ML062120472

From kanterella
Jump to navigation Jump to search

Watts Bar Nuclear Plant (WBN) Unit 1 - Generic Letter 2004-02 - Request for Additional Information Regarding the Nuclear Regulatory Commission Staff Audit on the Containment Sump Modifications
ML062120472
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 07/03/2006
From: Pace P L
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Lu S, NRR/DSS/SSIB, 415-2869
Shared Package
ML062120461 List:
References
GL-04-002, TAC MC4730
Download: ML062120472 (47)


Text

PROPRIETARY INFORMATION ENCLOSED UNDER 10 CFR 2.390(b)(4)

July 3, 2006

10 CFR 50.54(f)

U. S. Nuclear Regulatory Commission

ATTN: Document Control Desk

Washington, D.C. 20555-0001

Gentlemen: In the Matter of ) Docket No. 50-390 Tennessee Valley Authority )

WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 - GENERIC LETTER 2004 REQUEST FOR ADDITIONAL INFORMATION REGARDING THE NUCLEAR

REGULATORY COMMISSION STAFF AUDIT ON THE CONTAINMENT SUMP

MODIFICATIONS (TAC NO. MC4730)

The purpose of this letter is to respond to NRC's request for additional information (RAI) dated May 10, 2006 concerning the

subject Staff audit of the containment sump modifications.

TVA coordinated an extension of this response with NRC Project

Manager to July 5, 2006.

TVA's responses to NRC's questions are provided in Enclosure

1. The documents requested by NRC's RAI are provided on the

enclosed Compact Discs (CD) two per set. A list of documents

on the CDs is provided in the Attachment to Enclosure 1.

Calculation FSDA-C-597, "RHR Pump NPSH," in response to

Question 1 under Net Positive Suction Head/Loss-of-Coolant Accident and the "WBN ECCS Analysis Report" in response to Question 1 under Downstream Effects (Components) on the CD contain information proprietary to Westinghouse Electric

Corporation for which withholding is being requested.

Westinghouse is providing these documents for use by the NRC

staff in its audit activities and requests that these

documents be considered proprietary in their entirety. As

such, a non-proprietary version will not be issued.

PROPRIETARY INFORMATION ENCLOSED UNDER 10 CFR 2.390(b)(4)

U.S. Nuclear Regulatory Commission Page 2

July 3, 2006

The proprietary information for which withholding is being

requested is further identified in Affidavit CAW-06-2163 and

CAW-06-2169 signed by the owner of the proprietary

information, Westinghouse Electric Company LLC. The affidavit

sets forth the basis on which the information may be withheld

from public disclosure by the Commission and addresses with

specificity the considerations listed in 10 CFR 2.390(b)(4).

contains Westinghouse authorization letters,

CAW-06-2163 and CAW-06-2169, accompanying affidavits, Proprietary Information Notices, and Copyright Notices.

Correspondence with respect to the proprietary aspects of the

application for withholding or the Westinghouse affidavits

should reference CAW-06-2163 or CAW-06-2169 and should be

addressed to B.F. Maurer, Acting Manager, Regulatory

Compliance and Plant Licensing, or J. A. Gresham, Manager, Regulatory Compliance and Plant Licensing, Westinghouse

Electric Company LLC, P. O. Box 355, Pittsburgh, Pennsylvania

15230-0355.

The remaining open items to respond to NRC's audit request for

additional information are being tracked as part of the

previous commitment to provide a supplemental response. If

you have any questions concerning this matter, please call

P. L. Pace at (423) 365-1824.

I declare under penalty of perjury that the foregoing is true

and correct. Executed on this 30th day of June 2006.

Sincerely,

P. L. Pace

Manager, Site Licensing

and Industrial Affairs

Enclosures

cc See page 3 PROPRIETARY INFORMATION ENCLOSED UNDER 10 CFR 2.390(b)(4)

U.S. Nuclear Regulatory Commission Page 3

July 3, 2006

Enclosures

cc (Enclosures): NRC Resident Inspector Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

Mr. D. V. Pickett, Senior Project Manager U.S. Nuclear Regulatory Commission MS 08G9a One White Flint North 11555 Rockville Pike Rockville, Maryland 20852-2738

U.S. Nuclear Regulatory Commission Region II Sam Nunn Atlanta Federal Center 61 Forsyth St., SW, Suite 23T85 Atlanta, Georgia 30303 ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-1 Break Selection and Zone of Influence Analysis QUESTION 1 Tennessee Valley Authority (TVA, the licensee) stated that

because the quantity of reflective metallic insulation is not a

significant contributor to head loss, and the quantity of fibrous

material, Min-K, would remain relatively unchanged for each

break, the bounding case for each loop is the reactor coolant

system break which would destroy the most coatings. The licensee

indicated that a thorough analysis showed that a break in each of

the crossover legs near the steam generator nozzle yielded the

most coating debris due to the size of the zone of influence (ZOI) applied in the analyses. The Nuclear Regulatory Commission (NRC) staff (the staff) determined that such an analysis was not

clearly documented in the calculations and information provided

for the staff's audit. Please provide the referenced analysis to

verify that the limiting break is at the base of the steam

generator.

RESPONSE As a result of questions raised during the audit, ALION has

revised and expanded the debris generation calculation. The

revision to the debris generation calculation (Revision 2) no

longer makes reference to undocumented analyses for the paint

calculations. Since the ZOIs used in the debris generation

analysis are large, moving locations along the primary loop

piping would not have a significant impact on the debris

quantities generated. The break selection considered all debris

sources. The silicon coatings protecting the carbon steel shell

of the steam generators were the reason to select the steam

generator nozzle as well as the large amount of reflective metal

insulation (RMI) on the steam generators. The new steam

generators that are being installed in the Fall 2006, will not

have a coating on the shell. The steam generators continue to be

the largest source of RMI debris for large breaks. Also, since

the crossover leg is larger than the hot and cold legs, selecting

a break on the crossover leg piping is conservative because the

ZOI is larger.

