ML050380436

From kanterella
Jump to navigation Jump to search
Undated Draft, Revision 2, NRC Fire Protection Inspection Report No. 05000400/2003007
ML050380436
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 02/03/2005
From: Ogle C
NRC/RGN-II/DRP/RPB1
To: Scarola J
Carolina Power & Light Co
References
EA-00-022, EA-01-310, FOIA/PA-2004-0277 IR-03-007
Download: ML050380436 (14)


See also: IR 05000400/2003007

Text

EA-00-022

EA-01 -310

Carolina Power & Light Company

ATTN: Mr. James Scarola

Vice President - Harris Plant

Shearon Harris Nuclear Power Plant

P. 0. Box 165, Mail Code: Zone 1

New Hill, North Carolina 27562-0165

SUBJECT: SHEARON HARRIS NUCLEAR POWER PLANT - NRC FIRE PROTECTION

INSPECTION REPORT NO. 05000400/2003007

Dear Mr. Scarola:

On October_, 2003, the U.S. Nuclear Regulatory Commission (NRC) completed an in-office

review of the significance of the triennial fire protection inspection findings of inspection report

05000400/2002011 related to your Shearon Harris Nuclear Power Plant. The enclosed report

documents the results of our significance determination, which was discussed on October-,

2003, by telephone with Mr. _ _ and other members of your staff.

This report documents two NRC-identified findings of very low significance (Green). Both of

these findings were determined to involve violations of NRC requirements. However, because

of the very low safety significance and because they are entered into your corrective action

program, the NRC is treating these two findings as non-cited violations (NCVs) consistent with

Section VI.A. of the NRC enforcement Policy. If you contest any NCV in this report, you should

provide a response within 30 days of the date of this inspection report, with the basis for your

denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,

DC 20555-0001; with copies to the Regional Administrator, Region Il; the Director, Office of

Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001;

and the NRC Resident Inspector at the Shearon Harris Nuclear Power Plant.

In accordance with 10 CFR 2.790 of the NRC's uRules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at

httD://www.nrc.cov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No.: 50-400

<L/

CP&L 2

License No.: NPF-63

Enclosure: Inspection Report 05000400/200307

w/Attachment: Supplemental Information

cc w/encl: (use normal distribution list plus EICS and OE)

Distribution w/encl:

L. Slack, EICS

B. Mozafari, NRR

OEMAIL

RIDSNRRDIPMLIPB

PUBLIC

OFFICE RII:DRS RII:DRS RII:DRS RII:DRP RII:EICS

SIGNATURE

NAME RSchin WRogers DCPayne PFredrickson CEvans

DATE

E-MAIL COPY? YES NO YES NO YES -NO A TYENO YES No -SNo

PUBLIC DOCUMENT I YES NO I I __ _

OFFICIAL RECORD COPY DOCUMENT NAME: P:WVarris IR 03-07R2.wpd

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.: 50-400

License No.: NPF-63

Report No.: 05000400/2003007

Licensee: Carolina Power & Light (CP&L)

Facility: Shearon Harris Nuclear Power Plant

Location: 5413 Shearon Harris Road

New Hill, NC 27562

Dates: February 1, 2003 - October _, 2003

Inspectors: W. Rogers, Senior Reactor Analyst, Region II

R. Schin, Senior Reactor Inspector, Region II

Approved by: Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000400/2003-007; 02/01/2003 - 10/J2003; Shearon Harris Nuclear Power Plant;

Significance Determination of Fire Protection Findings.

The in-office review was conducted by a regional inspector, a regional senior reactor analyst,

and NRC Headquarters senior reactor Analysts. Two Green findings, each a non-cited violation

(NCV), were identified. The significance of issues is indicated by their color (Green, White,

Yellow, Red) using IMC 0609 "Significance Determination Process" (SDP). Findings for which

the SDP does not apply may be "Green" or be assigned a severity level after NRC management

review. The NRC's program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1 649, "Reactor Oversight Process," Revision 3, dated July

2000.

A. Inspector Identified Findings

Cornerstones: Mitigating Systems and Initiating Events

Green. An NCV of Operating License Condition 2.F, the Fire Protection Program, and

Technical Specification (TS) 6.8.1, Procedures and Programs, was identified for

inadequate implementation of the fire protection program. Physical and procedural

protection for equipment that was relied on for safe shutdown (SSD) during a fire in fire

safe shutdown analysis (SSA) areas 1-A-BAL-B-B1, 1-A-BAL-B-B2, 1-A-BAL-B-B3, 1-A-

BAL-B-B4, 1-A-EPA, and 1-A-BAL-C of the reactor auxiliary building was inadequate.

Consequently, a fire in one of these SSA areas could result in a reactor coolant pump

seal loss of coolant accident (LOCA) event, a main steam line break (MSLB) event, a

loss of high pressure safety injection, and/or a loss of component cooling water to the

reactor coolant pump seals. The licensee has initiated corrective actions including

assigning an additional operator to be available to perform post-fire safe shutdown

actions and performing a complete review of the safe shutdown analysis and related

operating procedures.

This finding was greater than minor because it involved a lack of required fire barriers

for equipment that was relied upon for safe hot shutdown following a fire. The finding

also had more than minor safety significance because it affected the objectives of the

Mitigating Systems and Initiating Events Cornerstones of Reactor Safety. The finding

affected the availability and reliability of systems that mitigate initiating events to prevent

undesirable consequences. It also affected the likelihood of occurrence of initiating

events that challenge critical safety functions. The finding was of very low significance

(Green) because of the low fire ignition frequencies, lack of combustible materials in

critical locations, and the effectiveness of the fire protection features and the unaffected

SSD equipment to mitigate a fire in each of the affected fire zones/areas. (Section

1R05.03.b.1)

Green. An NCV of Operating License Condition 2.F, the Fire Protection Program, and

Technical Specification (TS) 6.8.1, Procedures and Programs, was identified for

inadequate corrective action for previous Violation 50-400/02-08-01. Physical and

procedural protection for equipment that was relied on for safe shutdown (SSD) during a

Enclosure

fire in the new auxiliary control panel fire area 1-A-ACP was inadequate. Consequently,

a fire in area 1-A-ACP could result in a loss of auxiliary feedwater and a main steam line

break (MSLB) event. The licensee has initiated corrective actions including assigning

an additional operator to be available to perform post-fire safe shutdown actions and

performing a complete review of the safe shutdown analysis and related operating

procedures.

This finding was greater than minor because it involved inadequate fire barriers for

equipment that was relied upon for safe hot shutdown following a fire. The finding also

had more than minor safety significance because it affected the objectives of the

Mitigating Systems Cornerstone of Reactor Safety. The finding affected the availability

and reliability of systems that mitigate initiating events to prevent undesirable

consequences. The finding was of very low significance (Green) because of the very

low ignition sources in the fire area, manual suppression capability, and the power

conversion system not being affected by a fire in this fire area. (Section 1R05.03.b.2)

B. Licensee-Identified Violations

None

Enclosure

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 FIRE PROTECTION

.01 Significance Determination for Triennial Fire Protection Inspection Findings

a. Inspection Scope

In inspection report (IR) 50-400/02-11, nine findings had been identified as unresolved

items (URIs) pending completion of the NRC significance determination process (SDP).

The nine URIs were:

  • URI 50-400/02-11 -01, Failure to Protect Charging System MOV 1CS-1 65, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

  • URI 50-400/02-11-02, Failure to Protect Charging System MOVs 1CS-1 69, 1CS-

214,1 CS-218, and 1CS-219 From Maloperation Due To a Fire

  • URI 50-400/02-11-03, Failure to Protect Charging System MOVs 1CS-166, 1CS-

168, and 1CS-217 From Maloperation Due To a Fire

  • URI 50-400/02-11-04, Failure to Protect Component Cooling MOVs 1CC-251

and 1CC-208, CC for RCP Seals, From Maloperation Due To a Fire

  • URI 50-400/02-11-05, Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire

  • URI 50-400/02-11-06, Fire SSD Operator Actions With Excessive Challenges
  • URI 50-400/02-11-07, Too Many Fire SSD Actions for Operators to Perform
  • URI 50-400/02-11-08, Using the Boric Acid Tank Without Level Indication

Operator Actions

This inspection report documents the results of the in-office completion of the NRC SDP

with respect to those nine URls. The significance determination was accomplished as

described in NRC Inspection Manual Chapter (IMC) 0609, Signification Determination

Process; IMC 0609A, Significance Determination of Reactor Inspection Findings for At-

Power Situations; and IMC 0609F, Determining Potential Risk Significance of Fire

Protection and Post-Fire Safe Shutdown Inspection Findings. This involved evaluating

the significance of a potential fire in each of the seven affected fire safe shutdown

Enclosure

2

analysis (SSA) areas using the Phase 11SDP, considering all examples of the findings

that could be involved in each fire. To better assess the overall significance of all of the

performance deficiencies, they were recharacterized as two overall findings: 1)

Inadequate Implementation of the Fire Protection Program for Safe Shutdown; and 2)

Inadequate Corrective Action for a Previous White Fire Protection Finding.

In addition, the performance deficiencies which could result in the loss of a safety

function were evaluated by Office of Nuclear Reactor Regulation (NRR) analysts using

the Phase Ill portion of the SDP. Inclusive in this evaluation were extensive walkdowns

of the applicable fire SSA areas by two fire protection contractors to observe ignition

sources and possible fire propagation from these ignition sources that could affect the

unprotected cables of concern. Also, electrical circuit drawings and the latest

information on cable hot short failure mechanisms and probabilities were used to

develop cable failure probabilities that could cause a loss of function for the unprotected

cables of concern.

b. Findings

(1) Inadeauate Imrlementation of the Fire Protection Program for Safe Shutdown

Introduction: An overall finding was identified in that the implementation of the fire

protection program was inadequate. Eight of the nine URIs described in IR 50-400/02-

11 were considered to include performance deficiencies related to this overall finding.

Based on evaluating those performance deficiencies for their effects during fires that

could occur in each of six affected fire SSA areas, this overall finding was determined to

have a very low significance (Green).

Description: The licensee's implementation of the fire protection program for ensuring

the ability to safely shut down the plant during a fire was inadequate, in that:

  • The fire SSA failed to identify some cables that were relied upon for safe

shutdown (SSD) during a fire. Consequently, those cables were not provided

with the required protection from fire damage. A fire could cause hot shorts in

the cables which would result in maloperation of equipment that was relied upon

for SSD during that fire.

  • The SSA identified many cables that were relied upon for SSD during a fire, but

the licensee generally failed to provide the required physical protection from fire

damage. Instead, the SSA designated that operator actions would be taken to

prevent or mitigate the effects of the fire damage. However, the licensee did not

obtain NRC approval for these deviations from the approved fire protection

program.

  • Some of the operator actions that were designated by the SSA were not

incorporated into operating procedures for SSD. Also, the operator actions in

procedures differed in many respects from the operator actions that were

Enclosure

3

analyzed in the SSA. For example, the operating procedures directed operators

to use some different flowpaths than those analyzed in the SSA.

  • Some operator actions in the SSD procedures would not work. They were too

challenging, involved entering the area of the fire, were not adequately analyzed,

or were too numerous for the available SSD non-licensed operator to perform.

Examples of this overall finding were included in the following eight URls: URI 50-

400/02-11-01, -02, -03, -04, -05, -07, -08, and -09. The inspectors and analysts

evaluated the effects of the multiple examples of this overall finding during a fire that

could occur in each of the six affected fire SSA areas of the reactor auxiliary building

(RAB) using Phase II and Phase IlIl of the SDP. Based on that analysis, the inspectors

and analysts concluded that the overall finding did not have more than very low safety

significance (Green) because of the low fire ignition frequencies that could impact the

cables of interest, the lack of combustible materials in critical locations, and the

effectiveness of the fire protection features and the unaffected SSD equipment to

mitigate a fire in each of the affected fire zones/areas.

Analysis: This finding had more than minor safety significance because it involved a

lack of required fire barriers for equipment that was relied upon for safe hot shutdown

following a fire. The finding also had more than minor safety significance because it

affected the objectives of the Mitigating Systems and Initiating Events Cornerstones of

Reactor Safety. The finding affected the availability and reliability of systems that

mitigate initiating events to prevent undesirable consequences. It also affected the

likelihood of occurrence of initiating events that challenge critical safety functions. The

finding did not have more than very low safety significance (Green) because of the low

fire ignition frequencies, lack of combustible materials in critical locations, and the

effectiveness of the fire protection features and the unaffected SSD equipment to

mitigate a fire in each of the affected fire zones/areas.

Enforcement: As described in IR 50-400/02-11, Operating License Condition (OLC) 2.F

required that the licensee implement and maintain in effect all provisions of the

approved Fire Protection Program (FPP) as described in the Final Safety Analysis

Report (FSAR). The Updated FSAR (UFSAR), Section 9.5.1, FPP, stated that outside

containment, where cables or equipment (including associated non-essential circuits

that could prevent operation or cause maloperation due to hot shorts, open circuits, or

shorts to ground) of redundant safe shutdown divisions of systems necessary to achieve

and maintain cold shutdown conditions are located within the same fire area outside of

primary containment, one of the redundant divisions must be ensured to be free of fire

damage. Section 9.5.1 further stated that if both divisions are located in the same fire

area, then one division is to be physically protected from fire damage by one of three

methods: 1) a three-hour fire barrier, 2) a one-hour fire barrier plus automatic detection

and suppression, or 3) a 20-foot separation with no intervening combustibles and with

automatic detection and suppression. The licensee had received no NRC approvals for

deviating from these requirements.

