IR 05000400/2020004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000400/2020004
ML21027A108
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 01/27/2021
From: Stewart Bailey
NRC/RGN-II/DRP/RPB4
To: Maza K
Duke Energy Progress
References
IR 2020004
Download: ML21027A108 (30)


Text

January 27, 2021

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - INTEGRATED INSPECTION REPORT 05000400/2020004

Dear Ms. Maza:

On December 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Shearon Harris Nuclear Power Plant. On January 20, 2021, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of Enforcement; and the NRC Resident Inspector at Shearon Harris Nuclear Power Plant. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Stewart N. Bailey, Chief Reactor Projects Branch 4 Division of Reactor Projects

Docket No. 05000400 License No. NPF-63

Enclosure:

As stated

Inspection Report

Docket Number:

05000400

License Number:

NPF-63

Report Number:

05000400/2020004

Enterprise Identifier: I-2020-004-0042

Licensee:

Duke Energy Progress, LLC

Facility:

Shearon Harris Nuclear Power Plant

Location:

New Hill, NC 27562

Inspection Dates:

October 1, 2020 to December 31, 2020

Inspectors:

J. Zeiler, Senior Resident Inspector

A. Patz, Resident Inspector

J. Diaz-Velez, Senior Health Physicist

B. Kellner, Senior Health Physicist

J. Rivera, Health Physicist

G. Smith, Senior Resident Inspector

J. Steward, Resident Inspector

Approved By:

Stewart N. Bailey, Chief

Reactor Projects Branch 4

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Shearon Harris Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Inadequate Surveillance Procedure for Control Rod Testing Resulted in Unnecessary Manual Reactor Trip in Response to a Dropped Control Rod Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000400/2020004-01 Open/Closed None (NPP)71153 A self-revealing finding of very low safety significance (Green) and associated non-cited violation (NCV) of Technical Specification (TS) 6.8.1.a, Procedures and Programs, was identified for the licensees failure to maintain an adequate procedure for conducting control rod TS surveillance testing. Specifically, the procedure inappropriately directed operator action to manually trip the reactor for a dropped control rod that occurred during testing.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000400/2020-002-00 Unit 1 Manual Reactor Trip Due to Control Rod Drop During Surveillance Testing 71153 Closed

PLANT STATUS

Unit 1 operated at or near rated thermal power until December 15, 2020, when the unit was down powered to 80 percent for a degraded lube oil problem on the 'A' condensate booster pump. On December 16, 2020, while preparing to make repairs on the condensate booster pump, an unrelated automatic reactor trip occurred due to a main generator lockout resulting from an electrical fault on the 'B' train non-safety electrical distribution system. Following a forced outage to address the electrical fault and 'B' condensate booster pump, as well as conduct other plant repair items, Unit 1 was restarted on December 21, 2020. The unit was returned to near rated thermal power on December 23, 2020 and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures on December 1, 2020

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)

'B' emergency service water (ESW) train while 'A' ESW train was out of service for preventive maintenance on October 13, 2020 (2)

'B' emergency diesel generator (EDG) while 'A' EDG was out of service for emergent output breaker relay failure on October 15, 2020 (3)

'A' and 'B' motor driven auxiliary feedwater systems during startup from reactor trip and forced outage on December 20, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the alternate seal injection system on October 6, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Reactor Auxiliary Building (RAB) 261' elevation alternate seal injection and filter area (fire zone 1-A-4-COMC) on October 6, 2020 (2)

'A' and 'B' ESW pump intake structure (fire zones 12-I-ESWPA, 12-I-ESWPA-BAL, 12-I-ESWPB, 12-I-ESWPB-BAL, and 12-I-ESW-BAL) on October 13, 2020 (3)

'B' EDG room and support equipment areas (fire zones 1-D-1-DGB-RM, 1-D-3-DGB-ES, 1-D-DTB, 1-D-1-DGB-ASU, and 1-D-1-DGB-ER) on October 15, 2020

(4) RAB 236' elevation mechanical penetration room (fire zone 1-A-30MP) on December 3, 2020
(5) RAB 286' elevation 'B' train essential switchgear room, ventilation room, and battery room (fire zones 1-A-SWGRB, 1-A-HVB, and 1-A-BATB) on December 21, 2020

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) Diesel fuel oil storage transfer building on October 13, 2020

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1)

'B' essential services chilled water (ESCW) condenser heat exchanger and service water valves

'B' train containment fan cooler units AH-1 and AH-4 heat exchangers and service water valves

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

The licensee completed the annual requalification operating examinations required to be administered to all licensed operators in accordance with Title 10 of the Code of Federal Regulations 55.59(a)(2), Requalification Requirements, of the NRCs Operators Licenses. During the week of November 23, 2020, the inspector performed an in-office review of the overall pass/fail results of the individual operating examinations, the crew simulator operating examinations, and the biennial written examinations in accordance with IP 71111.11, Licensed Operator Requalification Program. These results were compared to the thresholds established in Section 3.02, Requalification Examination Results, of IP

===71111.11.

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam and biennial written examination completed on November 6, 2020.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)

=

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during control rod testing and select control rod drive mechanism coil current data acquisition on November 2, 2020

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a simulator scenario for an annual operator requalification examination involving a faulted steam generator tube rupture on October 28, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Failure of the 'A' EDG output breaker ability to automatically open on valid signal on October 14, 2020

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Electrical ground fault in 'B' EDG governor digital speed reference unit on October 28, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated (Green) risk during emergent alternate seal injection system non-functionality due to squib valves exceeding vendor assigned usage dates on October 6, 2020
(2) Elevated (Green) risk during planned unavailability of the 'A' ESW pump for preventive maintenance on October 13, 2020
(3) Elevated (Green) risk during unavailability of 'A' EDG and engineered safety features actuation system sequencer during emergent repair of failed 'A' EDG output breaker position status light and associated sequencer relay on October 15, 2020
(4) Elevated (Green) risk during planned unavailability of the 'B' EDG during corrective maintenance on October 27, 2020
(5) Elevated (Green) risk during startup from reactor trip on December 16, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Alternate seal injection squib valves installed past their vendor recommended expiration date (Nuclear Condition Report (NCR) 02351994) on October 6, 2020 (2)125 volt direct current (VDC) ground indication on 'B' EDG governor digital speed reference unit (NCRs 02355227 and 02352458) on October 28, 2020 (3)

'A' EDG output breaker position status circuitry sequencer relay failure (NCR 02353323) on October 17, 2020

(4) Scaffold clearance deviation on safety-related 'B' ESCW make-up tank service water inlet piping (NCR 02354131) on December 3, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (7 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Operations procedure (OP)-139, Service Water System, Section 5.2, Supplying ESW Headers with an ESW Pump, following scheduled cleaning of stuffing box and seal water piping of 'A' ESW pump on October 13, 2020
(2) OP-155, Diesel Generator Emergency Power System, Section 5.1 and 5.3, for starting 'A' EDG and synchronizing/paralleling to bus, following replacement of failed output breaker relay SN-SA on October 15, 2020
(3) OP-155, Diesel Generator Emergency Power System, Section 8.20 for resetting the governor electronic speed control on October 27, 2020
(4) Operations periodic test (OPT)-1546, TSC Emergency Ventilation System Performance Test Quarterly Interval at All Times, following emergent repair of failed air line to outside air intake damper on December 2, 2020
(5) PM-E0003, 6.9KV Bus and Cubicle, switchgear/bus inspections and testing following electrical fault repairs to 'B' Auxiliary Bus on December 17-19, 2020
(6) Post-modification functional testing under instructions in Engineering Change 418833 following cable repairs resulting from electrical fault on December 20, 2020
(7) OPT-1512, Essential Chilled Water Turbopak Units Quarterly Inspection/Checks Modes 1-6, following emergent repair of 'B' ESCW chiller hot gas bypass valve actuator on December 30, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated forced outage activities during recovery from an electrical fault in the busduct from the 'B' Unit Auxiliary Transformer to the 'B' Auxiliary Bus from December 16-22, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) OST-1005, Control Rod and Rod Position Indicator Exercise Quarterly Interval Modes 1-3, on November 2, 2020
(2) OST-1010A, A Train Containment Cooling System Operability Test Monthly Interval Modes 1-4, on November 27, 2020
(3) OP-104, Rod Control System, Section 8.19, for exercising all control rods during forced outage using work order 20423639 on December 18-19, 2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) OST-1076, Auxiliary Feedwater Pump 1B-SB Operability Test Quarterly Interval Modes 1 - 4, on October 5, 2020

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) A simulator-based licensed operator training evolution involving a faulted steam generator tube rupture on October 28,

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards.

Instructions to Workers (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated radiological protection-related instructions to plant workers.

Contamination and Radioactive Material Control (IP Section 03.03) (3 Samples)

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) Observed licensee surveys of potentially contaminated material leaving the radiological controlled area (RCA) exit point
(2) Observed workers exiting the RCA exit point
(3) Observed licensee routine periodic radiological survey of the old reactor head storage facility

High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (4 Samples)

The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:

(1) RAB - Spent Fuel Transfer Tube Hatch (Locked and Posted Grave Danger)
(2) Waste Processing Building (WPB) - Waste Holdup Tank (Locked and posted Locked High Radiation Area (LHRA))
(3) WPB Room 144A - Access Gate (LHRA key control and posted LHRA)
(4) WPB Room 144A Drum Crane - Crane controls Locked (LHRA lock/key and posted LHRA)

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)

(1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements.

71124.06 - Radioactive Gaseous and Liquid Effluent Treatment

Walkdowns and Observations (IP Section 03.01) (4 Samples)

The inspectors evaluated the following radioactive effluent systems during walkdowns:

(1) Turbine building wide range gaseous detection system to turbine vent stack
(2) Reactor auxiliary building wide range gaseous detection system to plant vent stack
(3) WPB wide range gaseous detection system to WPB vent stack
(4) Liquid effluent discharge and detection system

Sampling and Analysis (IP Section 03.02) (4 Samples)

Inspectors evaluated effluent samples reports and selective compensatory samples.

(1) Liquid Effluent Radiochemistry Surveillance Report #L-2020-0003 and L-2020-0029
(2) Liquid Effluent Radiochemistry Surveillance Report #L-2020-0031 and L-2020-0032
(3) Gaseous Effluent Radiochemistry Surveillance Reports #G-2020-0002, G-2020-0003, and G-2020-0181
(4) Gaseous Effluent Radiochemistry Surveillance Reports #G-2020-0182 and G-2020-0183

Dose Calculations (IP Section 03.03) (2 Samples)

The inspectors evaluated the following dose calculations:

(1) Dose Calculations associated with Liquid Effluent Radiochemistry Surveillance Report
  1. L-2020-0003, L-2020-0029, L-2020-0031, and L-2020-0032
(2) Dose Calculations associated with Gaseous Effluent Radiochemistry Surveillance Reports #G-2020-0182, G-2020-0183, G-2020-0002, G-2020-0003, and G-2020-0181

Abnormal Discharges (IP Section 03.04) (1 Sample)

The inspectors evaluated the following abnormal discharges:

(1) Sample completed in accordance with NRC IMC 306, Planning, Scheduling, Tracking and Reporting of the Reactor Oversight Process (ROP). The sample was not available because there were no unmonitored releases in 2018 and 2019.

