IR 05000400/2021011
| ML22025A255 | |
| Person / Time | |
|---|---|
| Site: | Harris (NPF-063) |
| Issue date: | 01/24/2022 |
| From: | James Baptist NRC/RGN-II/DRS/EB1 |
| To: | Maza K Duke Energy Progress |
| References | |
| IR 2021011 | |
| Download: ML22025A255 (8) | |
Text
January 24, 2022
SUBJECT:
SHEARON HARRIS NUCLEAR POWER PLANT - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000400/2021011
Dear Ms. Maza:
On December 15, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Shearon Harris Nuclear Power Plant and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
James B. Baptist, Chief Engineering Br 1 Division of Reactor Safety Docket No. 05000400 License No. NPF-63
Enclosure:
As stated
Inspection Report
Docket Number:
05000400
License Number:
Report Number:
Enterprise Identifier:
I-2021-011-0026
Licensee:
Duke Energy Progress, LLC.
Facility:
Shearon Harris Nuclear Power Plant
Location:
New Hill, NC
Inspection Dates:
November 29, 2021 to December 17, 2021
Inspectors:
P. Braaten, Senior Reactor Inspector
E. Coffman, Reactor Inspector
L. Jones, Senior Reactor Inspector
M. Singletary, Reactor Inspector
Approved By:
James B. Baptist, Chief
Engineering Br 1
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Shearon Harris Nuclear Power Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)
The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).
(1)
"A" Train 125v Vital DC
- (3) Cable Spreading Room "B" Suppression System
- (4) Cable Spreading Room "B" Incipient Fire Detection System
Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)
The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.
- (1) Transient Combustibles Control Program
Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)
The inspectors verified the following:
a. Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.
b. The adequacy of the design modification, if applicable.
c. Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.
d. The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.
e. Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.
- (1) EC 419044 - Replacement of Non-Segregated Phase Bus Duct
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On December 15, 2021, the inspectors presented the triennial fire protection inspection results to Kim Maza and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
HNP-E/ELEC-
0001
SAFE SHUTDOWN ANALYSIS IN CASE OF FIRE
Rev. 09
HNP-E/ELEC-
0002
NFPA 805 TRANSITION-NON-POWER OPERATIONAL
MODES REVIEW
Rev. 06
HNP-E/ELEC-
0003
Safe Shutdown Analysis Manual Action Feasibility
Rev. 08
HNP-F/PSA-0079
Harris Fire PRA - Quantification
2/1/2020
Calculations
HNP-M/MECH-
1106
NFPA 805 Transition - Fire Area 12-A-BAL Fire Safety
Analysis
Rev. 03
2362644
2/17/2020
Corrective Action
Documents
RCE 2362309
Shearon Harris Reactor Trip Due to Fault on Unit Auxiliary
1B
Rev. 02
2409451
2/15/2021
Corrective Action
Documents
Resulting from
Inspection
2409532
2/15/2021
6-B-041 0674
25V DC PP DP-1A-SA
Rev. 15
6-B-041 0678
25V DC Power Panel DP-1B-SB
Rev. 17
6-B-401 1976
Rev. 12
6-B-401 1977
Auxiliary Feedwater Turbine 1X-SB Stop Valve SB
Solenoid Trip
Rev. 09
6-G-0029
Main & 6900 Volt Auxiliary One Line Wiring Diagram
Rev. 29
6-G-0042 S01
250V DC, 125V DC & 120V Uninterruptible AC One Line
Wiring Diagram
Rev. 33
6-G-0042 S01
250V DC, 125V Uninterruptable AC One Line Wiring
Diagram
Rev. 33
CPL-2165-G-
1000S02
Safe Shutdown Feedwater and Aux. Feedwater Systems
Rev. 07
Drawings
PD5165-BC-01
AC Power Distribution System Unit 1
Rev. 017
Engineering
Changes
Non-Segregated Phase Bus Duct Sections
Rev. 00
71111.21N.05
Engineering
51-9089752-000
HNP Communication Study
08/27/08
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Evaluations
Safe Shutdown (Including NPO) Common Power Supply
Coordination and MHIF Study
Rev. 20
Auxiliary Feedwater System
Rev. 17
Plant Electrical Distribution System
Rev. 43
Design Basis Document - Fire Detection System
Rev. 18
Design Basis Document - Water-Based Fire Suppression
System
Rev. 15
Harris NFPA 805
Shearon Harris Safety Evaluation Report for Transition to
a Risk-Informed, Performance Based Fire Protection
Program
06/28/2010
VM-PAA
Batteries & Chargers
Rev. 29
VM-SFD
Air Sampling Fire Detector
Rev. 03
Miscellaneous
VM-TDL
Johnson Controls - Fire Detection System
Rev. 10
AD-OP-HNP-
205
HNP Time Critical Actions/Time Sensitive Actions
Rev. 00
ADG-EL-ALL-
20
Transient Combustible Control Program
Rev. 14
Rev. 71
Safe Shutdown Following A Fire
Rev. 52
CMP-009
Installation of Fire Wrap
Rev. 17
Fire Protection Program Manuak
Rev. 44
Fire Emergency
Rev. 46
Fire Protection - Minimum Requirements, Mitigating
Actions, and Surveillance Requirements
Rev. 109
Procedures
PLP-400
Post Maintenance Testing
Rev. 64
2038402301
06/21/2020
2039918801
08/25/2020
2041581901
2/18/2021
2044145901
01/05/2021
Work Orders
2045164301
09/15/2021