ML050380428

From kanterella
Jump to navigation Jump to search
Undated Draft NRC Fire Protection Inspection Report No. 05000400/2003007
ML050380428
Person / Time
Site: Harris Duke Energy icon.png
Issue date: 02/03/2005
From: Ogle C
NRC/RGN-II/DRP/RPB1
To: Scarola J
Carolina Power & Light Co
References
EA-00-022, EA-01-310, FOIA/PA-2004-0277 IR-03-007
Download: ML050380428 (17)


See also: IR 05000400/2003007

Text

EA-00-022

EA-01 -310

Carolina Power & Light Company

ATTN: Mr. James Scarola

Vice President - Harris Plant

Shearon Harris Nuclear Power Plant

P. 0. Box 165, Mail Code: Zone 1

New Hill, North Carolina 27562-0165

SUBJECT: SHEARON HARRIS NUCLEAR POWER PLANT - NRC FIRE PROTECTION

INSPECTION REPORT NO. 05000400/2003007

Dear Mr. Scarola:

On _ _, 2003, the U.S. Nuclear Regulatory Commission (NRC) completed an in-office

review of the significance of the triennial fire protection inspection findings of inspection report

05000400/2002011 related to your Shearon Harris Nuclear Power Plant. The enclosed

inspection report documents the results of our significance determination, which was discussed

on ,2003, by telephone with Mr. and other members of your staff.

This report documents two NRC-identified findings of very low significance (Green). Both of

these findings were determined to involve violations of NRC requirements. However, because

of the very low safety significance and because they are entered into your corrective action

program, the NRC is treating these two findings as non-cited violations (NCVs) consistent with

Section VI.A. of the NRC enforcement Policy. If you contest any NCV in this report, you should

provide a response within 30 days of the date of this inspection report, with the basis for your

denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington,

DC 20555-0001; with copies to the Regional Administrator, Region II; the Director, Office of

Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001;

and the NRC Resident Inspector at the Shearon Harris Nuclear Power Plant.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at

httD://www.nrc.aov/readina-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket No.: 50-400

CP&L 2

License No.: NPF-63

Enclosure: Inspection Report 05000400/200307

cc w/encl:

James W. Holt, Manager

Performance Evaluation and

Regulatory Affairs CPB 9

Carolina Power & Light Company

Electronic Mail Distribution

Robert J. Duncan II

Director of Site Operations

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Benjamin C. Waldrep

Plant General Manager--Harris Plant

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

Terry C. Morton, Manager

Support Services

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

(cc w/encl cont'd - See page 3)

(cc w/encl cont'd)

John R. Caves, Supervisor

Licensing/Regulatory Programs

Carolina Power & Light Company

Shearon Harris Nuclear Power Plant

Electronic Mail Distribution

William D. Johnson

Vice President & Corporate Secretary

Carolina Power & Light Company

Electronic Mail Distribution

John H. O'Neill, Jr.

Shaw, Pittman, Potts & Trowbridge

2300 N. Street, NW

Washington, DC 20037-1128

Beverly Hall, Acting Director

,I

CP&L 3

Division of Radiation Protection

N. C. Department of Environmental

Commerce & Natural Resources

Electronic Mail Distribution

Peggy Force

Assistant Attorney General

State of North Carolina

Electronic Mail Distribution

Public Service Commission

State of South Carolina

P.O. Box 11649

Columbia, SC 29211

Chairman of the North Carolina

Utilities Commission

P. O. Box 29510

Raleigh, NC 27626-0510

Robert P. Gruber

Executive Director

Public Staff NCUC

4326 Mail Service Center

Raleigh, NC 27699-4326

(cc w/encl cont'd - See page 4)

(cc w/encl cont'd)

Linda Coleman, Chairman

Board of County Commissioners

of Wake County

P. O. Box 550

Raleigh, NC 27602

Gary Phillips, Chairman

Board of County Commissioners

of Chatham County

Electronic Mail Distribution

Distribution w/encl:

L. Slack, EICS

C. Patel, NRR

OEMAIL

RIDSNRRDIPMLIPB

PUBLIC

CP&L 4

OFFICE RII:DRS RII:DRS RII:DRS RIl:DRP RII:EICS

SIGNATURE

NAME RSchin WRogers DC Payne PFredrickson CEvans

DATE

E-MAIL COPY? YES NTO I YES NO I YES NO YES NO YES NO YES NO

PUBLIC DOCUMENT I YES NO I I I I I I

0FUttIML rir-UL~Iu LUrT LUvJUM~lcN I I'dMMe r;~nirnris It¶ U3-UIlwpu

U.S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket No.: 50-400

License No.: NPF-63

Report No.: 05000400/2003007

Licensee: Carolina Power & Light (CP&L)

