Letter Sequence Approval |
|---|
TAC:MC3272, Control Room Habitability (Approved, Closed) TAC:MC3273, Control Room Habitability (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
- Supplement, Supplement, Supplement, Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML042450123, ML043000333, ML043150211, ML043210580, ML050120217, ML050420328, ML050680270, ML050690308, ML051440459, ML051650086, ML052000147, ML052000163, ML052000175, ML052500572, ML052940236, ML052970007, ML053120311, ML053320201, ML053430012, ML053460458, ML053470313, ML053630052, ML060180205, ML060890579, ML060940577, ML060940622, ML060950413, ML061020154, ML061020166, ML061080367, ML061090064, ML062830307, ML062830317, ML082530250, ML091830049, ML091980454, ML110680289, ML110680291, ML13294A039, ML14063A184, ML14078A594, ML14106A053, ML14148A114
|
MONTHYEARML0414700602004-05-26026 May 2004 Independent Survey of Power-Reactor Licensees Project stage: Request ML0414902132004-05-26026 May 2004 Transmittal of Nine Mile Point Units 1 & 2 Application for Renewed Operating Licenses, Including Environmental Report Project stage: Request ML0419802972004-06-15015 June 2004 License Renewal Application (E-Mail) - Enclosure 4. Gurdziel E-mail, Dated 06/15/2004, Comments to Nine Mile Point License Extension Meeting Project stage: Meeting ML0418404122004-07-0202 July 2004 Summary of Meeting Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Constellation Energy, Inc Representatives to Discuss the Nine Mile Point Power Station, Units 1 & 2 License Renewal Application Project stage: Meeting ML0424501232004-09-0202 September 2004 License Renewal Application Work Split Tables Project stage: Other ML0430003332004-10-26026 October 2004 To Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Other 05000220/LER-2004-004, Regarding Manual Reactor Scram Due to Failure of 13 Feedwater Flow Control Valve Positioner2004-10-29029 October 2004 Regarding Manual Reactor Scram Due to Failure of 13 Feedwater Flow Control Valve Positioner Project stage: Request ML0432002282004-11-0101 November 2004 Draft Safety Evaluation Report Related to the License Renewal of the Arkansas Nuclear One, Unit 2 Project stage: Draft Approval ML0431502112004-11-0909 November 2004 Audit Trip Report Regarding the Constellation Energy Group Application for License Renewal for the Nine Mile Nuclear Station, Units 1 and 2, Dated May 27, 2004 Project stage: Other ML0432105802004-11-15015 November 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC Nos MC3272 and MC3273.) Project stage: Other ML0432706342004-11-17017 November 2004 Summary of a Meeting Held on October 28, 2004, Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group, Inc. Concerning the Review for the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Meeting ML0432806832004-11-22022 November 2004 Requests for Additional Information for Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0434200492004-12-0303 December 2004 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0434504402004-12-0707 December 2004 Status of Staff Review of the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0435703682004-12-21021 December 2004 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0500403152004-12-21021 December 2004 License Renewal Application - Responses to NRC Requests for Additional Information Regarding Sections 2.3.2, 2.3.4, and B2. 1.32 Project stage: Response to RAI ML0436500032004-12-22022 December 2004 Request for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application, Project stage: RAI ML0500403322004-12-22022 December 2004 License Renewal Application - Responses to NRC Request for Additional Information Regarding Scoping and Screening Methodology Project stage: Response to RAI ML0500601822004-12-22022 December 2004 License Renewal Application - Responses to NRC Requests for Additional Information Regarding Sections 2.2, 2.3.3, and 2.3.4 Project stage: Response to RAI ML0436500062004-12-27027 December 2004 Request for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application, Project stage: RAI ML0501202172005-01-0303 January 2005 License Renewal Application - Response to NRC Letter Dated December 7, 2004 Regarding Status of NRC Staff Review Project stage: Other ML0501102352005-01-0303 January 2005 License Renewal Application - Responses to NRC Requests for Additional Information Regarding the Reactor Recirculation Systems Project stage: Response to RAI ML0500604212005-01-0505 January 2005 Revision of Schedule for the Conduct of Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0501902962005-01-0707 January 2005 License Renewal Application - Response to NRC Request for Additional Information Regarding the Nine Mile Point Unit 1 Containment System Project stage: Response to RAI ML0501902922005-01-10010 January 2005 License Renewal Application - Responses to NRC Requests for Additional Information Regarding Structures Project stage: Response to RAI ML0501902952005-01-10010 January 2005 License Renewal Application - Responses to NRC Requests for Additional Information Regarding Aging Management of Electrical and Instrumentation and Control Systems Project stage: Response to RAI ML0502404242005-01-13013 January 2005 Request for Additional Information - Nine Mile Point Nuclear Station, Units 1 and 2, Fire Protection Open Items Project stage: RAI ML0501302832005-01-13013 January 2005 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0502103762005-01-13013 January 2005 Request for Additional Information on Open Items for Balance of Plant Section Project stage: RAI ML0502501882005-01-14014 January 2005 License Renewal Application - Responses to NRC Requests for Additional Information Regarding the Time-Limited Aging Analysis for Main Steam Isolation Valve Corrosion Allowance and the Closed-Cycle Cooling Water System Project stage: Response to RAI ML0503304632005-01-20020 January 2005 License Renewal Application - Responses to NRC Requests for Additional Information Regarding Aging Management of Bolting Project stage: Response to RAI ML0503903702005-01-26026 January 2005 . License Renewal Application - Responses to NRC Requests for Additional Information Regarding Aging Management of Auxiliary Systems Project stage: Response to RAI ML0504602332005-01-31031 January 2005 . License Renewal Application - Responses to NRC Requests for Additional Information Regarding Sections 2.2, 2.3.3, and 2.3.4, and Scoping and Screening Methodology Project stage: Response to RAI ML0504504852005-02-0404 February 2005 License Renewal Application - Submittal of Supplemental Information Resulting from the NRC Audit of Aging Management Reviews Project stage: Supplement ML0504104282005-02-10010 February 2005 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0505601992005-02-11011 February 2005 License Renewal Application - Submittal of Supplemental Information for Review of the License Renewal Application Project stage: Supplement ML0504203872005-02-11011 February 2005 Summary of a Conference Call Held with Constellation Energy Group Inc. Concerning the Review of the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Project stage: Approval ML0504203282005-02-11011 February 2005 Summary of a Conference Call Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group, Inc. Concerning the Review for the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Other ML0506100592005-02-14014 February 2005 License Renewal Application - Responses to NRC Requests for Additional Information Regarding the Reactor Vessel and Reactor Vessel Internal Components Project stage: Response to RAI ML0504601382005-02-14014 February 2005 Summary of a Conference Call Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group Inc. Concerning the Review of the Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Approval ML0505401962005-02-22022 February 2005 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0505402632005-02-23023 February 2005 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0506802702005-03-0303 March 2005 Recovery of Nine Mile Point License Renewal Application Quality Project stage: Other ML0506205912005-03-0303 March 2005 Requests for Additional Information for the Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: RAI ML0506601472005-03-0707 March 2005 Extension of Staff Review Schedule for Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0506903082005-03-10010 March 2005 Summary of a Conference Call Held on February 28, 2005, Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group Inc. Concerning the Review for the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal App Project stage: Other ML0507001342005-03-11011 March 2005 Revision of Schedule for the Conduct of Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0510905402005-04-19019 April 2005 Summary of Meeting Held on March 30, 2005, Between the NRC Staff and the Constellation Energy Group, Inc. Representatives to Discuss the Status of Their Recovery Effort for Nine Mile Point, Units 1 and 2, License Renewal Application Project stage: Meeting ML0514404592005-05-13013 May 2005 Recovery of Nine Point License Renewal Application Quality Project stage: Other ML0516500862005-06-0909 June 2005 Presentation Slides, Nine Mile Point, Units 1 and 2, LRA Status Update Project stage: Other 2005-01-14
[Table View] |
Text
March 7, 2005 Mr. James A. Spina Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093
SUBJECT:
EXTENSION OF STAFF REVIEW SCHEDULE FOR NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MC3272 AND MC3273)
Dear Mr. Spina:
We are in receipt of the Nine Mile Point (NMP) letter dated March 3, 2005, wherein NMP addressed the staffs concerns previously communicated to you on various occasions. In addition, the NMP letter requested a grace period not to exceed 90 days to recover the quality of your license renewal project. We acknowledge your commitment to address quality issues, including those we have discussed on the telephone. We have stopped our review in response to your request. However, as a result of this delay, we will not meet the standard 22 month review schedule.
As part of your recovery efforts, we request that you perform a thorough review of your license renewal supplements, responses to staffs audit questions, and responses to staffs requests for additional information. Upon receipt of your submittal confirming the completion of your recovery efforts, the staff will resume our review and audits. Assuming a satisfactory submittal and adequate support from your staff for these review and audit activities, we will extend the review schedule, as appropriate, to accommodate the additional time needed to complete the NMP review and in consideration of competing priorities posed by other concurrent license renewal reviews.
If you have any questions regarding this letter, please contact the NRC Project Manager, Tommy Le, at 301-415-1458; or by e-mail at NBL@nrc.gov.
Sincerely,
/RA/
Pao-Tsin Kuo, Program Director License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-220 and 50-410 cc: See next page
March 7, 2005 Mr. James A. Spina Vice President Nine Mile Point Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093
SUBJECT:
EXTENSION OF STAFF REVIEW SCHEDULE FOR NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION (TAC NOS. MC3272 AND MC3273)
Dear Mr. Spina:
We are in receipt of the Nine Mile Point (NMP) letter dated March 3, 2005, wherein NMP addressed the staffs concerns previously communicated to you on various occasions. In addition, the NMP letter requested a grace period not to exceed 90 days to recover the quality of your license renewal project. We acknowledge your commitment to address quality issues, including those we have discussed on the telephone. We have stopped our review in response to your request. However, as a result of this delay, we will not meet the standard 22 month review schedule.
As part of your recovery efforts, we request that you perform a thorough review of your license renewal supplements, responses to staffs audit questions, and responses to staffs requests for additional information. Upon receipt of your submittal confirming the completion of your recovery efforts, the staff will resume our review and audits. Assuming a satisfactory submittal and adequate support from your staff for these review and audit activities, we will extend the review schedule, as appropriate, to accommodate the additional time needed to complete the NMP review and in consideration of competing priorities posed by other concurrent license renewal reviews.
If you have any questions regarding this letter, please contact the NRC Project Manager, Tommy Le, at 301-415-1458; or by e-mail at NBL@nrc.gov.
Sincerely,
/RA/
Pao-Tsin Kuo, Program Director License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket Nos.: 50-220 and 50-410 cc: See next page Adams accession no.: ML050660147 Document Name:E:\\Filenet\\ML050660147.wpd OFFICE RLEP:PM RLEP:LA RLEP:SC-A RLEP:PD NAME N. Le Y. Edmonds S. Lee PT Kuo DATE 03/07/2005 03/07/2005 03/07/2005 03/07/2005 OFFICIAL RECORD COPY
DISTRIBUTION: Letter to Mr. Spina, Constellation Energy Group, Inc. Re: Nine Mile Point Nuclear Station, Units 1 and 2, Dated: March 7, 2005 Adams Accession No.: ML050660147 HARD COPY RLEP RF N. Le (PM)
E-MAIL:
RidsNrrDrip RidsNrrDe G. Bagchi K. Manoly W. Bateman J. Calvo R. Jenkins P. Shemanski J. Fair RidsNrrDssa RidsNrrDipm D. Thatcher R. Pettis G. Galletti C. Li K. Winsberg (RidsOgcMailCenter)
M. Mayfield A. Murphy S. Smith (srs3)
S. Duraiswamy Y. L. (Renee) Li RLEP Staff S. Lee T. Smith M. Lemoncelli C. Holden R. Laufer P. Tam B. Fuller, RI E. Knutson, RI J. Trapp, RI T. Mensah S. Burnett B. Hayden OPA
Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 cc:
Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 126 Lycoming, NY 13093 Supervisor Town of Scriba Route 8, Box 382 Oswego, NY 13126 Mr. James R. Evans LIPA P.O. Box 129 Lycoming, NY 10393 Charles Donaldson, Esquire Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Mr. Paul D. Eddy Electric Division NYS Department of Public Service Agency Building 3 Empire State Plaza Albany, NY 12223 C. Adrienne Rhodes Chairman and Executive Director State Consumer Protection Board 5 Empire State Plaza, Suite 2101 Albany, NY 12223-1556 Kathryn M. Sutton, Esquire Morgan, Lewis & Bockius LLP 1111 Pennsylvania Avenue, NW Washington, DC 20004 Mark J. Wetterhahn, Esquire Winston & Strawn 1400 L Street, NW Washington, DC 20005-3502 Mr. Michael J. Wallace President Nine Mile Point Nuclear Station, LLC c/o Constellation Energy Group, Inc.
750 East Pratt Street Baltimore, MD 21202 Mr. James M. Petro, Jr., Esquire Counsel Constellation Energy Group 750 East Pratt Street, 5th Floor Baltimore, MD 21202 Mr. Peter R. Smith, President New York State Energy, Research, and Development Authority 17 Columbia Circle Albany, NY 12203-6399 Mr. Fred Emerson Nuclear Energy Institute 1776 I St., NW, Suite 400 Washington, DC 20006-3708 Mr. Mark Flaherty Manager - Fleet Licensing R.E. Ginna Nuclear Power Plant 1503 Lake Rd.
Ontario, NY 14519 Mr. M. Steven Leonard General Supervisor - Nuclear Regulatory Matters Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093
Nine Mile Point Nuclear Station, Unit Nos. 1 and 2 cc:
Mr. Peter Mazzaferro Site Project Manager - License Renewal Nine Mile Point Nuclear Station, LLC P.O. Box 63 Lycoming, NY 13093 Mr. Mike Heffley Senior Vice President and Chief Nuclear Officer Constellation Generation Group 1997 Annapolis Exchange Parkway Suite 500 Annapolis, MD 21401