August 30, 2005 Mr. Michael A. Balduzzi Site Vice President Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - PILGRIM NUCLEAR POWER STATION
Dear Mr. Balduzzi:
On August 3, 2005, the NRC staff completed its performance review of Pilgrim Nuclear Power Station for the first half of the calender year 2005 assessment cycle. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results over the previous twelve months. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include physical protection information. A separate letter designated and marked as Exempt from Public Disclosure in accordance with 10 CFR 2.390 will include the physical protection review and resultant inspection plan.
Plant performance for the most recent quarter was within the Licensee Response Column of the NRCs Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we currently plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
Additionally, on July 14, 2005, the staff issued a severity level III Notice of Violation in accordance with the NRCs Enforcement Policy. The NRC has concluded that information regarding the reason for the violation, the corrective actions taken and planned to correct the violation and prevent recurrence, and the date when full compliance was achieved are already adequately addressed on the docket in the letter transmitting the Notice of Violation (EA -039).
The enclosed inspection plan details the inspections, less those related to physical protection scheduled through March 31, 2007. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature.
The inspections in the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle review.
Mr. Michael A. Balduzzi 2
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at 610-337-5227 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Clifford J. Anderson, Chief Projects Branch 5 Division of Reactor Projects Docket Nos. 50-293 License Nos. DPR-35
Enclosure:
Pilgrim Inspection/ Activity Plan
Mr. Michael A. Balduzzi 3
cc w/encl:
G. J. Taylor, Chief Executive Officer, Entergy Operations M. Kansler, President, Entergy Nuclear Operations, Inc.
J. T. Herron, Senior Vice President and Chief Operating Officer C. Schwarz, Vice-President, Operations Support S. J. Bethay, Director, Nuclear Safety Assurance O. Limpias, Vice President, Engineering J. F. McCann, Director, Licensing C. D. Faison, Manager, Licensing M. J. Colomb, Director of Oversight, Entergy Nuclear Operations, Inc.
B. S. Ford, Manager, Licensing, Entergy Nuclear Operations, Inc.
T. C. McCullough, Assistant General Counsel S. Lousteau, Treasury Department, Entergy Services, Inc.
R. Walker, Department of Public Health, Commonwealth of Massachusetts The Honorable Therese Murray The Honorable Vincent deMacedo Chairman, Plymouth Board of Selectmen Chairman, Duxbury Board of Selectmen Chairman, Nuclear Matters Committee Plymouth Civil Defense Director D. OConnor, Massachusetts Secretary of Energy Resources J. Miller, Senior Issues Manager Office of the Commissioner, Massachusetts Department of Environmental Protection Office of the Attorney General, Commonwealth of Massachusetts Electric Power Division, Commonwealth of Massachusetts R. Shadis, New England Coalition Staff D. Katz, Citizens Awareness Network Chairman, Citizens Urging Responsible Energy J. Sniezek, PWR SRC Consultant M. Lyster, PWR SRC Consultant C. McCombs, Acting Director, MEMA and Commonwealth of Massachusettts, SLO Designee Commonwealth of Massachusetts, Secretary of Public Safety Institute of Nuclear Power Operations (INPO)
Mr. Michael A. Balduzzi 4
Distribution w/encl: (via E-mail)
S. Collins, RA M. Dapas, DRA S. Lee, RI EDO Coordinator C. Anderson, DRP D. Florek, DRP RidsNrrDipmIipb@nrc.gov J. Shea, PM, NRR R. Ennis, NRR W. Raymond, DRP, Senior Resident Inspector C. Welch, DRP, Resident Inspector A. Ford, DRP, Resident OA Region I Docket Room (with concurrences)
ROPreports@nrc.gov DOCUMENT NAME: S:\\ROP-6 Mid-Cycle Review\\2005 Mid-Cycle Letters\\Pilgrim Mid-Cycle Letter.wpd SISP Review Complete: CJA (Reviewers Initials)
After declaring this document An Official Agency Record it will be released to the Public.
