ML043210580
Letter Sequence Other | |
---|---|
Initiation | |
MONTHYEARML0414902132004-05-26026 May 2004
[Table View]Transmittal of Nine Mile Point Units 1 & 2 Application for Renewed Operating Licenses, Including Environmental Report Project stage: Request ML0430003332004-10-26026 October 2004 to Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2. Project stage: Other ML0432105802004-11-15015 November 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC Nos MC3272 and MC3273.) Project stage: Other ML0504601382005-02-14014 February 2005 Summary of a Conference Call Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group Inc. Concerning the Review of the Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Approval ML0516500862005-06-0909 June 2005 Presentation Slides, Nine Mile Point, Units 1 and 2, LRA Status Update Project stage: Other ML0516704462005-06-16016 June 2005 Summary of Meeting Held on June 9, 2005, Between the U.S. Nuclear Regulatory Commission (NRC) Staff and the Constellation Energy Group, Inc. Representatives to Discuss the Status of Their Recovery Effort, Nine Mile Point Nuclear Station, Un Project stage: Meeting ML0529702752005-10-20020 October 2005 E-mail from Ngoc Le of NRC to David Dellario Regarding the Audit and Review Plan for Plant Aging Management Programs and Reviews for Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Acceptance Review ML0536300522005-12-13013 December 2005 License Renewal Application (LRA) - Editorial Changes to Letter NMP1L 2005 and NMP1L 2007 Project stage: Other ML0601301972006-01-11011 January 2006 Amended License Renewal Application - Responses to NRC Requests for Additional Information - Sections 3.4 and 4.7 Project stage: Response to RAI ML0601802052006-01-18018 January 2006 1/18/06 - Audit and Review Report for the Nine Mile Point Nuclear Station, Units 1 and 2, Amended License Renewal Application (TAC Nos. MC3272 and MC3273 Project stage: Other ML0602200092006-01-18018 January 2006 Summary of Meeting with the Constellation Energy Group Inc. to Discuss Results of the Staff Audit of the Aging Management Programs and Reviews for Nine Mile Point, Units 1 and 2 Project stage: Meeting ML0605807562006-03-0303 March 2006 Transmittal Letter - Safety Evaluation Report for the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0605807582006-03-0303 March 2006 Safety Evaluation Report for the Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application Project stage: Approval ML0609504132006-03-23023 March 2006 SER Open Item 4.7B.1-1 and Closure of Amended License Renewal Application (Alra) Section A2.4, Commitment 39 - Biological Shield Wall Neutron Fluence Analysis Project stage: Other ML0608905792006-03-29029 March 2006 01/23/2006 Summary of a Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group, Inc. Concerning the Review for the Nine Mile Point, Units 1 & 2, License Renewal Application Project stage: Other ML0609406222006-03-29029 March 2006 Email (3/29/06) from Peter Mazzaferro to Ngoc (Tommy) B. Le NMP2 Bioshield Fluence Calc Info Project stage: Other ML0610201662006-04-0303 April 2006 Safety Evaluation Report with Open Items Related to the License Renewal of Nine Mile Point, Dated March 2006 - NMPNS Comments (TAC Nos. MC3272 and MC3273) Project stage: Other ML0610201542006-04-0404 April 2006 Safety Evaluation Report (Ser), with Open Items Related to the License Renewal Dated March 2006 - SER Open Item 3.0.3.2.17-1 Project stage: Other ML0609405772006-04-0404 April 2006 Note to File - Docketing of Additional Information Pertaining to License Renewal Application of the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC Nos. MC3272 and MC3273) Project stage: Other ML0610900642006-04-18018 April 2006 Note to File - Docketing of Additional Information Pertaining to License Renewal Application of the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC No'S. MC3272 and MC3273) Project stage: Other ML0610901062006-04-19019 April 2006 Request for Additional Information, Review of Nine Mile Point Nuclear Station, Units 1 and 2, License Renewal Application (TAC Nos. MC3272 and MC3273) Project stage: RAI ML0612205952006-04-21021 April 2006 Amended License Renewal Application - NRC Request for Additional Information (RAI) 4.7.5. A-1 Project stage: Request ML0611802422006-06-0101 June 2006 