Issue date | Title | Topic | |
---|---|---|---|
L-23-188, Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments | 7 August 2023 | Energy Harbor Nuclear Corp., Supplement to Application for Order Consenting to Transfer of Licenses and Conforming License Amendments | Cyber Security Safeguards Contingency Plan Fire Protection Program |
L-22-253, Submittal of Pressure and Temperature Limits Report, Revision 5 | 10 January 2023 | Submittal of Pressure and Temperature Limits Report, Revision 5 | Hydrostatic Pressure and Temperature Limits Report |
L-22-211, Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report | 29 September 2022 | Technical Specification 5.6.6 Steam Generator Tube Inspection 180-Day Report | Nondestructive Examination |
L-22-216, Submittal of Pressure and Temperature Limits Report. Revision 4 | 27 September 2022 | Submittal of Pressure and Temperature Limits Report. Revision 4 | Hydrostatic Pressure and Temperature Limits Report |
L-22-149, Post Accident Monitoring Report | 23 June 2022 | Post Accident Monitoring Report | Post Accident Monitoring |
ML22202A436 | 8 April 2022 | Enclosure F: Updated Inputs to 52 EFPY P-T Operating Curves | Hydrostatic |
ML22202A437 | 2 March 2022 | Enclosure G: Framatome Inc. Document 86-9344713-000, Davis-Besse Reactor Vessel Embrittlement Fluence Reconciliation Through 60 Years | |
IR 05000346/2021090 | 16 December 2021 | Reissue Davis-Besse NRC Inspection Report (05000346/2021090) Preliminary White Finding | Significance Determination Process Preliminary White Finding |
ML21322A289 | 9 December 2021 | Approval of Plant-Specific Analysis of Certain Reactor Vessel Internal Components in Accordance with License Renewal Commitment No. 53 | Aging Management |
ML20302A302 | 25 September 2020 | 1 to Technical Requirements Manual | Boric Acid Shutdown Margin Grab sample Post Accident Monitoring Functionality Assessment Incorporated by reference Pressure and Temperature Limits Report Annual Radiological Environmental Operating Report Process Control Program Operability Determination Earthquake Offsite Circuit Scaffolding |
ML19255H099 | 10 October 2019 | Staff Assessment of Flooding Focused Evaluation | High winds Internal Flooding FLEX Fukushima Dai-Ichi Flooding Focused Evaluation |
L-19-189, 54010-CALC-01, Davis-Besse Nuclear Power Station: Evaluation of Risk Significance of Permanent ILRT Extension. | 29 July 2019 | 54010-CALC-01, Davis-Besse Nuclear Power Station: Evaluation of Risk Significance of Permanent ILRT Extension. | Hot Short Safe Shutdown High winds Internal Flooding Probabilistic Risk Assessment FLEX Tornado Generated Missile Thermoset Large early release frequency |
ML22262A152 | 1 May 2019 | Framatome Inc., Document ANP-2718NP, Revision 007, Appendix G Pressure-Temperature Limits for 52 EFPY for the Davis-Besse Nuclear Power Station | Hydrostatic Pressure and Temperature Limits Report Exemption Request |
ML22202A433 | 30 April 2019 | Enclosure C: Framatome ANP-2718NP, Rev. 7, Appendix G Pressure-Temperature Limits for 52 EFPY for the Davis-Besse Nuclear Power Station | Hydrostatic Pressure and Temperature Limits Report |
L-18-108, Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformance Identified in Response to Regulatory Issue Summary 2015-06, Tornado Missile.... | 12 April 2018 | Request to Extend Enforcement Discretion Provided in Enforcement Guidance Memorandum 15-002 for Tornado-Generated Missile Protection Non-Conformance Identified in Response to Regulatory Issue Summary 2015-06, Tornado Missile.... | Safe Shutdown Unanalyzed Condition Boric Acid High winds Tornado Missile Enforcement Discretion Probabilistic Risk Assessment FLEX Tornado Generated Missile Tornado Missile Protection |
ML18149A281 | 16 February 2018 | 2017 ATI Environmental Inc. Midwest Laboratory Radiological Environmental Monitoring Program | Grab sample |
L-17-270, Notification of Emergency Core Cooling System (ECCS) Evaluation Model Change Pursuant to 10 CFR 50.46 | 1 September 2017 | Notification of Emergency Core Cooling System (ECCS) Evaluation Model Change Pursuant to 10 CFR 50.46 | |
