06-06
[Table view] Category:Slides and Viewgraphs
MONTHYEARML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21025A1752021-01-26026 January 2021 License Amendment Request to Adopt TSTF-505 - Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Pre-Application Meeting, January 26, 2021 (Slides) ML20163A6542020-06-18018 June 2020 2020 NRC Annual Assessment Webinar Presentation - Pennsylvania and Maryland Facilities (Beaver Valley, Calvert Cliffs, Limerick, Peach Bottom, Susquehanna) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20058B1672020-02-27027 February 2020 Talen Energy Presentation Slides Susquehanna Steam Electric Station Pre-Application Meeting of February 27, 2020 License Amendment Request to Create an Action for an Inoperable Manual Synchronization Circuit ML19165A0062019-06-18018 June 2019 (SSES) License Amendment Request for Proposed Changes to Emergency Response Organization Staffing Augmentation. Pre-Submittal Call Meeting June 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML15264A6872015-09-21021 September 2015 SSES Slide Presentation in Support of 9/23 Public Meeting EAL Scheme Change LAR ML14247A2612014-09-0303 September 2014 NRC Slides for 95002 Presentation for Susquehanna & PPL Public Meeting ML14182A3222014-06-10010 June 2014 Presentation in Support of PPL Meeting with NRC Staff License Transfer Pre-Application Meeting to Be Held July 2, 2014 ML14100A3712014-04-0909 April 2014 Susq 2014 Aam Slides ML13107B1962013-04-10010 April 2013 Slide Presentation for Susquehanna 2012 EOC Annual Assessment Meeting, on April 10, 2013 ML12296A6702012-10-16016 October 2012 SCCI Public Meeting - Slides, 10-16-12 ML12089A4302012-03-21021 March 2012 Aam 95002 Slide Presentation ML12089A1342012-03-21021 March 2012 Annual Assessment Meeting NRC Slide Presentation ML1114407092011-05-19019 May 2011 Aam Slides, May 19, 2011, 2010 Reactor Oversight Process ML1014503572010-05-25025 May 2010 PPL Slides for Susquehanna Annual Assessment Meeting, April 27, 2010 ML1014500762010-05-25025 May 2010 Susq NRC Slides for Aam, April 27, 2010 ML0919402082009-07-13013 July 2009 PPL Slides for Susquehanna SCWE Public Mtg July 6, 2009 ML0919401892009-07-0606 July 2009 Meeting Slides, NRC Susquehanna Safety Conscious Work Environment (SCWE Public Meeting ML0913906312009-06-0404 June 2009 ACRS Meeting with the U.S. Nuclear Regulatory Commission, - June 4, 2009, Slides ML0828807292008-05-31031 May 2008 Draft Comprehensive Plan for the Water Resources of the Susquehanna River Basin ML0915201302008-05-19019 May 2008 Annual Assessment Meeting Slides for 5/19/09, 2008 Reactor Oversight Process ML0811206272008-04-16016 April 2008 SSES 2007 ROP Slides ML0808103392008-03-18018 March 2008 Meeting on March 18, 2008 (NON-Proprietary Version) Presentation (Tac No. MD8099) ML0719802842007-07-19019 July 2007 Meeting Slides for Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Asension Test Plans ML0733409182007-05-31031 May 2007 05/31/2007 Presentation by J. Cudsworth NRC Treatment of Issues Other than Category 2 Issues for License Renewal ML0715101782007-05-30030 May 2007 Attachment 2 to PLA-6211, Steam Dryer Replacement, NRC Meeting ML0714401562007-04-24024 April 2007 EOC Meeting Slides (NRC) on NRC Annual Performance Assessment of Susquehanna Steam Electric Station - 2006 Reactor Oversight Program ML0714401792007-04-24024 April 2007 EOC 2006 Meeting Slides (PPL) ML0632401502006-11-15015 November 2006 11/15/06 Environmental Scoping Meeting Slide Handouts ML0631701532006-11-0606 November 2006 Meeting Slides ML0611100212006-04-12012 April 2006 NRC Annual Assessment Meeting, PPL Susquehanna Slides ML0609602842006-04-0606 April 2006 Public Meeting, Susquehanna, Slides on Reactor Oversight Program - Cy 2005 ML0534604562005-12-0808 December 2005 Update on Control Cell Friction ML0536201842005-11-21021 November 2005 NRC-PPL Extended Power Uprate