Ltr to Timothy O' Connor - Final Safety Evaluation Report Related to the License Renewal of the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC Nos. MC3272 and MC3273) Project stage: Approval ML0614603132006-06-0101 June 2006 Safety Evaluation Report Related to the License Renewal of the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC Nos. MC3272 and MC3273) Project stage: Approval ML0619800502006-07-13013 July 2006 03/27/2006 Summary of Meeting Between U.S. Nuclear Regulatory Commission Staff & Constellation Energy Group Inc. Representatives to Discuss Status of Open Item 3.0.3.2.17-1 for Nine Mile Point Nuclear Station, Units 1 & 2, License Renewal A Project stage: Meeting ML0628302732006-10-31031 October 2006 Issuance of Renewed Facility Operating License Nos. DPR-63 and NPF-69 for the Nine Mile Point Nuclear Station, Units 1 and 2 Project stage: Approval ML0628303172006-10-31031 October 2006 LLC Docket No. 50-410 Nine Mile Point Nuclear Station, Unit 2 Renewed Facility Operating License Renewed License No. NPF-69 Project stage: Other ML0628304332006-10-31031 October 2006 Federal Register Notice for Nine Mile Point Nuclear, LLC Nine Mile Point Nuclear Station Units 1 and 2, Notice of Issuance of Renewed Facility Operating License Nos. DPR-63 and NPF-69 for an Additional 20-Year Period Project stage: Approval ML0628303072006-10-31031 October 2006 LLC Docket No. 50-220 Nine Mile Point Nuclear Station, Unit 1 Renewed Facility Operating License Renewed License No. DPR-63 Project stage: Other ML0825302502008-08-29029 August 2008 Request to Utilize an Alternative to the Requirements of 10 CFR 50.55a(g) for the Repair and Inservice Inspection of Control Rod Drive Stub Tubes for the License Renewal Period of Extended Operation Project stage: Other ML0907101082009-03-17017 March 2009 Request for Additional Information, Alternative for the Repair and Inservice Inspection of Control Rod Drive Stub Tubes for the License Renewal Period of Extended Operation Project stage: RAI ML0914104472009-05-14014 May 2009 Request to Utilize an Alternative to the Requirements of 10 CFR 50.55a(g) for the Repair and Inservice Inspection of Control Rod Drive Stub Tubes for the License Renewal Period of Extended Operation - Response to NRC Request for Additional Project stage: Request ML0918300492009-06-25025 June 2009 Request to Utilize an Alternative to the Requirements of 10 CFR 50.55a(g) for the Repair & Inservice Inspection of Control Rod Drive Stub Tubes for the License Renewal Period of Extended Operation - Response. Project stage: Other ML0919804542009-08-0303 August 2009 Request to Utilize Alternative of Applying ASME Code Case 730 for Repair and ISI of Control Rod Drive Bottom Head Penetrations for the License Renewal Period of Extended Operation Project stage: Other ML1106802892011-03-0404 March 2011 Areva Calculation No. 32-9138066-000, NMP-1 CRD Housing Idtb Weld Anomaly Analysis. (Non-Proprietary) Project stage: Other ML1106802912011-03-0404 March 2011 Request to Utilize an Alternative to the Requirements of 10CFR50.55a(g) for Repair of Control Rod Drive Housing Penetrations for the Remainder of License Renewal Period of Extended Operation Project stage: Other ML13256A3642013-09-17017 September 2013 Nine Mile Point Nuclear Station, Unit Nos. 1 and 2, and R.E. Ginna Nuclear Power Plant - Acceptance of Requested Licensing Action Regarding Direct License Transfer (TAC MF2584 - MF2588) Project stage: Acceptance Review ML13269A3122013-10-0202 October 2013 Request for Withholding Information from Public Disclosure for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, Nine Mile Point Nuclear Station, Unit Nos. 1 and 2, and R.E. Ginna Nuclear Power Plant (TAC Nos. MF2584, MF2585, MF2586, M Project stage: Withholding Request Acceptance ML13294A0392013-11-0707 November 2013 Notice of Consideration of Approval of Transfer of Renewed Facility Operating Licenses and Conforming Amendments,.. Project stage: Other ML13337A3902013-12-0505 December 2013 Request for Additional Information Regarding Order Approving Direct Transfer of Renewed Facility Operating License and Conforming Amendments Project stage: RAI ML13294A0702013-12-18018 December 2013 Consideration of Approval of Transfer of Renewed Facility Operating Licenses, Materials Licenses, and Conforming