71124.07 - Radiological Environmental Monitoring Program

Environmental Monitoring Equipment and Sampling (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated environmental monitoring equipment and observed collection of environmental samples.

Radiological Environmental Monitoring Program (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the implementation of the licensees radiological environmental monitoring program.

GPI Implementation (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees implementation of the Groundwater Protection Initiative program to identify incomplete or discontinued program elements.

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

(1) Inspectors evaluated the licensees performance in controlling, labeling and securing radioactive materials.

Radioactive Waste System Walkdown (IP Section 03.02) (1 Sample)

(1) Inspectors walked down accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality.

Waste Characterization and Classification (IP Section 03.03) (3 Samples)

(1) The inspectors evaluated the licensees characterization and classification of radioactive waste associated with shipments19-124 and 20-270.
(2) The inspectors evaluated the licensees characterization and classification of radioactive waste associated with shipments19-008 and 19-109.
(3) The inspectors evaluated the licensees characterization and classification of radioactive waste.

Shipping Records (IP Section 03.05) (5 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1) Shipping records for shipment 19-008
(2) Shipping records for shipment 19-124
(3) Shipping records for shipment 19-109
(4) Shipping records for shipments20-270
(5) Shipping records for shipment 18-067

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS08: Heat Removal Systems (IP Section 02.07)===

(1) Unit 1 (October 1, 2019 - September 30, 2020)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 1 (October 1, 2019 - September 30, 2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) Unit 1 (November 1, 2019 through October 31, 2020)

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) Unit 1 (November 01, 2019 through October 31, 2020)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in equipment and human performance that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Control rod F-2 in control bank A dropped into the core during routine quarterly control rod surveillance testing on August 13, 2020 (NCRs 02343834 and 02347492)

71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event report (LER):

(1) LER 05000400/2020-002-00, Manual Reactor Trip Due to Control Rod Drop During Surveillance Testing (ADAMS Accession No. ML20286A166). The inspection conclusions associated with this LER are documented in this report under Inspection Results Section 71153. This LER is closed.

Personnel Performance (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated an automatic reactor trip due to an electrical fault in the bus duct for the electrical feeder from the 'B' Unit Auxiliary Transformer (UAT) to the 'B' Auxiliary Bus and licensees performance on December 16,

INSPECTION RESULTS

Inadequate Surveillance Procedure for Control Rod Testing Resulted in Unnecessary Manual Reactor Trip in Response to a Dropped Control Rod Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events

Green NCV 05000400/2020004-01 Open/Closed

None (NPP)71153 A self-revealing finding of very low safety significance (Green) and associated non-cited violation (NCV) of Technical Specification (TS) 6.8.1.a, Procedures and Programs, was identified for the licensees failure to maintain an adequate procedure for conducting control rod TS surveillance testing. Specifically, the procedure inappropriately directed operator action to manually trip the reactor for a dropped control rod that occurred during testing.

Description:

On August 13, 2020, with the unit operating at full power, a single control rod in control bank A, (i.e., rod F-2), dropped into the reactor core during ongoing control rod quarterly TS surveillance testing using procedure OST-1005, Control Rod and Rod Position Indicator Exercise Quarterly Interval Modes 1-3. At the time of the dropped rod, control bank A was being withdrawn from step 225 back to its pre-test position at step 228. Guidance in the procedure via Precaution and Limitations item 11, stated that a dropped rod with any control rods inserted into the core other than the controlling bank is an unanalyzed condition and the reactor must be tripped. In accordance with this instruction, the operators inserted a manual reactor trip in response to the dropped rod. All plant safety systems operated as designed during the reactor trip and the operators successfully placed the plant in a safe configuration.

The licensee determined the cause of the dropped control rod was due to the accumulation of corrosion products in the dashpot region of the control rod drive mechanism (CRDM) for rod F-2 movable gripper latch support assembly. This corrosion prevented the stationary gripper from latching onto the control rod drive shaft when the movable gripper was released. With both the movable and stationary grippers not engaged on the drive shaft, the control rod dropped into the fuel assembly. Corrosion buildup in the CRDM dashpot region was a known industry issue periodically experienced after new CRDMs are installed as part of reactor vessel head replacement projects such as that implemented by Shearon Harris Unit 1 during the Fall 2019 refueling outage. This corrosion buildup continues until a tightly adhered oxide (passivation) layer develops on the CRDM latch assemblies, at which time the accumulation of new corrosion is significantly reduced.

The guidance in OST-1005 to manually trip the reactor for a dropped rod during testing was added to the procedure in May 2008; however, there was no technical basis for the statement that the condition was an unanalyzed condition. Based on a review of the plant licensing basis and safety analysis for a dropped control rod event, the licensee determined that a single dropped control rod that occurs during control rod testing was not an unanalyzed plant condition. Therefore, the operator actions to manually trip the unit on August 13, 2020, was unnecessary.

Corrective Actions: Prior to restarting the unit, the licensee conducted multiple full length exercising all control rods in order to flush corrosion products from the dashpot region of the CRDMs and obtain CRDM coil current traces to detect the presence of corrosion. A preventive maintenance program was developed to routinely exercise the rods while taking coil current traces to break up any further corrosion and monitor performance of the gripper mechanisms to ensure continued CRDM proper operation. The licensee revised OST-1005, to remove the guidance to manually trip the reactor during surveillance testing for a dropped control rod and added direction that the existing guidance for a dropped control rod contained in Abnormal Operating Procedure (AOP)-001, Malfunction of Rod Control and Indication System, should be implemented, which required a controlled plant shutdown if more than two control rods dropped.

