Susquehanna Steam Electric Station Pre-Application Meeting January 26, 2021 License Amendment Request to Adopt TSTF-505 Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b
Meeting Purpose
- Describe a future license amendment request
- Scope of Request
- Variations from TSTF-505
- Schedule
© Talen Energy 2
Scope of Amendment
- TSTF-505, Revision 2
- Applicable in Modes 1 and 2
- No Loss of Function Actions
© Talen Energy 3
Variations
- Propose to include TS 3.3.2.1 in RICT Program
- Administrative Changes
© Talen Energy 4
TS 3.3.2.1 - Control Rod Block Inst.
- Propose to include Condition A in scope
- Generically excluded per criterion 11
- Conservative surrogate identified
© Talen Energy 5
CONDITION REQUIRED ACTION COMPLETION TIME A. One rod block monitor (RBM) channel inoperable.
A.1 Restore RBM channel to OPERABLE status.
24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />
PRA Technical Adequacy
- Internal Events, Fire, and Flooding Models
- RG 1.200, Revision 2 Peer Review
- Appendix X F&O Closure Review
- 13 F&O Findings remain open
- Internal Events - 1
- Fire - 12
© Talen Energy 6
PRA Technical Adequacy (cont.)
- Seismic
- No Seismic PRA Model
- Seismic penalty will be applied to all RICTs
- Additional LERF penalties will be applied when containment is de-inerted
- Other external hazards
- All other external hazards screen out
© Talen Energy 7
Real-Time Risk Model
- Similar to Maintenance Rule (a)(4) CRMP
- Incorporates RICT/RMAT calculation features
- Incorporates seismic penalty factor
© Talen Energy 8
Schedule
- Submit by end of March 2021
- Requested issuance in April 2022
- Requested implementation period of 180 days and no earlier than August 31, 2022
© Talen Energy 9
List of Acronyms CRMP Configuration Risk Management Program F&O Fact and Observation LCO Limiting Condition for Operation LERF Large Early Release Frequency PRA Probabilistic Risk Assessment RA Required Action RG Regulatory Guide RICT Risk Informed Completion Time RITSTF Risk-Informed Technical Specifications Task Force RMAT Risk Management Action Time SSES Susquehanna Steam Electric Station TS Technical Specifications TSTF Technical Specifications Task Force