Semiannual Fitness-For-Duty Report, January - June 2004 for the Davis-Besse Nuclear Power Station
ML042450340
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 08/30/2004
From: Bezilla M
FirstEnergy Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
3085
Download: ML042450340 (4)


Text

FENOC 5501 North State Route 2 FirstEnergy Nuclear Operating Company Oak Harbor, Ohio 43449 Mark B. Bezilla 419-321-7676 Vice President - Nuclear Fax: 419-321-7582 Docket Number 50-346 License Number NPF-3 Serial Number 3085 August 30, 2004 United States Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555-0001

Subject:

Semiannual Fitness-For-Duty Report, January - June 2004 for the Davis-Besse Nuclear Power Station Ladies and Gentlemen:

Pursuant to 10 CFR 26.71(d), "Recordkeeping Requirements," FirstEnergy Nuclear Operating Company (FENOC) submits the semiannual Fitness-For-Duty (FFD) report for the period of January through June 2004 for the Davis-Besse Nuclear Power Station, Unit 1 (DBNPS).

Attachment I provides FENOC's DBNPS FFD Program Performance Data. Attachment 2 provides a summary of management actions taken by FENOC based on positive FFD testing results, presumptive positives, and a list of FFD event reports submitted by FENOC.

Should you have any questions or require additional information, please contact Mr. Robert W. Schrauder, Director - Performance Improvement, at (419) 321-7181.

Sincerely, GMW/s Attachments cc: Regional Administrator, NRC Region III DB-I NRC/NRR Senior Project Manager DB-1 Senior NRC Resident Inspector Utility Radiological Safety Board

Docket Number 50-346 License Number NPF-3 Serial Number 30S5 Page I of 1 Fitness for Duty Program Performance Data Personnel Subject to 10 CFR 26 FirstEnergy Nuclear Operating Companv June 30. 2004 Company 6 Months Ending Davis-Besse Nuclear Power Station (419) 321-7181 Location Phone R. W. Schrauder. Director - Performance Improvement Contact Name Cutoffs: Screen/Confirmation (n/mil) ADoendix A to 10 CFR 26 Marijuana 100/15 Amphetamines 1000/500 Cocaine 300/150 Phencyclidine 25/25 Opiates 300/300 Alcohol (%BAC) 0.04 Long-Term Short-Term Testing Results Licensee Employees Contractor Personnel Contractor Personnel Average Number with Unescorted Access 874 0 174 Categories Tested Positive Tested Positive Tested Positive Pre-Access 86 0 0 0 76 0 For Post Accident 0 0 0 0 0 0 Cause Observed Behavior 3 0 0 0 1 1 Random 270 0 0 0 31 0 Follow-up 13 0 0 0 6 0 Other 0 0 0 0 0 0 Total 372 0 0 0 114 1 Breakdown of Confirmed Positive Tests for Specific Substances Mariuana lCocaine Opiates Amphe-tamiAlcoholineto Phency- Alcohol Refusal test Licensee Employees 0 0 0 0 0 0 0 Long-Term Contractors 0 0 0 0 0 0 0 Short-Term Contractors 1 0 0 0 0 0 0 Total 1 0 0 0 0 0 0

Docket Number 50-346 License Number NPF-3 Serial Number 3085 Page 1 of 1 FENOC MANAGEMENT ACTIONS RELATING TO FITNESS-FOR-DUTY FENOC Contractor Personnel Personnel Referred to Employee 0 0 Assistance Program (EAP)

Management Sanctions 0 1 FENOC does not perform onsite initial drug screening tests; therefore, there are no unconfirmed positive results on which to base management actions.

FENOC FITNESS-FOR-DUTY REPORTS There were no Fitness-For-Duty reports submitted during this reporting period (January- June 2004).

Docket Number 50-346 License Number NPF-3 Serial Number 3085 Page 1 of 1 COMMITMENT LIST The following list identifies those actions committed to by the Davis-Besse Nuclear Power Station in this document. Any other actions discussed in the submittal represent intended or planned actions by Davis-Besse. They are described only as information and are not regulatory commitments. Please notify the Director - Performance Improvement (419) 321-7181 at Davis-Besse of any questions regarding this document or associated regulatory commitments.

COMMITMENTS DUE DATE None N/A