The revised analysis results in revised debris quantities

projected for WBN. Some of the fiber quantities due to min-K and

3M fire wrap have increased with respect to that tested in WBN's

strainer test. WBN is looking at several options to reduce these

quantities to within the tested configuration. These include:

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-2 credit for additional jet shielding due to robust barriers and large structures, material testing under jet impingement loading

to reduce the ZOI for encapsulated fiber, removal of material, and/or sump strainer re-testing. The total fiber quantities

still remain low and with WBN's large strainer area, TVA is

confident the WBN strainer design will have a low head loss. The

final debris calculation will be provided as part of an update of

the remaining open items.

QUESTION 2 As discussed in Sections 3.1 - 3.4 of Watts Bar calculation

ALION-CAL-TVA-2739-03, the licensee credits the reactor annulus

and refueling canal as robust barriers in the analysis. As

stated, the licensee's analysis showing that a break in each of

the crossover legs near the steam generator nozzle yielded the

most coating debris was not clearly documented in the

calculations and information provided for the staff's audit.

Therefore, Watts Bar calculation ALION-CAL-TVA-2739-03 does not

clearly show the extent to which the licensee credited truncation

due to robust barriers. Using the response to question 1 above, please show the extent to which truncation is credited.

RESPONSE The revised debris generation calculation (Revision 2) now shows the shielding that is currently credited and includes appendices

to clearly document which of the line items from the insulation

spreadsheet that were included as debris for each break location.

The revised analysis will be provided to NRC in the supplemental

report. Follow-up work may be required as described in the

response to Question 1 above.

QUESTION 3 Steam line breaks in the debris generation calculation are ruled

out because recirculation is not required for cooling the core

following a steam line break. However, recirculation using spray

flow for environmental qualification of equipment is required.

Please explain why this scenario was not analyzed.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-3 RESPONSE A main steam line break (MSLB) in the lower compartment would result in a smaller ZOI volume compared to the reactor coolant

system (RCS) line break since the main steam pressure is less

than half of the RCS pressure. A loss-of-coolant accident (LOCA)

was considered to be bounding to a MSLB since ECCS recirculation

is not required for decay heat removal following a postulated

MLSB. Recirculation using spray flow for environmental

qualification of equipment is required long term following a

MSLB. The ice condenser ice melt depletion is bounded by the

LOCA and occurs later in time due to less energy release for the

MSLB. Eventually the ice is depleted, even for the MSLB, and

containment spray in conjunction with air flow from the lower

compartment coolers is used to maintain the containment

temperature in the long term. However, operators are not

required to restart the lower compartment cooler fans to

recirculate air throughout the lower compartment and the dead-

ended spaces to prevent hot spots from developing for at least

1.5 hour5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br />s

after the event. In addition, the containment spray is

only required to remove ambient heat loss from the RCS. Periodic

use of one train of spray is needed. Therefore, there would be

less flow to transport debris, less debris to transport, and

intermittent flow to move the debris. Thus, it was determined

that a MSLB was bounded by a Large Break LOCA and was not

required to be analyzed.

Debris Generation

QUESTION 1 Please provide the complete walk-down report, "Report on Watts

Bar Unit 1 Containment Building Walkdowns for Emergency Sump

Strainer Issues," TVAW001-RPT-001, Revision 0.

RESPONSE A compact disc (CD) is enclosed with the requested information in

electronic format.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-4 Chemical Effects QUESTION 1 Please provide the amounts of various Watts Bar containment materials (I) submerged and (ii) in the containment spray zone

for the following materials: aluminum, zinc (from galvanized

steel and inorganic zinc (IOZ) coatings), copper, carbon steel, and uncoated concrete. These amounts should include any

scaffolding material or metallic-based paints (e.g., aluminum-

based paints used on pressure vessels).

RESPONSE The material amounts requested were provided in TVA's response dated April 11, 2006 in response to NRC's Request for Additional

Information dated February 10, 2006 under Plant Materials, Question 2. The quantities provided included scaffolding stored

inside the crane wall that would be subject to spray or

submergence. WBN controls this material to minimize quantities.

There is no other metallic based paint other than those listed in

the April 11, 2006 response.

QUESTION 2 Provide a discussion concerning the post loss-of-coolant accident (LOCA) containment pool pH, including the range of pH values

possible. The values discussed by the licensee at the audit

meeting were more refined than the licensee's response to the NRC

Generic Letter (GL) 2004-02. Please clarify.

RESPONSE The expected sump pH is 7.8 to 8.2 for a LOCA at any time during

the fuel cycle. The sump pH range includes conditions for the

beginning and end of core life, the minimum and maximum

quantities of boron and buffering agent in the RCS, the

accumulators, the refueling water storage tank (RWST), and in the

ice condenser. The range also includes the maximum and minimum

water and ice volumes. The temperature variation of the RWST and

accumulators was included in developing this range.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-5 QUESTION 3 If possible, provide the containment pool temperatures as a

function of time during the emergency core cooling system (ECCS)

mission time for the limiting combination of conditions that

would produce (i) the highest pool temperatures with time, and (ii) the lowest pool temperatures with time.

RESPONSE

SUMP WATER TEMPERATURE

The figure above shows the sump temperature for the limiting

large break LOCA. The analysis is based on one train of ECCS and

containment spray which minimizes containment heat removal. The

analysis also assumed an ultimate heat sink temperature of 88

degrees Fahrenheit (F) which is higher than the current technical

specification limit of 85 degrees F. It also assumes that river

stays at this temperature for the entire 30 day period. This is

a very conservative assumption. It should be noted that TVA has

submitted a Proposed License Amendment Request (WBN-TS-06-09)

dated May 8, 2006, to increase the design basis ultimate heat

sink temperature to 88 degrees F. The RWST temperature was 60 80 100 120 140 160 180 2000.005.0010.0015.0020.0025.0030.00DaysTemperature (F)

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-6 assumed at the technical specification maximum of 105 degrees F.

The amount of ice in the ice condenser was assumed to be at the

minimum safety limit value. It should also be noted that the

maximum pH used to evaluate chemical effects was based on the

maximum amount of ice in the ice bed. Using this ice mass in the

containment analysis would have resulted in a lower sump

temperature and a higher water level for net positive suction

head (NPSH).

A similar analysis for minimum sump temperature has not been

performed. A sensitivity study on the amounts of chemical

precipitants was performed assuming that sump temperature was

lowered considerably. This sensitivity study showed that the

amount of corrosion products produced was lower than in the high

temperature case. As such, the high temperature case is limiting

and there is not a need for a detailed formal analysis of minimum

sump temperature.