To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RI/DRP RI/DRP
/
NAME APatel CAnderson DATE 08/10/05 08/30/05 OFFICIAL RECORD COPY
Pilgrim Inspection / Activity Plan 08/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 1 of 2 08/30/2005 10:28:20 Report 22 3
7111111B
- LICENSED OPERATOR REQUAL PROGRAM Baseline Inspections 09/12/2005 09/16/2005 Licensed Operator Requalification Program IP 7111111B 1
Baseline Inspections 09/19/2005 09/23/2005 Licensed Operator Requalification Program IP 7111111B 1
1 7111112B
- MAINTENANCE RULE Baseline Inspections 08/29/2005 09/02/2005 Maintenance Effectiveness IP 7111112B 1
1 7112203
- PUB RAD SAFETY - REMP Baseline Inspections 09/12/2005 09/16/2005 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control P IP 7112203 1
1 71121
- OCC RAD SAFETY Baseline Inspections 11/07/2005 11/11/2005 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 11/07/2005 11/11/2005 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 11/07/2005 11/11/2005 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 11/07/2005 11/11/2005 Performance Indicator Verification IP 71151 1
1 71121
- OCC RADIATION SAFETY Baseline Inspections 01/30/2006 02/03/2006 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 01/30/2006 02/03/2006 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 01/30/2006 02/03/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 01/30/2006 02/03/2006 Performance Indicator Verification IP 71151 1
1 7111107B
- HEAT SINK Baseline Inspections 02/06/2006 02/10/2006 Heat Sink Performance IP 7111107B 1
6 7111121
- SSD&PC Baseline Inspections 04/10/2006 04/14/2006 Safety System Design and Performance Capability IP 7111121 1
Baseline Inspections 04/24/2006 04/28/2006 Safety System Design and Performance Capability IP 7111121 1
Baseline Inspections 05/08/2006 05/12/2006 Safety System Design and Performance Capability IP 7111121 1
Baseline Inspections 05/15/2006 05/19/2006 Safety System Design and Performance Capability IP 7111121 1
1 7112201
- PUB RAD SAFETY - RETS Baseline Inspections 06/12/2006 06/16/2006 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems IP 7112201 1
Baseline Inspections 06/12/2006 06/16/2006 Performance Indicator Verification IP 71151 1
3 TRI FIRE
- TRIENNIAL FIRE PROTECTION INSPECTION Baseline Inspections 07/24/2006 07/28/2006 Fire Protection [Triennial]
IP 7111105T 1
Baseline Inspections 08/07/2006 08/11/2006 Fire Protection [Triennial]
IP 7111105T 1
1 71121
- OCC RAD SAFETY Baseline Inspections 08/21/2006 08/25/2006 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 08/21/2006 08/25/2006 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 08/21/2006 08/25/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 08/21/2006 08/25/2006 Performance Indicator Verification IP 71151 1
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Pilgrim Inspection / Activity Plan 08/01/2005 - 03/31/2007 Inspection Type Inspection Activity Planned Dates Start End No. of Staff on Site Title Unit Number Page 2 of 2 08/30/2005 10:28:20 Report 22 1
7112202
- PUB RAD SAFETY - RADWASTE Baseline Inspections 09/25/2006 09/29/2006 Radioactive Material Processing and Transportation IP 7112202 1
Baseline Inspections 09/25/2006 09/29/2006 Performance Indicator Verification IP 71151 1
5 7111401
- EXERCISE EVALUATION & EP PI VERIFICATION Baseline Inspections 10/23/2006 10/27/2006 Exercise Evaluation IP 7111401 1
Baseline Inspections 10/23/2006 10/27/2006 Performance Indicator Verification IP 71151 1
1 71121
- OCC RAD SAFETY Baseline Inspections 12/11/2006 12/15/2006 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 12/11/2006 12/15/2006 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 12/11/2006 12/15/2006 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 12/11/2006 12/15/2006 Performance Indicator Verification IP 71151 1
3 2/26 EXM
- OPERATOR LICENSING INITIAL EXAMS Not Applicable 01/29/2007 02/02/2007 PILGRIM INITIAL EXAM (FY07)
U01637 1
Not Applicable 02/26/2007 03/01/2007 PILGRIM INITIAL EXAM (FY07)
U01637 1
1 71121
- OCC RAD PROT Baseline Inspections 02/05/2007 02/09/2007 Access Control to Radiologically Significant Areas IP 7112101 1
Baseline Inspections 02/05/2007 02/09/2007 ALARA Planning and Controls IP 7112102 1
Baseline Inspections 02/05/2007 02/09/2007 Radiation Monitoring Instrumentation and Protective Equipment IP 7112103 1
Baseline Inspections 02/05/2007 02/09/2007 Performance Indicator Verification IP 71151 1
This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.