Facility: Shearon Harris Nuclear Power Plant

Location: 5413 Shearon Harris Road

New Hill, NC 27562

Dates:

Inspectors: W. Rogers, Senior Reactor Analyst, Region II

R. Schin, Senior Reactor Inspector, Region II

Approved by: Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000400/2003-007; .J.J2003- .J.J2003; Shearon Harris Nuclear Power Plant; Fire

Protection.

The in-office review was conducted by a regional inspector, a regional senior reactor analyst,

and NRC Headquarters Senior Reactor Analysts. Two Green findings, each a Non-Cited

Violation (NCV), were identified. The significance of issues is indicated by their color (Green,

White, Yellow, Red) using IMC 0609 "Significance Determination Process" (SDP). Findings for

which the SDP does not apply may be uGreen" or be assigned a severity level after NRC

management review. The NRC's program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-1 649, "Reactor Oversight Process," Revision 3,

dated July 2000.

A. InsDector Identified Findings

Cornerstones: Mitigating Systems and Initiating Events

Green. An NCV of Operating License Condition 2.F, the Fire Protection Program, and

Technical Specification (TS) 6.8.1, Procedures and Programs, was identified for

inadequate implementation of the fire protection program. Physical and procedural

protection for equipment that was relied on for safe shutdown (SSD) during a fire in fire

safe shutdown analysis (SSA) areas 1-A-BAL-B-B1, 1-A-BAL-B-B2, 1-A-BAL-B-B3, 1-A-

BAL-B-B4, 1-A-EPA, and 1-A-BAL-C of the reactor auxiliary building was inadequate.

Consequently, a fire in one of these SSA areas could result in a reactor coolant pump

seal loss of coolant accident (LOCA), a main steam line break (MSLB) event, a loss of

high pressure safety injection, and/or a loss of component cooling water to the reactor

coolant pump seals. The licensee has initiated corrective actions including assigning an

additional operator to be available to perform post-fire safe shutdown actions and

performing a complete review of the safe shutdown analysis and related operating

procedures.

This finding was greater than minor because it could initiate a LOCA or MSLB event and

could result in a loss of equipment that was relied upon for SSD from a fire. The finding

was of very low significance (Green) because of the low fire ignition frequencies and

lack of combustible materials in critical locations and because of the effectiveness of the

fire protection features and the remaining SSD equipment to mitigate a fire in each of

the affected fire zones/areas. (Section 1R05.03.b.1)

Technical Specification (TS) 6.8.1, Procedures and Programs, was identified for

inadequate corrective action for previous Violation 50-400/02-08-01. Physical and

procedural protection for equipment that was relied on for safe shutdown (SSD) during a

fire in the new auxiliary control panel fire area 1-A-ACP was inadequate. Consequently,

a fire in area 1-A-ACP could result in a loss of auxiliary feedwater and a main steam line

break (MSLB) event. The licensee has initiated corrective actions including assigning

an additional operator to be available to perform post-fire safe shutdown actions and

performing a complete review of the safe shutdown analysis and related operating

procedures.

This finding was greater than minor because it could initiate a MSLB event and could

result in a loss of equipment that was relied upon for SSD from a fire. The finding was

of very low significance (Green) because of the low fire ignition frequencies and lack of

combustible materials and because of the effectiveness of the fire protection features

and the remaining SSD equipment to mitigate a fire in area 1-A-ACP. (Section

1R05.03.b.1)

B. Licensee-Identified Violations

None

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 FIRE PROTECTION

.01 Significance Determination for Triennial Fire Protection Inspection Findings

a. Inspection Scope

In inspection report 50-400/02-11, nine findings had been identified as unresolved items

(URls) pending completion of the NRC significance determination process (SDP). This

inspection report documents the results of the in-office completion of the NRC SDP with

respect to those nine URIs. The significance determination was accomplished as

described in NRC Inspection Manual Chapter (IMC) 0609, Signification Determination

Process; IMC 0609A, Significance Determination of Reactor Inspection Findings for At-

Power Situations; and IMC 0609F, Determining Potential Risk Significance of Fire

Protection and Post-Fire Safe Shutdown Inspection Findings. This involved evaluating

the significance of a potential fire in each of the seven affected fire safe shutdown

analysis (SSA) areas, considering all examples of the findings that could be involved in

each fire.

