IR 05000293/2013006

From kanterella
Jump to navigation Jump to search
Revised Mid-Cycle Performance Review and Inspection Plan - Pilgrim Nuclear Power Station (Report 05000293-13-006)
ML13248A317
Person / Time
Site: Pilgrim
Issue date: 09/03/2013
From: Fred Bower
NRC/RGN-I/DRP/PB5
To: Dent J
Entergy Nuclear Operations
Bower F
References
IR-13-006
Download: ML13248A317 (5)


Text

UNITED STATES mber 3, 2013

SUBJECT:

MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN - PILGRIM NUCLEAR POWER STATION (REPORT 05000293/2013006)

Dear Mr. Dent:

On August 15, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of the Pilgrim Nuclear Power Station (Pilgrim). The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from July 1, 2012, through June 30, 2013. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined that overall, Pilgrim operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Pilgrim during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low safety significance (Green), and all performance indicators demonstrated that your performance was within the nominal, expected range (Green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2014.

Routine inspections performed by resident inspectors are not included in the inspection plan. In addition to baseline inspections, the NRC will perform Temporary Instruction 2515/182, Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping and Tanks, Inspection Procedure (IP) 60853, Onsite Fabrication of Components and Construction of an Independent Spent Fuel Storage Installation, IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants, IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants, and IP 60856.1, Review of 10 CFR 72.212(b) Evaluations at Operating Plants. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Section 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS)

component of the NRC's Agencywide Document Access and Management System (ADAMS).

ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at (610) 337-5200 with any questions you have regarding this letter.

Sincerely,

/RA/

Fred L. Bower III, Acting Chief Projects Branch 5 Division of Reactor Projects Docket No: 50-293 License No: DPR-35 Enclosure: Pilgrim Inspection/Activity Plan cc w/encl: Distribution via ListServ

ML13248A317 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE klm RI/DRP RI/DRP RI/DRP MSchneider/SMS via NAME SShaffer/SWS FBower/FLB email DATE 8/27/13 8/27/13 9/3/13

Page 1 of 2 Pilgrim 08/30/2013 09:12:15 Inspection / Activity Plan Report 22 07/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 7111107T - TRIENNIAL HEAT SINK 1 1 07/08/2013 07/12/2013 IP 7111107T Heat Sink Performance 7111111B - PILGRIM REQUAL INSPN WITH P/F RESULTS 2 1 10/07/2013 10/11/2013 IP 7111111B Licensed Operator Requalification Program 71124 - RADIATION SAFETY INSPECTION 1 1 08/12/2013 08/16/2013 IP 71124.05 Radiation Monitoring Instrumentation 1 08/12/2013 08/16/2013 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 08/12/2013 08/16/2013 IP 71124.07 Radiological Environmental Monitoring Program PI&R - PI&R 7 1 09/16/2013 09/20/2013 IP 71152B Problem Identification and Resolution 1 09/30/2013 10/04/2013 IP 71152B Problem Identification and Resolution TI 182 - DEGRAD UNDERGROUND PIPING - PHASE 2 1 1 09/23/2013 09/27/2013 IP 2515/182 Review of the Implementation of the Industry Initiative to Control Degradation of Underground Piping ISFSI - ISFSI PAD CONSTRUCTION 3 1 09/30/2013 10/04/2013 IP 60853 On-Site Fabrication Of Components And Construction On An ISFSI 2/24 EXM - PILGRIM INITIAL OL EXAM 4 1 01/27/2014 01/31/2014 U01876 FY14-PILGRIM INITIAL OPERATOR LICENSING EXAM 1 02/24/2014 02/28/2014 U01876 FY14-PILGRIM INITIAL OPERATOR LICENSING EXAM EP PROGR - EP PROGRAM INSPECTION 1 1 11/04/2013 11/08/2013 IP 7111402 Alert and Notification System Testing 1 11/04/2013 11/08/2013 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1 11/04/2013 11/08/2013 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 71124 - RADIATION SAFETY INSPECTION 1 1 10/21/2013 10/25/2013 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 10/21/2013 10/25/2013 IP 71124.02 Occupational ALARA Planning and Controls 1 10/21/2013 10/25/2013 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 10/21/2013 10/25/2013 IP 71124.04 Occupational Dose Assessment 1 10/21/2013 10/25/2013 IP 71151-OR01 Occupational Exposure Control Effectiveness 7111117 - PERMANENT PLANT MODIFICATIONS 3 1 11/04/2013 11/08/2013 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1 11/18/2013 11/22/2013 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 71124 - RADIATION SAFETY INSPECTION 1 1 02/10/2014 02/14/2014 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1 02/10/2014 02/14/2014 IP 71124.02 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 Pilgrim 08/30/2013 09:12:15 Inspection / Activity Plan Report 22 07/01/2013 - 12/31/2014 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site CDBI - CDBI 7 1 03/17/2014 03/21/2014 IP 7111121 Component Design Bases Inspection 1 03/31/2014 04/03/2014 IP 7111121 Component Design Bases Inspection 1 04/14/2014 04/18/2014 IP 7111121 Component Design Bases Inspection EP EXER - EP EXERCISE INSPECTION 1 1 04/28/2014 05/02/2014 IP 7111407 Exercise Evaluation - Hostile Action (HA) Event 71124 - RADIATION SAFETY INSPECTION 1 1 05/05/2014 05/09/2014 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1 05/05/2014 05/09/2014 IP 71124.04 Occupational Dose Assessment 71124 - RADIATION SAFETY INSPECTION 1 1 07/14/2014 07/18/2014 IP 71124.05 Radiation Monitoring Instrumentation ISFSI - DRY RUN & INITIAL ISFSI INSPECTION 5 1 09/01/2014 10/31/2014 IP 60853 On-Site Fabrication Of Components And Construction On An ISFSI 1 09/01/2014 10/31/2014 IP 60854.1 Preoperational Testing of Independent Spent Fuel Storage Facility Installation at Operating Plants 1 09/01/2014 10/31/2014 IP 60855.1 Operation of an Independent Spent Fuel Storage Installation at Operating Plants 1 09/01/2014 10/31/2014 IP 60856.1 Review of 10 CFR 72.212(b) Evaluations at Operating Plants 71124 - RADIATION SAFETY INSPECTION 1 1 09/29/2014 10/03/2014 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1 09/29/2014 10/03/2014 IP 71151 Performance Indicator Verification This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure