ML052030194

From kanterella
Jump to navigation Jump to search
U1R28 OCC Interactive Turnover Meeting Agenda
ML052030194
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 05/29/2004
From:
Nuclear Management Co
To:
Office of Nuclear Reactor Regulation
References
FOIA/PA-2004-0282
Download: ML052030194 (5)


Text

,,0. -.11. .'aq 8 NMi Committed to Nuclcar Excellence PUP

_ER~lERCE Am= 110101 - 01St2 Point Beach Nucleai r Plant U1R28 OCC Interactive Tur ,nover Meeting Agenda Saturday, May 29, 2004 Start Time: 0600 NSB Cafeteria ATTENDEES Shift Outage Directors Shift Outage Managers (SOM)

Operations Coordinators (SOC)

Maintenance Coordinators (MOC)

Engineer/ Projects Coordinators (EOM)

Rad Protection Manager (RPM)

Site Safety Coordinator (SSC)

Shutdown Safety Assessor (SSA)

Site Management (SSM)

General Supervisors .

First Line Supervisors Agenda

1. Safety Issue Discussion (SSC) . -
2. Radiation Protection (RPM)
3. Operations Coordinator Turnover (SOC)
4. Shutdown Safety Assessment (SSA)
a. Containment Fire Loading SAT / UNSAT -+ Review Deficiencies
5. Maintenance Coordinator Turnover (MOC)
6. Engineering Coordinator Turnover (EOM)
7. Major Projects Update (EOM)
8. Schedule Review (SOM)
9. Management Expectations (SSM)
10. ACEMAN Assessment Results (SOM)
11. Shift Goals (SOM)

Items Included in Daily Package:

- Site Communication

- Safety Snippet

- Outage Alara Report p

- Outage Status Report

- Shutdown Safety Assessment a

- Defined Critical Path 4\ iyfr

- Work Activity Risk Assignment

- Outage Schedule I _

1

Committed to Nuclear ) 2VEta::

Point Beach Nuclear Plant U1R28 Refueling Outage

¢ -- t;-<it nSafety Topnic for week -of May 23 -:29, 2004 - .-: $.j + ,,¢ r' Theme for the week This week's theme deals with odds and ends for Completing the Outage. We are almost done.

A number of critical work activities will be conducted this week in containment and we will begin a major battery change out It is time to review industry OE from other sites to make sure we've learned from their experiences. Nothing will stop our progress faster than a serious iniury!

  • ~Daily Safety Snippets.

Sunday Iss there an obstruction in your way that might not stay?'

OE13857 May 2002, Fort Calhoun -While moving the reactor vessel head assembly during a refueling outage, the control pendant for the polar crane caught a handrail vertical support pipe, lifting the pipe out of Its mount and causing it to fall 20 ft to the walkway below. Individuals were Inthe area at the time, but not Injured. A review indicated the pendant caught on nearby equipment many times during past refueling outages and corrective actions were not put In place.

Are there any items were our equipment gets caught during moves that we have not resoved?

Monday The big picture do we see? And communication Is the key.*

OE12357 January 2001, River Bend -Avworker focused on a moving load and did not pay attention to the movement of the crane. He ended up being forced against a handrail by the cab of the crane, luckily resulting only inminor injuries.

The entire crew was focused on the load with no one person having oversight of the whole evolution.

During crane operations, do we designate an indwidual to 'watch the big picture?'

Tuesday "Peerchecks - do we use them?"

December 1997, Byron -An electrician was taken to the hospital for treatment of second-degree bums on his hand and flash burns to his eyes as a result of a mishap. He was one of three electricians assisting a system engineer during a battery discharge test on a new battery bank when he accidentally shorted across the battery with one of the cables used to connect the battery to a resistor bank. An investigation showed that the electricians and the system engineer had not verified the correct cable configuration. Also, the injured electrician was not wearing low voltage gloves and had rolled up the sleeves of the long-sleeve shirt he was required to wear for this job.

What PPE do we wear during battery work?

Wednesday.

vust a reminder to he told, balance that Joaod OE10902 March 2000, Seabrook - Electricians were offloading battery cells from a metal pallet on a forklift. The offload sequence went from Inside, closest to the forklift, to the outside, furthest from IL The result - Instability inthe load and the pallet tipped under the weight of the batteries. The cells fractured spilling 19 gallons of sulfuric acd/water electrolyte in the switchgearroom. This OEIsnotjustforbatteryremoval. Balance allyour badsl Thursday hoake sure the scaffold doesn't slip and came down too quick.,

OE14551 July2002, Davis-Besse - A diamond deck plate slipped through a gap between two pieces of floor grating and dropped 20 ft to the level below, damaging an Instrument lne. The restofourscaffolding is coming down.

Am we aware of the potential 'holes' for material to go through?