ML17086A032 | 31 March 2017 | Enclosure B to L-17-105, Areva Report ANP-3542NP, Revision 1, Time-Limited Aging Analysis (TLAA) Regarding Reactor Vessel Internals Loss of Ductility at 60 Years | Aging Management Earthquake |
L-17-088, Independent Spent Fuel Storage Installation Changes, Tests and Experiments | 27 March 2017 | Independent Spent Fuel Storage Installation Changes, Tests and Experiments | |
ML17026A008 | 31 December 2016 | Areva Report ANP-3542NP, Time-Limited Aging Analysis (TLAA) Regarding Reactor Vessel Internals Loss of Ductility for Davis-Besse Nuclear Power Station, Unit No. 1 at 60 Years (Non Proprietary) | Aging Management Earthquake |
L-16-229, Submittal of Pressure and Temperature Limits Report, Revision 3 | 28 July 2016 | Submittal of Pressure and Temperature Limits Report, Revision 3 | Pressure and Temperature Limits Report |
L-16-148, Fatigue Monitoring Program Evaluation of Reactor Coolant Pressure Boundary Components for Effects of the Reactor Coolant Environment on Fatigue Usage (I.E., Environmentally-Assisted Fatigue) | 21 April 2016 | Fatigue Monitoring Program Evaluation of Reactor Coolant Pressure Boundary Components for Effects of the Reactor Coolant Environment on Fatigue Usage (I.E., Environmentally-Assisted Fatigue) | |
L-15-288, Response to NRC Letter. Request for Information, Per 10 CFR 50.54(f) Regarding Recommendations 2.1. 2.3. and 9.3. of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident | 2 October 2015 | Response to NRC Letter. Request for Information, Per 10 CFR 50.54(f) Regarding Recommendations 2.1. 2.3. and 9.3. of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident | High Radiation Area Ultimate heat sink Emergency Lighting FLEX Fukushima Dai-Ichi Severe Accident Management Guideline |
ML15230A289 | 25 August 2015 | Staff Assessment of Information Provided Pursuant to Title 10 of the Code of Federal Regulations Part 50 Seismic Hazard Reevaluations for Recommendation 2.1 of the Near-Term Task Force Review | Safe Shutdown Earthquake Operating Basis Earthquake Fukushima Dai-Ichi Earthquake |
L-14-401, First Energy Nuclear Operating Company (FENOC) Expedited Seismic Evaluation Process (ESEP) Reports Response to NRC Request for Information Pursuant to 10 CFR50.54(f) Regarding Recommendation.1 of the Near-Term Task Force (NTTF) Review of In | 19 December 2014 | First Energy Nuclear Operating Company (FENOC) Expedited Seismic Evaluation Process (ESEP) Reports Response to NRC Request for Information Pursuant to 10 CFR50.54(f) Regarding Recommendation.1 of the Near-Term Task Force (NTTF) Review of In | |
ML14353A060 | 3 November 2014 | 2734296-R-010, Rev. 0, Expedited Seismic Evaluation Process (ESEP) Report Davis-Besse Nuclear Power Station | |
L-14-289, Pressure and Temperature Limits Report. Revision 2 | 22 September 2014 | Pressure and Temperature Limits Report. Revision 2 | Hydrostatic Pressure and Temperature Limits Report |
L-14-259, Firstenergy Nuclear Operating Company'S (Fenoc'S) Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 28 August 2014 | Firstenergy Nuclear Operating Company'S (Fenoc'S) Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | FLEX Spent Fuel Pool Instrumentation |
ML14141A525 | 30 June 2014 | Staff Assessment of the Flooding Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident | Unanalyzed Condition High winds Operator Manual Action Fukushima Dai-Ichi Earthquake |
L-14-167, Report of Facility Changes, Tests and Experiments for the Period Ending May 26, 2014 | 18 June 2014 | Report of Facility Changes, Tests and Experiments for the Period Ending May 26, 2014 | Incorporated by reference Turbine Missile |
ML14134A517 | 30 May 2014 | Staff Assessment of the Seismic Walkdown Report Supporting Implementation of Near-Term Task Force Recommendation 2.3 Related to the Fukushima DAI-ICHI Nuclear Power Plant Accident | Unanalyzed Condition Fukushima Dai-Ichi Earthquake |
