Pre-Inspection Cover Sheet and Inspection Plan - Pilgrim Nuclear Generating Station; 05000293/2006007
ML070670370
Person / Time
Site: Pilgrim
Issue date: 02/15/2007
From:
Engineering Region 1 Branch 1
To:
Meyer G, RI/DRS/EB1, (610) 337-5211
References
IR-06-007
Download: ML070670370 (4)


See also: IR 05000293/2006007

Text

PRE-INSPECTION COVER SHEET AND INSPECTION PLAN

INSPECTORS:

Lead: _Glenn Meyer_______ FACILITY: Pilgrim Nuclear Generating Station__________

Other:_Suresh Chaudhary________REPORT NO: 05000293/2006007

Dante Johnson

Paul Kaufman

Shani Lewis REPORT TYPE: TEAM REPORT

Tim OHara _____ INSP DATES: 9/18-22, 10/2-6 EXIT DATE: 11/TBD

John Richmond

INSPECTION PLAN ATTACHED

INSPECTION PROCEDURE DATA

Procedure-Occ. Nos IPE Code Title of Procedure On MIP (Y/N)

-

-

-

IFS ITEMS ASSIGNED FOR REVIEW

Procedure-Occ. Nos IPE Code IFS Number Brief Description

NA - RI

- RI

- RI

ALLEGATIONS ASSIGNED FOR REVIEW

Procedure-Occ. Nos IPE Code ALG Number Brief Description

NA - 26 AF

- 26 AF

- 26 AF

PROJECTS COORDINATION: Date Discussed with DRP Section Chief:________________

COORDINATED:______________ ACKNOWLEDGED:______________APPROVED:_______________

(DRP) (Accomp. Insp. Super.) (Inspectors Supervisor)

ARRANGEMENTS:

Hotel: ___Hilton Garden Inn_____________________ Phone: ( 508) 830-0200

Contact: ___Fred Mogelesko, Entergy LR Proj. Mgr.______ Phone: ( 508) 830-7832

g:\pre-insp.frm

LICENSE RENEWAL INSPECTION PLAN

FOR

PILGRIM NUCLEAR GENERATION STATION

I PURPOSE

This plan specifies areas that must be inspected in order to assure the thoroughness and accuracy of the

screening and scoping of non-safety related structures, systems, and components, as required in 10 CFR 54.4(a)(2) and to assure aging management programs are capable of managing the identified aging affect in a

reasonable manner. This inspection plan describes how Manual Chapter 2516 requirements for activities

relating to 10 CFR Part 54 will be inspected. This plan defines the scope of the inspections planned to verify

that Entergys license renewal program for the Pilgrim Nuclear Generating Station is in compliance with the

requirements of the rule and is consistent with the license renewal application and the staffs safety evaluation

of Entergys license renewal application. The plan also provides guidance for inspection scheduling, inspector

training, inspection activities, and resource requirements.

Entergys license renewal application identified the systems and structures that Entergy had determined were

within the scope of the rule.

II OBJECTIVES

The overall objective of this plan is to provide guidance for inspecting the implementation and effectiveness of

the programs and activities associated with Entergys license renewal program. The inspection will verify there

is reasonable assurance that the effects of aging will be adequately managed so that the intended function(s)

of structures, and components, for which an aging management review is required, will be maintained

consistent with the current licensing basis during the period of extended operation. Region I will implement

the license renewal inspection plan at Pilgrim before NRR approves Entergys license renewal application to

verify that Entergy meets the requirements of the rule and has implemented license renewal programs and

activities consistent with the rule, the license renewal application, and the staffs safety evaluation report on

the license renewal application.

III INSPECTION ACTIVITIES

Inspection Procedure (IP) 71002, License Renewal Inspections, will be the primary procedure used to

inspect Pilgrim Nuclear Generating Stations implementation of the requirements of the rule. The latest

revision of IP 71002 can be reviewed by accessing http://www.nrc.gov/reading-rm/doc-collections/insp-

manual/inspection-procedure/ip71002.pdf

Scoping and Screening The inspection will focus on the methodology used by the applicant to

determine which non-safety systems are within the scope of the license renewal. This will be

accomplished by walk-downs of accessible portions of selected systems and structures to identify

observable inconsistencies in the scoping and screening activities. Any aging effects on the systems

and structures that are not covered in the license renewal application will be noted for inclusion in the

Aging Management portion of the inspection.