Corrective Action References: NCRs 02343834 and 02347492

Performance Assessment:

Performance Deficiency: The licensees failure to maintain an adequate control rod surveillance test procedure that resulted in an unnecessary manual reactor trip when a control rod drop occurred during testing was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Procedure Quality attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations. Specifically, the failure to maintain adequate instructions for addressing a control rod drop transient during testing resulted in an unnecessary manual reactor trip.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The finding was determined to be of very low safety significance (Green) because when screened as a transient initiator using Exhibit 1, "Initiating Events Screening Questions," it did not cause both a reactor trip AND the loss of mitigation equipment relied upon to transition the plant from the onset of the trip to a stable shutdown condition (e.g., loss of condenser or loss of feedwater).

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance. The inadequate direction to manually trip the reactor if a dropped control rod occurred in any control bank other than the controlling bank was added to OST-1005 in 2008.

Enforcement:

Violation: TS 6.8.1.a, Programs and Procedures, requires, in part, that written procedures shall be established, implemented, and maintained covering the activities described in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978. Section 8.b of Appendix A includes surveillance procedures for control rod testing. The licensees procedure for control rod surveillance testing is OST-1005, Quarterly Rod Exercise Testing.

Contrary to the above, from May 2008 to August 13, 2020, the licensee failed to establish, implement, and maintain an adequate surveillance procedure for conducting quarterly control rod testing. Specifically, OST-1005 incorrectly stated that a dropped control rod with any control rods inserted into the core other than the controlling bank was an unanalyzed plant condition and directed the operators to manually trip the reactor. As a result, an unnecessary manual reactor trip was initiated during surveillance testing when a control rod dropped in control bank A during testing on August 13, 2020.

Enforcement Action: This violation is being treated as an non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

The disposition of this violation closes LER 05000400/2020-002-00, Manual Reactor Trip Due to Control Rod Drop During Surveillance Testing.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 20, 2021, the inspectors presented the integrated inspection results to Kim Maza, Site Vice President (Site VP) and other members of the licensee staff.
  • On November 23, 2020, the inspectors presented the RP Occupational and Public Radiation Safety Inspection results to Kim Maza, Site VP and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

Action Request

(AR) 02038102

Winter Readiness

10/08/2020

Procedures

AD-WC-ALL-0230

Seasonal Readiness

Rev. 0

AP-301

Seasonal Weather Preparations and Monitoring

Rev. 86

71111.04

Drawings

2165-G-0871

Flow Diagram Alternate Seal Injection System Unit 1

Rev. 1

2165-S-1371

Simplified Flow Diagram Alternate Seal Injection System Unit

Rev. 1

Miscellaneous

DBD-320

Alternate Seal Injection System (ASI-System 2007)

Rev. 4

Procedures

OP-137

Auxiliary Feedwater System

Rev. 46

OP-139

Service Water System

Rev. 138

OP-155

Diesel Generator Emergency Power System

Rev. 91

OP-185

Alternate Seal Injection

Rev. 12

OP-186

Dedicated Shutdown Diesel Generator

Rev. 9

71111.05

Fire Plans

CSD-HNP-PFP-

RAB-261

Reactor Auxiliary Building Elevation 261 Pre-Fire Plan

Rev. 1

CSD-HNP-PFP-

DGB

Diesel Generator Building Pre-Fire Plan

Rev. 1

CSD-HNP-PFP-

RAB-236

Reactor Auxiliary Building Elevation 236 Pre-Fire Plan

Rev. 2

CSD-HNP-PFP-

RAB-286

Reactor Auxiliary Building Elevation 286 Pre-Fire Plan

Rev. 1

CSD-HNP-PFP-

SEC

Out Building Pre-Fire Plan

Rev. 5

Procedures

AD-EG-ALL-1520

Transient Combustible Control

Rev. 13

FPP-001

Fire Protection Program Manual

Rev. 44

FPP-013

Fire Protection - Minimum Requirements, Mitigating Actions

and Surveillance Requirements

Rev. 105

FPT-3220A

Incipient Fire Detection Alarm Notification Functional Test -

Monthly Interval

Rev. 2

71111.06

Calculations

CALC-HNP -

PRA F-E-0010

Diesel Fuel Oil Storage Transfer Building Internal Flooding

Evaluation

Rev. 3

71111.07A

Procedures

AD-EG-ALL-1312

Raw Water Program Implementation

Rev. 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

EPT-163

Generic Letter 89-13 Inspections (Raw Water Systems and

Local Area Air Handler Inspection and Documentation)

Rev. 19

MPT-M0091

Heat Exchanger Opening/Closure for NRC Generic Letter 89-

Inspections

Rev. 18

PLP-620

Service Water Program (Generic Letter 89-13)