In addition, the performance deficiencies which could result in the loss of a safety

function were evaluated by the Office of Nuclear Reactor Regulation (NRR) using the

Phase IlIl portion of the SDP. Inclusive in this evaluation were extensive walkdowns of

the applicable fire SSA areas by two contractors to observe ignition sources and

possible fire propagation from these ignition sources that could affect the unprotected

cables of concern. Also, electrical circuit drawings and the latest information on cable

hot short failure mechanisms and probabilities were used to develop cable failure

probabilities that could cause a loss of function for the unprotected cables of concern.

b. Findings

(1) Inadeguate Implementation of the Fire Protection Program

Introduction: An overall finding was identified in that the implementation of the fire

protection program was inadequate. Eight of the nine URis described in IR 50-400/02-

11 were considered to include examples of this overall finding. Based on evaluating the

eight examples of this overall finding for their effects during a fire that could occur in

each of the six affected fire SSA areas, this overall finding was determined to have a

very low significance (Green).

Description: The licensee's implementation of the fire protection program for ensuring

the ability to safely shut down the plant during a fire was inadequate, in that:

relied upon for safe shutdown (SSD) during a fire. Consequently, those cables

2

were not provided with the required protection from fire damage. A fire could

cause hot shorts in the cables which would result in maloperation of equipment

that was relied upon for SSD during that fire.

  • The SSA identified many cables that were relied upon for SSD during a fire, but

the licensee generally failed to provide the required physical protection from fire

damage. Instead, the SSA designated that operator actions would be taken to

prevent or mitigate the effects of the fire damage. However, the licensee did not

obtain NRC approval for these deviations from the approved fire protection

program.

  • Some of the operator actions that were designated by the SSA were not

incorporated into operating procedures for SSD. Also, the operator actions in

procedures differed in many respects from the operator actions that were

analyzed in the SSA. For example, the operating procedures directed operators

to use some different flowpaths than those analyzed in the SSA.

  • Some operator actions in the SSD procedures would not work. They were too

challenging, involved entering the area of the fire, were not adequately analyzed,

or were too numerous for the available SSD non-licensed operator to perform.

The eight examples of this overall finding that are described in IR 50-400/02-11 include:

  • Physical and procedural protection for equipment that was relied on for safe

shutdown (SSD) during a fire in safe shutdown analysis (SSA) areas 1-A-BAL-

B1, 1-A-BAL-B2, and 1-A-EPA of the reactor auxiliary building was inadequate.

Motor-operated valve 1CS-1 65, volume control tank outlet to charging/safety

injection pumps was not protected physically or procedurally from maloperation

due to a fire. Also, per the SSA, component cooling (CC) to the RCPs was not

protected from the fire; and the control cable for 1CC-207, CC to RCP seals, was

in the same cable tray with the control cable for 1CS-165. Consequently, a fire

in one of the three SSA areas could result in a reactor coolant pump seal loss of

coolant accident (LOCA) with no high pressure safety injection available.

  • Physical and procedural protection for equipment that was relied on for SSD

during a fire in SSA area 1-A-BAL-B-B5 of the reactor auxiliary building was

inadequate. Motor-operated valves 1CS-1 69, charging/safety injection pump

(CSIP) suction cross-connect; 1CS-214, CSIP mini-flow isolation; 1CS-21 8,

CSIP discharge cross-connect; and 1CS-219, CSIP discharge cross-connect;

were not protected physically or procedurally from maloperation due to a fire.

Consequently, a fire in SSA area 1-A-BAL-B-B5 could result in a loss of all

charging and high pressure safety injection.

  • Physical and procedural protection for equipment that was relied on for SSD

during a fire in SSA area 1-A-BAL-B-B4 of the reactor auxiliary building was

inadequate. Motor operated valves 1CS-1 66, volume control tank outlet to

CSI Ps; and 1CS-1 68, CSIP suction cross-connect; were not protected physically

or procedurally from maloperation due to a fire. Consequently, a fire in SSA

3

area 1-A-BAL-B-B4 could result in a loss of all charging and high pressure safety

injection.

