|
---|
Category:Meeting Briefing Package/Handouts
MONTHYEARML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21025A1752021-01-26026 January 2021 License Amendment Request to Adopt TSTF-505 - Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Pre-Application Meeting, January 26, 2021 (Slides) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML19298A9552019-10-29029 October 2019 License Amendment Request for a Revision to the Dose Consequence Analysis for a Loss of Coolant Accident - Pre-Application Meeting, October 29, 2019 ML19165A0062019-06-18018 June 2019 (SSES) License Amendment Request for Proposed Changes to Emergency Response Organization Staffing Augmentation. Pre-Submittal Call Meeting June 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML19099A0162019-04-0909 April 2019 Pre-application Meeting for Framatome Fuel - Slide ML18305B0582018-11-0505 November 2018 Emergency Service Water Piping Replacement LAR - NRC Pre-Application Meeting ML18129A4242018-05-10010 May 2018 Advanced Framatome Methods LAR - NRC Pre-Application Meeting ML15264A6872015-09-21021 September 2015 SSES Slide Presentation in Support of 9/23 Public Meeting EAL Scheme Change LAR ML14182A3222014-06-10010 June 2014 Presentation in Support of PPL Meeting with NRC Staff License Transfer Pre-Application Meeting to Be Held July 2, 2014 ML14100A3712014-04-0909 April 2014 Susq 2014 Aam Slides ML13107B1962013-04-10010 April 2013 Slide Presentation for Susquehanna 2012 EOC Annual Assessment Meeting, on April 10, 2013 ML12296A6702012-10-16016 October 2012 SCCI Public Meeting - Slides, 10-16-12 ML12089A4302012-03-21021 March 2012 Aam 95002 Slide Presentation ML12089A1342012-03-21021 March 2012 Annual Assessment Meeting NRC Slide Presentation ML1014500762010-05-25025 May 2010 Susq NRC Slides for Aam, April 27, 2010 ML1014503572010-05-25025 May 2010 PPL Slides for Susquehanna Annual Assessment Meeting, April 27, 2010 ML0919402082009-07-13013 July 2009 PPL Slides for Susquehanna SCWE Public Mtg July 6, 2009 ML0919401892009-07-0606 July 2009 Meeting Slides, NRC Susquehanna Safety Conscious Work Environment (SCWE Public Meeting ML0913906312009-06-0404 June 2009 ACRS Meeting with the U.S. Nuclear Regulatory Commission, - June 4, 2009, Slides ML0900903402009-01-26026 January 2009 Transmittal of Summary of Telephone Conference Call Held on January 5, 2009, Between the U.S. Nuclear Regulatory Commission and PPL Susquehanna, Llc. Concerning the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Applicat ML0828807292008-05-31031 May 2008 Draft Comprehensive Plan for the Water Resources of the Susquehanna River Basin ML0915201302008-05-19019 May 2008 Annual Assessment Meeting Slides for 5/19/09, 2008 Reactor Oversight Process ML0808103392008-03-18018 March 2008 Meeting on March 18, 2008 (NON-Proprietary Version) Presentation (Tac No. MD8099) ML0725600652007-08-10010 August 2007 Susquehanna Meeting Presentation, ATWS and Stability Implementation ML0719802842007-07-19019 July 2007 Meeting Slides for Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Asension Test Plans ML0717104272007-06-13013 June 2007 Summary of June 13, 2007, Category 1 Working -Level Meeting with PPL to Discuss the Licensee'S Proposed License Amendment Request Regarding Electrical Distribution Systems Dated March 2, 2007 ADAMS Accession No. ML070720545 ML0733409182007-05-31031 May 2007 05/31/2007 Presentation by J. Cudsworth NRC Treatment of Issues Other than Category 2 Issues for License Renewal ML0715101782007-05-30030 May 2007 Attachment 2 to PLA-6211, Steam Dryer Replacement, NRC Meeting ML0714401562007-04-24024 April 2007 EOC Meeting Slides (NRC) on NRC Annual Performance Assessment of Susquehanna Steam Electric Station - 2006 Reactor Oversight Program ML0714401792007-04-24024 April 2007 EOC 2006 Meeting Slides (PPL) ML0703804702006-11-15015 November 2006 License Renewal Scoping Meeting Handouts: Public Input by Sue Fracke ML0609602842006-04-0606 April 2006 Public Meeting, Susquehanna, Slides on Reactor Oversight Program - Cy 2005 ML0602602402006-01-19019 January 2006 Enclosure 2 - Meeting Handouts from 1/19/06 Meeting with PPL