MONTHYEARML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21025A1752021-01-26026 January 2021 License Amendment Request to Adopt TSTF-505 - Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Pre-Application Meeting, January 26, 2021 (Slides) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML19298A9552019-10-29029 October 2019 License Amendment Request for a Revision to the Dose Consequence Analysis for a Loss of Coolant Accident - Pre-Application Meeting, October 29, 2019 ML19165A0062019-06-18018 June 2019 (SSES) License Amendment Request for Proposed Changes to Emergency Response Organization Staffing Augmentation. Pre-Submittal Call Meeting June 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML19099A0162019-04-0909 April 2019 Pre-application Meeting for Framatome Fuel - Slide ML18305B0582018-11-0505 November 2018 Emergency Service Water Piping Replacement LAR - NRC Pre-Application Meeting ML18129A4242018-05-10010 May 2018 Advanced Framatome Methods LAR - NRC Pre-Application Meeting ML15264A6872015-09-21021 September 2015 SSES Slide Presentation in Support of 9/23 Public Meeting EAL Scheme Change LAR ML14182A3222014-06-10010 June 2014 Presentation in Support of PPL Meeting with NRC Staff License Transfer Pre-Application Meeting to Be Held July 2, 2014 ML14100A3712014-04-0909 April 2014 Susq 2014 Aam Slides ML13107B1962013-04-10010 April 2013 Slide Presentation for Susquehanna 2012 EOC Annual Assessment Meeting, on April 10, 2013 ML12296A6702012-10-16016 October 2012 SCCI Public Meeting - Slides, 10-16-12 ML12089A4302012-03-21021 March 2012 Aam 95002 Slide Presentation ML12089A1342012-03-21021 March 2012 Annual Assessment Meeting NRC Slide Presentation ML1014500762010-05-25025 May 2010 Susq NRC Slides for Aam, April 27, 2010 ML1014503572010-05-25025 May 2010 PPL Slides for Susquehanna Annual Assessment Meeting, April 27, 2010 ML0919402082009-07-13013 July 2009 PPL Slides for Susquehanna SCWE Public Mtg July 6, 2009 ML0919401892009-07-0606 July 2009 Meeting Slides, NRC Susquehanna Safety Conscious Work Environment (SCWE Public Meeting ML0913906312009-06-0404 June 2009 ACRS Meeting with the U.S. Nuclear Regulatory Commission, - June 4, 2009, Slides ML0900903402009-01-26026 January 2009 Transmittal of Summary of Telephone Conference Call Held on January 5, 2009, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, Llc. Concerning the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Applicat ML0828807292008-05-31031 May 2008 Draft Comprehensive Plan for the Water Resources of the Susquehanna River Basin ML0915201302008-05-19019 May 2008 Annual Assessment Meeting Slides for 5/19/09, 2008 Reactor Oversight Process ML0808103392008-03-18018 March 2008 Meeting on March 18, 2008 (NON-Proprietary Version) Presentation (Tac No. MD8099) ML0725600652007-08-10010 August 2007 Susquehanna Meeting Presentation, ATWS and Stability Implementation ML0719802842007-07-19019 July 2007 Meeting Slides for Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Asension Test Plans ML0717104272007-06-13013 June 2007 Summary of June 13, 2007, Category 1 Working -Level Meeting with PPL to Discuss the Licensee'S Proposed License Amendment Request Regarding Electrical Distribution Systems Dated March 2, 2007 ADAMS Accession No. ML070720545 ML0733409182007-05-31031 May 2007 05/31/2007 Presentation by J. Cudsworth NRC Treatment of Issues Other than Category 2 Issues for License Renewal ML0715101782007-05-30030 May 2007 Attachment 2 to PLA-6211, Steam Dryer Replacement, NRC Meeting ML0714401792007-04-24024 April 2007 EOC 2006 Meeting Slides (PPL) ML0714401562007-04-24024 April 2007 EOC Meeting Slides (NRC) on NRC Annual Performance Assessment of Susquehanna Steam Electric Station - 2006 Reactor Oversight Program ML0703804702006-11-15015 