  • Physical and procedural protection for equipment that was relied on for SSD

during a fire in SSA area 1-A-BAL-C of the reactor auxiliary building was

inadequate. Motor operated valves 1CC-208, component cooling water (CC)

supply to reactor coolant pump (RCP) seals; and 1CC-251, CC return from RCP

seals; were not protected physically or procedurally from maloperation due to a

fire. The SSA did not analyze or credit RCP seal injection but subsequent

analysis after the inspection determined that RCP seal injection function would

not be affected by a fire in this area. Consequently, a fire in SSA area 1-A-BAL-

C could potentially result in only a loss of component cooling to the RCP seals.

protection of cables for equipment relied on for SSD during a fire, without

obtaining NRC approval for these deviations from the approved fire protection

program. This condition applied to the six inspected SSA areas that are listed

below. This reliance on large numbers of local manual actions, in place of the

required physical protection of cables, could potentially result in an increased risk

of loss of equipment that was relied upon for SSD from a fire.

  • The procedure for SSD from a fire was inadequate. For a fire in certain safe

shutdown analysis areas of the reactor auxiliary building, there were too many

SSD procedure contingency actions to respond to potential spurious actuations

for the one designated SSD non-licensed operator to perform. Consequently,

equipment that was relied on for SSD may not be available.

  • The procedure for SSD from a fire was inadequate. For a fire in safe shutdown

analysis areas near the boric acid tank (BAT) in the reactor auxiliary building, the

SSD procedure directed operators to take CSIP suction from the BAT even if

BAT level indication were lost. However, the charging volume needed for reactor

coolant system cooldown would have emptied the BAT and damaged the CSIP.

Consequently, a loss of charging/high pressure safety injection could have

resulted.

  • Required battery-backed emergency lights were not provided in locations where

operators were required to perform actions for SSD from a fire. This condition

affected SSD during fires in all of the areas inspected in the reactor auxiliary

building. The lack of required lighting could result in an increased risk of

operators failing to perform the SSD actions in a timely and accurate manner.

The inspectors evaluated the effects of the eight examples of this overall finding during

a fire that could occur in each of the following six affected fire SSA areas of the reactor

auxiliary building (RAB):

  • Fire SSA area 1-A-BAL-B-B1, on the 261 foot level of the RAB, including the 'A'

chiller and motor-driven auxiliary feedwater (AFW) pump flow control valves

(FCVs).

4.

  • Fire SSA area 1-A-BAL-B-B2, on the 261 foot level of the RAB, including the 'B'

chiller and turbine-driven AFW pump FCVs.

  • Fire area 1-A-EPA, on the 261 foot level of the RAB, including the electrical

penetration room 'A'.

  • Fire SSA area 1-A-BAL-B-B4, on the 261 foot level of the RAB, including 480V

motor control center (MCC) 1B35-SB.

  • Fire SSA area 1-A-BAL-B-B5, on the 261 foot level of the RAB, including 480V

MCC 1A35-SA.

  • Fire area 1-A-BAL-C, on the 286 foot level of the RAB, including 480V MCC

1B31 -SB.

The inspectors and analysts assessed that the in situ and allowed transient

combustibles were sufficient to support a credible fire scenario in each fire SSA area.

During this analysis, the inspectors considered the following combustibles:

  • The 'B' chiller, which was located below certain cable trays of concern, contained

an ignition source of a compressor with 12 gallons of lubricating oil (containing

approximately 1.7 million BTU). The 'B' chiller also included flammable thermal

insulation on its piping. This 12 gallons of oil and flammable thermal insulation

were apparently not included in the licensee's IPEEE fire analysis.

one million BTU above the analyzed combustible loading, to be temporarily

stored in any fire zones without a fire watch or other compensatory measures.

The transient combustible control program also allowed rubber mats up to 150

square feet (containing approximately 1.8 million BTU) to be installed without

continuous attendance.

  • The transient combustible control program included staging areas for 55 gallon

drums of oil (containing approximately 7.7 million BTU each) in or near three of

the fire SSA areas of concern. The program also allowed up to five gallons of

transient combustible liquids (containing approximately 0.7 million BTU) and two

gallons of transient flammable liquids (containing approximately 0.27 million

BTU) with no transient combustible permit required.

Inspector analysis indicated that, for the smaller enclosed fire SSA areas of concern

(e.g., 1-A-EPA, 1-A-BAL-C), a fire could start in any part of the room and cause a hot

gas layer that could ignite the IEEE 383 cables near the ceiling throughout the room.

