MONTHYEARML24295A3742024-10-23023 October 2024 Project Manager Assignment IR 05000354/20240032024-10-23023 October 2024 Integrated Inspection Report 05000354/2024003 ML24291A0572024-10-17017 October 2024 License Amendment Request (LAR) – Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5, Supplement 1 LR-N24-0063, Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF)2024-10-0707 October 2024 Emergency Plan Document Revision Implemented September 18, 2024. Includes NC.EP-EP.ZZ-0903, Rev. 7, Opening of Emergency Operations Facility (EOF) LR-N24-0059, 2024 Annual 10 CFR 50.46 Report2024-09-30030 September 2024 2024 Annual 10 CFR 50.46 Report LR-N24-0056, Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-09-26026 September 2024 Response to Request for Additional Information Associated with License Amendment Request - Revise Hope Creek Generating Station Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle IR 05000272/20244022024-09-23023 September 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24255A8042024-09-11011 September 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N24-0057, In-Service Inspection Activities2024-09-10010 September 2024 In-Service Inspection Activities 05000354/LER-2024-001-01, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement2024-09-0505 September 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) Supplement ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000354/20240052024-08-29029 August 2024 Updated Inspection Plan for Hope Creek Generating Station (Report 05000354/2024005) LR-N24-0044, Relief Request VR-042024-08-0606 August 2024 Relief Request VR-04 IR 05000354/20240022024-07-30030 July 2024 Integrated Inspection Report 05000354/2024002 ML24200A0572024-07-18018 July 2024 Request for Withholding Information from Public Disclosure for License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves NUREG-1433, – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 52024-07-16016 July 2024 – Acceptance of License Amendment Request Concerning Technical Specification Conversion to NUREG-1433, Revision 5 ML24145A1772024-07-15015 July 2024 And Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary ML24197A0552024-07-15015 July 2024 Requalification Program Inspection 05000354/LER-2024-001, Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT)2024-07-0202 July 2024 Invalid Primary Containment Integrated Leak Rate As-Found Test (ILRT) LR-N24-0030, License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves2024-06-28028 June 2024 License Amendment Request to Revise Technical Specification Lift Settings for Reactor Coolant System Safety/Relief Valves IR 05000272/20245012024-06-12012 June 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24150A1002024-05-28028 May 2024 Core Operating Limits Report, Reload 25, Cycle 26, Revision 23 ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response LR-N24-0004, License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle2024-05-20020 May 2024 License Amendment Request – Revise Technical Specification to Change Surveillance Intervals to Accommodate a 24-Month Fuel Cycle ML24142A4072024-05-20020 May 2024 License Amendment Request (LAR) - Hope Creek Technical Specification Conversion to NUREG-1433, Revision 5 IR 05000354/20240012024-05-0808 May 2024 Integrated Inspection Report 05000354/2024001 IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000354/20243012024-04-10010 April 2024 Initial Operator Licensing Examination Report 05000354/2024301 LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 And Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 LR-N24-0021, And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 And Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums 05000354/LER-2023-003-01, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0027, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-03-19019 March 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report IR 05000354/20230062024-02-28028 February 2024 Annual Assessment Letter for Hope Creek Generating Station (Report 05000354/2023006) IR 05000272/20244012024-02-26026 February 2024 And Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0010, Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges2024-02-22022 February 2024 Technical Specification 6.9.1.5.b: 2023 Annual Report of SRV Challenges 05000354/LER-2023-003, Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram2024-02-12012 February 2024 Inadvertent Main Turbine Control Valve Closure Caused Reactor Scram IR 05000354/20230042024-02-0101 February 2024 Integrated Inspection Report 05000354/2023004 ML24030A8752024-02-0101 February 2024 Operator Licensing Examination Approval ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000354/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000354/2023401 ML23341A1372024-01-16016 January 2024 Issuance of Amendment No. 235 Revise Trip and Standby Auto-Start Logic Associated with Safety Related Heating, Ventilation and Air Conditioning ML23335A1122023-12-15015 December 2023 Retest Schedule for Drywell to Suppression Chamber Vacuum Breakers 2024-09-05
