SSES Slide Presentation in Support of 9/23 Public Meeting EAL Scheme Change LAR
ML15264A687
Person / Time
Site: Susquehanna  
Issue date: 09/21/2015
From:
Susquehanna
To:
Plant Licensing Branch II
Whited J
References
TAC MF6057, TAC MF6058
Download: ML15264A687 (18)


Text

DISCUSSION OF ADDITIONAL PROPOSED CHANGES TO THE SUSQUEHANNA STEAM ELECTRIC STATION (SSES)

EMERGENCY ACTION LEVEL (EAL) BASIS DOCUMENT SINCE SUBMITTAL OF LICENSE AMENDMENT REQUEST TO ADOPT NEI 99-01, REVISION 6, EMERGENCY ACTION LEVEL SCHEME CHANGE (TAC NOS. MF6057 AND MF6058)

SUSQUEHANNA NUCLEAR, LLC REQUEST FOR PUBLIC MEETING

2 SeveralproposedchangesarebeingmadetotheSSESEALBasis documentasaresultofthefollowing:

CorrectiveactionstakeninresponsetotheNRCEPWhite finding,and SusquehannaNuclear,LLC,EmergencyOperatingProcedure (EOP)upgradeprojecttoRevision3oftheBWROG EmergencyProcedureGuidelines(EPGs)/SevereAccident Guidelines(SAGs).

TheseproposedchangesdonotrequirepriorNRCapprovaland wereidentifiedafterSSESsubmittedalicenseamendmenttothe NRCtoadopttheNEI9901,Rev.6EALschemechange.(ML#15091A657)

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

3 Section3.1.1-Addedlanguagedirectlyfromthe NSIR/DPRISG01InterimStaffGuidance EMERGENCYPLANNINGFORNUCLEARPOWER PLANTSRev.0(November2011)SectionIV.H EmergencyDeclarationTimelinesstoprovide completeclassificationtimelinessguidance.This changewasmadeasaresultofcorrectiveactions takenbySusquehannaNuclear,LLCinresponseto theNRCEPWhiteFinding.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

4 EALSS6.1-UpdatedtheHeatCapacity TemperatureLimitfigure.Thischangewasmade asaresultoftheSSESEOPupgradeprojectto conformtoRevision3ofthegenericBWROG EPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

5 EALSU6.1Bases-Addedlanguagecurrentlyinthe NRCapprovedSSESEALbases(NEI9901,Rev.4 version)thatclarifiesthattheEALisnotapplicable ifamanualscramisinitiatedandnoRPSsetpointis exceeded.Thischangewasmadeasaresultof correctiveactionstakenbySusquehannaNuclear, LLC,inresponsetotheNRCEPWhiteFinding.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

6 Table F1FissionProductBarrierThresholdMatrix-RevisedPCLoss#2forPCIntegrityorBypassthat intentionalPrimaryContainmentventingcanbe initiatedviavariousEPDSorEOproceduresnotjust EPDS004.Thischangewasmadeasaresultofthe SSESEOPupgradeprojecttoconformtoRevision3 ofthegenericBWROGEPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

7 FuelCladLossonReactorVesselLevelBases-UpdatedtheSAGentryconditions.Thischange wasmadeaspartoftheSSESEOPupgradeproject toconformtoRevision3ofthegenericBWROG EPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

8 FuelCladLossJudgmentBases-Addedlanguage currentlyintheNRCapprovedSSESEALbases(NEI 9901Rev.4version)thatclarifiesactionstotake on lossofwaterlevelindicationduetoanelectrical problem.Thischangewasmadeasaresultof correctiveactionstakenbySusquehannaNuclear, LLC,inresponsetotheNRCEPWhiteFinding.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

9 FuelCladPotential LossJudgmentBases-Added languagecurrentlyintheNRCapprovedSSESEAL bases(NEI9901Rev.4version)thatclarifies actionstotakeonlossofwaterlevelindicationdue toanelectricalproblem.Thischangewasmadeas aresultofcorrectiveactionstakenbySusquehanna Nuclear,LLC,inresponsetotheNRCEPWhite Finding.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

10 ReactorCoolantSystem(RCS)Loss#2onRCSLeak RateBases-Deletedthephraseandkeepthem opentoeliminatethepossibilityofnotdeclaring thebarrierlostifallSRVsarenotcontinuouslykept openduringemergencyreactorpressurevessel (RPV)depressurization.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

11 RCSPotentialLossforRCSleakageBases-Relocatedthephrase(EALtrigger)andaddedthe sentenceIfitcannotbedeterminedwithin15 minutesoftheEALTriggerthattheleakisisolable andnottheresultofaconditionpreviously described,theEALshallbedeclared.Thischange wasmadeasaresultofcorrectiveactionstakenin responsetotheNRCEPWhiteFinding.Nointent change.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

12 RCSLossJudgmentBases-Addedlanguage currentlyintheNRCapprovedSSESEALbases(NEI 9901,Rev.4version)thatclarifiesactionstotake onlossofwaterlevelindicationduetoanelectrical problem.Thechangewasmadeasaresultof correctiveactionstakenbySusquehannaNuclear, LLC,inresponsetotheNRCEPWhiteFinding.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

13 PrimaryContainmentPotentialLossonReactor VesselLevelBases-UpdatedtheSAGentry conditions.Thischangewasmadeasaresultofthe SSESEOPupgradeprojecttoconformtoRevision3 ofthegenericBWROGEPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

14 PrimaryContainmentLossforRCSleakageBases-RevisedMaxSafelanguagetoaligntheMaxNorm languagewithrespecttoEALtriggeranddeclaration requirements.Thisincludesdeletingthefollowing sentences:

Ifsubsequentactionstakentoisolatetheleakare successful,thethresholdforthisEALisstillmetand mustbedeclared.Onceleakageisisolated, downgradingtheemergencymaybeappropriate.

ThischangewasmadeinresponsetotheNRCEP WhiteFinding.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

15 PrimaryContainmentLossforRCSleakageBases-RevisedMaxSafelanguagetomatchMaxNorm language.

  • AddedthesentenceIfsubsequentactions takentoisolatetheleakaresuccessfulwithin the15minuteclassificationperiod,thisEAL shouldnotbedeclared.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

16 PrimaryContainmentPotentialLossonPrimary ContainmentConditionsBases-Revisedthe procedurethatdefinesdeflagration(Hydrogenand Oxygen)limitsaspartoftheSSESEOPupgrade projecttoconformtoRevision3ofthegeneric BWROGEPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

17 PrimaryContainmentLossonPCConditions-UpdatedtheHeatCapacityTemperatureLimit figure.Thischangewasmadeasaresultofthe SSESEOPupgradeprojecttoconformtoRevision3 ofthegenericBWROGEPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT

18 PrimaryContainmentLossonPCIntegrityor BypassBases-Revisedtostatethatintentional PrimaryContainmentventingcanbeinitiatedvia variousEPdamageproceduresoremergency operatingproceduresandnotjustEPDS004, PrimaryContainmentandRPVVenting.This changewasmadeasaresultoftheSSESEOP upgradeprojecttoconformtoRevision3ofthe genericBWROGEPGs/SAGs.

SUSQUEHANNA NUCLEAR, LLC PUBLIC MEETING TO DISCUSS PROPOSED CHANGES TO THE SSES EMERGENCY PREPAREDNESS EAL BASIS DOCUMENT