Susquehanna, LLC to Discuss an Impending Exemption Request to CoC 72-1004 ML0536201842005-11-21021 November 2005 NRC-PPL Extended Power Uprate Pre-Submittal Meetings. Start-Up Testing/Large Transient Testing Process Topics ML0514403502005-04-0606 April 2005 NRC Annual Assessment Meeting, PPL Susquehanna LLC Team (PPL Slides) ML0513704462005-04-0606 April 2005 Annual Assessment Meeting Notice, Slides ML0315307242003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F4 - Hubert J. Miller - Region I Breakout ML0314906962003-04-16016 April 2003 April 16, 2003 - RIC 2003 Presentation - W8 - Bryce L. Shriver - Safety Management - Promoting Safety Culture to Achieve Safe Performance ML0210903772002-04-16016 April 2002 NRC - Region I Susquehanna Steam Electric Station Annual Assessment Meeting Slides ML18025A2921975-08-25025 August 1975 Letter Attaching the Outline of the BWR Mark II Containment Supporting Program ML17037B8491975-08-23023 August 1975 08/21/1975 Summary of Meeting with Mark II Owners, Sargent & Lundy, Bechtel, Stone & Webster, Burns & Roe, and the NRC Staff to Discuss Load Factors and Load Combinations Proposed by the Mark II Owners and Their Architect ... 2024-05-16
[Table view] Category:Slides and Viewgraphs
MONTHYEARML24137A1882024-05-16016 May 2024 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML23157A0352023-06-0606 June 2023 Annual Assessment Meeting for Pa/Md/Ny/Nj Nuclear Power Plants - NRC Presentation Slides ML21165A1942021-06-16016 June 2021 Joint Annual Assessment Meeting for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation ML21165A2882021-06-16016 June 2021 Joint Annual Assessment for Pa/Md/Nj/Ny Nuclear Power Plants - Webinar Presentation (Updated) ML21025A1752021-01-26026 January 2021 License Amendment Request to Adopt TSTF-505 - Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b Pre-Application Meeting, January 26, 2021 (Slides) ML20163A6542020-06-18018 June 2020 2020 NRC Annual Assessment Webinar Presentation - Pennsylvania and Maryland Facilities (Beaver Valley, Calvert Cliffs, Limerick, Peach Bottom, Susquehanna) ML20168A3192020-06-15015 June 2020 Joint Annual Assessment Meeting for Pa/Md Power Plants - Webinar Presentation ML20058B1672020-02-27027 February 2020 Talen Energy Presentation Slides Susquehanna Steam Electric Station Pre-Application Meeting of February 27, 2020 License Amendment Request to Create an Action for an Inoperable Manual Synchronization Circuit ML19165A0062019-06-18018 June 2019 (SSES) License Amendment Request for Proposed Changes to Emergency Response Organization Staffing Augmentation. Pre-Submittal Call Meeting June 18, 2019 ML19157A0542019-06-0606 June 2019 Joint Annual Assessment Meeting (Webinar) for Pennsylvania Power Plants - NRC Presentation Slides ML15264A6872015-09-21021 September 2015 SSES Slide Presentation in Support of 9/23 Public Meeting EAL Scheme Change LAR ML14247A2612014-09-0303 September 2014 NRC Slides for 95002 Presentation for Susquehanna & PPL Public Meeting ML14182A3222014-06-10010 June 2014 Presentation in Support of PPL Meeting with NRC Staff License Transfer Pre-Application Meeting to Be Held July 2, 2014 ML14100A3712014-04-0909 April 2014 Susq 2014 Aam Slides ML13107B1962013-04-10010 April 2013 Slide Presentation for Susquehanna 2012 EOC Annual Assessment Meeting, on April 10, 2013 ML12296A6702012-10-16016 October 2012 SCCI Public Meeting - Slides, 10-16-12 ML12089A4302012-03-21021 March 2012 Aam 95002 Slide Presentation ML12089A1342012-03-21021 March 2012 Annual Assessment Meeting NRC Slide Presentation ML1114407092011-05-19019 May 2011 Aam Slides, May 19, 2011, 2010 Reactor Oversight Process ML1014503572010-05-25025 May 2010 PPL Slides for Susquehanna Annual Assessment Meeting, April 27, 2010 ML1014500762010-05-25025 May 2010 Susq NRC Slides for Aam, April 27, 2010 ML0919402082009-07-13013 July 2009 PPL Slides for Susquehanna SCWE Public Mtg July 6, 2009 ML0919401892009-07-0606 July 2009 Meeting Slides, NRC Susquehanna Safety Conscious Work Environment (SCWE Public Meeting ML0913906312009-06-0404 June 2009 ACRS Meeting with the U.S. Nuclear Regulatory Commission, - June 4, 