QUESTION 4 Provide the Watts Bar plant-specific chemical effects analysis.

Indicate if any more chemical effects related testing is planned.

RESPONSE Chemical effects were evaluated using a correlation developed by

Westinghouse from separate effects precipitation test data (WCAP-16530-NP, Evaluation of Post-Accident Chemical Effects in Containment Sump Fluids to Support GSI-191) and considering the results of the integrated chemical effects tests (ICET). The

evaluation using the WCAP correlation showed a total of 10 milli-

grams per liter (mg/l) for the precipitants based on the total

weight of the precipitants. The total weight of precipitants for

the base case was less than 45 pounds. The precipitants

predicted by the Westinghouse correlations were composed

principally of NaAlSi 3 O 8 (aluminum silicate) with a small amount of AlOOH (aluminum oxide hydroxide). This result was obtained

using the sump temperature profile discussed in response to

Question 3 above and the maximum sump pH was reached at about 30

minutes into the event. The maximum pH will not occur until ice

bed melt out at just over an hour into the event.

Temperature and pH sensitivities were run using the Westinghouse

correlations. Lower temperatures and lower pH result in lower

concentrations and total quantities. A case was run with a ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-7 maximum sump pH of 7.8 corresponding to a minimum ice case with somewhat lower long term sump temperatures. The amount of

precipitant was just over 23 pounds. Using the same temperature

profile with a maximum sump pH of 8.2, results in a total

precipitant weight of less than 28 pounds. Aluminum silicate and

aluminum oxide hydroxide were the only precipitants in all cases.

ICET 5 is the test most representative of the WBN environment of

the ICET series of tests. The boron concentration in the test is

2800 parts per million (ppm) versus a maximum WBN concentration

of 3300 ppm. The buffer is sodium tetraborate contained in the

ice of the ice condenser. A concentration for the sodium

tetraborate is not calculated. The solution used to form the ice

is sampled and has to have a boron concentration of 1800 to 2000

ppm and the pH is required to be between 9.0 and 9.5. The ICET 5

test pH range is 8.0 to 8.5 and the WBN sump pH is between 7.8

and 8.2 as discussed in the response to Question 2 above. The

amount of aluminum evaluated in ICET 5 is much higher than is

present in the plant. Since aluminum is the predominant

precipitant, this difference is significant. The other

significant difference is the ICET temperature is much higher

than is present in the plant. ICET 5 showed concentrations of

dissolved aluminum of 55 milligrams per liter (mg/l) and calcium

of 35 mg/l.

Given the very low quantities of chemical precipitants, TVA does

not plan further chemical testing.

QUESTION 5 During the integrated chemical effects testing (ICET), in certain

chemical environments such as sodium tetraborate, precipitates

formed as the solution cooled from the 140 o F test temperature.

These products could interact with other downstream debris to

cause clogging in narrow passages of downstream components such

as valves and pump internals, or affect internal surfaces of heat

exchangers or the reactor vessel. Describe your evaluation of

potential downstream effects related to interaction with chemical

products and the criteria used to determine that performance of

downstream components is acceptable for your plant-specific

chemical products and debris combination.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-8 RESPONSE The chemical analyses showed that the quantity of precipitants formed would be less than 45 pounds. These formed over the

course of the 30 day mission time not instantaneously. The

precipitants would initially form as small particles. If the

precipitants were to agglomerate, it would be more likely to

occur in the general sump pool as opposed to in piping where the

flow rates are much higher. Larger particles would be more

likely to settle out and be removed as a potential problem for

down stream effects. TVA has included chemical precipitants in

the evaluated particulate load for downstream wear and plugging.

The total quantity of chemical precipitants is so small that

there would be no noticeable effect on heat transfer in the RHR

and containment spray heat exchangers. The chemical load is less

than two percent of the total particulate load and as such does

not appreciably affect wear. The strainer hole size was selected

to be the smallest opening in the ECCS flow path when fuel bottom

nozzle changes are complete. The size of the strainer holes was

chosen to preclude plugging.

QUESTION 6 If all the coatings are assumed to fail, justify why this large

additional debris loading would not increase the analyzed amount

of chemical effects, or add another unanalyzed chemical product.

RESPONSE The principal coating materials in the containment are inorganic

zinc and phenolic topcoat. The chemical testing has established

that there are no noteworthy precipitants associated with the

zinc. Amounts of zinc in excess of the amount present in WBN

were considered in the ICET tests. The cured phenolic is not

chemically active in alkali and acid solutions per manufacturer's

data. The silicon coatings on the steam generator do not need

further consideration as the replacement steam generators do not

have a coating. WBN has not removed the contribution of this

coating from head loss used to design the new strainer. This

becomes margin, therefore, chemical considerations from these

coatings do not need further consideration. The other coating

type in containment is alkyds. This paint does not have a high

resistance to acidic or alkali solutions. While this is the

case, the sump pH is moderately acidic at the start of an

accident but the pH rapidly rises to a mild alkali. This would ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-9 limit chemical effects as would the low sump temperature. The total amount of alkyd paint in containment is 44 pounds. This

small amount in conjunction with low quantity of fiber and the

large strainer area is sized to prevent the formation of a

uniform fiber bed. There will be no measurable effect on head

loss due to alkyd based chemical effects. The alkyd coatings are

already assumed to be a debris source as are the other coatings.

As such, these coatings are accounted for in both head loss and

downstream effects considerations. If the coatings were assumed

to stay on the equipment or structure which the coatings were

applied and were not a debris source, the chemical material could

add to the debris loading as is the case with aluminum, where

absent the chemical consideration there would not be an aluminum

debris term. Given the low quantity and the fact all of the

alkyd coatings are considered as debris, further considerations

from a chemical effects standpoint are not needed.

Net Positive Suction Head / Loss-of-Coolant Accident QUESTION 1 Section 2.3 of ALION-REP-TVA-2739-02, Revision 0, notes that the

maximum containment sump temperature used to establish the

available net positive suction head (NPSH) for the containment

spray pumps during the recirculation phase was 190 o F. Please provide the temperature used to establish the available NPSH for

the residual heat removal (RHR) pumps during the recirculation

phase, and justify if it is different from that used for the

spray pumps during recirculation.