Rev. 21

Work Orders

WO 12080977

Inspect and replace AH-4 service water return header isolation

valve

10/16/2016

WO 12080978

Inspect and replace 1SW-98, AH-1 containment fan cooler

service water outlet valve

10/17/2016

WO 13300529

Inspection of AH-1 and AH-4 service water return valve

4/8/2015

WO 1563658

Inspect and replace containment air handler heat exchanger

for AH-4

10/17/2010

WO 20269012

Inspect 'B' ESCW chiller condenser

10/18/2019

WO 20342496

Inspection and cleaning of 'B" ESCW chiller condenser heat

exchanger

7/17/2019

WOs 1563658

and 1527037

Inspect containment air handler AH-1 and AH-4

10/17/2010

71111.11Q Procedures

AD-OP-ALL-1000

Conduct of Operations

Rev. 17

AD-OP-ALL-1001

Conduct of Abnormal Operations

Rev. 3

AOP-001

Malfunction of Rod Control and Indication System

Rev. 55

AOP-016

Excessive Primary Plant Leakage

Rev. 58

AOP-019

Malfunction of RCS Pressure Control

Rev. 25

AOP-042

Secondary Steam Leak/Efficiency Loss

Rev. 8

APP-ALB-007

Annunciator Panel Procedure

Rev. 16

EOP-E-3

Steam Generator Tube Rupture

Rev. 7

OMM-001

Operations Administrative Requirements

Rev. 121

OST-1005

Control Rod and Rod Position Indicator Exercise Quarterly

Interval Modes 1-3

Rev. 28

Work Orders

WO 20424460

CRDM coil current during control rod movement testing

11/02/2020

71111.12

Corrective Action

Documents

NCR 02353323

Breaker 106 Amber Light Not Lit

10/14/2020

NCR 02354050

Technical Specification Documentation on Common Mode

Failures

10/20/2020

NCR 02355227

Replace EDG 'B' digital reference unit due to ground fault

10/30/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Drawings

CAR 2166-B-401,

Sheet 1101

Emergency Load Sequencer ESS Cabinet 1A-SA

Rev. 014

Procedures

AD-QC-ALL-0108

Nuclear Oversight Vendor QC Acceptance

Rev. 2

AD-QC-ALL-1000

Conduct of Nuclear Oversight Quality Control

Rev. 9

OP-155

Diesel Generator Emergency Power System

Rev. 91

OST-1013

1A-SA Emergency Diesel Generator Operability Test Monthly

Interval, Modes 1-6

Rev. 043

Work Orders

WO 20412441

Troubleshooting DC ground indication in 'B' EDG governor

DRU

10/29/2020

WO 20429280

Breaker 106 Amber Light Not Lit

10/26/2020

WO 20431799

Replace 'B' EDG digital reference unit

2/01/2020

71111.13

Corrective Action

Documents

NCR 2355134

Work order 20283049-06 lost from T-0 workweek due to

cross-train work

10/27/2020

Procedures

AD-NF-ALL-0501

Electronic Risk Assessment Tool (ERAT)

Rev. 5

AD-OP-ALL-0201

Protected Equipment

Rev. 7

AD-WC-ALL-0200

On-Line Work Management

Rev. 17

AD-WC-ALL-0240

On-Line Risk Management Process

Rev. 2

AD-WC-ALL-0410

Work Activity Integrated Risk Management

Rev. 10

Work Orders

WO 20238078

OPT-1532 ASI Squib Valves Fire Test 54 Month Interval

Modes

10/06/2020

WO 20379279

'A' ESW pump stuffing box and seal water piping cleaning

10/13/2020

WO 20412441

-52.5 VDC ground indicated on panel for B EDG

10/27/2020

WO 20429280

'A' EDG troubleshooting and repair of output breaker position

status light not lit

10/15/2020

71111.15

Engineering

Evaluations

EC 418420

Shelf Plus Service Life Extension of ASI Squib Valves 1ASI-21

and 1ASI-22

Rev. 0

EC 418533

Scaffold clearance deviation from safety-related 'B' ESCW

system

11/16/2020

71111.19

Corrective Action

Documents

NCR 2339156

-52.5 VDC ground indicated on DP-1B-SB

07/20/2020

Drawings

CAR 2166-B-401,

Sheet 2007

Diesel Generator 1B-SB Engine Governor Control

Rev. 11

Engineering

Changes

EC 418833

Repair Cables in Cable Tray L1200 Damaged by Electrical

Fault

2/16/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

AD-EG-ALL-1155

Post Modification Testing

Rev. 4

PLP-400

Post Maintenance Testing

Rev. 64

Work Orders

20420667

TSC emergency ventilation testing failure and repairs

2/02/2020

WO 20379279

'A' ESW pump stuffing box and seal water piping cleaning

10/13/2020

WO 20412441

-52.5 VDC ground indicated on panel for B EDG

10/27/2020

WO 20429280

Replacement of failed 'A' EDG output breaker relay SN-SA

10/15/2020

WO 20440075

Inspection, repairs, and testing of Auxiliary Bus 1B following

electrical fault

2/16/2020

WO 20441385

Repair cables in L1200 cable tray damaged by electrical fault

2/16/2020

WO 20442682

Troubleshooting/repair of B ESCW chiller frequent cycling

2/28/2020

71111.20

Miscellaneous

Startup Reactivity

Manipulation Plan

H1C23 Forced Outage Power Escalation (December 2020)

Rev. 0

Procedures

GP-004

Reactor Startup (Mode 3 to Mode 2)

Rev. 66

GP-005

Power Operation (Mode 2 to Mode 1)

Rev. 110

GP-007

Normal Plant Cooldown Mode 3 to Mode 5

Rev. 72

71111.22

Procedures

OST-1076

Auxiliary Feedwater Pump 1B-SB Operability Test Quarterly

Interval Modes 1 - 4

Rev. 31

71114.06

Procedures

AD-EP-ALL-0101

Emergency Classification

Rev. 1

AD-EP-ALL-0111

Control Room Activation of the ERO

Rev. 1

CSD-EP-HNP-

0101-02

EAL Wallchart

Rev. 0

71124.01

Corrective Action

Documents

AR 2344247

OST-1112, Rod Position Indication Test 18 Month Interval

placed on hold to ensure fleet best practices are incorporated

regarding requirements to open the reactor trip breakers

following multiple dropped rods

08/18/2020

NCR 02303724,

2330239,

2331220,

2331403,

2334551,

2341730, and

235394,

Sampling of Radiation Safety Related Corrective Action

Documents written by the Licensee during the inspection

period being reviewed.