2009, Slides ML0828807292008-05-31031 May 2008 Draft Comprehensive Plan for the Water Resources of the Susquehanna River Basin ML0915201302008-05-19019 May 2008 Annual Assessment Meeting Slides for 5/19/09, 2008 Reactor Oversight Process ML0811206272008-04-16016 April 2008 SSES 2007 ROP Slides ML0808103392008-03-18018 March 2008 Meeting on March 18, 2008 (NON-Proprietary Version) Presentation (Tac No. MD8099) ML0719802842007-07-19019 July 2007 Meeting Slides for Category 1 Working-Level Meeting with PPL to Discuss Steam Dryer Analysis, Licensing, Design Approach, and Power Asension Test Plans ML0733409182007-05-31031 May 2007 05/31/2007 Presentation by J. Cudsworth NRC Treatment of Issues Other than Category 2 Issues for License Renewal ML0715101782007-05-30030 May 2007 Attachment 2 to PLA-6211, Steam Dryer Replacement, NRC Meeting ML0714401792007-04-24024 April 2007 EOC 2006 Meeting Slides (PPL) ML0714401562007-04-24024 April 2007 EOC Meeting Slides (NRC) on NRC Annual Performance Assessment of Susquehanna Steam Electric Station - 2006 Reactor Oversight Program ML0632401502006-11-15015 November 2006 11/15/06 Environmental Scoping Meeting Slide Handouts ML0631701532006-11-0606 November 2006 Meeting Slides ML0611100212006-04-12012 April 2006 NRC Annual Assessment Meeting, PPL Susquehanna Slides ML0609602842006-04-0606 April 2006 Public Meeting, Susquehanna, Slides on Reactor Oversight Program - Cy 2005 ML0534604562005-12-0808 December 2005 Update on Control Cell Friction ML0536201842005-11-21021 November 2005 NRC-PPL Extended Power Uprate Pre-Submittal Meetings. Start-Up Testing/Large Transient Testing Process Topics ML0536201932005-11-15015 November 2005 NRC Extended Power Uprate Pre-Submittal Meeting, Susquehanna, Flow Induced Vibration Evaluation & Reactor Pressure Vessel Steam Dryer Analysis ML0514403502005-04-0606 April 2005 NRC Annual Assessment Meeting, PPL Susquehanna LLC Team (PPL Slides) ML0513704462005-04-0606 April 2005 Annual Assessment Meeting Notice, Slides ML0412100952004-04-27027 April 2004 PPL Susquehanna, LLC Slides for the Annual Assessment Meeting ML0411906342004-04-27027 April 2004 NRC Region I Slides for the Susquehanna Annual Assessment Meeting with NRC Re Reactor Oversight Program - Cy 2003 ML0315307242003-04-18018 April 2003 April 18, 2003 - RIC 2003 Presentation - F4 - Hubert J. Miller - Region I Breakout ML0314906962003-04-16016 April 2003 April 16, 2003 - RIC 2003 Presentation - W8 - Bryce L. Shriver - Safety Management - Promoting Safety Culture to Achieve Safe Performance ML0310400692003-03-31031 March 2003 Susquehanna Annual Assessment Meeting Slides for Region I and PPL Susquehanna, LLC ML0210903912002-04-16016 April 2002 PPL Susquehanna, LLC Annual Assessment Meeting Slides 2024-05-16
[Table view] |
Text
NRC Annual Performance Assessment of Susquehanna Steam Electric Station 2006 Reactor Oversight Program
Purpose of Todays Meeting NRC will address Susquehannas performance as described in the annual assessment letter Susquehanna will be given the opportunity to respond to the information in the letter and inform the NRC of new or existing programs to maintain or improve their performance NRC will be available to engage interested stakeholders on performance of the plant and our role in ensuring safe plant operations 2
Agenda z Introduction and NRC Organization z Review of NRC Reactor Oversight Process z Regulatory Summary of National Plant Performance z NRC Assessment of Susquehannas Performance Results z Susquehanna Response and Remarks z NRC Closing Remarks z Break z NRC available to address public questions 3
Region I Organization Samuel J. Collins Regional Administrator Marc L. Dapas Deputy Regional Administrator David C. Lew A. Randolph Blough Director Division of Reactor Projects Director Division of Reactor Safety James W. Clifford Marsha K. Gamberoni Deputy Director Deputy Director Paul Krohn Regional Specialists Branch Chief PPL Susquehanna Project Engineers Resident Inspectors Roy Fuhrmeister - Senior SPE Alan Blamey - SRI Thomas Setzer - PE Fred Jaxheimer - RI 4
NRC Representatives z David C. Lew, Director, Division Reactor Projects (DRP)