RESPONSE The Westinghouse calculation FSDA-C-597, "RHR Pump NPSH," dated

November 16, 1994 is provided on the enclosed CD. Note that 190

degrees F was used in the analysis. Please note this document is considered "Proprietary Information" as classified by Westinghouse Electric company, LLC for which withholding is being

requested under 10 CFR 2.390(b)(4). Enclosure 2 to this letter

provides the required Affidavit (CAW-06-2163).

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-10 QUESTION 2 Please summarize the methodology and assumptions used to

determine the maximum sump pool water temperature at the

initiation of sump recirculation. Please justify if there is a

deviation of this temperature from the calculated maximum

containment temperature following a LOCA. If such calculation

assumptions were used to maximize containment pressure, please

explain the effect of such assumptions on containment

temperature.

RESPONSE The maximum sump temperature at recirculation was determined from

the containment analysis performed for the replacement steam

generator project. This analysis maximizes initial conditions to

determine the worst case containment pressure for the ultimate

heat sink worst case summer conditions. Some of the assumptions

which maximize containment and sump temperature include: Single train containment spray, Conservative core decay heat, Minimum technical specification ice mass, Single train RHR core cooling, Large break LOCA maximizing initial energy release, Single air return fan operation, Minimum RWST level and Maximum RWST temperature, Conservatively low heat sink area and mass, Maximum steam generator water inventory (includes uncertainty), Conservative RHR and Containment Spray heat exchanger coeffient, [UA], assumptions.

These assumptions are described in TVA's letter to NRC dated

June 7, 2006, "Watts Bar Nuclear Plant (WBN) - Unit 1 - Technical

Specification (TS) Change No. WBN-TS-05 Ice Condenser Ice

Weight Increase Due to Replacement Steam Generators -

Supplemental Information - (TAC No. MC 9270)"

The containment sump liquid temperature is not in equilibrium

with the containment atmosphere temperature at the time of

switchover to sump recirculation. This is due in part to the ice

condenser design where ice melt water mixes with the break

discharge and the containment spray drainage in the lower

compartment and active sump region. Maximum containment ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-11 atmosphere temperatures are approximately 240 degrees F reducing to 200 degrees F at approximately 800 seconds whereas maximum

containment sump liquid temperature is approximately 190 degrees

F reducing to approximately 165 degrees F at 800 seconds. The

cold ice melt water exits the ice condenser and falls through the

lower compartment picking up energy and cooling the air/steam

mixture but does not attain full equilibrium prior to reaching

the sump. The efficacy of this process is based on NRC approved

Westinghouse ice condenser containment analysis models including

scale test results.

For WBN recirculation occurs around 1600 seconds. The

assumptions for NPSH are based on sump temperatures at the

beginning of the event (190 degrees F) which is nearly identical

to the lower compartment temperature at 1600 seconds (191 degrees

F). At the same time the predicted sump temperature is less than

165 degrees F. Therefore, it can be concluded that a

conservative temperature is used when comparing to actual sump

temperature at recirculation or it can be concluded that a

consistent temperature is used when comparing to lower

compartment temperature at sump recirculation.

In summary, the analysis is based on one train of ECCS and

containment spray which minimizes containment heat removal. The

analysis assumes that the ultimate heat sink (river) stays at the

technical specification maximum temperature for the entire 30 day

period. This is a very conservative assumption because it also

minimizes containment heat removal. The RWST temperature was at

the technical specification maximum of 105 degrees F. The amount

of ice in the ice condenser was assumed to be at the minimum

safety limit value. The assumptions were set to produce the

maximum containment pressure. Other assumptions made were that

ECCS spill water is at the injection temperature and there is

limited heating of the ice melt water. Changing these last two

assumptions would increase sump temperature. Because of the ice

condenser containment design these assumptions have a minimal

impact on sump temperature at the initiation of sump

recirculation. The containment spray in the upper compartment is

not condensing steam. The spray flow does not provide heat

removal from the containment as long as ice is present. This

water enters the sump at the RWST temperature. The ice condenser

melt water even with different assumptions enters the sump pool

at a temperature below 100 degrees F. These are the two largest

sources of water prior to sump recirculation. The NPSH

calculations were performed assuming a sump temperature of 190

degrees F. The sump temperature at the time of switchover is ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-12 less than 190 degrees F and is decreasing. Containment temperature at this time is approximately 190 degrees F.

QUESTION 3 Please provide copies of the following calculation reports

referenced in Section 2.5 of ALION-REP-TVA-2739-02, Revision 0:

  • N3-74-4001, R12 - RHR System
  • Watts Bar calculation EPM-RCP-120291 Revision 2, Containment Spray Pump Net Positive Head (NPSH) Calculation.
  • Westinghouse calculation FSDA-C-597 dated 11/6/94 - RHR Pump NPSH. RESPONSE The requested information is provided on the enclosed CD. Note that the containment spray system description (N3-72-4001) is at

a higher revision level than requested. The changes are noted in

the revision log.

Debris Transport QUESTION 1 Please provide ALION's FLOW-3D Version 9 executable and the corresponding input deck for the Watts Bar analysis.

RESPONSE This executable was separately provided for NRC use by ALION. It is TVA's understanding that ALION considers this information to

be proprietary.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-13 Downstream Effects (Core)

These questions refer to the Watts Bar downstream effects calculations found in calculation CN-CSA-05-36, Fuel Evaluation:

QUESTION 1 Page 5 states that a fiber bed of less than 0.125 inch at the core inlet is acceptable. Page 40 states that a 7-foot head loss

is predicted for a 1/8-inch fiber bed. What head loss would be

produced at the core inlet following a large cold leg break?

Please explain and justify whether adequate flow to the core

would be provided with this head loss.

RESPONSE The 1/8-inch fiber bed is a pass/fail criterion based, in part, on NRC calculations of head loss in the Safety Evaluation of Nuclear Energy Institute (NEI) 04-07, Pressurized Water Reactor Sump Performance Evaluation Methodology. The 7-foot head loss approximates the maximum water head in the downcomer for a cold

leg break. No attempt was made to calculate the head loss

associated with the 1/8-inch fiber bed.