For the larger areas (e.g., 1-A-BAL-B-B1, 1 -A-BAL-B-82), a fire was unlikely to cause a

hot gas layer that could ignite all of the IEEE 383 cables in the area; however, a fire

starting below certain cables could generate a fire plume sufficiently large and hot to

ignite the cables that were in the plume.

5

The inspectors and analysts assessed that many fire protection features and event

mitigation functions would not be affected by a fire in the SSA areas of concern.

Examples included:

  • Based on no identified degradation of the automatic sprinklers and fire brigade

for each of the affected fire areas/zones, full credit was given for the

effectiveness of those fire protection features.

  • Based on the types of RCP seals installed, an RCP seal LOCA was judged to

result in a small break LOCA and not a larger LOCA.

  • For the fire areas/zones where a fire could cause an RCP seal LOCA, at least

one train of the following mitigation functions would be unaffected by the fire:

high pressure injection (HPI), including a pump and flowpath from the RWST to

the RCS; primary feed and bleed (FB), including a pressurizer power-operated

relief valve; low pressure injection (LPI), including an RHR pump and a flowpath

from the RWST to the RCS; low pressure recirculation (LPR), including a suction

path from the containment sump; high pressure recirculation (HPR), including a

flowpath from the RHR pump to the HPI pump; and auxiliary feedwater (AFW).

In addition, both trains of emergency power would be unaffected.

  • Also, for the fire areas/zones where a fire could cause an RCP seal LOCA, the

abnormal operating procedures would provide adequate direction, after the loss

of a CSIP, for operators to recover charging by aligning suction from the RWST

and starting the standby CSIP.

would not be affected. Also, for a fire in fire area 1-A-BAL-C, CSIPs and RCP

seal injection would be unaffected.

Analysis: This finding had more than minor safety significance because it involved a

lack of required fire barriers for equipment that was relied upon for safe hot shutdown

following a fire. The finding also had more than minor safety significance because it

affected the objectives of the Mitigating Systems and Initiating Events Cornerstones of

Reactor Safety. The finding affected the availability and reliability of systems that

mitigate initiating events to prevent undesirable consequences. It also affected the

likelihood of occurrence of initiating events that challenge critical safety functions. The

finding did not have more than very low safety significance (Green) because of the low

fire ignition frequencies and lack of combustible materials in critical locations and

because of the effectiveness of the fire protection features and the unaffected SSD

equipment to mitigate a fire in each of the affected fire zones/areas.

Enforcement: As described in IR 50-400/02-11, Operating License Condition (OLC) 2.F

required that the licensee implement and maintain in effect all provisions of the

approved Fire Protection Program (FPP) as described in the Final Safety Analysis

Report (FSAR). The Updated FSAR, Section 9.5.1, FPP, stated that outside

containment, where cables or equipment (including associated non-essential circuits

that could prevent operation or cause maloperation due to hot shorts, open circuits, or

6

shorts to ground) of redundant safe shutdown divisions of systems necessary to achieve

and maintain cold shutdown conditions are located within the same fire area outside of

primary containment, one of the redundant divisions must be ensured to be free of fire

damage. Section 9.5.1 further stated that if both divisions are located in the same fire

area, then one division is to be physically protected from fire damage by one of three

methods: 1) a three-hour fire barrier, 2) a one-hour fire barrier plus automatic detection

and suppression, or 3) a 20-foot separation with no intervening combustibles and with

automatic detection and suppression. The licensee had received no NRC approvals for

deviating from these requirements.

Also, OLC 2. F. and UFSAR Section 9.5.1 stated that BTP 9.5-1 was used in the design

of the fire protection program for safety-related systems and equipment and for other

plant areas containing fire hazards that could adversely affect safety-related systems.

BTP 9.5-1, Section C.5.g, "Lighting and Communication," paragraph (1), required that

fixed self-contained lighting consisting of fluorescent or sealed-beam units with

individual eight-hour-minimum battery power supplies should be provided in areas that

must be manned for safe shutdown and for access and egress routes to and from all fire

areas.

In addition, TS 6.8.1, Procedures and Programs, required procedures as recommended

by Regulatory Guide (RG) 1.33 and procedures for fire protection program

implementation. RG 1.33 recommended procedures for combating emergencies,

including fires. The licensee's interpretation of their fire protection program was that

they could and would rely on proceduralized operator actions in place of physically

protecting SSD equipment from fire damage (see Section 1R05.04.b.1).