Friday

'Before heat up, make sure someone has done the clean-upP OE57698 April 2004, Palo Verde - Two mechanics received second degree bums to the face as the result of a flash fire that occurred as they began pre-heating for welding. Isopropyl alcohol was used to clean and liquid had accumulated In the casing of the equipment. The oncoming crew was not aware of this buildup as they began work.

.Saturdav "Always remember to verify first, Saturday or you may take a ride in a.hearse. -

1992, Palisades -An experienced electrical technician at Palisades was electrocuted when he failed to Install a circuit Jumper before removing test equipment from a current transformer. The existing circuit configuration had not been anticipated during work planning, and the decision to use jumpers to maintain energized current transformer circuits during testing had not been reviewed by supervision.

2

Point Beach Nuclear Plant Outage 1R28 Path Picture DAY 54 _N _

Meets Supporting Operational Excellence Outage Radiation Performance Dlnnen't Meet Excends

. *- ----- -A This indicator measures cumulative dose radiation exposure and Day 54 - May 27 total number of personnel-contamination events (PCE's > 5000 Actual = 2.125 Cumulative = 84.005 cpm) during refueling outages. The dose indicator is measured in Cumulative Forecast =87.181 Rem and individual PCE events.

Meets: <=92 Rem Actual Cum.

Exceeds: <=88 Rem Dose: 84.005 Rem Meets: <= 18 Exceeds: <= 12 Actual PCE's: 11

. _ h.0 Stu Thomas I

Personnel Contamination Events Cumulative Dose Exposure 80 eCw a -- Actual M60 -- Actual z . . . . .Forecast .

E a)

Goal 0 Goal 0 040 E

2 020 0 5 10 15 20 25 30 35 40 45 50 55 60 n - . . . . . . . .

0 2 4 6 8 t~l2t4iel820222426283032343634042"4464850252R"""6

t NCd l Commirted to Nuclear Excellence Outage Status Report Plant: Point Beach Unit I Day: Saturday Today's Date / Time: 5/29/04 0330 Outage Duration: Day 56 OfRefueling Outage Number UIR28 Safety Status Industrial - Within the last 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> OSHA Recordables 0 First Aid cases 0 Near misses 0 Total for this outage I Summary:

Radiological Dose to date 84.005 Projected to date *87.181 Outage Goal S92 R Difference -3.176 Reforecast on 5/23 Number of PCEs 11 Summary:

Nuclear Significant human performance errors and events in last 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> 0 Summary:

Plant Status Mode: D Hot Standby (Mode 3) a Hot Shutdown (Mode 4) C Cold Shutdown (Modes) 0 Refueling Shutdown (Mode 6)

RCS: Temperature: 92 Pressure: 25 PSIG and Rising RV Level: RCS Filled with Pressurizer Solid Time to Boll: 126 minutes

^_____ Shutdown Safety Assessment Protected Equipment:

Major Activities Completed In Last 24 Hours Critical Path and Near Critical Path Activities (Next 24 Hours)

. Continued Containment Cleanup

  • Containment Cleanup
  • Containment Fan Cooler Testing
  • Vent RCS Instruments
  • Closed 'A' RCP Window
  • Closed CCW in Containment Window
  • Post Fill & Vent Valve Line Ups
  • Fill Pressurizer Solid
  • Establish Normal Operation of RCDT & PRT
  • Complete RCS Fill &-Vent Significant Outstanding Issues Date Issue Due Responsibility 5/17/04 Rx Head Relief Request 6/1/04 l Jim Schweitzer Upcoming Malor Milestones Scheduled A ctual Scheduled Actual Date Time Date Time Date Time Date Time Cooldown <2000 4/03/04 2100 4/03/04 2230 RCS Fill & Vent 4/23/04 1500 Head Lift 4/09/04 0900 4/21/04 1550 Heatup >2000 4/25/04 0900 Refueled 4/14/04 0300 5/02/04 1848 Reactor Critical 4/28/04 0800 RV Headset 4/18/04 1900 5/23/04 1338 On-Line 4/30/04 0100 .

4

Point Beach Nuclear Plant

- PBNP SHUTDOWN SAFETY ASSESSMENT AND FIRE CONDITION CHECKLIST OUTAGE SAFETY ASSESSMENT UNIT: 1 DATE: May 29, 2004 TIME: 0300 KEY SAFETY FUNCTIONS:

REACTIVITY: GREEN CORE COOLING: YELLOW POWER AVAILABLE: GREEN INVENTORY: YELLOW CONTAINMENT: GREEN SFP COOLING: NA PROTECTED EQUIPMENT:

COMMIENTS: ev

  • RCS is solid, S/G tubes not filled
  • RCS Fill and Vent in progess
  • Core Cooling and Inventory will remain YELLOW until the RCPs are bumped.

PBF-1562

References:

NP 10.3.6 Revision 2 10130/02 5 Page 5 of 9 NP 10.2.1