June 2, 2005 LICENSEE: FirstEnergy Nuclear Operating Company FACILITIES: Davis-Besse Nuclear Plant, Unit 1

SUBJECT:

SUMMARY

OF THE MAY 24, 2005, PUBLIC MEETING TO DISCUSS DAVIS-BESSE TRANSITION FROM THE MANUAL CHAPTER 0350 OVERSIGHT PROCESS TO THE NORMAL REACTOR OVERSIGHT PROCESS (ROP)

On May 24, 2005, the Nuclear Regulatory Commission (NRC) held a public meeting at the Camp Perry Clubhouse in Port Clinton, Ohio. The meeting was between the NRC Davis-Besse Oversight Panel and FirstEnergy Nuclear Operating Company (FENOC) to discuss licensee performance and planned transition of the facility from the Manual Chapter 0350 oversight process to the Reactor Oversight Process (ROP). The letter of notification, meeting notice, NRC presentation, and licensee presentation can be found in ADAMS as ML051430290, ML051310444, ML051460466, and ML051520318, respectively. The transcript of the meeting will be made publicly available in ADAMS and on the NRCs Davis-Besse web page when it is available. A list of NRC and licensee meeting participants can be found in the attached Enclosure.

The NRC began the meeting by announcing that Davis-Besse will transition from oversight under the IMC 0350 process to the Reactor Oversight Process, effective July 1, 2005. The Agency briefly described the assessment process on which this decision was based. The NRC provided a brief overview of the Reactor Oversight Process and informed the licensee that, based on their current level of performance, they would be placed in the Regulatory Response column of the Reactor Oversight Process Action Matrix. Also, the licensee was informed that inspection activities to ensure compliance with the requirements of the March 8, 2004, Confirmatory Order and in the area of Problem Identification and Resolution would be performed in addition to the inspections that are required by a facility that is in the Regulatory Response Column of the Action Matrix. The NRC concluded their initial remarks by outlining upcoming activities through the end of CY2006.

The licensee began their presentation by stating their desired outcomes for the meeting were:

demonstrate Davis-Besses operations continue to be safe and conservative; discuss site activities since that last public meeting; and status the improvement initiatives and Confirmatory Order Independent Assessments. Key topics that were discussed included: Plant Performance/Assessments; Operational Improvement Plan and Backlog Reduction; Safety Culture and Safety Conscious Work Environment; and Oversights Perspective. The closing message from the licensee was that Davis-Besse personnel were people with a strong safety focus delivering top fleet operating performance.

FirstEnergy Nuclear Operating Company Following the licensees presentation, the NRC provided the public with the opportunity to provide comments or ask questions. After two brief statement by local county officials, the meeting was concluded.

These documents and many others related to the IMC 0350 Process at Davis-Besse and the reactor vessel head degradation can also be found on the NRCs website at http://www.nrc.gov/reactors/operating/ops-experience/vessel-head-degradation.html.

Sincerely,

/RA by Monte Phillips for/

Christine A. Lipa, Chief Branch 4 Division of Reactor Projects Docket No. 50-346 License No. NPF-3

Enclosure:

As Stated See Attached Distribution DOCUMENT NAME: G:\Davis-Besse 0350\External Meetings\Public Meeting Summary\Published Summaries\ML051530370.wpd To receive a copy of this document, indicate in the box: "C" = Copy without attachment/enclosure "E" = Copy with attachment/enclosure "N" = No copy OFFICE RIII RIII NAME MPhillips:dtp CLipa(MP for)

DATE 06/02/05 06/02/05 OFFICIAL RECORD COPY

FirstEnergy Nuclear Operating Company cc w/encls: The Honorable Dennis Kucinich G. Leidich, President - FENOC J. Hagan, Senior Vice President Engineering and Services, FENOC L. Myers, Chief Operating Officer, FENOC Plant Manager Manager - Regulatory Compliance D. Jenkins, Senior Attorney, FirstEnergy Ohio State Liaison Officer R. Owen, Administrator, Ohio Department of Health Public Utilities Commission of Ohio President, Board of County Commissioners of Lucas County J. Papcun, President, Ottawa County Board of Commissioners D. Lochbaum, Union Of Concerned Scientists J. Riccio, Greenpeace P. Gunter, N.I.R.S.

R. Bratton, Ottawa County Sheriff J. P. Greer, Director, Ottawa County Emergency Management Agency J. Papcun, President, Ottawa County Board of Commissioners T. Wozniak, President, Lucas County Board of Commissioners J. Telb, Lucas County Sheriff W. Halsey, Director, Lucas County Emergency Management Agency G. Adams, Village Administrator, Genoa The Honorable John Weber The Honorable Lowell C. Krumnow The Honorable M. Thomas Perry The Honorable Thomas Leaser The Honorable Jack Ford The Honorable Thomas Brown The Honorable Jacqueline Bird The Honorable Wayne Butzin T. Wilkins, Oak Harbor Village Administrator The Honorable Bernard McCann INPO

FirstEnergy Nuclear Operating Company ADAMS Distribution:

GYS SPS1 RidsNrrDipmIipb GEG KGO CST1 CAA1 DRPIII DRSIII PLB1 JRK1 DB0350

Enclosure Meeting Participants NRC S. Reynolds, Davis-Besse Oversight Panel Chairman W. Ruland, Davis-Besse Oversight Panel Vice-Chairman J. Hopkins, Project Manager, NRR C. Lipa, Branch Chief, DRP, RIII S. Thomas, Senior Resident Inspector, Davis-Besse FirstEnergy Nuclear Operating Company M. Bezilla, Vice President, Davis-Besse B. Allen, Director, Site Operations, Davis-Besse S. Loehlein, Director, Engineering, Davis-Besse R. Hruby, Manager, Nuclear Oversight, Davis-Besse K. Ostrowski, Manager, Plant Operations, Davis-Besse