L-14-148, CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models | 19 May 2014 | CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models | |
ML14112A315 | 21 April 2014 | Review of Draft Plant-Specific Supplement 52 to the Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding | |
L-14-104, Firstenergy Nuclear Operating Co. Response to NRC Request for Information Pursuant to 10 CFR 50.54 (F) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident | 11 March 2014 | Firstenergy Nuclear Operating Co. Response to NRC Request for Information Pursuant to 10 CFR 50.54 (F) Regarding the Flooding Aspects of Recommendation 2.1 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident | Fukushima Dai-Ichi Earthquake |
ML14007A670 | 21 February 2014 | Interim Staff Evaluation Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) | Safe Shutdown Boric Acid High winds Shutdown Margin Ultimate heat sink Tornado Missile Time to boil Safe Shutdown Earthquake Internal Flooding Emergency Lighting FLEX Fukushima Dai-Ichi Frazil ice Battery sizing Earthquake |
ML14042A294 | 19 February 2014 | Mega-Tech Services, LLC, Technical Evaluation Report Regarding the Overall Integrated Plan for Davis-Besse Nuclear Power Station, TAC No.: MF0961 | Safe Shutdown Boric Acid High winds Shutdown Margin Ultimate heat sink Tornado Missile Time to boil Safe Shutdown Earthquake Internal Flooding Emergency Lighting FLEX Fukushima Dai-Ichi Frazil ice Battery sizing Earthquake |
ML13340A159 | 26 November 2013 | Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix a | |
ML13340A147 | 26 November 2013 | Davis-Besse Nuclear Power Station & Perry Nuclear Power Plant - Response to RAI Associated with Seismic Aspects of Recommendation 2.3 of the Near-Term Task Force Review of Insights from the Fukushima Dai-ichi Accident (TAC Nos. MF0116 & MF0 | Condition Adverse to Quality Fukushima Dai-Ichi |
ML13340A163 | 9 October 2013 | Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix C to Appendix G | Scaffolding |
ML13340A162 | 9 October 2013 | Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (2 of 2) | |
ML13340A160 | 9 October 2013 | Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1, Appendix B (1 of 2) | |
ML13340A158 | 9 October 2013 | Davis-Besse Nuclear Power Station Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report Revision 1 | |
L-13-154, CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models | 28 May 2013 | CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling System Evaluation Models | |
L-13-157, Generic Safety Issue 191 Resolution Plan | 15 May 2013 | Generic Safety Issue 191 Resolution Plan | Coatings Severe Accident Management Guideline |
ML13009A375 | 12 December 2012 | Enclosure B to L-12-444, Calculation No. 32-9195651-000, Equivalent Margins Assessment of Davis-Besse Transition Welds for 52 EFPY - Non-Proprietary. | Incorporated by reference Finite Element Analysis |
L-12-347, FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident | 27 November 2012 | FENOC Response to NRC Request for Information Pursuant to 10 CFR 50.54(f) Regarding Flooding Aspects of Recommendation 2.3 of Near-Term Task Force Review of Insights from Fukushima Dai-ichi Accident | Safe Shutdown Unanalyzed Condition Boric Acid High winds Safe Shutdown Earthquake Internal Flooding Hydrostatic Probabilistic Risk Assessment Coatings Locked High Radiation Area Fukushima Dai-Ichi Earthquake |
ML13135A245 | 10 August 2012 | Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 202 of 379 Through Sheet 379 of 379 | |
ML13135A244 | 10 August 2012 | Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix B - Seismic Walkdown Checklists (Swcs), Sheet 1 of 379 Through Sheet 201 of 379 | |
ML13135A243 | 10 August 2012 | Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Appendix a - Resumes and Qualifications | |
ML13135A242 | 10 August 2012 | Near-Term Task Force Recommendation 2.3 Seismic Walkdown Report, Cover Through Page 176 |