Contrary to the above requirements, the licensee failed to adequately implement and

maintain in effect all of the provisions of the approved FPP. The licensee failed to

ensure that one of the redundant safe shutdown divisions of systems necessary to

achieve and maintain cold shutdown conditions was protected from fire damage; failed

to have adequate procedures for combating fire emergencies; and failed to provide the

required emergency lighting in areas that must be manned for safe shutdown; as

described above in the eight examples of this overall finding. Because the identified

examples of this failure to adequately implement and maintain in effect all of the

provisions of the approved FPP are of very low safety significance and have been

entered into your corrective action program (ARs 76260, 80212, 80089, 69721, 80215,

75065, and 79047), this violation is being treated as an NCV, consistent with Section

VL.A of the NRC Enforcement Policy: NCV 50-400/03-07-01; Failure to Adequately

Implement the Approved Fire Protection Program for Safe Shutdown, Eight Examples.

(2) Inadequate Corrective Action for a Previous White Fire Protection Finding

Introduction: An overall finding was identified in that the corrective action for previous

Violation (VIO) 50-400/02-08-01 was inadequate. Four of the nine URIs described in IR

50-400/02-11 were considered to be examples of this overall finding. Based on

evaluating the three examples of this overall finding for their effects during a fire that

could occur in the six affected fire SSA area, this overall finding was determined to have

a very low significance (Green).

7

Description: The licensee's corrective action for a previous White fire protection finding

(VIO 50-400/02-08-01), associated with a Thermo-Lag fire barrier assembly between the

'B' train switchgear room / auxiliary control panel and the 'A' train cable spreading room,

was inadequate. Examples described in IR 50-400/02-11 include:

protection of cables for equipment relied on for SSD during a fire, without

obtaining NRC approval for these deviations from the approved fire protection

program. This condition applied to all areas that were inspected, including the

new auxiliary control panel fire area that had been recently created as corrective

action for previous Violation 50-400/02-08-01. This reliance on large numbers of

local manual actions, in place of the required physical protection of cables, could

potentially result in an increased risk of loss of equipment that was relied upon

for SSD from a fire. (Section 1R05.04.b.1)

  • Procedure steps for safe shutdown (SSD) from a fire and related corrective

action for previous Violation 50-400/02-08-01 were inadequate. For a fire in the

new auxiliary control panel fire area, certain cables were not physically protected

from the fire and certain SSD procedure steps, that were used in place of

physical protection of cables, involved excessive challenges to operators.

Consequently, a fire in the ACP fire area could result in a loss of all auxiliary

feedwater. (Section 1R05.04.b.2)

  • A procedure for SSD from a fire and related corrective action for previous

Violation 50-400/02-08-01 were inadequate. For a fire in certain safe shutdown

analysis areas of the reactor auxiliary building, including the new auxiliary control

panel fire area, there were too many SSD procedure contingency actions to

respond to potential spurious actuations for the one designated SSD non-

licensed operator to perform. Consequently, equipment that was relied on for

SSD may not be available. (Section 1R05.04.b.3)

  • Required battery-backed emergency lights were not provided in locations where

operators were required to perform actions for SSD from a fire. This condition

affected SSD during fires in all of the areas inspected in the reactor auxiliary

building, including the new auxiliary control panel fire area that was created as

corrective action for previous Violation 50-400/02-08-01. The lack of required

lighting could result in an increased risk of operators failing to perform the SSD

actions in a timely and accurate manner. (Section 1R05.06.b)

Analysis: This finding had more than minor safety significance because it involved a

lack of required fire barriers for equipment that was relied upon for safe hot shutdown

following a fire. The finding also had more than minor safety significance because it

affected the objectives of the Mitigating Systems Cornerstone of Reactor Safety. The

finding affected the availability and reliability of systems that mitigate initiating events to

prevent undesirable consequences. The finding did not have more than very low safety

significance (Green) because of the low fire ignition frequencies and lack of

combustible materials in the ACP fire area and because of the effectiveness of the fire

8

protection features and the unaffected SSD equipment to mitigate a fire in the ACP fire

area.