Various

Drawings

Locked High Radiation Area (LHRA) and Very High Radiation

Area (VHRA) Maps and Location Information

09/14/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

HNP eSOMS Log - Operations 08/13/2020 @ 0600 through

08/16/2020 @ 2400

Various

HNP eSOMS Log - RP 08/13/2020 @ 0600 through

08/16/2020 @ 2400

Various

High Radiation Area / Locked High Radiation Area Key Control

Log - 1/1/2020 through 11/18/2020

Various

HNP eSOMS Log - Outage 08/13/2020 @ 1100 through

08/16/2020 @ 0924

Various

CSD-RP-HNP-

0002

Neutron Survey Comparison

Revision 1

(09/19/2018)

Dose Reports for

RWP 40

Individual dose results for RWP 40 used during multiple at

power containment entries made for leak detection walkdowns

between 9/9 through 10/10/2020.

11/18/2020

HPP-800-19-60

Fuel Handling Building Underwater Material Storage Log

09/24/2019

RWP 46 Dose

Report

Daily and individual dose results for RWP 46 used during the

forced outage, 8/13 through 8/14/2020. Multiple entries made

to troubleshoot dropped rod issues and leak detection

walkdowns.

11/18/2020

Procedures

AD-PI-ALL-0100

Corrective Action Program

Revision 24

AD-RP-ALL-0002

Radiation And Contamination Surveys

Revision 2

AD-RP-ALL-0005

Access Controls for High and Locked High Radiation Areas

Revision 1

AD-RP-ALL-0010

Radiological Job Coverage

Revision 0

AD-RP-ALL-2011

Radiation Protection Briefings

Revision 5

AD-RP-ALL-2014

Work in Alpha Environments

Revision 7

AD-RP-ALL-2017

Access Controls To Very High Radiation Areas And

Supplemental Access Controls for HRA and LHRA

Revision 7

AP-545

Containment Entries

Revision 61

AP-545

Containment Entries

Revision 62

HPP-625

Performance of Radiological Surveys

Revision 49

OST-1005

Control Rod and Rod Position Indicator Exercise Quarterly

Interval Modes 1 - 3

Revision 28

OST-1112

Rod Position Indication Test 18 Month Interval

Revision 16

PD-RP-ALL-0001

Radiation Worker Responsibilities

Revision 13

PLP-511

Radiation Control and Protection Program

Revision 37

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Radiation Surveys HNP-M-

20191117-4

Incore Sump OPs Walk Down for Leaks Survey

11/17/2020

HNP-M-

200526-1

WPB 261' Room 144A Travel Path

05/26/2020

HNP-M-

200813-4

RCB 221' South

08/13/2020

HNP-M-

200813-5

Reactor Control Building - First Entry

08/13/2020

HNP-M-

200909-3

RCB 261' Seal Table 10 Path Inspection

09/09/2020

HNP-M-

201104-4

Waste Gas Compressors - Semi-Annual

11/04/2020

HNP-M-

201105-7

236' Piping Penetration Room - Monthly

11/07/2020

HNP-M-

201110-5

Spent Resin Transfer Pump

11/10/2020

HNP-M-

201110-6

Spent Resin Transfer Pump - Post Flush

11/10/2020

HNP-M-

201113-3

Weekly Hot Chem Lab

11/13/2020

HNP-M-

201118-5

Semi-Annual ORVH Storage Facility

11/18/2020

HNP-M-2020812-

RCB Excess Letdown walkdown

08/12/2020

HNP-M-2020813-

RCB Leak Inspection I/S Biowall

08/13/2020

HNP-M-2020814-

RCB Cabling Inspection on Rx Head

08/14/2020

HNP-M-2020814-

WPB Demin Skid

08/14/2020

HNP-M-2020814-

RCB 305' - MS-13 Isolation valve reseat

08/14/2020

HNP-M-2020909-

RCB 261' Seal Table

09/09/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HNP-M-2020915-

RCB 261' Seal table

09/15/2020

Radiation Work

Permits (RWPs)

List of 'Initiated' Outage RWPs

09/14/2020

List of 'Active' online RWPs

09/14/2020

RWP 33

Emergency Conditions and Drills

Revision 8

RWP 40

RCB Entries with the Rx Critical

Revision 39

RWP 46

Forced Outage

Revision 9

RWP 5000

Self Brief for Work Areas < 25 mr/hr

Revision 1

Self-Assessments 02331483-05

Field Operations and Radiation Worker Practices

10/21/2020

71124.06

Corrective Action

Documents

Corrective Actions

  1. 2257710,

267431,

269896,

276863,

287081,

294813,

2307733,

2339091 and

2342424

Corrective Actions #2257710, 2267431, 2269896, 2276863,

287081, 2294813, 2307733, 2339091 and 2342424

Various

Miscellaneous

ERC-009, Out of

Service Radiation

Monitor Reports

May 2019 to

August 2020.

ERC-009, Out of Service Radiation Monitor Reports May 2019

to August 2020.