Amendments Containing SUNSI Project stage: Request ML14050A3712014-02-0505 February 2014 Supplemental Response to Nrc'S Requests for Additional Information Regarding Application for Order Approving Transfer of Operating Authority and Conforming License Amendments Project stage: Supplement ML14063A1842014-03-25025 March 2014 Order Approving Direct Transfer of Renewed Operating Licenses and Conforming License Amendments Project stage: Other ML14106A0532014-03-25025 March 2014 Order Approving Direct Transfer of Renewed Operating Licenses and Conforming License Amendments Project stage: Acceptance Review ML14078A5942014-03-25025 March 2014 Enclosure 2 - Conforming Amendments to Nine Mile Point License Project stage: Other ML14078A6072014-03-25025 March 2014 Draft License Pages Project stage: Draft Other ML14091A3232014-04-0101 April 2014 Issuance of Amendments to Conform the Renewed Facility Operating Licenses and Materials License to Reflect the Direct Transfer of Operating Authority Project stage: Approval ML14105A1362014-05-0808 May 2014 Request for Withholding Information from Public Disclosure for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2, Nine Mile Point Nuclear Station, Unit Nos. 1 and 2, and R.E. Ginna Nuclear Power Plant Project stage: Withholding Request Acceptance ML14148A1142014-07-16016 July 2014 Correction Letter - Correction to the Title Page of the Renewed Facility Operating License No. NPF-69 and Change in the Title Page of the Current License No. NPF-69 Project stage: Other 2006-04-04 |
ML043210580 | |
Person / Time | |
---|---|
Site: | Nine Mile Point |
Issue date: | 11/15/2004 |
From: | Chang K NRC/NRR/DRIP/RLEP |
To: | Le N NRC/NRR/DRIP/RLEP |
Hsu RH, RLEP/DRIP/NRR, 415-4088 | |
Shared Package | |
ML043210581 | List: |
References | |
TAC MC3272, TAC MC3273 | |
Download: ML043210580 (3) | |
Similar Documents at Nine Mile Point | |
---|---|
Category:Memoranda
MONTHYEARML21277A2472021-11-0505 November 2021
[Table view]Notification of Significant Licensing Action - Proposed Issuance of Order Approving the Transfer of Licenses for Which a Hearing Has Been Requested - Exelon Generation Company, LLC; Et. Al ML21067A0922021-04-20020 April 2021 Documentation of Decision by NRC Staff That EPRI Report 3002012988, Alternative Approaches for Addressing Seismic Risk in 10 CFR 50.69 Risk-Informed Categorization, Meets Criteria for a Federal Record ML20358A2602020-12-28028 December 2020 Changes to Draft Request for Additional Information Regarding License Amendment Request and Relief Request to Change Excess Flow Check Valve Testing Frequency ML20213B2212020-11-20020 November 2020 Memo to File: Environmental Assessment and Finding of No Significant Impact and NRC Financial Analysis for Constellation and Exelon'S Decommissioning Funding Plan Submitted in Accordance with 10 CFR 72.30(b) and (C) for Nine Mile Point Unit ML20248H5192020-09-28028 September 2020 Changes to Draft Request for Additional Information Regarding Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times ML20157A1822020-06-0808 June 2020 Summary of May 8, 2020, Meeting with Exelon Generation Company, LLC, Regarding Proposed Emergency License Amendment Request Involving Control Room Air Treatment System ML17142A2382017-05-25025 May 2017 OEDO-17-00280 - Briefing Package for Drop-In Visit on June 9, 2017, by Senior Management of Exelon Generation Company, LLC with Chairman Svinicki, Commissioner Baran, and Commissioner Burns ML17037B8502017-02-0606 February 2017 08/21/1975 Notice of Meeting with Architect Engineers of Mark II Owners to Discuss Load Combinations and Analytical Techniques for Determining Stresses in Mechanical Components and Structures of Mark II Containments ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16075A3292016-03-16016 March 2016 OEDO-16-00165 - Briefing Package for Drop-In Visit on March 23, 2016, by Senior Management of Exelon Generation Company, LLC with the NRC Executive Director for Operations ML13309A0802013-12-11011 December 2013 Memorandum to File: Transcript for 10 CFR 2.206 Petition from Beyond Nuclear (Et Al) Regarding General Electric Mark I and Mark II Boiling-Water Reactors ML13122A0082013-05-22022 May 2013 Notice of Impending Public Release of Technical Letter Report (Tlr) on Summary of Aging Management Program Effectiveness Audits to Inform Subsequent License Renewal: R.E. Ginna Nuclear Power Plant and Nine Mile Point Nuclear Station, Unit 1 ML13158A1622013-05-10010 May 2013 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML13077A0472013-03-18018 March 2013 3/29/2013 - Notice of Category 1 Meeting with Nine Mile Point Nuclear Station, Llc. to Discuss Maximum Extended Load Line Limit Analysis Plus (Mellla+) License Amendment Request (LAR) Submittal and the Use of GESTR-M Vs. Prime Codes ML13036A0062013-02-0606 February 2013 Notice of Forthcoming Meeting with Nine Mile Point Nuclear Station, LLC to Discuss the Maximum Extended Load Line Limit Analysis Plus (Mellla+) Implementation for Nine Mile Point (NMP) Unit 2 ML12165A1902012-06-12012 June 2012 Memo to S. Wastler Technical Assistant Request - Review of Physical Security Plan of Nine Mile Point Nuclear Station (TAC No. L24655) ML12136A5672012-05-17017 May 2012 Summary of Meeting with Constellation Energy to Discuss the Constellation Apparent Violation of NRC Regulations at Title 10 of the Code of Federal Regulations Part 50.9 ML12107A5052012-04-16016 April 2012 Forthcoming Category 1 Public Meeting with Constellation Energy Nuclear Group, LLC to Discuss Preliminary Enforcement ML1207200542012-03-12012 March 2012 Notice of Forthcoming Pre-Application Meeting with Licensee for Nine Mile Point, Unit No. 1 to Discuss Proposed NFPA-805 License Amendment Request ML11354A1182011-12-22022 December 2011 12/8/2011 Summary of Meeting Between NRC Staff and the Nuclear Energy Institute to Discuss Current License Renewal Topics ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML11126A0962011-05-12012 May 2011 Notice of Meeting with Petitioner Requesting Action Under 10CFR2.206 Regarding Immediate Suspension of Operating Licenses of General Electric Mark 1 Boiling Water Reactors ML1108402192011-04-0404 April 2011 Memorandum to File: Transcripts for 10 CFR 2.206 Petition Regarding Oyster Creek and Nine Mile Point, Unit No. 1 Peak Cladding Temperature and ECCS Performance ML1023709572010-08-31031 August 2010 Notice of Closed Meeting with Nine Mile Point Nuclear Station, LLC, to Discuss the Review of Steam Dryer Analysis for the NMP2 Extended Power Uprate License Amendment Request ML1009105332010-04-0505 April 2010 U.S. Nuclear Regulatory Commission Staff Review of the Department of Homeland Security Consultation Reports ML1006301062010-03-10010 March 2010 Notice of Forthcoming Closed Meeting with Nine Mile Point Nuclear Station, LLC to Discuss the Review of Steam Dryer Analysis for the NMP2 Extended Power Uprate License Amendment Request ML0928100032009-10-0808 October 2009 Request for Additional Information Nine Mile Point Unit 2 (NMP2) Extended Power Uprate Application License Amendment Request ML0913405542009-05-14014 May 2009 Summary of Annual Assessment Open-House Public Meeting with Nine Mile Point and FitzPatrick ML0823407942008-08-27027 August 2008 Notice of Meeting with Nine Mile Point Nuclear Station to Discuss Proposed Extended Power Uprate Related to Steam Dryer Analysis for Unit No. 2 ML0818304792008-06-0303 June 2008 E-mail from R. Guzman to J. Dosa RR-ISI-007 Request for Clarification ML0807400842008-03-14014 March 2008 Draft Regulatory Guide for Comment ML0608905792006-03-29029 March 2006 01/23/2006 Summary of a Telephone Conference Call Held Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group, Inc. Concerning the Review for the Nine Mile Point, Units 1 & 2, License Renewal Application ML0607205152006-03-13013 March 2006 Forthcoming Meeting Between the U.S. Nuclear Regulatory Commission (NRC) Staff and Constellation Energy Group Inc (Ceg) to Discuss and Open Item for the Unit 1 Drywell Liner, at Nine Mile Point Nuclear Station, Units 1 and 2 ML0600300802006-02-17017 February 2006 Transmittal of Final ASP Analyses (August 14, 2003 Grid Disturbance Events) ML0601802052006-01-18018 January 2006 1/18/06 - Audit and Review Report for the Nine Mile Point Nuclear Station, Units 1 and 2, Amended License Renewal Application (TAC Nos. MC3272 and MC3273 ML0511203112005-05-11011 May 2005 Transmittal of Summaries of Final ASP Analyses ML0504702572005-03-14014 March 2005 Y020050009 - Use of Undocketed Information by the NRC Staff in Nine Mile Point Nuclear Station Amendment No. 161 (Inspector General Case No. 04-811; TAC MC5556) ML0504601382005-02-14014 February 2005 Summary of a Conference Call Between the U.S. Nuclear Regulatory Commission and the Constellation Energy Group Inc. Concerning the Review of the Nine Mile Point Nuclear Station, Units 1 and 2 ML0432105802004-11-15015 November 2004 Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2 (TAC Nos MC3272 and MC3273.) ML0425701122004-09-13013 September 2004 Notice of Exit Meeting with Constellation Energy to Discuss the Audit of the Methodology for the Scoping & Screening for the LRA for Nine Mile Point Nuclear Station Units 1 & 2 ML0423805622004-08-25025 August 2004 Notice of Meeting with Licensee to Discuss the Design Differences Between Nine Mile Point Nuclear Station, Units 1 and 2 and the Aging Operating Experiences for Both Units ML0405806902004-02-27027 February 2004 Transmittal of Preliminary ASP Analyses for Peer Review (August 14, 2003 Grid Event) ML0319705812003-07-14014 July 2003 Results of the Nine Mile Point Nuclear Plant Unit 2 SDP Phase 2 Notebook Benchmarking Visit ML0203003172002-01-30030 January 2002 Operating License Amendment Request Involving the Post-LOCA Containment Hydrogen Monitoring System NRC Generic Letter 1989-111989-06-30030 June 1989 NRC Generic Letter 1989-011: Resolution of Generic Issue 101 Boiling Water Reactor Water Level Redundancy ML18018A9321978-06-30030 June 1978 Letter Responding to November 4, 1977 and May 25, 1978 Letters and Forwarding Mark II Pressure Suppression Test Program, Phases I, II and III of the 4T Test - Application Memorandum, January 1977 ML17037B8031978-01-18018 January 1978 12/14/1977 Summary of Meeting with Mark II Owner'S Group and General Electric Company on Mark II Containment ML17037B8051978-01-16016 January 1978 Memorandum and 01/19/1978 Notice of Meeting with Mark II Owners Group and General Electric Company ML17037B8081978-01-0606 January 1978 Memorandum and 12/16/1977 Summary of Meeting with Mark II Owner'S Group and General Electric Company on Mark II Containment 2021-04-20 |
Text
November 15, 2004 MEMORANDUM TO: Ngoc (Tommy) Le, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation FROM: Kenneth Chang, Senior Mechanical Engineer /RA/
License Renewal Section B License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation
SUBJECT:
AUDIT AND REVIEW PLAN FOR PLANT AGING MANAGEMENT REVIEWS AND PROGRAMS FOR THE NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 (TAC NOS. MC3272 AND MC3273)
I have placed the Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2 into ADAMS (ML043000333). I am using this plan to manage the audits and reviews of the aging management programs and aging management review results assigned to Section B of the License Renewal and Environmental Impacts Program. Please inform the applicant that the audit and review plan may be downloaded from ADAMS.
Docket Nos.: 50-220 and 50-410
November 15, 2004 MEMORANDUM TO: Ngoc (Tommy) Le, Project Manager License Renewal Section A License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation FROM: Kenneth Chang, Senior Mechanical Engineer /RA/
License Renewal Section B License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation
SUBJECT:
AUDIT AND REVIEW PLAN FOR PLANT AGING MANAGEMENT REVIEWS AND PROGRAMS FOR THE NINE MILE POINT NUCLEAR STATION, UNITS 1 AND 2 (TAC NOS. MC3272 AND MC3273)
I have placed the Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Point Nuclear Station, Units 1 and 2 into ADAMS (ML043000333). I am using this plan to manage the audits and reviews of the aging management programs and aging management review results assigned to Section B of the License Renewal and Environmental Impacts Program. Please inform the applicant that the audit and review plan may be downloaded from ADAMS.
Docket Nos.: 50-220 and 50-410 Distribution: Hard Copy K. Chang S. Adams R. Hsu L. Tran S. West G. Cranston Adam Accession nos.:
- 1. Memo to Le, Ngoc (Tommy): ML043210580
- 2. Audit and Review Plan for Plant Aging Management Reviews and Programs for the Nine Mile Nuclear Station, Units 1 and 2: ML043000333
- 3. Pkg: ML043210581 Document name: E:\Filenet\ML043210580.wpd OFFICE PM:RLEP:DRIP LA:RLEP:DRIP PM:RLEP:LRA-B PM:RLEP:LRA-B ASC:RLEP:LRA-B NAME K. Chang M. Jenkins L. Tran R. Hsu G. Cranston DATE 11/13/04 11/10/04 11/15/04 11/13/04 11/15/04 RECORD COPY