QUESTION 2 Page 7 states that 95 percent of fibrous material would be trapped in the bottom fuel nozzle and that the remaining 5

percent is assumed to be returned to the sump. This assumption

is stated to be based on the similarity of the dimensions of the

flow path through the sump screen and the dimensions through the

screen at the bottom of the fuel.

a. Please provide drawings of the fuel element inlet screens showing the dimensions of the flow path into the fuel.
b. Provide comparisons of the dimensions of the sump screen holes to the debris screen at the inlet at the fuel

elements.

RESPONSE Drawings of the fuel design are shown in the Updated Final Safety Analysis Report (UFSAR), Section 4.2. Detailed drawings of the ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-14 fuel are considered proprietary to the fuel vendor and have been separately discussed with NRC staff on behalf of WBN on

June 8-9, 2006. It is TVA's understanding that information was

sufficient to disposition this RAI question.

QUESTION 3 Page 10 lists the volume concentration for 3M fiberglass passing through the sump screens as 2.351e-3 and the total fibrous

concentration to be 2.559e-3. Page 5 of calculation CN-CSA-05-14

lists the fibrous concentration passing through the sump screens

as 5 parts per million. Please relate these quantities.

RESPONSE The volume concentration on page 10 is an initial concentration value used in the fuel evaluation, and is the ratio of fiber

volume to sump pool volume assuming no sump screen filtering has

occurred.

The mass concentration on page 5 of CN-CSA-05-14 is used in the

wear and abrasion calculations, and is the ratio of fibrous mass

to sump pool water mass assuming that the entire fiber load has

passed through the sump screen one time. Therefore, the fiber

mass is multiplied by 0.05, and then divided by the sump pool

water mass.

QUESTION 4 Page 10 states that decay heat is based on American Nuclear Society (ANS) Standards 79 with 2 Since this is a LOCA calculation, please explain why the decay heat was not calculated

using ANS Standard 71 + 20 percent to be consistent with Appendix

K to Title 10 Code of Federal Regulations Part 50.

RESPONSE The evaluation method employed is based on the decay heat rate at the time of ECCS switchover from RWST injection to containment

sump recirculation and maintains the decay heat as a constant for

the time period considered in the calculation. While the

American Nuclear Standard (ANS) 1979 + 2 sigma decay heat curve

may slightly under-predict the head load for a cold leg break at

the time of switchover from RWST injection to sump recirculation, ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-15 the use of constant decay heat at time of switchover is conservative for the overall calculation.

QUESTION 5 Page 17 shows that following a hot leg break, the fiber bed at the core inlet will exceed the 1/8-inch acceptance criterion

within the first hour of recirculation. Please explain the

effect of this condition on the core. Describe alternate flow

paths for water to reach the core. Describe the transport and

deposition of debris through these alternate flow paths.

RESPONSE Alternate flow paths are currently being considered generically under a PWR Owners Group program. Calculations such as those

suggested by NRC have not been performed at this time.

QUESTION 6 The staff plans to perform audit calculations using the TRACE code to evaluate flow of water to the core through alternate flow

paths in the event that the core inlet becomes blocked. Please

provide the staff with the location and dimensions of any

alternate flow paths through which water could reach the core

under these circumstances. Provide the height of flow holes

above the bottom of the core as well as their radial distribution

about the core periphery.

RESPONSE This information was also provided to NRC by Westinghouse in a separate audit meeting on June 8-9, 2006, on behalf of WBN. It

is TVA's understanding that Westinghouse considers this

information to be proprietary.

QUESTION 7 Pages 18 and 19 show the depletion of fibrous material in the

recirculating water for hot and cold leg breaks. A range of 97

percent to 95 percent depletion on the sump screens and a range

of 95 percent to 50 percent depletion on the fuel screens is

assumed. The depletion fraction is assumed to remain constant ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-16 with time for each cycle as the recirculating water passes the screens. Please explain whether a fiber so short or a particle

so small that it can pass through the sump screen and the fuel

inlet screens once, will also pass through the sump screens and

fuel inlet screens for sequent recirculation passes. Please

justify your assumptions.

RESPONSE As previously noted, in the NRC's safety evaluation for NEI 04-07, debris that is larger than the sump screen holes may

pass through the sump screens. This may be due to orientation of

the debris as it passes through the screen, or due to deformation

of debris enabling it to pass through the screen. Thus, not all

debris that passes through the sump screen is "too small" to be

collected on subsequent passes. Therefore, this debris may be

filtered in subsequent passes. This approach provides for a

conservative estimation of the collection of fibrous debris.

QUESTION 8 Pages 36 and 37 state that the fuel assembly support grids

typically have flow dimensions of 0.04 to 0.115 inches. How do

these dimensions compare with those of the Watts Bar fuel? Page

37 further states that the support grids may cause a fiber bed to

form across a given elevation to resemble a bed forming across a

flat plate. Please explain how the trapping of debris within the

support grids and the resulting effect on core heat transfer has

been evaluated for Watts Bar. In particular, consider the

possibility that a layer of debris and steam forms between a fuel

rod and the adjacent support grid so as to prevent water from

contacting the fuel rod surface within the support grid. Please

explain whether excessive local temperatures would be encountered

in this scenario.

RESPONSE With a 95 percent capture efficiency at the fuel bottom nozzle, this location became limiting with respect to

potential blockage. An assumed capture efficiency of 95

percent for the sump screen allows only 5 percent of the

debris reaching the screen to pass through it. If fuel

nozzle is taken to be 95 percent efficient at capturing

debris, then only 0.25 percent of the debris that reaches

the sump screen is available to the fuel. With the 50 ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-17 percent to 95 percent capture of fibrous debris on the fuel bottom nozzle, only 0.125 percent to 0.0125 percent of the

fiber reaching the sump screen was available to the first

support grid of the fuel. This amount of fibrous debris

available for collection along the active length of the fuel

is very small compared to the amount of fibrous debris that

might be collected on the fuel bottom nozzle. With the

large depletion of fibrous debris at the sump screen and the

bottom nozzle, there was insufficient remaining fibrous

debris to evaluate blockage higher in the fuel. As noted

above, the effects of potential debris collection behind

spacer grids is currently being considered generically under

a PWR Owners Group program.

QUESTION 9 Pages 43 through 47 evaluate the potential of particulate material such as reflective metal fragments, concrete, latent

containment debris and paint chips to flow into the core. It is

generally concluded that this material will not reach the core, but will settle out in the lower plenum of the reactor vessel.