Various

Results of

Radiochemistry

Cross Check

Program 1st QTR

2019, 2nd QTR

2019, 1st QTR

20, 2nd QTR

20 and 3rd

QTR 2020

Results of Radiochemistry Cross Check Program

Various

Procedures

CRC-240

Plant Vent Stack 1 Effluent Sampling

Rev. 20

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CRC-241

Turbine Building Vent Stack 3A Effluent Sampling

Rev. 23

CRC-242

Waste Processing Building Vent Stack 5 Effluent Sampling

Rev. 25

CRC-243

Waste Processing Building Vent Stack 5A Effluent Sampling

Rev. 19

CRC-255

Waste Gas Decay Tank And Waste Gas (VCT, PRT, RCDT,

and RHT) Sampling

Rev. 41

CRC-265

Chemistry Control of the Laundry and Hot Shower, Chemical

Drains, and Floor Drains Waste Treatment System

Rev. 17

CRC-851

ODCM Software Instructions and Documentation

Rev. 39

Radiation Surveys Radiochemistry

Analysis Report

for Sample

  1. 191096

Radiochemistry Analysis Report for Sample #191096

07/08/2019

RST-210 - Liquid

Effluent

Radiochemistry

Surveillance

Liquid Effluent Radiochemistry Surveillance Reports #L-2020-

0003, L-2020-0029, L-2020-0031 and L-2020-0032

Various

RST-211 -

Gaseous Effluent

Radiochemistry

Surveillance

Gaseous Effluent Radiochemistry Surveillance Reports #G-

20-0002, G-2020-0003, G-2020-0181, G-2020-0182 and G-

20-0183

Various

Self-Assessments Self-Assessment

  1. 22826173-05

Verification of Maintenance Rule Classification of Plant

Installed Radiation Monitor

10/03/2019

Self-Assessment

  1. 2342172-05

Extent of Condition Assessment to SA 2229376

08/06/2020

71124.07

Calculations

2019 Annual XOQDOQ Modeling and Meteorological

Evaluation for Shearon Harris Nuclear Station

03/20/2020

2018 Annual XOQDOQ Modeling and Meteorological

Evaluation for Shearon Harris Nuclear Station

03/04/2019

Calibration

Records

EnRad 03145

Calibration record for ISCO-Model 3710 water sampler

08/06/2018

and

07/08/2019

EnRad 09059

Calibration record for ISCO-Model 3710 water sampler

1/21/2019

EnRad 09072

Calibration record for environmental air sampler Model LV-1D

04/10/2019

EnRad 09083

Calibration record for environmental air sampler Model LV-1D

03/09/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

and

03/31/2020

EnRad 09128

Calibration record for ISCO-Model 3710 water sampler

03/20/2020

Corrective Action

Documents

NCR 02255956,

268125,

268808,

276866, and

2337157

Sampling of REMP Related Corrective Action Documents

written by the Licensee during the inspection period being

reviewed.

Various

NCR 02354142

Met Tower Lower Wind Speed sensor not calibrated (WO 20395270-01)

10/20/2020

Corrective Action

Documents

Resulting from

Inspection

2358620

NCR written for damaged MW-10 monitoring well pad

damage. Does not appear to have any damaged to the well

casing. [NRC identified]

11/18/2020

Miscellaneous

Shearon Harris Nuclear Power Plant 2019 Annual Radiological

Environmental Operating Report (AREOR)

Shearon Harris Nuclear Power Plant 2018 Annual Radiological

Environmental Operating Report (AREOR)

Harris REMP TLD Summary Report [Environmental TLD data]

- First thru third quarter 2020

11/03/2020

Shearon Harris Nuclear Power Plant Unit 1 2019 Annual

Radioactive Effluent Release Report

Harris Ground Water Protection Initiative and Tritium Sampling

Summaries and Reports [Individual Sampling Location Data

and 10 Year Trend] - 2019 and 2020

Various

List of REMP Telemetry ALERT emails (Pump Failure, Utility

Power Failure, etc)

10/19/2020

Harris Nuclear Plant 2018 Annual Land Use Census

08/28/2018

Harris Nuclear Plant 2019 Annual Land Use Census

08/22/2019

Harris Nuclear Plant 2020 Annual Land Use Census

08/10/2020

Harris Nuclear Plant Meteorological Tower Data Recovery -

January 2018 to August 2020

Various

HNP Environmental Risk Registry [List and risk ranking of

11/12/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Systems, Structures, and Components (SSCs) and buried

piping that could pose a risk to groundwater]

