IR 05000400/2021011

From kanterella
Jump to navigation Jump to search
Triennial Fire Protection Inspection Report 05000400/2021011
ML22025A255
Person / Time
Site: Harris 
(NPF-063)
Issue date: 01/24/2022
From: James Baptist
NRC/RGN-II/DRS/EB1
To: Maza K
Duke Energy Progress
References
IR 2021011
Download: ML22025A255 (8)


Text

January 24, 2022

SUBJECT:

SHEARON HARRIS NUCLEAR POWER PLANT - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000400/2021011

Dear Ms. Maza:

On December 15, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Shearon Harris Nuclear Power Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket No. 05000400 License No. NPF-63

Enclosure:

As stated

Inspection Report

Docket Number:

05000400

License Number:

NPF-63

Report Number:

05000400/2021011

Enterprise Identifier:

I-2021-011-0026

Licensee:

Duke Energy Progress, LLC.

Facility:

Shearon Harris Nuclear Power Plant

Location:

New Hill, NC

Inspection Dates:

November 29, 2021 to December 17, 2021

Inspectors:

P. Braaten, Senior Reactor Inspector

E. Coffman, Reactor Inspector

L. Jones, Senior Reactor Inspector

M. Singletary, Reactor Inspector

Approved By:

James B. Baptist, Chief

Engineering Br 1

Division of Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Shearon Harris Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)

The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).

(1)

"A" Train 125v Vital DC

(2) Auxiliary Feedwater
(3) Cable Spreading Room "B" Suppression System
(4) Cable Spreading Room "B" Incipient Fire Detection System

Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)

The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.

(1) Transient Combustibles Control Program

Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)

The inspectors verified the following:

a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.

b. The adequacy of the design modification, if applicable.

c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.

d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.

e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.

(1) EC 419044 - Replacement of Non-Segregated Phase Bus Duct

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On December 15, 2021, the inspectors presented the triennial fire protection inspection results to Kim Maza and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

HNP-E/ELEC-

0001

SAFE SHUTDOWN ANALYSIS IN CASE OF FIRE

Rev. 09

HNP-E/ELEC-

0002

NFPA 805 TRANSITION-NON-POWER OPERATIONAL

MODES REVIEW

Rev. 06

HNP-E/ELEC-

0003

Safe Shutdown Analysis Manual Action Feasibility

Rev. 08

HNP-F/PSA-0079

Harris Fire PRA - Quantification

2/1/2020

Calculations

HNP-M/MECH-

1106

NFPA 805 Transition - Fire Area 12-A-BAL Fire Safety

Analysis

Rev. 03

2362644

2/17/2020

Corrective Action

Documents

RCE 2362309

Shearon Harris Reactor Trip Due to Fault on Unit Auxiliary

1B

Rev. 02

2409451

2/15/2021

Corrective Action

Documents

Resulting from

Inspection

2409532

2/15/2021

6-B-041 0674

25V DC PP DP-1A-SA

Rev. 15

6-B-041 0678

25V DC Power Panel DP-1B-SB

Rev. 17

6-B-401 1976

AFW Turb 1X-SB Stop Valve SB

Rev. 12

6-B-401 1977

Auxiliary Feedwater Turbine 1X-SB Stop Valve SB

Solenoid Trip

Rev. 09

6-G-0029

Main & 6900 Volt Auxiliary One Line Wiring Diagram

Rev. 29

6-G-0042 S01

250V DC, 125V DC & 120V Uninterruptible AC One Line

Wiring Diagram

Rev. 33

6-G-0042 S01

250V DC, 125V Uninterruptable AC One Line Wiring

Diagram

Rev. 33

CPL-2165-G-

1000S02

Safe Shutdown Feedwater and Aux. Feedwater Systems

Rev. 07

Drawings

PD5165-BC-01

AC Power Distribution System Unit 1

Rev. 017

Engineering

Changes

EC 419044

Non-Segregated Phase Bus Duct Sections

Rev. 00

71111.21N.05

Engineering

51-9089752-000

HNP Communication Study

08/27/08

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Evaluations

EC0000418216

Safe Shutdown (Including NPO) Common Power Supply

Coordination and MHIF Study

Rev. 20

DBD-114

Auxiliary Feedwater System

Rev. 17

DBD-202

Plant Electrical Distribution System

Rev. 43

DBD-315

Design Basis Document - Fire Detection System

Rev. 18

DBD-317

Design Basis Document - Water-Based Fire Suppression

System

Rev. 15

Harris NFPA 805

SE

Shearon Harris Safety Evaluation Report for Transition to

a Risk-Informed, Performance Based Fire Protection

Program

06/28/2010

VM-PAA

Batteries & Chargers

Rev. 29

VM-SFD

Air Sampling Fire Detector

Rev. 03

Miscellaneous

VM-TDL

Johnson Controls - Fire Detection System

Rev. 10

AD-OP-HNP-

205

HNP Time Critical Actions/Time Sensitive Actions

Rev. 00

ADG-EL-ALL-

20

Transient Combustible Control Program

Rev. 14

AOP-004

Remote Shutdown

Rev. 71

AOP-036

Safe Shutdown Following A Fire

Rev. 52

CMP-009

Installation of Fire Wrap

Rev. 17

FPP-001

Fire Protection Program Manuak

Rev. 44

FPP-002

Fire Emergency

Rev. 46

FPP-013

Fire Protection - Minimum Requirements, Mitigating

Actions, and Surveillance Requirements

Rev. 109

Procedures

PLP-400

Post Maintenance Testing

Rev. 64

2038402301

06/21/2020

2039918801

08/25/2020

2041581901

2/18/2021

2044145901

01/05/2021

Work Orders

2045164301

09/15/2021