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24253A1942024-09-0909 September 2024 NRR E-mail Capture - Final Eeeb RAI - Hope Creek Amendment to Revise TS to Change Surveillance Interval to Accommodate 24-Month Fuel Cycle IR 05000354/20240102024-05-0707 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000354/2024010 IR 05000272/20244032024-03-20020 March 2024 And Hope Creek Generating Station - Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection 05000272/2024403, 05000311/2024403, and 05000354/2024403 ML24060A0492024-02-28028 February 2024 NRR E-mail Capture - Final Exhb RAI for Hope Creek, Salem 1 and 2 Amendment to Modify Exclusion Area Boundary ML22006A3212022-01-0606 January 2022 NRR E-mail Capture - Final RAI - Hope Creek - Revise TS Limits for Ultimate Heat Sink ML21300A0222021-10-27027 October 2021 Notification of Conduct of a Fire Protection Team Inspection ML21041A3972021-02-18018 February 2021 Request for Additional Information Revise Low Pressure Safety Limit to Address General Electric Part-21 Safety Communications (Non-Proprietary) ML20295A4922020-10-21021 October 2020 NRR E-mail Capture - Hope Creek - Final RAI Revise ECCS TS with Respect to HPCI System Inoperability (L-2020-LLA-0131) ML18263A1442018-09-12012 September 2018 NRR E-mail Capture - Final RAI from Apla: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18250A3142018-09-0606 September 2018 NRR E-mail Capture - Final RAI: Revise Technical Specifications to Increase Inverter AOT Extension (L-2018-LLA-0101) ML18150A6912018-05-30030 May 2018 NRR E-mail Capture - Hope Creek - Final RAI Revise TS to Adopt TSTF-542 ML18120A2482018-04-27027 April 2018 Information Request for the Cyber-Security Inspection, Notification to Perform Inspection 05000354/2018403 ML18094B0832018-04-0505 April 2018 Enclosurequest for Additional Information (Letter to P. Duke RAI Regarding Entergy Operations, Inc.'S Decommissioning Funding Plan Update for Salem and Hope Creek, and Peach Bottom ISFSIs Docket Nos. 72-48 and 72-29) ML17349A0812017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Reactor Systems Branch (Srxb) - Hope Creek Mur ML17348A9972017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6242017-12-14014 December 2017 NRR E-mail Capture - Final Request for Additional Information for Human Factors Associated with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17348A6282017-11-21021 November 2017 NRR E-mail Capture - Draft Request for Additional Information for Steam Dryer Analysis with the Hope Creek Measurement Uncertainty Recapture Uprate Request (L-2017-LLS-002) ML17331A0072017-11-21021 November 2017 E-mail Regarding Final Eicb Request for Additional Information - Hope Creek Power Uprate ML17324A2602017-11-17017 November 2017 NRR E-mail Capture - Final Request for Additional Information - Hope Creek Mur Electrical Instrumentation and Controls ML17320A2152017-11-16016 November 2017 NRR E-mail Capture - Hope Creek Measurement Uncertainty Recapture Application Review - Electrical Engineering (Eeob) Request for Additional Information (L-2017-LLS-0002) ML17290B0132017-10-17017 October 2017 NRR E-mail Capture - Hope Creek Mur Request for Additional Information for Apla and Snpb ML17222A1652017-08-10010 August 2017 NRR E-mail Capture - Hope Creek: Final Request for Information, Pressure-Temperature Limit Report Request (MF9502) ML17181A1352017-06-29029 June 2017 NRR E-mail Capture - Request for Additional Information Related to Hope Creek and Salem Emergency Action Level Scheme Change License Amendment Request (MF9268/69/70) ML17164A4062017-06-13013 June 2017 NRR E-mail Capture - Hope Creek - Final Request for Additional Information Concerning ILRT (MF8462) ML17027A3282017-02-27027 February 2017 Request for Additional Information Regarding License Amendment Request to Permanently Extend Type a and Type C Leak Rate Test Frequencies ML16321A4642016-11-21021 November 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Request for Additional Information Regarding License Amendment Request to Remove Certain Training Requirements ML16277A5142016-11-0303 November 2016 Request for Additional Information Regarding License Amendment Request to Permit Operability of Low Pressure Coolant Injection While Aligned to Shutdown Cooling ML16271A2052016-11-0202 November 2016 Request for Additional Information Regarding Request to Delete Technical Specifications Action Statement 3.4.2.1.b Associated with Stuck Open Safety/Relief Valves ML16231A4272016-08-24024 August 2016 Request for Additional Information Regarding Relief Request VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16217A4302016-08-17017 August 2016 