Aging Management Review Aging effects identified by Entergy will be principally reviewed and

evaluated during the NRR technical review and on-site audit. As part of an aging management

program inspection, the regional inspection team will perform a sample review of related maintenance

records of the selected systems and structures in an attempt to identify any previously unrecognized

aging.

Aging Management Programs The inspection team will inspect the aging management programs,

including aging management programs where Entergy claims they are consistent with the Generic

Aging Lessons Learned report, for important aging effects in selected systems and structures. The

inspection team will examine records for existing aging management programs to evaluate the

programs effectiveness and will review plans for new aging management programs. The inspection

team will then document the teams findings on the effectiveness of the aging management programs

to maintain the systems and structures intended function(s) consistent with the current licensing basis

for the period of extended operation.

IV INSPECTION SCOPE

The Pilgrim license renewal inspection activities will be implemented through an on-site inspection.

1. The inspection will last two weeks. One inspection man-week will focus on the scoping and screening

processes as it relates to non-safety systems that affect safety systems. The inspection will verify non-

safety systems have been included or excluded consistent with the rule, methodology, and the staffs

evaluation of Entergys methodology. The inspection will verify there is reasonable assurance that

Entergys scoping and screening processes have identified the non-safety systems, structures, and

components for which an aging management review is required consistent with the requirements of the

rule.

2. The remainder of the inspection resources will focus on the aging management programs designated

in the Entergy application. This inspection will examine a sample of existing and proposed aging

management programs and compare the programs against actual past results.

2. If open inspection items warrant a third inspection week, the team will followup on previous inspection

activities and may inspect Entergy actions on any safety evaluation open items requested by NRR.

This inspection may also include portions of the license renewal application updated by the applicant

as a result of recent plant modifications. The scope of any third inspection week (and, thus, the

resources) will depend on how many open issues remain from the previous inspection activities.

V INSPECTION RESOURCES

The inspection is expected to have the following inspection resources:

1. Inspectors

C One team leader - Glenn Meyer

C Six inspectors - Chaudhary, D. Johnson, Kaufman, Lewis, OHara, and Richmond

  • Region II inspector for familiarization purposes - B. Miller

2. Skills

The inspection team has a cross-section of skills, including mechanical, material, civil/structural, and

electrical engineering skills.

VI AGING MANAGEMENT PROGRAMS

The inspectors will sample from the following aging management programs (AMPs), which are either explicitly

provided in a separate AMP or included as part of another AMP:

Water Chemistry

Flow-Accelerated Corrosion

Fuel Oil Chemistry

10 CFR Part 50, Appendix J

Closed Cycle Cooling Water System

ASME,Section XI, Subsection IWE

TLAA, Drywell Corrosion and Protective Coating Monitoring and Maintenance Program

Buried Piping Inspection

Aboveground Outdoor Tanks

Fire Protection

Fire Water System

Electrical Cables and Connections Not Subject to EQ

Electrical Cables and Connections Not Subject to EQ Used in Instrumentation Circuits

Inaccessible Medium Voltage Cables Not Subject to EQ

Standby Liquid Control System

Feedwater System

Core Spray System

Isolation Condenser System

Component Supports Commodity Group

Fire Protection

Fire Water System

Electrical Cables & Connectors not subject to 10CFR50.49 Env. Qual

Electrical Cables & Connectors not subject to 10CFR50.49 Env. Qual, Requirements used in Instrument

Circuits

Inassessible Medium Voltage Cables not subject to 10CFR50.49 Env. Qual Requirements

Masonry Wall Program

Structures Monitoring Program

Protective Coating Monitoring and Maintenance

ASME Section XI, Subsection IWF

Various plant systems will be evaluated for the purposes of reviewing the AMPs.

VII Contact

The Entergy project manager for license renewal is Fred Mogolesko, who can be reached at 508-830-7832.