Pre-Submittal Meetings. Start-Up Testing/Large Transient Testing Process Topics ML0536201932005-11-15015 November 2005 NRC Extended Power Uprate Pre-Submittal Meeting, Susquehanna, Flow Induced Vibration Evaluation & Reactor Pressure Vessel Steam Dryer Analysis ML0514403502005-04-0606 April 2005 NRC Annual Assessment Meeting, PPL Susquehanna LLC Team (PPL Slides) ML0513704462005-04-0606 April 2005 Annual Assessment Meeting Notice, Slides ML0411906342004-04-27027 April 2004 NRC Region I Slides for the Susquehanna Annual Assessment Meeting with NRC Re Reactor Oversight Program - Cy 2003 ML0412100952004-04-27027 April 2004 PPL Susquehanna, LLC Slides for the Annual Assessment Meeting ML0315307242003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F4 - Hubert J. Miller - Region I Breakout ML0314906962003-04-16016 April 2003 April 16, 2003 - RIC 2003 Presentation - W8 - Bryce L. Shriver - Safety Management - Promoting Safety Culture to Achieve Safe Performance ML0310400692003-03-31031 March 2003 Susquehanna Annual Assessment Meeting Slides for Region I and PPL Susquehanna, LLC ML0210903912002-04-16016 April 2002 PPL Susquehanna, LLC Annual Assessment Meeting Slides 2023-06-06
[Table view] |
Text
Susquehanna Annual Assessment Meeting 2008 Reactor Oversight Process Nuclear Regulatory Commission - Region I
Purpose of Todays Meeting
- Discuss Susquehanna Steam Electric Station performance for 2008
- Provide PPL the opportunity to respond to the NRCs annual performance assessment and discuss its actions to maintain or improve performance
- Provide stakeholders the opportunity to ask the NRC staff questions about Susquehanna plant performance and our role in ensuring safe plant operations 2
Agenda
- NRC Organization and Performance Goals
- Reactor Oversight Process (ROP)
- National Summary of Plant Performance
- Susquehanna Plant Performance Assessment
- NRC available to address public questions 3
Region I Organization Samuel J. Collins Regional Administrator Marc L. Dapas Deputy Regional Administrator Division of Reactor Safety Division of Reactor Projects Division of Nuclear Materials Safety Darrell J. Roberts, Director David C. Lew, Director John D. Kinneman, Director Peter Wilson, Acting Deputy Director James W. Clifford, Deputy Director Daniel S. Collins, Deputy Director Paul G. Krohn Regional Specialists Regional Specialists Branch 4 Chief Project Engineers Susquehanna Resident Inspection Staff Andrew Rosebrook, Senior Project Engineer Roy L. Fuhrmeister, Senior Project Engineer Frederick W. Jaxheimer Senior Resident Inspector Jeffrey Bream, Project Engineer Patrick Finney, Resident Inspector Edgardo Torres, Project Engineer 4
NRC Strategic Plan Goals
- Safety: Ensure adequate protection of public health and safety and the environment
- Security: Ensure adequate protection in the secure use and management of radioactive materials 5
NRC Regulatory Functions What We Regulate
- Commercial power, research, test, and new reactor designs
- Reactor fuel, radioactive material for medical, industrial, and academic uses
- Transportation, storage, disposal, and facility decommissioning
- Facility physical security 6
Reactor Oversight Process 3 Strategic Areas & 7 Cornerstones Reactor Radiation Safeguards Safety Safety Public Occupational Initiating Mitigating Barrier Emergency Physical Radiation Radiation Events Systems Integrity Preparedness Protection Safety Safety 7
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix Regulatory Response 8
Examples of Baseline Inspection Areas
- Corrective Action Program
NRC Performance Indicators
- Security PIs are not Publicly Available 10
Significance Threshold Performance Indicators Green Baseline Inspection White Requires additional NRC oversight Yellow Requires more NRC oversight Red Requires most NRC oversight Inspection Findings Green Very low safety issue White Low to moderate safety issue Yellow Substantial safety issue Red High safety issue 11
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone
- Increasing Safety Significance
- Increasing NRC Inspection Efforts
- Increasing NRC/Licensee Management Involvement
- Increasing Regulatory Actions 12
National Summary of Plant Performance (at end of 2008)
Licensee Response 86 Regulatory Response 14 Degraded Cornerstone 3 Multiple/Repetitive Degraded Cornerstone 1 Unacceptable 0 Total 104 13
National Summary of Plant Performance (at end of 2008)
Performance Indicator Results Green 1762 White 6 Yellow 0 Red 0 Total Inspection Findings Green 776 White 17 Yellow 0 Red 0 14
NRC Inspection Activities at Susquehanna (for 2008)
- 6400 hours0.0741 days <br />1.778 hours <br />0.0106 weeks <br />0.00244 months <br /> of inspection and related activities
- 2 resident inspectors on-site
- 4 major team inspections:
Problem Identification & Resolution License Renewal Physical Security Area Team EP Exercise Evaluation 15
Susquehanna PIs / Findings (January 1 - December 31, 2008)
- All Green Performance Indicators
- 9 Green Non-Cited Violations (NCV)
- 1 SL IV Traditional Enforcement NCV
- Overall Susquehanna was operated safely in 2008.
16
NRC Inspection Findings Susquehanna
- Ineffective Evaluation and Incorporation of Operating Experience (OE) into the Corrective Action Program (CAP)
- SQ received and entered OE regarding control of field work for nitrogen freeze seals into the CAP
- PPL determined no changes were needed to the procedures and the information was not communicated to the workers.
- Result was an oxygen deficient atmosphere in a plant vital area, declaration of an Alert, and unplanned unavailablity of safety related equipment.
17
Susquehanna Potential Chilling Effect Letter
- The NRC issued a Potential Chilling Effect Letter (CEL) to Susquehanna on Jan. 28, 2009, regarding the Safety Conscious Work Environment (SCWE) at the site.
- The NRC expressed concern with the progress and effectiveness of PPL actions during 2008 to address indications of a declining SCWE and negative employee perceptions, because it may impact employee willingness to raise safety concerns and lead to a chilling effect at the site.
18
What is SCWE?
- A work environment where employees are encouraged to raise safety concerns without fear of retaliation and where concerns are promptly reviewed, given the proper priority based on their potential safety significance, and appropriately resolved with timely feedback to the originator of the concerns and to other employees.
19
NRC Actions to Date
- Office of Investigations assist visit.
- Interviews and focus groups with Susquehanna staff.
- Several PI&R sample inspections
- Issued Chilling Effect Letter Jan. 28, 2009
- Focused baseline inspections and NRC Management visits during 2009.
20
Licensee Response and Remarks William Spence Chief Operating Officer PPL 21
NRC Annual Assessment Summary Susquehanna
- PPL operated the plant safely and in a manner that preserved public health and safety and protected the environment
- Susquehanna was in the Licensee Response column of the NRCs Action Matrix for all of 2008
- All cornerstone objectives were fully met
- NRC plans baseline inspections at Susquehanna for the remainder of 2009 22
Contacting the NRC
(800) 695-7403 Allegation@nrc.gov
- General information or questions:
www.nrc.gov Public Affairs Officers:
Diane Screnci 610-337-5330 Neil Sheehan 610-337-5331 23
NRC Representatives
- David C. Lew, Division Director, DRP 610-337-5229
- Paul G. Krohn, Branch Chief 610-337-5120
- Frederick Jaxheimer, Senior Resident Inspector 570-542-2134
- Roy L. Fuhrmeister, Senior Project Engineer 610-337-5059 24
Reference Sources
- Reactor Oversight Process
- Public Document Room 1-800-397-4209 (Toll Free) 25
End of the Presentation Nuclear Regulatory Commission Region I King of Prussia, Pennsylvania May 19, 2009