Please provide an evaluation of the potential to clog the core

inlet due to filling the lower reactor vessel with a volume of

debris.

RESPONSE The debris ingestion evaluation determined that the total volume of particulate and coatings debris that may pass into the

containment sump following switchover of the ECCS is

approximately 16 cubic feet (ft 3). Based on a preliminary evaluation, the volume of the reactor vessel lower plenum below

the core support plate is calculated to be approximately 612 ft 3 for Watts Bar. If all of the approximately 16 ft 3 of the debris entering the ECCS downstream of the screen is conservatively

assumed to settle out in the lower plenum and assuming that the

debris bed is twice the theoretical volume of the debris (i.e.,

32 ft 3), the free volume of the lower plenum would not be challenged by blockage and a sufficient area would remain open to

provide for continued flow into the core.

In addition, the velocity in the lower vessel plenum is higher

than the velocity in the sump pool. Any material that will drop

out in the reactor vessel will settle out in the sump pool and

not make it to the reactor vessel.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-18 QUESTION 10 Page 43 refers to recent internal studies using disk-like particulates of various shapes with a specific gravity of 1.6.

These studies were reported to have shown that particulates

having a characteristic length of about 70 mils and thickness of

5 mils or greater would settle out in a reactor vessel lower

plenum. Please provide documentation for this study describing

the test apparatus and procedures. What vertical velocities were

used?

RESPONSE TVA will provide the documentation for the recent internal

Westinghouse studies using disk-like particulates of various

shapes in the supplemental response.

QUESTION 11 Page 47 states that coating debris no larger than 0.02 inch are

expected to be transported through the fuel. Although this

statement may be true for hot leg breaks, it would not be true

for large cold leg breaks where the boiling process would cause

this material to congregate in the core. Please provide the

results of an evaluation of the effect of paint debris on core

boiling heat transfer, including the effect of reaction products

from the mix of chemicals which would be concentrated in the core

by the boiling process following a cold leg break. The effect of

the high-radiation field within the core on the chemical and

physical nature of the mixture within the core needs to be

considered. The potential for heat transfer loss from a chemical

film that might form or be plated out by the boiling process

needs to be evaluated. Please justify that adequate heat

transfer will be maintained during the long-term cooling period.

RESPONSE There is very little material in the core at the initiation of hot leg recirculation besides boron and sodium tetraborate.

There are less than 1.5 pounds of chemical compounds formed at

three hours into the accident. This is negligible compared to

the amount of boron. This 1.5 pounds is present in the entire

sump pool not just the core. Even assuming all 1.5 pounds was in ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-19 the core at time zero and dissolved in the water, it would have no effect on heat transfer. As a point of comparison, there is

over 19,000 pounds of boron in the sump water. The boron is

dissolved in the water not suspended solids. Boron plates out on

the fuel when the water boils at the clad surface. The effect of

boron was reviewed by the NRC for WBN very recently during the

license amendment (Amendment 40) associated with the inclusion of

the tritium production rods. The coatings are particulates in

suspension not dissolved which would stay in the liquid. The

inorganic zinc coating fails as a small particulate. The

phenolic fails as chips. The chips will either settle out on the

floor of the containment or be trapped on the sump screen. There

will be virtually no phenolics in the core. The silicon coating

on the steam generators is being eliminated with the installation

of the replacement generators. The new generators are being

installed during the Fall 2006 outage and thus this coating

material is not an issue for the core. The remaining coating is

an alkyd which is present in very small quantities. There is a

total of 44 pounds of this material. Therefore, it is TVA's

conclusion that coatings in the core in the first 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> are not

of a concern.

Also, the following conservatisms are not directly credited but

should be considered before pursuing this issue further:

1. It was assumed that all coatings failed and were available for transport to the sump strainers for evaluation of head

loss. Most coatings either inside or outside of the ZOI of

the break, will not fail whether qualified or not.

2. The high energy jet from a large break has a very short duration. In a fraction of a second, the RCS pressure will

drop 500 pounds per square inch (psi). By ten seconds, the

pressure is well below 1000 psi and by 30 seconds the RCS

pressure is about 100 psi.

3. All of the RCS piping has been rigorously analyzed. While it has been assumed that a break can occur at any location, the reality is that if a break were to occur, it would be

where stresses are high. These are known and stresses are

going to be at welds to the reactor vessel, coolant pumps, or steam generator.

4. The piping is restrained in these locations such that if a break occurred the ends of the break will not fully offset.

Much of the jet energy will be dissipated on the pipe ends ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-20 and the reactor coolant pumps, steam generators, or reactor vessel.

For large breaks, there is no sustained jet to strip coatings.

In addition, the ends of the pipes will not offset to direct a

jet directly at floors or walls. Small breaks that can have a

sustained jet are small and impact a very small area. Such small

breaks may erode coatings but the affected area will be small and

the coatings debris generated is also small. Few of the coatings

are chemically reactive. Thus, the conservatism in the modeling

of coating debris is large.

QUESTION 12 Please provide an evaluation of the concentration of various materials that would occur following a large cold leg break under

the conditions that water enters the bottom of the core and is

boiled leaving all dissolved and suspended material behind.

Consider that hot leg injection begins at 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> after the

accident. Consider all the constituents within the ECCS water

including boric acid, containment spray buffering agents, paint

and fibrous debris.

a. Provide graphs showing the concentration of each constituent as a function of time.
b. Concentration of material within the reactor core will depend on the water volume that is assumed to be available

for mixing. Since the core will be boiling at low pressure

it will be in a highly voided condition as will the upper

plenum. Please provide and justify the values used for core

void fraction and upper plenum void fraction used in the

concentration analysis. Provide justification for the

fraction of the lower plenum volume, which is included, as

well as for any other contribution to the total mixing

volume.

c. Provide the flow rates into the reactor system as a function of time during cold leg recirculation and during hot leg

recirculation.

d. Provide and justify the concentrations flowing into the reactor core as a function of time for each constituent in

the ECCS water for both cold leg and hot leg recirculation.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-21 Consider boric acid, containment spray buffering solution, paint debris, and fibrous debris.

RESPONSE The PWR Owners Group Program is looking generically at post-LOCA

core heat transfer, however based on the response to Question 4

above, TVA does not consider chemical effects on core heat

transfer to be an issue for WBN.