Enclosure

4

Also, OLC 2. F. and UFSAR Section 9.5.1 stated that Branch Technical Position (BTP)

9.5-1 was used in the design of the fire protection program for safety-related systems

and equipment and for other plant areas containing fire hazards that could adversely

affect safety-related systems. BTP 9.5-1, Section C.5.g, "Lighting and Communication,"

paragraph (1), required that fixed self-contained lighting consisting of fluorescent or

sealed-beam units with individual eight-hour-minimum battery power supplies should be

provided in areas that must be manned for safe shutdown and for access and egress

routes to and from all fire areas.

In addition, TS 6.8.1, Procedures and Programs, required procedures as recommended

by Regulatory Guide (RG) 1.33 and procedures for fire protection program

implementation. RG 1.33 recommended procedures for combating emergencies,

including fires. The licensee's interpretation of their fire protection program was that

they could and would rely on proceduralized operator actions in place of physically

protecting SSD equipment from fire damage (see Section 1R05.04.b.1).

Contrary to the above requirements, the licensee failed to adequately implement and

maintain in effect all of the provisions of the approved FPP. The licensee failed to

ensure that one of the redundant safe shutdown divisions of systems necessary to

achieve and maintain cold shutdown conditions was protected from fire damage; failed

to have adequate procedures for combating fire emergencies; and failed to provide the

required emergency lighting in areas that must be manned for safe shutdown; as

described above in the eight examples of this overall finding. Because the identified

examples of this failure to adequately implement and maintain in effect all of the

provisions of the approved FPP are of very low safety significance and have been

entered into your corrective action program [Action Reports (ARs) 76260, 80212, 80089,

69721, 80215, 75065, and 79047], this violation is being treated as a non-cited violation

(NCV), consistent with Section VL.A of the NRC Enforcement Policy: NCV 50-400/03-

07-01; Inadequate Implementation of the Fire Protection Program for Safe Shutdown.

(2) Inadequate Corrective Action for a Previous White Fire Protection Finding

Introduction: An overall finding was identified in that the corrective action for previous

White finding and related Violation (VIO) 50-400/02-08-01 was inadequate. Four of the

nine URIs described in IR 50-400/02-11 included examples of this overall finding.

Based on evaluating the multiple examples of this overall finding for their effects during

a fire that could occur in the one affected fire area, this overall finding was determined to

have a very low significance (Green).

Description: The licensee's corrective action for a previous White fire protection finding

(VIO 50-400/02-08-01), associated with a Thermo-Lag fire barrier assembly between the

'B' train switchgear room / auxiliary control panel and the 'A' train cable spreading room,

was inadequate. The corrective action contributed to four new findings:

  • The corrective action created a new fire area and many new manual operator

actions for a fire in the new fire area instead of providing the required physical

Enclosure

5

protection of cables. This finding was described in URI 50-400/02-11-05,

Reliance on Manual Actions in Place of Required Physical Separation or

Protection From a Fire.

challenges such that there was not reasonable assurance that all non-licensed

operators (NLOs) would be able to perform the action during a fire event. This

finding was described in URI 50-400/02-11-06, Fire SSD Operator Actions With

Excessive Challenges.

Examples of this overall finding were included in the following four URls: URI 50-

400/02-11-05, -06, -07, and -09. The inspectors and analysts evaluated the effects of

the multiple examples of this overall finding during a fire that could occur in the 1-A-ACP

fire area of the RAB, using Phase II of the SDP. Based on that evaluation, the

inspectors and analysts concluded that the overall finding did not have more than very

low safety significance (Green) because of the very low ignition sources in the fire area,

manual suppression capability, and the power conversion system not being affected by

a fire in this fire area. The Green significance determination was also confirmed by a

walkdown of the fire area by two contractors.

Analysis: This finding had more than minor safety significance because it involved

inadequate fire barriers for equipment that was relied upon for safe hot shutdown

following a fire. The finding also had more than minor safety significance because it

affected the objectives of the Mitigating Systems Cornerstone of Reactor Safety. The

finding affected the availability and reliability of systems that mitigate initiating events to

prevent undesirable consequences. The finding did not have more than very low safety

significance (Green) because of the very low ignition sources in the fire area, manual

suppression capability, and the power conversion system not being affected by a fire in

this fire area.

Enforcement: OLC 2.F and the UFSAR, Section 9.5.1, FPP, included quality assurance

(QA) requirements for fire protection. The FPP stated that a QA program was being

used to identify and rectify any possible deficiencies in design, construction, and

operation of the fire protection systems. Also, as described in Section 1R05.01.b.1

above, OLC 2.F required that one of the redundant divisions would be free of fire

damage. Further, if both divisions were located in the same area, then one of the

divisions was to be physically protected from fire damage by one of three specified

methods. Further, OLC.2.F required that battery-backed emergency lights be provided

in locations where operators were required to perform actions for SSD from a fire. In

addition, TS 6.8.1, Procedures and Programs, required procedures for implementing the

fire protection program and for combating fires.

Contrary to the above requirements, the licensee's corrective actions for previous VIO

50-400/02-08-01 were inadequate because they failed to rectify deficiencies in design,

Enclosure

6

construction, and operation related to SSD from a fire in the area of the ACP room. The

licensee failed to protect various equipment either physically or procedurally from the

effects of a fire where that equipment was relied on for SSD. The licensee entered the

finding into the corrective action program as AR 80215. Because the identified

examples of this inadequate corrective action are of very low safety significance and

have been entered into the corrective action program, this violation is being treated as

an NCV, consistent with Section VL.A of the NRC Enforcement Policy: NCV 50-400/03-

07-02; Inadequate Corrective Action for a Previous White Fire Protection Finding.

The previous open items related to these two overall findings are closed; including VIO

50-400/02-08-01 and URIs 50-400/02-11-01, -02, -03, -04, -05, -06, -07, -08, and -09.

Enclosure

7

40A6 Meetings, including Exit

The team presented the inspection results to Mr. _ _ and members of his staff

at the conclusion of the inspection on , 2003. The licensee acknowledged the

findings presented. Proprietary information is not included in this inspection report.

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel

D. Baksa, Supervisor, Equipment Performance

J. Caves, Licensing Supervisor

R. Duncan, Director of Site Operations

M. Fletcher, Manager, Fire Protection Program

A. Khanpour, Manager, Engineering

NRC personnel

J. Brady, Senior Resident Inspector, Shearon Harris

C. Ogle, Chief, Engineering Branch 1 (EBI), Division of Reactor Safety (DRS), Region II (Rll)

C. Payne, Fire Protection Team Leader, EBI, DRS, RII

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

50-400/03-07-01 NCV Inadequate Implementation of the Fire Protection Program

for Safe Shutdown (Section 1R05.01.b.1)

50-400/03-07-02 NCV Inadequate Corrective Action for a Previous White Fire

Protection Finding (Section 1R05.01.b.2)

Closed

50-400/02-08-01 VIO Failure to Implement and Maintain NRC Approved Fire

Protection Program Safe Shutdown System Separation

Requirements (Section 1R05.01.b.2)

50-400/02-11-01 URI Failure to Protect Charging System MOV 1CS-1 65, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

(Section 1R05.01.b.1)

50-400/02-11-02 URI Failure to Protect Charging System MOVs I CS-1 69,1 CS-

214,1 CS-218, and 1CS-219 From Maloperation Due To a

Fire (Section 1R05.01.b.1)

50-400/02-11-03 URI Failure to Protect Charging System MOVs 1CS-1 66, 1CS-

168, and 1CS-217 From Maloperation Due To a Fire

(Section 11R05.01.b.1)

Attachment

2

50-400/02-11-04 URI Failure to Protect Component Cooling MOVs 1CC-251 and

1CC-208, CC for RCP Seals, From Maloperation Due To a

Fire (Section 1R05.01.b.1)

50-400/02-11-05 URI Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire (Section

1R05.01.b.2)

50-400/02-11-06 URI Fire SSD Operator Actions With Excessive Challenges

(Section 1R05.01.b.2)

50-400/02-11-07 URI Too Many Fire SSD Actions for Operators to Perform

(Section 1R05.01.b.2)

50-400/02-11-08 URI Using the Boric Acid Tank Without Level Indication

(Section 1R05.01.b.1)

50-400/02-11-09 URI Failure to Provide Required Emergency Lighting for SSD

Operator Actions (Section 1R05.01.b.2)

Attachment