Request for Additional Information Regarding Digital Power Range Neutron Monitoring System Upgrade ML16007A1742016-05-31031 May 2016 Request for Additional Information Regarding Review of Post-EPU Steam Dryer Stress Calculation Acoustic Circuit Model Software Error ML16089A0792016-05-0505 May 2016 Request for Additional Information Regarding Relief Requests GR-01, PR-01, PR-02, VR-01, and VR-02, Associated with the Fourth 10-Year Inservice Test Interval ML16124A5802016-05-0303 May 2016 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Redacted - Request for Additional Information Review of Security Plan Revision 17 Changes ML15055A3772015-03-10010 March 2015 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information Request to Update Appendix B to Renewed Facility Operating License DPR-70, DPR-75 and NPF-57 ML14197A6192014-07-24024 July 2014 and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding Cyber Security Plan Milestone 8 Implementation Schedule (Tac Nos. MF3384, MF3385 and MF3386) ML14168A2352014-07-0202 July 2014 Request for Additional Information Regarding Flooding Hazard Reevaluation ML13309B5922013-11-22022 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13304B4182013-11-0101 November 2013 Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Seismic Walkdowns ML13168A2762013-08-12012 August 2013 Peach Bottom, Units 2 and 3, Request for Additional Information Decommissioning Funding Status Report (TAC No. MF2202; MF2227; MF2228) ML13193A2912013-07-22022 July 2013 Request for Additional Information Regarding Overall Integrated Plan for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) TAC MF1031 ML13204A2532013-07-19019 July 2013 Draft RAIs - Decommissioning Funding Status Report for Hope Creek and Peach Bottom ML13190A2212013-07-0202 July 2013 RAIs for Hope Creek Regarding Response to Order EA-12-051 ML13154A4952013-06-0404 June 2013 Rai'S Following Ifib Analysis of Pseg'S 2013 Decommissioning Funding Status Report for Hope Creek Generating Station ML12334A3102012-12-0505 December 2012 Request for Additional Information Request to Correct Technical Specification and Facility Operating License Editorial Items ML12310A1672012-11-0101 November 2012 Draft RAI to License Amendment Request Regarding Average Power Range Monitoring Operability Requirements in Operational Condition 5 ML1227901012012-10-0505 October 2012 Clarifying Information for Question No. 4 (with Attachment) ML12212A1032012-08-0808 August 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Request for Additional Information ML12216A1792012-08-0303 August 2012 Draft RAI Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML12213A6162012-07-30030 July 2012 Draft Request for Additional Information Related to Request for Exemption from Certain Requirements of the Fitness for Duty Rule ML1209002372012-03-29029 March 2012 and Salem Nuclear Generating Station, Unit Nos. 1 and 2, Draft Request for Additional Information 2024-09-09
[Table view] |
Text
November 22, 2002 Mr. Harold W. Keiser Chief Nuclear Officer & President PSEG Nuclear LLC - X04 Post Office Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
HOPE CREEK GENERATING STATION - REQUEST FOR ADDITIONAL INFORMATION REGARDING INTEGRATED LEAK RATE TEST INTERVAL EXTENSION (TAC NO. MB6551)
Dear Mr. Keiser:
By letter dated October 9, 2002, PSEG Nuclear, LLC requested an amendment that would allow a one-time extension of the Integrated Leak Rate Test (ILRT) interval for the Hope Creek Generating Station, Unit No. 1. The U.S. Nuclear Regulatory Commission (NRC) staff has begun its review of the proposed change and requests that you answer the enclosed questions regarding your submittal. These questions were discussed with Mr. Mike Mosier and other members of your staff in a telephone call on November 21, 2002.
Your October 9, 2002, amendment request asks for the ILRT test interval to be extended from 10 to 20 years. Following an initial review by the technical staff I called Mr. Nagle on or about November 7, 2002, and stated that it was unlikely that we could grant such a request; I informed him that the NRC staff considered an extension to 15 years much more reasonable.
As a result of this conversation, Mr. Nagle stated that PSEG Nuclear, LLC would modify the amendment request accordingly and ask for an extension of the ILRT interval to 15 years. I understand that I should have this modified request in a matter of days.
In your October 9, 2002, request you asked that the amendment be issued in time to support your spring 2003 outage. Please note that ILRT interval extensions are technically complex and require review by experts from several branches of the NRC staff. Many reviews have taken 6 to 7 months to complete. While the NRC staff will make every effort to meet your requested date, we cannot assure you that the amendment will be issued in time to support your outage.
