UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 January 13, 2021 Ms. Pamela B. Cowan Senior Vice President and Chief Operating Officer Holtec Decommissioning International, LLC 1 Holtec Blvd., Krishna P. Singh Technology Campus Camden, NJ 08104
SUBJECT:
PILGRIM NUCLEAR POWER STATION SECURITY INSPECTION PLAN
Dear Ms. Cowan:
The enclosed inspection plan lists the security inspections scheduled through December 31, 2022. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well before our inspectors arrive on site.
In accordance with Title 10 of the Code of Federal Regulations 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (610) 337-5200 with any questions you may have regarding the inspection plan.
Sincerely, 1/13/2021 X /RA/
Fred L. Bower, Chief Signed by: Fred L. Bower Fred L. Bower III, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-293 License No. DPR-35
Enclosure:
Pilgrim Nuclear Power Station Security Inspection Plan cc w/encl; B. McWilliams, Protective Services Manager S. Phillips, Director, Massachusetts Emergency Management Agency
ML21012A431 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRS RI/DNMS RI/DRS NAME JRey/JR
- ADimitriadis/AD
- FBower/ FB
- DATE 01/06/2021 01/11/2021 01/13/2021
- - concur via email
07201044 - Pilgrim Power Station (ISFSI) 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count Pilgrim-Security ISFSI Inspection 2
1 03/01/2021 03/03/2021 IP 81311 001006 Physical Security Requirements for Independent Spent Fuel Storage Installations 1/4/2021 6:37:43 AM Page 1 of 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report
Pilgrim 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count Access Control, Training, Protective Strategy, TSR-PL 3
1 04/19/2021 04/23/2021 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 1
04/19/2021 04/23/2021 IP 81200.05 000027 Protective Strategy Evaluation and Performance Evaluation Program for Decommissioning Nuclear Reactors 1
04/19/2021 04/23/2021 IP 81200.07 000029 Security Training for Decommissioning Nuclear Power Reactors 1
04/19/2021 04/23/2021 IP 81200.14 000030 Review of Decommissioning Reactor Target Sets Access Control, Equip Perf-PIL 2
1 09/12/2022 09/16/2022 IP 81200.02 000025 Access Control for Decommissioning Nuclear Power Reactors 1
09/12/2022 09/16/2022 IP 81200.04 000026 Equipment Performance, Testing, and Maintenance for Decommissioning Nuclear Power Reactors 1/4/2021 6:37:43 AM Page 2 of 2 This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
IP 22 Inspection Activity Plan Report