QUESTION 13 Following the initiation of hot leg recirculation, material which passes through the sump screen will be available to flow to the

reactor core from the top. Please provide a comparison of flow

restrictions at the top of the core including the fuel elements

to that of the sump screens.

RESPONSE Drawings of the fuel design are included in the UFSAR. Detailed drawings of the fuel are considered proprietary to the fuel

vendor and have been separately discussed with the NRC staff on

behalf of WBN on June 8 and 9, 2006. If WBN can facilitate

additional data transfer please let us know.

Head Loss Testing

QUESTION 1 Please provide the Sequoyah head loss test report that may provide validation that the paint chips would not have

transported in the Watts Bar tests had the flow velocities been

more prototypical.

RESPONSE The Sequoyah Nuclear Plant test report is enclosed on the CD for

your information.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-22 QUESTION 2 Please provide the paint chip specification parameters used in

the cell floor drain analyses, specifically the floor tumbling

velocity and the settling velocity for the turbulence model.

RESPONSE Test data on the transport metrics for paint chips is limited.

However, in general, the available test data shows that the

tumbling and settling velocities of paint chips are more

dependent on the paint chip thickness and density than the paint

chip size.

NUREG/CR-6772, "GSI-191: Separate-Effects Characterization of

Debris Transport in Water," dated August 31, 2002, (Section

3.3.2) discusses tests that were performed on epoxy-based paint

chips ranging in size from 1-inch x 1/2-inch to 1/8-inch x 1/8-

inch. The chips were approximately 15 mils thick. The results

of the tests showed that the chips first started tumbling at 0.4

feet per second (ft/s). At 0.45 ft/s bulk motion occurred and at

0.5 ft/s transport was almost instantaneous. The settling

velocity for these chips was also reported as a single value

(0.15 ft/s).

Testing performed by ALION (formerly ITSC) in 1999 for

Fitzpatrick Nuclear Power Plant showed similar results for the

settling of 5 mil thick epoxy paint chips. The chips ranged in

size, but had an approximate settling velocity of 0.08 ft/s.

QUESTION 3 Please provide an evaluation of the 3M fiber glass insulation to

justify why other fiber surrogate material can be used to

represent the 3M fiber glass in the head loss test.

RESPONSE No surrogate material was used for 3M-M20C fiber glass insulation

in the head loss test performed for the WBN strainers. The test

used 3M. Therefore, an evaluation of surrogate material is not

required.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-23 Downstream Effects (Component)

QUESTION 1 Please provide the downstream component hardware change plan, design and completion report.

RESPONSE A hardware change that resulted from the downstream effects

evaluation is to replace the orifice in 1-FE-63-170 in the common

header downstream of the centrifugal charging pumps but upstream

of the four boron injection line throttle valves. This will add

head loss upstream of the individual branch line orifices and the

branch line throttle valves to reduce the pressure drop required

across the throttle valves and allow the valves to opened such

that potential blockage of the valves does not occur.

Please see the Westinghouse report, LTR-SEE-06-118, Revision 1, Watts Bar ECCS Analysis Report, dated June 21, 2006, on the

enclosed CD. Please note this document is considered "Proprietary Information" as classified by Westinghouse Electric company, LLC for which withholding is being requested under

10 CFR 2.390(b)(4). Enclosure 2 to this letter provides the

required Affidavit (CAW-06-2169).

QUESTION 2 C hemical Considerations

a. During the ICET, in certain chemical environments such as sodium tetraborate, precipitates formed as the solution

cooled from the 140 o F test temperature. These products could interact with other downstream debris to cause

clogging in narrow passages of downstream components such as

valves and pump internals, or affect internal surfaces of

heat exchangers or the reactor vessel. Describe your

evaluation of potential downstream effects related to

interaction with chemical products and the criteria used to

determine that performance of downstream components is

acceptable for your plant-specific chemical products and

debris combination.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-24 RESPONSE The chemical constituents are considered as part of the downstream effects. TVA notes that the amount of chemical

constituents is small compared to the other debris.

The total amount of chemical precipitants is less than 45 pounds. The latent dirt weight is 170 pounds. The design basis coating debris is over 2000 pounds.

As a comparison, the amount of boron in the sump water is 19,000

pounds. The chemical precipitants quantity is so low that heat

transfer in heat exchangers will not be degraded. Similarly the

surface area of the reactor vessel and main loop RCS piping is

sufficiently large that any film layer will be so thin that it

will not have any affect. Also, the reactor vessel is stainless

steel. If the chemicals will plate out on the vessel, it will

also plate out on the RMI insulation that has a huge surface area

as well as the outside of RCS piping, and the sump strainer

surface. This means that the film layer if it exists, will be so

thin as to have no impact on the operation of equipment

downstream of the sump screen.

b. Explain how the interaction of downstream chemical effects combined with debris will be evaluated.

RESPONSE The chemicals are considered as one of several particulate debris types. There are no materials in the downstream that are not

present in the sump pool at large. The chemical precipitants are

such a small fraction of the total debris source term that it

will not result in a different behavior. There is no indication

that chemical precipitants bind to other debris present in WBN

containment. However, should chemical precipitants bind to other

debris, it would occur in the sump pool. This would result in

somewhat larger particles. This would make the particles more

likely to settle out or not make it through the strainer to have

a downstream effect. Particles that are small enough to go

through the strainer are too small to be captured downstream.

The chemical precipitants are being considered as a downstream

particulate with other particles that will go through the

strainer.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-25 QUESTION 3 Throttle Valves

a. The TVA response to NRC GL 2004-02 dated September 1, 2005, indicated that an updated evaluation will be performed

following final selection of strainer design and that the

conclusions will be provided in a supplemental response.

Describe the approach, including testing program, and

schedule to finalize throttle valve positions/openings.

RESPONSE Based on a walkdown of a sample of Unit 1 throttle valves, a position or number of turns open was determined by correlating

the valve stem position measured, to the valve stem position

measurements on the valve drawing.