- (610) 337-5229 z James W. Clifford, Deputy Division Director, DRP
- (610) 337-5080 z Paul Krohn, Branch Chief
- (610) 337-5120 z Rich Guzman, Project Manager, NRR
- (301) 415-1030 z Alan Blamey, Senior Resident Inspector
- (570) 542-2134 z Fred Jaxheimer, Resident Inspector
- (570) 542-2134 z Roy Fuhrmeister, Senior Project Engineer 5
- (610) 337-5059
NRC Performance Goals z Safety: Ensure protection of the public health and safety and the environment z Security: Ensure the secure use and management of radioactive materials z Openness: Ensure openness in our regulatory process z Effectiveness: Ensure that NRC actions are effective, efficient, realistic, and timely z Management: Ensure excellence in agency management to carry out the NRCs strategic objectives 6
Reactor Oversight Process Strategic Performance Areas Safety Cornerstones Baseline Inspection Performance Indicator Results Results Significance Significance Threshold Threshold Action Matrix 7
Regulatory Response
Typical Baseline Inspection Areas z Equipment Alignment z Triennial Fire Protection z Operator Response z Emergency Preparedness z Radiation Release Controls z Worker Radiation Protection z Corrective Action Program z Corrective Action Case Reviews 8
Significance Threshold Performance Indicators Green: Only Baseline Inspection White: May increase NRC oversight Yellow: Requires more NRC oversight Red: Requires more NRC oversight Inspection Findings Green: Very low safety issue White: Low to moderate safety issue Yellow: Substantial safety issue Red: High safety issue 9
Action Matrix Concept Licensee Regulatory Degraded Multiple/Rep. Unacceptable Response Response Cornerstone Degraded Performance Cornerstone Increasing Safety Significance Increasing NRC Inspection Efforts Increasing NRC/Licensee Management Involvement Increasing Regulatory Actions 10
Regulatory Summary of National Plant Performance Status at End of 2006 Licensee Response 73 Regulatory Response 21 Degraded Cornerstone 5 Multiple/Repetitive Degraded Cornerstone 4 Unacceptable 0 Total 103 11
National Summary z Performance Indicator Results (at end of 2006)
Green 1635 White 11 Yellow 0 Red 0 z Total Inspection Findings (2006)
Green 676 White 19 Yellow 3 Red 3 12
Susquehanna Inspection Activities (Jan 1 - Dec 31, 2006) z 5275 hours0.0611 days <br />1.465 hours <br />0.00872 weeks <br />0.00201 months <br /> of inspection and assessment related activities z 2 resident inspectors assigned to the site z 11 regional inspections z 3 team inspections 13
Susquehanna Inspection Activities (Jan 1 - Dec 31, 2006)
Daily Resident Inspections Completed a Problem Identification and Resolution (PI&R) Team Inspection Completed a Plant Modifications Team Inspection 14
Susquehanna Assessment Results (Jan 1 - Dec 31, 2006) z PPL operated Susquehanna in a manner that preserved public health and safety z All cornerstone objectives were met z Susquehanna was in the licensee response column of the Action Matrix for all of 2006 z All performance indicators were green (very low safety significance) in 2006 z Fifteen green inspection findings were identified during 2006 z NRC plans baseline inspections for 2007 15
Susquehanna Sample Inspection Findings Inadequate work instructions for the disassembly and inspection of In-service Test check valves Inadequate design review of the Power Range Neutron Monitoring System modification resulted in an automatic reactor shutdown Inadequate corrective actions for Reactor Protection System Electrical Protective Assembly circuit breaker failures 16
Licensee Response and Remarks Mr. Britt McKinney Senior Vice President PPL Susquehanna, LLC 17
Contacting the NRC z Report an emergency (301) 816-5100 (call collect) z Report a safety concern:
(800) 695-7403 Allegation@nrc.gov z General information or questions www.nrc.gov Select Public Meetings and Involvement z Paul G. Krohn, Branch Chief pgk1@nrc.gov 18
Reference Sources z Reactor Oversight Process http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/index.html z Public Electronic Reading Room http://www.nrc.gov/reading-rm.html z Public Document Room 1-800-397-4209 (Toll Free) 19