November 2006 License Renewal Scoping Meeting Handouts: Public Input by Sue Fracke ML0609602842006-04-0606 April 2006 Public Meeting, Susquehanna, Slides on Reactor Oversight Program - Cy 2005 ML0602602402006-01-19019 January 2006 Enclosure 2 - Meeting Handouts from 1/19/06 Meeting with PPL Susquehanna, LLC to Discuss an Impending Exemption Request to CoC 72-1004 ML0536201842005-11-21021 November 2005 NRC-PPL Extended Power Uprate Pre-Submittal Meetings. Start-Up Testing/Large Transient Testing Process Topics ML0514403502005-04-0606 April 2005 NRC Annual Assessment Meeting, PPL Susquehanna LLC Team (PPL Slides) ML0513704462005-04-0606 April 2005 Annual Assessment Meeting Notice, Slides ML0315307242003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F4 - Hubert J. Miller - Region I Breakout ML0314906962003-04-16016 April 2003 April 16, 2003 - RIC 2003 Presentation - W8 - Bryce L. Shriver - Safety Management - Promoting Safety Culture to Achieve Safe Performance ML0210903772002-04-16016 April 2002 NRC - Region I Susquehanna Steam Electric Station Annual Assessment Meeting Slides ML18025A2921975-08-25025 August 1975 Letter Attaching the Outline of the BWR Mark II Containment Supporting Program ML17037B8491975-08-23023 August 1975 08/21/1975 Summary of Meeting with Mark II Owners, Sargent & Lundy, Bechtel, Stone & Webster, Burns & Roe, and the NRC Staff to Discuss Load Factors and Load Combinations Proposed by the Mark II Owners and Their Architect ... 2023-06-06
[Table view] |
Text
Susquehanna Steam Electric Station License Amendment Request for a Temporary Completion Time Extension to Support Emergency Service Water Piping Replacement Pre-Application Meeting November 5, 2018
Meeting Purpose
- Describe a future license amendment request
- Establish a common understanding of the scope of the request
- Establish a common understanding of the schedule
© Talen Energy 2
Proposed Change
- Temporary extension to Completion Times in LCOs 3.7.1 and 3.7.2
- Increase from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and 7 days to 14 days
- Work is projected to take 11 days plus contingency
- Extension is necessary for the online unit
- Only one subsystem of ESW/RHRSW is required for the outage unit
- Extension would expire in 2026 for Unit 2 and 2027 for Unit 1
© Talen Energy 3
Emergency Service Water System
- Cools diesel generators, ECCS pumps and room coolers, and other heat exchangers
- ESW and RHRSW share a common return line to the spray pond via spray arrays or bypass valves
© Talen Energy 4
RHR Service Water System
- 2 divisions per unit shared between units
- (e.g., Unit 1 A RHRSW pump can feed Unit 2 RHR HX)
- Cools RHR Heat Exchangers
- ESW and RHRSW share a common return line to the spray pond via spray arrays or bypass valves
© Talen Energy 5
Location of Pipe Replacement
- Initially, will replace Unit 1, Division 1 supply and return line near the Reactor Building Isolation valves
- May replace Unit 1 Division 2 and both Divisions on Unit 2
© Talen Energy 6
Upcoming Refueling Outages
- Divisional outages at Year Unit 1 Unit 2 Susquehanna 2020 Division 1 2021 Division 1 2022 Division 2
- Two opportunities for each 2023 Division 2 division 2024 Division 1 2025 Division 1
- Allows time to interpret results, 2026 Division 2 appropriately plan and 2027 Division 2 schedule subsequent replacements, and account for increased scope
© Talen Energy 7
Summary
- Susquehanna intends to replace ESW piping in 2020
- Based on initial replacement and inspection, may make subsequent replacements
- Requesting an extension to LCOs 3.7.1 and 3.7.2 for the online unit
- Extend to 14 days from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> and 7 days
- Extension would expire in 2026 for Unit 2 and 2027 for Unit 1
© Talen Energy 8