H. Keiser In order that we may complete our review in a timely manner we understand that you intend to submit your response to the enclosed request for additional information within 15 days of the date of this letter. If any of the information above is incorrect or if you have any questions, please do not hesitate to call. I can be reached at (301) 415-1494.
Sincerely,
/RA/
George F. Wunder, Project Manager, Section 2 Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation Docket No. 50-354
Enclosure:
As stated cc w/encl: See next page
ML023260336 OFFICE PDI-2/PM EMEB/SC PDI-1/LA PDI-1/SC(A)
NAME GWunder DTerao LCox JAndersen DATE 11/22/02 11/22/02 11/22/02 Hope Creek Generating Station cc:
Jeffrie J. Keenan, Esquire Richard Hartung PSEG Nuclear - N21 Electric Service Evaluation P.O. Box 236 Board of Regulatory Commissioners Hancocks Bridge, NJ 08038 2 Gateway Center, Tenth Floor Newark, NJ 07102 Hope Creek Resident Inspector U.S. Nuclear Regulatory Commission Lower Alloways Creek Township Drawer 0509 c/o Mary O. Henderson, Clerk Hancocks Bridge, NJ 08038 Municipal Building, P.O. Box 157 Hancocks Bridge, NJ 08038 Mr. David F. Garchow Vice President - Operations PSEG Nuclear - X10 P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. Gabor Salamon Manager - Nuclear Safety and Licensing PSEG Nuclear - N21 P.O. Box 236 Hancocks Bridge, NJ 08038 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection and Energy CN 415 Trenton, NJ 08625-0415
REQUEST FOR ADDITIONAL INFORMATION REGARDING REQUEST FOR INTEGRATED LEAK RATE TEST INTERVAL EXTENSION HOPE CREEK GENERATING STATION UNIT NO. 1 DOCKET NO. 50-354 Question 1: Your request for amendment dated October 9, 2002, does not describe the containment Inservice Inspection (ISI) program being implemented at Hope Creek Unit 1.
Please provide a description of the ISI methods (with Code Edition and addenda) that provide assurance that in the absence of an Integrated Leak Rate Test (ILRT) for 15 years, the containment structural and leak tight integrity will be maintained. Also provide start and completion dates of the first IWE and IWL examinations performed as required by 10CFR50.55a, and a schedule for conducting the future examinations.
Question 2: IWE-1240 requires licensees to identify the surface areas requiring augmented examinations. Please provide the NRC staff with the list of the areas (such as shell near sand cushion areas and vertical portions of the drywell) identified for augmented examination and a summary of examinations performed.
Question 3: For the examination of seals and gaskets, and examination and testing of bolts associated with the primary containment pressure boundary (examination categories E-D and E-G, IWE-1992), you have previously requested relief from the IWE-1992; this relief was authorized by NRC letter dated June 6, 2000. As an alternative, to IWE-1992 you planned to examine these components during leak rate testing of the primary containment. With the flexibility provided in Option B of Appendix J for Type B and Type C testing, and the extension requested in this amendment for Type A testing, please provide the schedule for examination and testing of seals, gaskets, and bolts that provide assurance of the integrity of the containment pressure boundary.
Question 4: The stainless steel bellows have been found to be susceptible to trans-granular stress corrosion cracking, and leakages through them are not readily detectable by Type B testing (see NRC Information Notice 92-20, "Inadequate Local Leak Rate Testing"). In general, boiling water reactor Mark I primary containments have bellows on the vent lines between the drywell and the torus, as well as on several process piping penetrations in the drywell. If degraded, the bellows could allow the drywell steam and air to bypass the suppression pool during loss-of-coolant accidents and core damage accidents. Please provide information regarding inspection and testing of the bellows at Hope Creek.
Question 5: Inspections of some reinforced and steel containments (e.g., North Anna, Brunswick, D. C. Cook, and Oyster Creek), have indicated degradation from the uninspectable side of the steel shell and liner of primary containments. The major uninspectable areas of the Mark I containment are the vertical portion of the drywell shell and part of the shell sandwiched between the drywell floor and the basemat. Please discuss what programs are used to monitor their condition. Also, address how potential leakage due to age related degradation from these uninspectable areas is factored into the risk assessment in support of the requested ILRT interval extension.
Enclosure