Harris Lake Tritium Concentration - 2010 thru June 2019

06/18/2019

Procedures

AD-CP-ALL-0015

Radiological Environmental Monitoring Program Data

Evaluation

Revision 3

AD-CP-ALL-0017

Radiological Groundwater Protection

Revision 4

AD-EG-ALL-1613

Buried Piping Integrity Program Implementation

Revision 5

EMP-012

Groundwater Monitoring Program

Revision 11

EnRad 207

Configuration and Set Up of the ISCO 3710 Water Sampler

Revision 6

EnRad 746

Transfer of Harris REMP Samples from Harris Nuclear Plant

To EnRad Laboratories

Revision 5

EnRad 749

Airborne Radioiodine And Airborne Particulate Sampling At

Harris Nuclear Plant

Revision 3

EnRad 753

Milk Sampling At Harris Nuclear Plant

Revision 4

EnRad 767

Ground Water Sampling At Harris Nuclear Plant

Revision 2

Enrad 850

Calibration of REMP Air Sampling Equipment

Revision 2

MPT-I0129

Meteorology Tower Equipment Calibration

Revision 16

PLP-504

Tritium Management

Revision 4

Self-Assessments 02198443-05

Radiological Environmental Monitoring Program (REMP) Self-

Assessment at Shearon Harris Nuclear Plant: Airborne

Particulate and Airborne Radioiodine, Drinking Water, and

Surface Water

04/16/2018

271393-05

Radiological Environmental Monitoring Program (REMP) Self-

Assessment at Shearon Harris Nuclear Plant: Airborne

Particulate and Airborne Radioiodine, Drinking Water, and

Surface Water

05/13/2019

240431

Optimization of HNP Radiological Environmental Monitoring

Program

11/15/2018

Self-Assessment

  1. 02020000

Quick Hit Self Assessment Radiological Environmental

Monitoring Program

04/25/2016

Self-Assessment

  1. 02133131

Radiological Environmental Monitoring Program (REMP) Self

Assessment

10/03/2017

Self-Assessment

  1. 2173466

NEI 07-07 Groundwater Protection Initiative Assessment

08/13/2018

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Self-Assessment

  1. 2236139

Possible trending in REMP air sampling equipment

10/09/2018

Self-Assessment

  1. 2240431

Optimization of HNP Radiological Environmental Monitoring

Program

11/05/2018

Work Orders

209742-01

MET TOWER EQUIP CAL (SEMIANNUAL PORTION)

03/06/2018

211627-01

MET TOWER EQUIPMENT CAL (ANNUAL PORTION)

11/01/2018

288663-01

MET TOWER EQUIP CAL (SEMIANNUAL) PORTION

04/25/2019

295719-01

MET TOWER EQUIPMENT CAL (ANNUAL PORTION)

09/23/2019

20358932-01

MET TOWER EQUIP CAL (SEMI-ANNUAL PORTION)

04/27/2020

Work Order (WO)

20395270-01

Replaced lower wind speed and direction sensor only

11/11/2020

71124.08

Corrective Action

Documents

Corrective Actions

  1. 2312255,

2331522 and

2331608

Corrective Actions #2312255, 2331522 and 2331608

Various

Corrective Action

Documents

Resulting from

Inspection

2358615

Water found in ORVH storage building

11/18/2020

2359102

10CFR37 training not validated as complete

11/22/2020

Miscellaneous

HPP-800 - Semi-

Annual Source

Inventory

HPP-800 - Semi-Annual Source Inventory

10/26/2020

HPP-800 - Semi-

Annual Source

Inventory

HPP-800 - Semi-Annual Source Inventory

04/13/2020

Procedures

AD-RP-ALL-0007

Control of Radioactive Material

Rev. 2

AD-RP-ALL-3003

OUTSIDE RADIOACTIVE MATERIAL CONTAINER

INVENTORY AND CONTROL

Rev. 3

AD-RP-ALL-5000

PREPARATION AND SHIPMENT OF RADIOACTIVE

MATERIAL AND RADIOACTIVE WASTE

Rev. 4

AD-RP-ALL-5002

CFR 61 RADIOACTIVE WASTE CLASSIFICATION

Rev. 1

AD-RP-ALL-5003

RECEIPT OF RADIOACTIVE MATERIAL

Rev. 2

AD-SY-ALL-0270

Physical Protection of Category 1 and Category 2 Quantities

of Radioactive Material

Rev. 6

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HPP-063

RESIN SAMPLE/SLUICE/TRANSFER AND FILTER

BACKWASH ACTIVITIES

Rev. 31

HPP-800

HANDLING RADIOACTIVE MATERIAL

Rev. 64

PLP-300

PROCESS CONTROL PROGRAM

Rev. 14

Self-Assessments Self-Assessment

  1. 02186418-05

2018 NRC RP ORS Inspection, Inspection Manual Procedure

71124.08 - Radioactive Solid Waste Processing and

Radioactive Material Handling, Storage, and Transportation

03/15/2018

Self-Assessment

  1. 2345263-05

Extent of Condition Assessment to SA 02186418-05

08/26/2020

Shipping Records19-008, 19-109,19-124 and 20-

270

Shipping papers associated with shipments19-008, 19-109,19-124 and 20-270

Various

71151

Calculations

HNP-F/PSA-0068

NRC Mitigating System Performance Index (MSPI) PRA Input

Document

Rev. 11

HNP-M/MECH-

231

Mitigating System Performance Index Basis Document

Rev. 2

Corrective Action

Documents

NCR 02312255

and 02337154

Sampling of Radiation Safety Related Corrective Action

Documents written by the Licensee during the inspection

period being reviewed.

Various

Corrective Action

Documents

Resulting from

Inspection

NCR 02357703

March 2020 INPO IRIS Data Not Entered

11/12/2020

Miscellaneous

Electronic Dosimeter dose and dose rate log - 11/1/2019

through 9/12/2020

Various

2019 ARERR

Shearon Harris Nuclear Power Plant Unit 1 2019 Annual

Radioactive Effluent Release Report (ARERR)

April 2020

G-2020-0183

Radioactive Gaseous Release Permit

11/3/2020

L-2020-0032

Radioactive Liquid Waste Release Permit - Monitor Tank B

09/19/2020

Procedures

AD-EG-ALL-1217

Mitigating System Performance Index (MSPI)

Rev. 1

AD-PI-ALL-0700

Performance Indicators

Rev. 4

AD-PI-ALL-0700

Performance Indicators

Revision 4

AD-RP-ALL-1101

Performance Indicators (PI) for the Occupational and Public

Radiation Safety Cornerstones

Revision 0

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71153

Procedures

AOP-039

Startup and Unit Auxiliary Transformer Trouble

Rev. 17

EOP-E-0

Reactor Trip or Safety Injection

Rev. 15

EOP-ES-0.1

Reactor Trip Response

Rev. 4

FPP-002

Fire Emergency

Rev. 45

OMM-004

Post-Trip/Safeguards Actuation Review

Rev. 43

OP-156

AC Electrical Distribution

Rev. 172