August 16, 2007 LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Plant

SUBJECT:

SUMMARY

OF THE AUGUST 8, 2007, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On August 8, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at the Davis-Besse Energy Education Center in Oak Harbor, Ohio. The meeting was between NRC Region III management and FirstEnergy Nuclear Operating Company (FENOC) management to discuss the NRCs assessment of Davis-Besse Nuclear Plant's safety performance for the period from January 1 through December 31, 2006. The meeting notice, NRC presentation, and licensee presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML071980196, ML072220189, and ML072220198, respectively. A list of principal NRC and licensee meeting participants is attached to this letter.

The NRC began the meeting with an overview of the Reactor Oversight Program (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of the Davis-Besse plants performance in calendar year 2006, which was documented in the March 2, 2007, end-of-cycle assessment letter. As part of this regulatory performance meeting, FENOC acknowledged the results and presented a summary of the Davis-Besse plants accomplishments and current focus areas. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and FENOC representatives.

/RA/

Bruce L. Burgess, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated DISTRIBUTION See next page

LICENSEE: FirstEnergy Nuclear Operating Company FACILITY: Davis-Besse Nuclear Plant

SUBJECT:

SUMMARY

OF THE AUGUST 8, 2007, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On August 8, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at the Davis-Besse Energy Education Center in Oak Harbor, Ohio. The meeting was between NRC Region III management and FirstEnergy Nuclear Operating Company (FENOC) management to discuss the NRCs assessment of Davis-Besse Nuclear Plant's safety performance for the period from January 1 through December 31, 2006. The meeting notice, NRC presentation, and licensee presentation can be found in the Agencywide Documents Access and Management System (ADAMS) as ML071980196, ML072220189, and ML072220198, respectively. A list of principal NRC and licensee meeting participants is attached to this letter.

The NRC began the meeting with an overview of the Reactor Oversight Program (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of the Davis-Besse plants performance in calendar year 2006, which was documented in the March 2, 2007, end-of-cycle assessment letter. As part of this regulatory performance meeting, FENOC acknowledged the results and presented a summary of the Davis-Besse plants accomplishments and current focus areas. At the end of the meeting, members of the public were given the opportunity to ask questions of NRC officials and FENOC representatives.

Bruce L. Burgess, Chief Branch 6 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated DISTRIBUTION See next page DOCUMENT NAME:C:\FileNet\ML072280328.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME RRuiz:dtp*BLB for BBurgess DATE 08/16/07 08/16/07 OFFICIAL RECORD COPY

Letter to FirstEnergy Nuclear Operating Company from B. Burgess dated

SUBJECT:

SUMMARY

OF THE AUGUST 8, 2007, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT cc w/encl: The Honorable Dennis Kucinich J. Hagan, President and Chief Nuclear Officer - FENOC J. Lash, Senior Vice President of Operations and Chief Operating Officer - FENOC Richard Anderson, Vice President, Nuclear Support - FENOC Manager - Site Regulatory Compliance - FENOC D. Pace, Senior Vice President of Fleet Engineering - FENOC J. Rinckel, Vice President, Fleet Oversight - FENOC D. Jenkins, Attorney, FirstEnergy Corp.

Director, Fleet Regulatory Affairs - FENOC Manager - Fleet Licensing - FENOC Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Lucas County Board of Commissioners President, Ottawa County Board of Commissioners Ottawa County Sheriff Director, Ottawa County EMA Lucas County Sheriff Director, Lucas County EMA Genoa Village Administrator Mayor of Clay Center Mayor of Elmore Mayor of Genoa Mayor of Oak Harbor Mayor of Toledo Mayor of Port Clinton Mayor of Marblehead Mayor of Rocky Ridge Village Administrator of Oak Harbor Mayor of Put-in-Bay INPO

Letter to FirstEnergy Nuclear Operating Company from B. Burgess dated August 16, 2007

SUBJECT:

SUMMARY

OF THE AUGUST 8, 2007, PUBLIC MEETING TO DISCUSS THE DAVIS-BESSE END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT DISTRIBUTION:

TEB RAG1 SPS1 TJW2 RidsNrrDirslpab JLC1 MAS JKH3 KGO RML2 SAM9 SRI Davis-Besse DRPIII DRSIII PLB1 TXN

Enclosure Principal Meeting Participants NRC C. Pederson, Director, Division of Reactor Projects B. Burgess, Chief, Branch 6, Division of Reactor Projects R. Gibbs, Chief, Division of Operating Reactor Licensing, NRR J. Rutkowski, Senior Resident Inspector, Davis-Besse FirstEnergy Nuclear Operating Company M. Bezilla, Site Vice President, Davis-Besse V. Kaminskas, Davis-Besse Director, Site Operations B. Boles, Davis-Besse Director, Maintenance C. Price, Davis-Besse Director, Performance Improvement J. Grabnar, Davis-Besse Director, Engineering