As a result of this walkdown, it could not be concluded that the

boron injection valves were open such that the valve blockage

would not occur. Steps have been taken to reposition these

valves such that adequate clearance is available for potential

debris passing through the sump strainers as discussed in the

response to Question 1 of this section. The valve position will

be recorded during the performance of 1-SI-63-905, "Boron

Injection Check Valve Flow Test During Refueling Outages," with

the current acceptance criterion and an additional acceptance

criteria that the valves be open at least 1.5 turns. This

approach and applicable procedures will be finalized during the

Design Change process for the installation of the orifice.

The remaining valves could be positively confirmed to have an

adequate clearance such that blockage of these valves due to

debris passing through the sump strainers would not occur. The

final calculation has not been issued since it is impacted by the

revised debris generation results. As previously committed, the

final results will be provided in a supplemental response.

The strainer design includes a hole size of 0.085-inch diameter.

An additional orifice is being added into the centrifugal

charging pump injection line to permit the throttle valves to be

opened wider. The new throttle valve position will provide an

opening that is more than 1.15 times greater than the strainer

hole size. Thus, the throttle valve will not be subject to

potential blockage from strainer bypass.

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-26 b. Explain how NRC Information Notice 96-27, and the recent NRC Throttle Valve Testing (NUREG/CR-6902), when available, will

be considered in the throttle valve evaluation.

RESPONSE With the modification discussed above, all valves will have

adequate clearance such that the valves will not be susceptible

to debris blockage. If the debris is small enough to pass

through the 0.085-inch nominal diameter hole in the sump

strainers, the debris will also pass through the throttle valves

given that an additional acceptance criteria for valve position

is required. As a result, NRC Information Notice 96-27, "Potential Clogging of High Pressure Safety Injection Throttle

Valves During Recirculation" and NUREG/CR-6902, "Effects of

Insulation Debris on Throttle-Valve Flow Performance," have been

addressed since no credit is being given for ECCS pumps

pulverizing the material that passes through the sump strainers.

QUESTION 4 Methodology

a. The TVA response to GL 2004-02 dated September 1, 2005, indicated that the evaluation of downstream effects is

consistent with the Westinghouse Commercial Atomic Power (WCAP) Report, WCAP-16406-P, and during the audit the

licensee confirmed that they are not taking any exceptions

to the WCAP-16406-P methodology. The NRC staff has

outstanding questions (NRC letter dated October 27, 2005) on

the WCAP-16406-P methodology, and has recently been

requested by the Westinghouse Owners Group to formally

review WCAP-16406-P as a topical report. Explain how you

plan to address comments that result in a revision or

addendum to the methodology for topics such as:

  • Validation of potential non-conservative assumptions,
  • Conservatism to account for uncertainties,
  • Wear rates correlated to testing data,
  • Debris adhesion to solid surfaces, and

ENCLOSURE 1 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1-27

  • Downstream matting effect.

RESPONSE Westinghouse has responded to the questions asked the NRC's

October 27, 2006 letter. These responses were discussed with NRC

staff members during a technical exchange meeting held in May, 2006. It is Westinghouse's opinion that the responses to the

questions poised by NRC do not affect or change the evaluation

methods described in the WCAP. Rather, those responses are

considered clarificiation of the methods presented in

WCAP 16406-P

Following that meeting, a draft Revision 1 of WCAP 16406-P that

contains line-in/line-out edits was prepared and submitted to NRC

in June 2006. This submittal was made to support NRC's review

and issuance of a Safety Evaluation Report on WCAP 16406-P. NRC

is currently reviewing this document.

Sump Structure QUESTION 1 Please provide the strainer final design and structure analyses

report. If it is not available now, please indicate when it will

be available.

RESPONSE The final design and structural analysis report has received TVA

review and is being held open by the vendor pending shop

fabrication of the strainer packages. This fabrication is

currently underway. Any required design changes will be reviewed

for incorporation during this shop fabrication and assembly

process. Assembly, drawing issuance, and final analysis are

expected by the end of July. The analysis will be submitted for

your use following final issuance in the supplemental response.

ENCLOSURE 1 ATTACHMENT WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS E1A-1 LIST OF DOCUMENTS ON COMPACT DISC (CD)

Debris Generation

Question 1 TVAW001-RPT-001 - "Report on Watts Bar Unit 1 Containment Building

Walkdowns for Emergency Sump Strainer Issues," Revision 0.

Net Positive suction Head/Loss-of-Coolant Accident

Question 1 FSDA-C-597 "RHR Pump NPSH," dated November 16, 1994 (PROPRIETARY INFORMATION)

Question 3 N3-72-4001 - Containment Spray System Description, Revision 16.

N3-74-4001 - Residual Heat Removal System Description, Revision

12.

Watts Bar Calculation EPM-RCP-120291, "Containment Spray Pump Net

Positive Head (NPSH)," Revision 2.

Westinghouse Calculation FSDA-C-597 - See Question 1 above.

Head Loss Testing

Question 1 Sequoyah Nuclear Plant head loss test report.

Downstream Effects

Question 1 LTR-SEE-06-118, Revision 1, Watts Bar ECCS Analysis Report, dated June 21, 2006. (PROPRIETARY INFORMATION)

ENCLOSURE 2 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS WESTINGHOUSE APPLICATIONS FOR WITHHOLDING PROPRIETARY INFORMATION CAW-06-2163 and CAW-06-2169

ENCLOSURE 3 WATTS BAR NUCLEAR PLANT (WBN) UNIT 1 GENERIC LETTER 2004-02 RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION NRC AUDIT OF CONTAINMENT SUMP MODIFICATIONS LIST OF OPEN ITEMS E3-1 The following items remain open in the NRC Audit scope for the containment sump:

1. The final debris calculation will be provided as part of an update of the remaining open items.

[Break Selection and Zone of Influence Analysis, Question 1]

2. A hardware change that resulted from the downstream effects evaluation, is to replace the orifice in 1-FE-63-170 in the

common header downstream of the centrifugal charging pumps

but upstream of the four boron injection line throttle

valves. [Downstream Effects (Component), Question 1]

3. TVA will provide the documentation for the recent internal studies using disk-like particulates of various shapes in

the supplemental response. [Downstream Effects (Core), Question 10]

4. The final results of the Downstream Effects Calculation will be provided in a supplemental response. [Downstream Effects (Component), Question 3a]
5. The design and structural analysis The analysis will be submitted for your use following final issuance in the

supplemental response. [Sump Structure, Question 1]