Enforcement: OLC 2.F and the UFSAR, Section 9.5.1, FPP, included quality assurance

requirements for fire protection. The FPP stated that a QA program was being used to

identify and rectify any possible deficiencies in design, construction, and operation of the

fire protection systems. Also, as described in Section 1R05.01.b.1 above, OLC 2.F

required that one of the redundant divisions would be free of fire damage. Further, if

both divisions were located in the same area, then one of the divisions was to be

physically protected from fire damage by one of three specified methods. Further,

OLC.2.F required that battery-backed emergency lights be provided in locations where

operators were required to perform actions for SSD from a fire. In addition, TS 6.8.1,

Procedures and Programs, required procedures for implementing the fire protection

program and for combating fires.

Contrary to the above requirements, the licensee's corrective actions for previous VIO

50-400/02-08-01 were inadequate because they failed to rectify deficiencies in design,

construction, and operation related to SSD from a fire in the area of the ACP room. The

licensee failed to protect various equipment either physically or procedurally from the

effects of a fire where that equipment was relied on for SSD. The licensee entered the

finding into the corrective action program as AR 80215. Because the identified

examples of this failure to adequately implement and maintain in effect all of the

provisions of the approved FPP are of very low safety significance and have been

entered into the corrective action program, this violation is being treated as an NCV,

consistent with Section Vl.A of the NRC Enforcement Policy: NCV 50-400/03-07-02;

Inadequate Corrective Action for a Previous White Fire Protection Finding.

40A6 Meetings

Exit Meeting Summary

The team presented the inspection results to Mr. _ _ and members of his staff

at the conclusion of the inspection on. , 2003. The licensee acknowledged the

findings presented. Proprietary information is not included in this inspection report.

SUPPLEMENTAL INFORMATION

Partial List of Persons Contacted

Licensee

D. Baksa, Supervisor, Equipment Perfromance

J. Caves, Licensing Supervisor

R. Duncan, Director of Site Operations

M. Fletcher, Manager, Fire Protection Program

Attachment 1

9

P. Fulford, Superintendent, Design Engineering

C. Georgeson, Supervisor, El&C Design

W. Gregory, Operations Fire Protection Specialist

W. Gurganious, Manager, NAS

T. Hobbs, Manager, Operations

A. Khanpour, Manager, Engineering

F. Lane, Jr., Senior Nuclear Work Management Specialist

J. Laque, Manager, Maintenance

T. Morton, Site Services Manager

J. Scarola, Site Vice President

B. Waldrep, Plant General Manager

NRC

J. Brady, Senior Resident Inspector, Shearon Harris

H. Christensen, Deputy Director, Division of Reactor Safety (DRS), Region II (R1l)

C. Ogle, Chief, Engineering Branch 1, DRS, Rll

Items Opened. Closed, and Discussed

Opened

50-400/03-07-01 NCV Failure to Adequately Implement the Approved Fire

Protection Program for Safe Shutdown, Eight Examples

(Section 1R05.01.b.1)

50-400/03-07-02 NCV

Closed

50-400/02-11-01 URI Failure to Protect Charging System MOV 1CS-1 65, VCT

Outlet to CSIPs, From Maloperation Due To a Fire

(Section 1R05.01.b.1)

50-400/02-11-02 URI Failure to Protect Charging System MOVs 1CS-1 69, 1CS-

214, 1CS-218, and 1CS-219 From Maloperation Due To a

Fire (Section 1R05.01.b.1)

50-400/02-11-03 URI Failure to Protect Charging System MOVs 1CS-1 66, 1CS-

168, and 1CS-217 From Maloperation Due To a Fire

(Section 1R05.01.b.1)

Attachment 1

10

50-400/02-11-04 URI Failure to Protect Component Cooling MOVs 1CC-251 and

1CC-208, CC for RCP Seals, From Maloperation Due To a

Fire (Section 1R05.01.b.1)

50-400/02-11-05 URI Reliance on Manual Actions in Place of Required Physical

Separation or Protection From a Fire (Section

1R05.01.b.2)

50-400/02-11-06 URI Fire SSD Operator Actions With Excessive Challenges

(Section 1R05.01.b.2)

50-400/02-11-07 URI Too Many Fire SSD Actions for Operators to Perform

(Section 1R05.01.b.2)

50-400/02-11-08 URI Using the Boric Acid Tank Without Level Indication

(Section 1R05.01.b.1)

50-400/02-11-09 URI Failure to Provide Required Emergency Lighting for SSD

Operator Actions (Section 1R05.01.b.2)

Discussed

50-400/02-08-01 V10 Failure to Implement and Maintain NRC Approved Fire

Protection Program Safe Shutdown System Separation

Requirements (Section 1R05.01.b.2)

Attachment 1